CN109736843B - A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork - Google Patents
A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork Download PDFInfo
- Publication number
- CN109736843B CN109736843B CN201910049724.8A CN201910049724A CN109736843B CN 109736843 B CN109736843 B CN 109736843B CN 201910049724 A CN201910049724 A CN 201910049724A CN 109736843 B CN109736843 B CN 109736843B
- Authority
- CN
- China
- Prior art keywords
- upper section
- pilot tunnel
- pouring
- construction
- side wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 34
- 238000004078 waterproofing Methods 0.000 title description 9
- 238000009415 formwork Methods 0.000 title description 8
- 238000010276 construction Methods 0.000 claims abstract description 58
- 229910000831 Steel Inorganic materials 0.000 claims description 25
- 238000009412 basement excavation Methods 0.000 claims description 25
- 239000010959 steel Substances 0.000 claims description 25
- 238000005422 blasting Methods 0.000 claims description 18
- 238000005266 casting Methods 0.000 claims description 13
- CURLTUGMZLYLDI-UHFFFAOYSA-N Carbon dioxide Chemical compound O=C=O CURLTUGMZLYLDI-UHFFFAOYSA-N 0.000 claims description 12
- 229910002092 carbon dioxide Inorganic materials 0.000 claims description 6
- 239000001569 carbon dioxide Substances 0.000 claims description 6
- 238000005507 spraying Methods 0.000 claims description 5
- 238000005336 cracking Methods 0.000 claims description 4
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims 2
- 238000005516 engineering process Methods 0.000 description 6
- 230000003014 reinforcing effect Effects 0.000 description 5
- 239000007921 spray Substances 0.000 description 5
- 239000004570 mortar (masonry) Substances 0.000 description 4
- 230000002787 reinforcement Effects 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 2
- 229910000514 dolomite Inorganic materials 0.000 description 2
- 239000010459 dolomite Substances 0.000 description 2
- 239000003673 groundwater Substances 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
技术领域technical field
本发明涉及隧道施工技术领域,具体涉及一种小模板拼装浇注二衬的逆作防水方法。The invention relates to the technical field of tunnel construction, in particular to a reverse working waterproof method for assembling and pouring a secondary lining with a small formwork.
背景技术Background technique
狭小场地施工大跨暗挖隧道是城市地铁车站建设中的常见问题,受场地条件限制,地铁车站施工时往往利用横通道转入主隧道进行施工。因而,横通道安全快速施工对节省地铁车站施工工期有着重要的意义。横通道开挖以后,为了保持围岩的稳定性,一般需要进行初期支护和浇筑衬砌。实际施工时,出于施工工期及开挖风险管理的考虑,二次衬砌可能需要分段浇筑而后再封闭成环,整体性较差,往往导致上下施工面接口处出现渗、漏水现象,尤其在地下水丰富地区,工程质量受到严重影响。Construction of large-span underground tunnels in narrow sites is a common problem in the construction of urban subway stations. Due to site conditions, subway stations often use horizontal passages to transfer into the main tunnel for construction. Therefore, the safe and rapid construction of the horizontal passage is of great significance to save the construction period of the subway station. After the excavation of the transverse channel, in order to maintain the stability of the surrounding rock, initial support and lining are generally required. During actual construction, due to the consideration of construction period and excavation risk management, the secondary lining may need to be poured in sections and then closed into a ring. In areas with abundant groundwater, the quality of the project is seriously affected.
发明内容SUMMARY OF THE INVENTION
本发明的目的在于针对现有技术的缺陷和不足,提供一种结构简单,设计合理、使用方便的小模板拼装浇注二衬的逆作防水方法,解决上下施工面接口处防水难题,加快施工进度,提高二次衬砌的质量,保证横通道乃至车站主隧道安全快速施工。The purpose of the present invention is to aim at the defects and deficiencies of the prior art, to provide a simple structure, reasonable design and convenient use of a small formwork assembling and pouring a reverse waterproofing method for the secondary lining, so as to solve the problem of waterproofing at the interface of the upper and lower construction surfaces and speed up the construction progress. , improve the quality of the secondary lining, and ensure the safe and rapid construction of the cross passage and even the main tunnel of the station.
为实现上述目的,本发明采用的技术方案是:它的施工方法如下:To achieve the above object, the technical scheme adopted in the present invention is: its construction method is as follows:
1、利用上一循环架立的钢架施作隧道侧壁Ф42注浆小导管;利用CD法开挖顶部右导坑上断面和顶部左导坑上断面;喷射封闭掌子面;施作顶部右导坑上断面的导坑周边的初期支护和临时支护,即初喷4CM厚砼,铺设钢筋网,架立型钢钢架和I20a临时钢架,并设锁脚锚杆和定位钢筋;设置系统锚杆后复喷砼至设计厚度;在滞后于顶部右导坑上断面和顶部左导坑上断面一段距离后,再开挖顶部右导坑下端面和顶部左导坑下断面;1. Use the steel frame erected in the previous cycle to apply the Ф42 grouting small duct on the side wall of the tunnel; use the CD method to excavate the upper section of the top right guide pit and the upper section of the top left guide pit; spray the closed face; apply the top The initial support and temporary support around the guide pit on the upper section of the right guide pit, that is, the initial spraying of 4CM thick concrete, the laying of steel mesh, the erection of section steel frame and I20a temporary steel frame, and the setting of locking anchors and positioning steel bars; After setting the system bolt, re-spray concrete to the design thickness; after a certain distance behind the upper section of the top right pilot pit and the upper section of the top left pilot pit, excavate the lower end face of the top right pilot pit and the lower section of the top left pilot pit;
2、拱部开挖支护成型20米后进行顶部右导坑上断面以及顶部左导坑上断面部分的防水系统处理和二次浇注作业;2. After the arch is excavated and supported for 20 meters, the waterproof system treatment and secondary pouring of the upper section of the top right pilot pit and the upper section of the top left pilot pit are carried out;
3、利用台阶法进行中部右导坑上断面、中部有左导坑上断面、中部右导坑下端面和中部左导坑下断面的开挖,左右交叉作业,二衬浇注作业前后错开,施工长度大于15m时进行单侧中部边墙的二衬防水、钢筋、浇筑作业,前次浇注强度达到70%后,进行另一侧中部边墙的二衬浇注作业;3. Use the step method to excavate the upper section of the middle right pilot pit, the upper section of the left pilot pit in the middle, the lower end face of the middle right pilot pit and the lower section of the middle left pilot pit. When the length is greater than 15m, carry out the secondary lining waterproofing, reinforcing bars and pouring operations of the middle side wall on one side. After the previous pouring strength reaches 70%, carry out the secondary lining casting operation of the middle side wall on the other side;
4、利用台阶法进行底部右导坑上断面、底部左导坑上断面、底部右导坑下断面和底部左导坑下断面的开挖,左右侧交叉施作,施工长度大于10m时,施作底部拱部二衬浇注作业,然后再进行单侧底部边墙的二衬防水、钢筋、浇筑作业,二衬浇注作业前后错开,即,当前次浇注强度达到70%后,进行另一侧底部边墙的二衬浇注作业。4. Use the step method to excavate the upper section of the bottom right pilot pit, the upper section of the bottom left pilot pit, the lower section of the bottom right pilot pit and the lower section of the bottom left pilot pit. The left and right sides are crossed. When the construction length is greater than 10m, the Perform the second lining pouring operation of the bottom arch, and then carry out the second lining waterproofing, reinforcing bars, and pouring operations of the bottom side wall on one side. The secondary lining pouring operation of the side wall.
进一步地,所述的步骤2中浇注二衬混凝土一次性浇注20米,强度达到70%后,再进行浇注段下部一侧的开挖。Further, in the
进一步地,所述的步骤3中的中部边墙浇注控制在5米范围内,其余段边墙浇注控制在15米范围内。Further, the casting of the middle side wall in the
进一步地,所述的步骤3和步骤4中的浇注采取整体浇筑的模式,顺作法施工工艺,浇筑长度控制在10米范围内。Further, the pouring in the
进一步地,所述的步骤1-步骤4的开挖过程中,遇到二衬混凝土连接处时,先进行中槽的弱爆破开挖,边墙采取弱爆破、二氧化碳欲裂和冷开的施工工艺,加强对浆砌片石的保护,完全杜绝爆破对已完成二衬的影响。Further, in the excavation process of the described
采用上述结构后,本发明有益效果为:本发明所述的一种小模板拼装浇注二衬的逆作防水方法,解决上下施工面接口处防水难题,加快施工进度,提高二次衬砌的质量,保证横通道乃至车站主隧道安全快速施工,本发明具有结构简单,设置合理,制作成本低等优点。After the above structure is adopted, the beneficial effects of the present invention are as follows: the retrograde waterproofing method for assembling and pouring the secondary lining with a small formwork according to the present invention solves the problem of waterproofing at the interface of the upper and lower construction surfaces, accelerates the construction progress, and improves the quality of the secondary lining, To ensure the safe and rapid construction of the transverse passage and even the main tunnel of the station, the invention has the advantages of simple structure, reasonable setting, low production cost and the like.
附图说明Description of drawings
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to explain the embodiments of the present invention or the technical solutions in the prior art more clearly, the following briefly introduces the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are only These are some embodiments of the present invention. For those of ordinary skill in the art, other drawings can also be obtained according to these drawings without creative efforts.
图1是本发明的断面示意图。Figure 1 is a schematic sectional view of the present invention.
图2是本发明中顶部右导坑上断面以及顶部左导坑上断面施工立面图。Figure 2 is a construction elevation view of the upper section of the top right guide pit and the upper section of the top left guide pit in the present invention.
图3是本发明中顶部右导坑上断面以及顶部左导坑上断面施工平面图。Figure 3 is a construction plan view of the upper section of the top right guide pit and the upper section of the top left guide pit in the present invention.
图4是本发明中中部右导坑上断面以及中部左导坑上断面施工立面图。4 is a construction elevation view of the upper section of the middle right pilot pit and the upper section of the middle left pilot pit of the present invention.
图5是本发明中中部右导坑上断面以及中部左导坑上断面施工平面图。5 is a construction plan view of the upper section of the middle right pilot pit and the upper section of the middle left pilot pit in the present invention.
图6是本发明中底部右导坑上断面以及底部左导坑上断面施工立面图。Fig. 6 is the construction elevation view of the upper section of the bottom right guide pit and the upper section of the bottom left guide pit in the present invention.
图7是本发明中底部右导坑上断面以及底部左导坑上断面施工平面图。7 is a construction plan view of the upper section of the bottom right guide pit and the upper section of the bottom left guide pit in the present invention.
图8是本发明中施工缝处钢筋接头以及防水处理施工措施图。FIG. 8 is a drawing of the steel bar joint at the construction joint and the construction measures for waterproof treatment in the present invention.
图9是本发明中施工缝混凝土浇筑不紧密的处理施工措施图。FIG. 9 is a drawing of the construction measures for the treatment of incompact concrete pouring of construction joints in the present invention.
附图标记说明:Description of reference numbers:
顶部右导坑上断面1、顶部右导坑下端面1-1、顶部左导坑上断面2、顶部左导坑下断面2-1、中部右导坑上断面3、中部右导坑下端面3-1、中部有左导坑上断面4、中部左导坑下断面4-1、底部右导坑上断面5、底部右导坑下断面5-1、底部左导坑上断面6、底部左导坑下断面6-1、顶部拱部7、中部边墙8、底部边墙9、底部拱部10、衬砌模板11、浆砌片石12、防水板材13、钢板14、可绕注浆管15。Top right pilot pit
具体实施方式Detailed ways
下面结合附图对本发明作进一步的说明。The present invention will be further described below in conjunction with the accompanying drawings.
参看如图1-图9所示,本具体实施方式应用实施于贵阳轨道交通2#线观水路车站2号风亭横通道施工。观水路站2号风亭位于观水路站-YDK36+300段区间左隧道左侧民房区内,横通道中线与路线相交于ZDK36+136.287里程处,横通道与正洞相连,与正洞正交。2号风亭竖井内净空尺寸为6.6*15m,井深32.998m;横通道长51.03m,开挖宽*高=12.26*18.293m,竖井所处地层至上而下依次为砼地面,人工杂填土,红黏土,三叠系下统安顺组白云岩,井身主要位于白云岩内;横通道顶拱埋深14.7-16.5m,拱顶基岩厚0.3-4.2m。Referring to Fig. 1-Fig. 9, this specific embodiment is applied and implemented in the construction of the horizontal passage of the wind pavilion on the No. 2 Guanshui Road Station of Guiyang Rail Transit Line 2#. No. 2 wind pavilion at Guanshui Road Station is located in the residential area on the left side of the left tunnel in the section between Guanshui Road Station and YDK36+300. The middle line of the cross passage intersects the route at the mileage of ZDK36+136.287. The cross passage is connected to the main hole and is orthogonal to the main hole. . The clearance size in the shaft of No. 2 wind pavilion is 6.6*15m, and the well depth is 32.998m; the length of the horizontal passage is 51.03m, and the excavation width*height=12.26*18.293m. , red clay, dolomite of the Lower Triassic Anshun Formation, the wellbore is mainly located in the dolomite; the depth of the top arch of the transverse channel is 14.7-16.5m, and the thickness of the vault bedrock is 0.3-4.2m.
本具体实施方式的施工方法如下:The construction method of this specific embodiment is as follows:
1、利用上一循环架立的钢架施作隧道侧壁Ф42注浆小导管;利用CD法开挖顶部右导坑上断面1和顶部左导坑上断面2;喷射封闭掌子面;施作顶部右导坑上断面的导坑周边的初期支护和临时支护,即初喷4CM厚砼,铺设钢筋网,架立型钢钢架和I20a临时钢架,并设锁脚锚杆和定位钢筋;设置系统锚杆后复喷砼至设计厚度;在滞后于顶部右导坑上断面1和顶部左导坑上断面2一段距离后,开挖顶部右导坑下端面1-1和顶部左导坑下断面2-1;1. Use the steel frame erected in the previous cycle to apply the Ф42 grouting small pipe on the side wall of the tunnel; use the CD method to excavate the
2、拱部开挖支护成型20米后,安装拱部二衬多功能组装台车,设计小模板拼装的方案浇筑顶部拱部7的混凝土;2. After the arch is excavated and supported for 20 meters, install the multi-functional assembly trolley for the second lining of the arch, and design a plan for small formwork assembly to pour the concrete of the
3、利用台阶法进行中部右导坑上断面3、中部有左导坑上断面4、中部右导坑下端面3-1和中部左导坑下断面4-1的开挖,左右交叉作业,二衬浇注作业前后错开,施工长度大于15m时进行单侧中部边墙8的二衬防水、钢筋、浇筑作业,前次浇注强度达到70%后,进行另一侧中部边墙8的二衬浇注作业;3. Use the step method to excavate the
4、利用台阶法进行底部右导坑上断面5、底部左导坑上断面6、底部右导坑下断面5-1和底部左导坑下断面6-1的开挖,左右侧交叉施作,施工长度大于10m时,施作底部拱部10二衬浇注作业,然后再进行单侧底部边墙9的二衬防水、钢筋、浇筑作业,二衬浇注作业前后错开,即,当前次浇注强度达到70%后,进行另一侧底部边墙9的二衬浇注作业。4. Use the step method to excavate the
进一步地,所述的步骤2中浇注二衬混凝土一次性浇注20米,强度达到70%后,再进行浇注段下部一侧的开挖。Further, in the
进一步地,所述的步骤3中的中部边墙8浇注控制在5米范围内,其余段边墙浇注控制在15米范围内。Further, the casting of the middle side wall 8 in the
进一步地,所述的步骤3和步骤4中的浇注采取整体浇筑的模式,顺作法施工工艺,浇筑长度控制在10米范围内。Further, the pouring in the
进一步地,所述的步骤1-步骤4的开挖过程中,遇到二衬混凝土连接处时,先进行中槽的弱爆破开挖,边墙采取弱爆破、二氧化碳欲裂和冷开的施工工艺,加强对浆砌片石的保护,完全杜绝爆破对已完成二衬的影响。Further, in the excavation process of the described
进一步地,所述的顶部拱部7、中部边墙8、底部边墙9以及底部拱部10的施工缝处需要进行钢筋接头及防水处理,流程如下:在顶部拱部7的混凝土浇筑前,预留钢筋,底部和侧面铺设模板11,模板11下用方浆砌片石12至基岩面,浇筑中部边墙8前完成对浆砌片石12的保护和加固(必要时挂网喷射混凝土),上下钢筋通过接驳器连接,防水板13受填充细砂的保护,均不会受到破坏,浆砌片石12上方钢板设置成10%的倾角,成型以后的二次衬砌将“外低内高”,有利于防止地下水回流。Further, the construction joints of the described
进一步地,所述的顶部拱部7、中部边墙8、底部边墙9以及底部拱部10的施工缝处的施工缝止水带处预埋可绕注浆管15,采取后回填水泥浆液的工艺处理,横向、纵向均布设注浆管,且注浆管两头引出浇筑面,目的在于为了整体连接处的密实。Further, the construction joint waterstops at the construction joints of the
本具体实施方式中的Φ42注浆小导管,壁厚4.0mm,L=3.5m,环向间距0.35m,纵向间距1.5m,外插角5~7°,小导管搭接长度不小于1m, 注浆加固地层,土方开挖每榀开挖进尺为0.5m,开挖时严禁掏底施工,由上至下逐层开挖,土方开挖完成后对欠挖部分进行处理,初喷40mm厚混凝土。钢架:I25b型钢钢架全环设置,间距0.5m/榀。系统锚杆:拱部采用Φ32注浆钢花管,外插角为60°,环纵间距1.0*1.0m,梅花形布置,L=3.5m,壁厚3mm,前部钻注浆孔,孔径6~8mm,孔间距20cm,尾部预留不小于30cm的止浆段,Φ32注浆钢花管注浆参数参照超前小导管注浆参数办理;边墙采用Φ22砂浆锚杆,L=4.5m;锚杆间距:1.0*1.0m(环*纵),梅花形布置。钢筋网:Φ8钢筋,构成20*20cm网格,全环设置;钢筋网应与锚杆尾端焊接牢固。The Φ42 grouting small duct in this specific embodiment has a wall thickness of 4.0 mm, L=3.5 m, a circumferential spacing of 0.35 m, a longitudinal spacing of 1.5 m, an outer gusset angle of 5 to 7°, and the overlapping length of the small duct is not less than 1 m. The stratum is reinforced by grouting. The excavation footage of each excavation is 0.5m. During excavation, it is strictly forbidden to excavate the bottom. The excavation is carried out layer by layer from top to bottom. concrete. Steel frame: I25b steel frame is set in full ring, with a spacing of 0.5m/square. System bolt: The arch adopts Φ32 grouting steel flower tube, the outer angle is 60°, the longitudinal spacing of the ring is 1.0*1.0m, the plum blossom-shaped arrangement, L=3.5m, the wall thickness is 3mm, and the front part is drilled with grouting holes, with a diameter of 6 ~8mm, the hole spacing is 20cm, and a grouting section of not less than 30cm is reserved at the tail. The grouting parameters of the Φ32 grouting steel flower tube are handled with reference to the grouting parameters of the advanced small pipe; the side wall adopts the Φ22 mortar bolt, L=4.5m; Spacing: 1.0*1.0m (ring*longitudinal), plum-shaped arrangement. Reinforcement mesh: Φ8 steel bars, forming a 20*20cm grid, set in a full ring; the reinforcement mesh should be firmly welded to the end of the anchor rod.
采用上述结构后,本具体实施方式有益效果为:After adopting the above structure, the beneficial effects of this specific embodiment are:
横通道开挖以后,现有技术待车站和区间隧道施工完成以后进行二次衬砌。但实际施工过程中,各开挖步开挖风险可能较大,施工工期较短,必须进行采用分段分时浇筑二次衬砌时,相应的防水措施过于简单,并不能较好的解决上下施工面接口处渗、漏水问题,本发明结合现场施工经验,充分考虑施工实际,基于传统施工方法,提出新的防水方法以解决现有技术缺点。After the excavation of the horizontal passage, the existing technology is to carry out secondary lining after the completion of the construction of the station and section tunnels. However, in the actual construction process, the excavation risk of each excavation step may be relatively large, and the construction period is short. When the secondary lining must be poured in sections and time-sharing, the corresponding waterproof measures are too simple and cannot solve the upper and lower construction well. To solve the problems of seepage and water leakage at the surface interface, the present invention combines the on-site construction experience, fully considers the construction practice, and proposes a new waterproof method based on the traditional construction method to solve the shortcomings of the existing technology.
以上所述,仅用以说明本发明的技术方案而非限制,本领域普通技术人员对本发明的技术方案所做的其它修改或者等同替换,只要不脱离本发明技术方案的精神和范围,均应涵盖在本发明的权利要求范围当中。The above is only used to illustrate the technical solution of the present invention and not to limit it. Other modifications or equivalent replacements made by those of ordinary skill in the art to the technical solution of the present invention, as long as they do not depart from the spirit and scope of the technical solution of the present invention, should be Included within the scope of the claims of the present invention.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910049724.8A CN109736843B (en) | 2019-01-18 | 2019-01-18 | A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910049724.8A CN109736843B (en) | 2019-01-18 | 2019-01-18 | A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109736843A CN109736843A (en) | 2019-05-10 |
CN109736843B true CN109736843B (en) | 2020-06-19 |
Family
ID=66365300
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910049724.8A Active CN109736843B (en) | 2019-01-18 | 2019-01-18 | A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109736843B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110593893B (en) * | 2019-11-01 | 2024-04-12 | 中建八局轨道交通建设有限公司 | Main body structure construction method and system at intersection of main tunnel and construction transverse channel |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1563671A (en) * | 2004-03-19 | 2005-01-12 | 刘昌用 | Dormant digging and separating construction method for underground two layers and multilayer composite lining structure |
CN101067374A (en) * | 2007-02-13 | 2007-11-07 | 铁道第二勘察设计院 | Single-hole double-layer overlapping tunnel structure and its construction method |
CN104806251B (en) * | 2015-04-27 | 2017-05-17 | 北京市轨道交通建设管理有限公司 | Subsidiary inverted excavation construction method for urban subway station under complex environment |
CN108005660A (en) * | 2017-11-16 | 2018-05-08 | 党文华 | A kind of Optimization of Expressway Tunnel Construction method |
-
2019
- 2019-01-18 CN CN201910049724.8A patent/CN109736843B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN109736843A (en) | 2019-05-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2021223573A1 (en) | Construction structure for communication and connection between newly added mined channel and existing station hall layer | |
CN105041349B (en) | A kind of excavating construction method that station is digged on the basis of Subway Tunnel shield tunnel | |
CN106761778B (en) | A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground | |
JP7394252B1 (en) | Protruding type wind duct structure perpendicular to the vertical direction and construction method at deep subway station | |
CN108412501B (en) | Under wear oil pipeline shallow depth loess tunnels construction method | |
CN110905530B (en) | Stability control construction method for water-rich soft rock tunnel penetrating fault fracture zone | |
CN105003272B (en) | Reversed construction method for expanding and excavating stations on sectional shield tunnel foundations of subways | |
CN105064397B (en) | Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation | |
CN109026064B (en) | Construction method for large-span multi-arch tunnel with semi-bright and semi-dark | |
CN105201516B (en) | A kind of main structure of subway station and its tetrad arch PBA excavating construction methods | |
CN105156121A (en) | Construction method of large-cross section loess tunnel cave entering shallow buried section | |
CN101929340A (en) | Construction technology of pre-grouting and advance support for pipe shed in horizontal inclined roadway in coal mine | |
CN106703814A (en) | Mined metro station hole pile construction method | |
CN111677520A (en) | Construction method of excavating station structure by tunnel first and then station pipe curtain hole pile method | |
CN107939415A (en) | Stay the micro- two step constructions method of Core Soil in the soft plastic clay tunnel of Shallow-buried Large-span | |
CN107905814A (en) | Large span loess tunnel top bar CD construction methods | |
CN207033463U (en) | Mine shield handing-over tunnel folded type joint design in the middle part of marine site | |
CN112443331B (en) | Disturbance sensitive stratum ultra-small clear distance large section group-hole parallel subway tunnel construction method | |
CN205036380U (en) | Block of four encircles PBA and secretly digs subway station major structure | |
CN114412509A (en) | A support method suitable for large deformation of mudstone tunnel | |
CN114542086A (en) | Construction method of large-span section underground excavation tunnel influenced by underground water | |
CN111911169B (en) | A shallow buried deep tunnel construction method and structure under an existing railway line | |
CN109736843B (en) | A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork | |
CN205036388U (en) | Block of four encircles knot hunch construction structures that PBA secretly dug subway station | |
CN105178355B (en) | The stratum pre-reinforcement processing method of underground space construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |