CN109736843B - A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork - Google Patents

A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork Download PDF

Info

Publication number
CN109736843B
CN109736843B CN201910049724.8A CN201910049724A CN109736843B CN 109736843 B CN109736843 B CN 109736843B CN 201910049724 A CN201910049724 A CN 201910049724A CN 109736843 B CN109736843 B CN 109736843B
Authority
CN
China
Prior art keywords
upper section
pilot tunnel
pouring
construction
side wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910049724.8A
Other languages
Chinese (zh)
Other versions
CN109736843A (en
Inventor
赵迎
王西波
宋战平
霍奇
胡敏
刘宪永
谭文浩
闫彪
麻海涛
于磊
张发财
时光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Architecture and Technology
Beijing Municipal Road and Bridge Co Ltd
Original Assignee
Xian University of Architecture and Technology
Beijing Municipal Road and Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Architecture and Technology, Beijing Municipal Road and Bridge Co Ltd filed Critical Xian University of Architecture and Technology
Priority to CN201910049724.8A priority Critical patent/CN109736843B/en
Publication of CN109736843A publication Critical patent/CN109736843A/en
Application granted granted Critical
Publication of CN109736843B publication Critical patent/CN109736843B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to a reverse waterproof method for assembling and pouring a secondary lining by a small template, belonging to the technical field of tunnel construction; after lagging behind the upper section of the top right pilot tunnel and the upper section of the top left pilot tunnel by a certain distance, excavating the lower end surface of the top right pilot tunnel and the lower section of the top left pilot tunnel; excavating an upper section of the middle right pilot tunnel, an upper section of the middle left pilot tunnel, a lower end surface of the middle right pilot tunnel and a lower section of the middle left pilot tunnel; and excavating the upper section of the bottom right pilot tunnel, the upper section of the bottom left pilot tunnel, the lower section of the bottom right pilot tunnel and the lower section of the bottom left pilot tunnel by using a step method, wherein the left side and the right side are crossed. The waterproof difficult problem of construction face kneck about solving for the construction progress improves secondary lining's quality, guarantees the safe quick construction of cross access and even station main tunnel.

Description

一种小模板拼装浇注二衬的逆作防水方法A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork

技术领域technical field

本发明涉及隧道施工技术领域,具体涉及一种小模板拼装浇注二衬的逆作防水方法。The invention relates to the technical field of tunnel construction, in particular to a reverse working waterproof method for assembling and pouring a secondary lining with a small formwork.

背景技术Background technique

狭小场地施工大跨暗挖隧道是城市地铁车站建设中的常见问题,受场地条件限制,地铁车站施工时往往利用横通道转入主隧道进行施工。因而,横通道安全快速施工对节省地铁车站施工工期有着重要的意义。横通道开挖以后,为了保持围岩的稳定性,一般需要进行初期支护和浇筑衬砌。实际施工时,出于施工工期及开挖风险管理的考虑,二次衬砌可能需要分段浇筑而后再封闭成环,整体性较差,往往导致上下施工面接口处出现渗、漏水现象,尤其在地下水丰富地区,工程质量受到严重影响。Construction of large-span underground tunnels in narrow sites is a common problem in the construction of urban subway stations. Due to site conditions, subway stations often use horizontal passages to transfer into the main tunnel for construction. Therefore, the safe and rapid construction of the horizontal passage is of great significance to save the construction period of the subway station. After the excavation of the transverse channel, in order to maintain the stability of the surrounding rock, initial support and lining are generally required. During actual construction, due to the consideration of construction period and excavation risk management, the secondary lining may need to be poured in sections and then closed into a ring. In areas with abundant groundwater, the quality of the project is seriously affected.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于针对现有技术的缺陷和不足,提供一种结构简单,设计合理、使用方便的小模板拼装浇注二衬的逆作防水方法,解决上下施工面接口处防水难题,加快施工进度,提高二次衬砌的质量,保证横通道乃至车站主隧道安全快速施工。The purpose of the present invention is to aim at the defects and deficiencies of the prior art, to provide a simple structure, reasonable design and convenient use of a small formwork assembling and pouring a reverse waterproofing method for the secondary lining, so as to solve the problem of waterproofing at the interface of the upper and lower construction surfaces and speed up the construction progress. , improve the quality of the secondary lining, and ensure the safe and rapid construction of the cross passage and even the main tunnel of the station.

为实现上述目的,本发明采用的技术方案是:它的施工方法如下:To achieve the above object, the technical scheme adopted in the present invention is: its construction method is as follows:

1、利用上一循环架立的钢架施作隧道侧壁Ф42注浆小导管;利用CD法开挖顶部右导坑上断面和顶部左导坑上断面;喷射封闭掌子面;施作顶部右导坑上断面的导坑周边的初期支护和临时支护,即初喷4CM厚砼,铺设钢筋网,架立型钢钢架和I20a临时钢架,并设锁脚锚杆和定位钢筋;设置系统锚杆后复喷砼至设计厚度;在滞后于顶部右导坑上断面和顶部左导坑上断面一段距离后,再开挖顶部右导坑下端面和顶部左导坑下断面;1. Use the steel frame erected in the previous cycle to apply the Ф42 grouting small duct on the side wall of the tunnel; use the CD method to excavate the upper section of the top right guide pit and the upper section of the top left guide pit; spray the closed face; apply the top The initial support and temporary support around the guide pit on the upper section of the right guide pit, that is, the initial spraying of 4CM thick concrete, the laying of steel mesh, the erection of section steel frame and I20a temporary steel frame, and the setting of locking anchors and positioning steel bars; After setting the system bolt, re-spray concrete to the design thickness; after a certain distance behind the upper section of the top right pilot pit and the upper section of the top left pilot pit, excavate the lower end face of the top right pilot pit and the lower section of the top left pilot pit;

2、拱部开挖支护成型20米后进行顶部右导坑上断面以及顶部左导坑上断面部分的防水系统处理和二次浇注作业;2. After the arch is excavated and supported for 20 meters, the waterproof system treatment and secondary pouring of the upper section of the top right pilot pit and the upper section of the top left pilot pit are carried out;

3、利用台阶法进行中部右导坑上断面、中部有左导坑上断面、中部右导坑下端面和中部左导坑下断面的开挖,左右交叉作业,二衬浇注作业前后错开,施工长度大于15m时进行单侧中部边墙的二衬防水、钢筋、浇筑作业,前次浇注强度达到70%后,进行另一侧中部边墙的二衬浇注作业;3. Use the step method to excavate the upper section of the middle right pilot pit, the upper section of the left pilot pit in the middle, the lower end face of the middle right pilot pit and the lower section of the middle left pilot pit. When the length is greater than 15m, carry out the secondary lining waterproofing, reinforcing bars and pouring operations of the middle side wall on one side. After the previous pouring strength reaches 70%, carry out the secondary lining casting operation of the middle side wall on the other side;

4、利用台阶法进行底部右导坑上断面、底部左导坑上断面、底部右导坑下断面和底部左导坑下断面的开挖,左右侧交叉施作,施工长度大于10m时,施作底部拱部二衬浇注作业,然后再进行单侧底部边墙的二衬防水、钢筋、浇筑作业,二衬浇注作业前后错开,即,当前次浇注强度达到70%后,进行另一侧底部边墙的二衬浇注作业。4. Use the step method to excavate the upper section of the bottom right pilot pit, the upper section of the bottom left pilot pit, the lower section of the bottom right pilot pit and the lower section of the bottom left pilot pit. The left and right sides are crossed. When the construction length is greater than 10m, the Perform the second lining pouring operation of the bottom arch, and then carry out the second lining waterproofing, reinforcing bars, and pouring operations of the bottom side wall on one side. The secondary lining pouring operation of the side wall.

进一步地,所述的步骤2中浇注二衬混凝土一次性浇注20米,强度达到70%后,再进行浇注段下部一侧的开挖。Further, in the step 2, the secondary lining concrete is poured for 20 meters at one time, and after the strength reaches 70%, the excavation of the lower side of the pouring section is carried out.

进一步地,所述的步骤3中的中部边墙浇注控制在5米范围内,其余段边墙浇注控制在15米范围内。Further, the casting of the middle side wall in the step 3 is controlled within a range of 5 meters, and the casting of the remaining side walls is controlled within a range of 15 meters.

进一步地,所述的步骤3和步骤4中的浇注采取整体浇筑的模式,顺作法施工工艺,浇筑长度控制在10米范围内。Further, the pouring in the steps 3 and 4 adopts the mode of integral pouring, and the construction technology is followed by the method, and the pouring length is controlled within the range of 10 meters.

进一步地,所述的步骤1-步骤4的开挖过程中,遇到二衬混凝土连接处时,先进行中槽的弱爆破开挖,边墙采取弱爆破、二氧化碳欲裂和冷开的施工工艺,加强对浆砌片石的保护,完全杜绝爆破对已完成二衬的影响。Further, in the excavation process of the described steps 1 to 4, when encountering the joint of the second lining concrete, the weak blasting excavation of the middle groove is carried out first, and the side wall adopts the construction of weak blasting, carbon dioxide cracking and cold opening. technology, strengthen the protection of the mortar rubble, and completely eliminate the impact of blasting on the completed secondary lining.

采用上述结构后,本发明有益效果为:本发明所述的一种小模板拼装浇注二衬的逆作防水方法,解决上下施工面接口处防水难题,加快施工进度,提高二次衬砌的质量,保证横通道乃至车站主隧道安全快速施工,本发明具有结构简单,设置合理,制作成本低等优点。After the above structure is adopted, the beneficial effects of the present invention are as follows: the retrograde waterproofing method for assembling and pouring the secondary lining with a small formwork according to the present invention solves the problem of waterproofing at the interface of the upper and lower construction surfaces, accelerates the construction progress, and improves the quality of the secondary lining, To ensure the safe and rapid construction of the transverse passage and even the main tunnel of the station, the invention has the advantages of simple structure, reasonable setting, low production cost and the like.

附图说明Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to explain the embodiments of the present invention or the technical solutions in the prior art more clearly, the following briefly introduces the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are only These are some embodiments of the present invention. For those of ordinary skill in the art, other drawings can also be obtained according to these drawings without creative efforts.

图1是本发明的断面示意图。Figure 1 is a schematic sectional view of the present invention.

图2是本发明中顶部右导坑上断面以及顶部左导坑上断面施工立面图。Figure 2 is a construction elevation view of the upper section of the top right guide pit and the upper section of the top left guide pit in the present invention.

图3是本发明中顶部右导坑上断面以及顶部左导坑上断面施工平面图。Figure 3 is a construction plan view of the upper section of the top right guide pit and the upper section of the top left guide pit in the present invention.

图4是本发明中中部右导坑上断面以及中部左导坑上断面施工立面图。4 is a construction elevation view of the upper section of the middle right pilot pit and the upper section of the middle left pilot pit of the present invention.

图5是本发明中中部右导坑上断面以及中部左导坑上断面施工平面图。5 is a construction plan view of the upper section of the middle right pilot pit and the upper section of the middle left pilot pit in the present invention.

图6是本发明中底部右导坑上断面以及底部左导坑上断面施工立面图。Fig. 6 is the construction elevation view of the upper section of the bottom right guide pit and the upper section of the bottom left guide pit in the present invention.

图7是本发明中底部右导坑上断面以及底部左导坑上断面施工平面图。7 is a construction plan view of the upper section of the bottom right guide pit and the upper section of the bottom left guide pit in the present invention.

图8是本发明中施工缝处钢筋接头以及防水处理施工措施图。FIG. 8 is a drawing of the steel bar joint at the construction joint and the construction measures for waterproof treatment in the present invention.

图9是本发明中施工缝混凝土浇筑不紧密的处理施工措施图。FIG. 9 is a drawing of the construction measures for the treatment of incompact concrete pouring of construction joints in the present invention.

附图标记说明:Description of reference numbers:

顶部右导坑上断面1、顶部右导坑下端面1-1、顶部左导坑上断面2、顶部左导坑下断面2-1、中部右导坑上断面3、中部右导坑下端面3-1、中部有左导坑上断面4、中部左导坑下断面4-1、底部右导坑上断面5、底部右导坑下断面5-1、底部左导坑上断面6、底部左导坑下断面6-1、顶部拱部7、中部边墙8、底部边墙9、底部拱部10、衬砌模板11、浆砌片石12、防水板材13、钢板14、可绕注浆管15。Top right pilot pit upper section 1, top right pilot pit bottom face 1-1, top left pilot pit upper section 2, top left pilot pit lower section 2-1, middle right pilot pit upper section 3, middle right pilot pit lower end face 3-1. There is an upper section of the left guide pit in the middle section 4, a lower section of the left guide pit in the middle section 4-1, an upper section of the bottom right guide pit 5, a lower section of the bottom right guide pit 5-1, an upper section of the bottom left guide pit 6, the bottom Left pilot pit lower section 6-1, top arch 7, middle side wall 8, bottom side wall 9, bottom arch 10, lining formwork 11, grout rubble 12, waterproof board 13, steel plate 14, grouting pipe 15.

具体实施方式Detailed ways

下面结合附图对本发明作进一步的说明。The present invention will be further described below in conjunction with the accompanying drawings.

参看如图1-图9所示,本具体实施方式应用实施于贵阳轨道交通2#线观水路车站2号风亭横通道施工。观水路站2号风亭位于观水路站-YDK36+300段区间左隧道左侧民房区内,横通道中线与路线相交于ZDK36+136.287里程处,横通道与正洞相连,与正洞正交。2号风亭竖井内净空尺寸为6.6*15m,井深32.998m;横通道长51.03m,开挖宽*高=12.26*18.293m,竖井所处地层至上而下依次为砼地面,人工杂填土,红黏土,三叠系下统安顺组白云岩,井身主要位于白云岩内;横通道顶拱埋深14.7-16.5m,拱顶基岩厚0.3-4.2m。Referring to Fig. 1-Fig. 9, this specific embodiment is applied and implemented in the construction of the horizontal passage of the wind pavilion on the No. 2 Guanshui Road Station of Guiyang Rail Transit Line 2#. No. 2 wind pavilion at Guanshui Road Station is located in the residential area on the left side of the left tunnel in the section between Guanshui Road Station and YDK36+300. The middle line of the cross passage intersects the route at the mileage of ZDK36+136.287. The cross passage is connected to the main hole and is orthogonal to the main hole. . The clearance size in the shaft of No. 2 wind pavilion is 6.6*15m, and the well depth is 32.998m; the length of the horizontal passage is 51.03m, and the excavation width*height=12.26*18.293m. , red clay, dolomite of the Lower Triassic Anshun Formation, the wellbore is mainly located in the dolomite; the depth of the top arch of the transverse channel is 14.7-16.5m, and the thickness of the vault bedrock is 0.3-4.2m.

本具体实施方式的施工方法如下:The construction method of this specific embodiment is as follows:

1、利用上一循环架立的钢架施作隧道侧壁Ф42注浆小导管;利用CD法开挖顶部右导坑上断面1和顶部左导坑上断面2;喷射封闭掌子面;施作顶部右导坑上断面的导坑周边的初期支护和临时支护,即初喷4CM厚砼,铺设钢筋网,架立型钢钢架和I20a临时钢架,并设锁脚锚杆和定位钢筋;设置系统锚杆后复喷砼至设计厚度;在滞后于顶部右导坑上断面1和顶部左导坑上断面2一段距离后,开挖顶部右导坑下端面1-1和顶部左导坑下断面2-1;1. Use the steel frame erected in the previous cycle to apply the Ф42 grouting small pipe on the side wall of the tunnel; use the CD method to excavate the upper section 1 of the top right pilot pit and the upper section 2 of the top left pilot pit; spray the closed tunnel face; For the initial support and temporary support around the guide pit on the upper section of the right guide pit at the top, that is, initial spraying of 4CM thick concrete, laying steel mesh, erecting profiled steel frame and I20a temporary steel frame, and setting up locking anchors and positioning Reinforcing bars; re-spray concrete to the design thickness after setting the system bolt; after a certain distance behind the top right pilot pit upper section 1 and the top left pilot pit upper section 2, excavate the lower end face 1-1 of the top right pilot pit and the top left pilot pit The lower section of the guide pit is 2-1;

2、拱部开挖支护成型20米后,安装拱部二衬多功能组装台车,设计小模板拼装的方案浇筑顶部拱部7的混凝土;2. After the arch is excavated and supported for 20 meters, install the multi-functional assembly trolley for the second lining of the arch, and design a plan for small formwork assembly to pour the concrete of the top arch 7;

3、利用台阶法进行中部右导坑上断面3、中部有左导坑上断面4、中部右导坑下端面3-1和中部左导坑下断面4-1的开挖,左右交叉作业,二衬浇注作业前后错开,施工长度大于15m时进行单侧中部边墙8的二衬防水、钢筋、浇筑作业,前次浇注强度达到70%后,进行另一侧中部边墙8的二衬浇注作业;3. Use the step method to excavate the upper section 3 of the middle right pilot pit, the upper section 4 of the left pilot pit in the middle, the lower end face 3-1 of the middle right pilot pit and the lower section 4-1 of the middle left pilot pit, and the left and right crossing operations. The secondary lining is staggered before and after the pouring operation. When the construction length is greater than 15m, the secondary lining waterproofing, reinforcing bars and pouring operations of the middle side wall 8 on one side are performed. After the previous casting strength reaches 70%, the secondary lining casting of the middle side wall 8 on the other side is performed. Operation;

4、利用台阶法进行底部右导坑上断面5、底部左导坑上断面6、底部右导坑下断面5-1和底部左导坑下断面6-1的开挖,左右侧交叉施作,施工长度大于10m时,施作底部拱部10二衬浇注作业,然后再进行单侧底部边墙9的二衬防水、钢筋、浇筑作业,二衬浇注作业前后错开,即,当前次浇注强度达到70%后,进行另一侧底部边墙9的二衬浇注作业。4. Use the step method to excavate the upper section 5 of the bottom right pilot pit, the upper section 6 of the bottom left pilot pit, the lower section 5-1 of the bottom right pilot pit and the lower section 6-1 of the bottom left pilot pit, and the left and right sides are crossed. , when the construction length is greater than 10m, perform the second lining pouring operation of the bottom arch 10, and then carry out the second lining waterproofing, reinforcing bars, and pouring operations of the unilateral bottom side wall 9. The second lining pouring operation is staggered before and after, that is, the current casting strength After reaching 70%, the secondary lining pouring operation of the bottom side wall 9 on the other side is carried out.

进一步地,所述的步骤2中浇注二衬混凝土一次性浇注20米,强度达到70%后,再进行浇注段下部一侧的开挖。Further, in the step 2, the secondary lining concrete is poured for 20 meters at one time, and after the strength reaches 70%, the excavation of the lower side of the pouring section is carried out.

进一步地,所述的步骤3中的中部边墙8浇注控制在5米范围内,其余段边墙浇注控制在15米范围内。Further, the casting of the middle side wall 8 in the step 3 is controlled within a range of 5 meters, and the casting of the remaining side walls is controlled within a range of 15 meters.

进一步地,所述的步骤3和步骤4中的浇注采取整体浇筑的模式,顺作法施工工艺,浇筑长度控制在10米范围内。Further, the pouring in the steps 3 and 4 adopts the mode of integral pouring, and the construction technology is followed by the method, and the pouring length is controlled within the range of 10 meters.

进一步地,所述的步骤1-步骤4的开挖过程中,遇到二衬混凝土连接处时,先进行中槽的弱爆破开挖,边墙采取弱爆破、二氧化碳欲裂和冷开的施工工艺,加强对浆砌片石的保护,完全杜绝爆破对已完成二衬的影响。Further, in the excavation process of the described steps 1 to 4, when encountering the joint of the second lining concrete, the weak blasting excavation of the middle groove is carried out first, and the side wall adopts the construction of weak blasting, carbon dioxide cracking and cold opening. technology, strengthen the protection of the mortar rubble, and completely eliminate the impact of blasting on the completed secondary lining.

进一步地,所述的顶部拱部7、中部边墙8、底部边墙9以及底部拱部10的施工缝处需要进行钢筋接头及防水处理,流程如下:在顶部拱部7的混凝土浇筑前,预留钢筋,底部和侧面铺设模板11,模板11下用方浆砌片石12至基岩面,浇筑中部边墙8前完成对浆砌片石12的保护和加固(必要时挂网喷射混凝土),上下钢筋通过接驳器连接,防水板13受填充细砂的保护,均不会受到破坏,浆砌片石12上方钢板设置成10%的倾角,成型以后的二次衬砌将“外低内高”,有利于防止地下水回流。Further, the construction joints of the described top arch 7, the middle side wall 8, the bottom side wall 9 and the bottom arch 10 need to carry out steel bar joints and waterproof treatment, and the process is as follows: before the concrete pouring of the top arch 7, Reserving steel bars, laying formwork 11 at the bottom and sides, and laying rubble 12 under formwork 11 to the bedrock surface. Before pouring the middle side wall 8, complete the protection and reinforcement of the rubble 12 (if necessary, hang the net to spray concrete), The upper and lower steel bars are connected by connectors, and the waterproof plate 13 is protected by filling fine sand and will not be damaged. The steel plate above the mortar rubble 12 is set at a 10% inclination angle, and the secondary lining after forming will be "low outside and high inside" , help prevent groundwater backflow.

进一步地,所述的顶部拱部7、中部边墙8、底部边墙9以及底部拱部10的施工缝处的施工缝止水带处预埋可绕注浆管15,采取后回填水泥浆液的工艺处理,横向、纵向均布设注浆管,且注浆管两头引出浇筑面,目的在于为了整体连接处的密实。Further, the construction joint waterstops at the construction joints of the top arch 7, the middle side wall 8, the bottom side wall 9 and the bottom arch 10 are pre-buried and can be wrapped around the grouting pipe 15, and the backfill cement slurry is taken. The grouting pipe is arranged horizontally and vertically, and the two ends of the grouting pipe lead out of the pouring surface, the purpose is to make the overall connection dense.

本具体实施方式中的Φ42注浆小导管,壁厚4.0mm,L=3.5m,环向间距0.35m,纵向间距1.5m,外插角5~7°,小导管搭接长度不小于1m, 注浆加固地层,土方开挖每榀开挖进尺为0.5m,开挖时严禁掏底施工,由上至下逐层开挖,土方开挖完成后对欠挖部分进行处理,初喷40mm厚混凝土。钢架:I25b型钢钢架全环设置,间距0.5m/榀。系统锚杆:拱部采用Φ32注浆钢花管,外插角为60°,环纵间距1.0*1.0m,梅花形布置,L=3.5m,壁厚3mm,前部钻注浆孔,孔径6~8mm,孔间距20cm,尾部预留不小于30cm的止浆段,Φ32注浆钢花管注浆参数参照超前小导管注浆参数办理;边墙采用Φ22砂浆锚杆,L=4.5m;锚杆间距:1.0*1.0m(环*纵),梅花形布置。钢筋网:Φ8钢筋,构成20*20cm网格,全环设置;钢筋网应与锚杆尾端焊接牢固。The Φ42 grouting small duct in this specific embodiment has a wall thickness of 4.0 mm, L=3.5 m, a circumferential spacing of 0.35 m, a longitudinal spacing of 1.5 m, an outer gusset angle of 5 to 7°, and the overlapping length of the small duct is not less than 1 m. The stratum is reinforced by grouting. The excavation footage of each excavation is 0.5m. During excavation, it is strictly forbidden to excavate the bottom. The excavation is carried out layer by layer from top to bottom. concrete. Steel frame: I25b steel frame is set in full ring, with a spacing of 0.5m/square. System bolt: The arch adopts Φ32 grouting steel flower tube, the outer angle is 60°, the longitudinal spacing of the ring is 1.0*1.0m, the plum blossom-shaped arrangement, L=3.5m, the wall thickness is 3mm, and the front part is drilled with grouting holes, with a diameter of 6 ~8mm, the hole spacing is 20cm, and a grouting section of not less than 30cm is reserved at the tail. The grouting parameters of the Φ32 grouting steel flower tube are handled with reference to the grouting parameters of the advanced small pipe; the side wall adopts the Φ22 mortar bolt, L=4.5m; Spacing: 1.0*1.0m (ring*longitudinal), plum-shaped arrangement. Reinforcement mesh: Φ8 steel bars, forming a 20*20cm grid, set in a full ring; the reinforcement mesh should be firmly welded to the end of the anchor rod.

采用上述结构后,本具体实施方式有益效果为:After adopting the above structure, the beneficial effects of this specific embodiment are:

横通道开挖以后,现有技术待车站和区间隧道施工完成以后进行二次衬砌。但实际施工过程中,各开挖步开挖风险可能较大,施工工期较短,必须进行采用分段分时浇筑二次衬砌时,相应的防水措施过于简单,并不能较好的解决上下施工面接口处渗、漏水问题,本发明结合现场施工经验,充分考虑施工实际,基于传统施工方法,提出新的防水方法以解决现有技术缺点。After the excavation of the horizontal passage, the existing technology is to carry out secondary lining after the completion of the construction of the station and section tunnels. However, in the actual construction process, the excavation risk of each excavation step may be relatively large, and the construction period is short. When the secondary lining must be poured in sections and time-sharing, the corresponding waterproof measures are too simple and cannot solve the upper and lower construction well. To solve the problems of seepage and water leakage at the surface interface, the present invention combines the on-site construction experience, fully considers the construction practice, and proposes a new waterproof method based on the traditional construction method to solve the shortcomings of the existing technology.

以上所述,仅用以说明本发明的技术方案而非限制,本领域普通技术人员对本发明的技术方案所做的其它修改或者等同替换,只要不脱离本发明技术方案的精神和范围,均应涵盖在本发明的权利要求范围当中。The above is only used to illustrate the technical solution of the present invention and not to limit it. Other modifications or equivalent replacements made by those of ordinary skill in the art to the technical solution of the present invention, as long as they do not depart from the spirit and scope of the technical solution of the present invention, should be Included within the scope of the claims of the present invention.

Claims (1)

1. A reverse waterproof method for assembling and pouring a second lining by a small template is characterized by comprising the following steps: the construction method comprises the following steps:
(1) constructing a small grouting guide pipe on the side wall phi 42 of the tunnel by using the steel frame erected in the previous cycle; excavating an upper section of the top right pilot tunnel and an upper section of the top left pilot tunnel by using a CD method; spraying a closed palm surface; constructing primary support and temporary support at the periphery of the guide pit of the upper section of the right guide pit at the top, namely initially spraying 4CM thick concrete, laying a steel bar mesh, erecting a steel frame and an I20a temporary steel frame, and arranging a foot locking anchor rod and a positioning steel bar; after setting a system anchor rod, re-spraying concrete to the designed thickness; after lagging behind the upper section of the top right pilot pit and the upper section of the top left pilot pit by a certain distance, excavating the lower end face of the top right pilot pit and the lower section of the top left pilot pit, in the excavating process, when meeting the joint of the two linings of concrete, firstly performing weak blasting excavation of a middle groove, and adopting the construction process of weak blasting, carbon dioxide presplitting and cold opening on a side wall to strengthen the protection of the grouted rubble and completely avoid the influence of blasting on the completed two linings;
(2) after arch excavation supporting and forming is carried out for 20 meters, waterproof system treatment and secondary pouring operation of the upper section of the right pilot tunnel at the top and the upper section of the left pilot tunnel at the top are carried out, secondary lining concrete is poured for 20 meters at one time, after the strength reaches 70%, excavation of one side of the lower part of a pouring section is carried out, in the excavation process, when the joint of the secondary lining concrete is met, weak blasting excavation of a middle groove is carried out firstly, and the side wall adopts the construction processes of weak blasting, carbon dioxide presplitting and cold opening, so that the protection of grouted rubble stones is enhanced, and the influence of blasting on the completed secondary lining is completely avoided;
(3) excavating the upper section of the middle right pilot tunnel, the upper section of the middle left pilot tunnel, the lower end surface of the middle right pilot tunnel and the lower section of the middle left pilot tunnel by using a step method, controlling the pouring of the middle side wall within the range of 5 meters, controlling the pouring of the other side walls within 15m, performing left-right cross operation, staggering the front and back of the second lining pouring operation, performing the second lining waterproof, reinforcing steel bar and pouring operation of the middle side wall on one side when the construction length is more than 15m, and after the previous pouring strength reaches 70%, performing secondary lining pouring operation of the side wall at the middle part of the other side, wherein the pouring adopts an integral pouring mode and a sequential construction method, the pouring length is controlled within 10 meters, and when a joint of secondary lining concrete is encountered in the excavation process, weak blasting excavation of the middle groove is firstly carried out, and the side wall adopts the construction processes of weak blasting, carbon dioxide presplitting and cold cracking, so that the protection of the grouted rubble is enhanced, and the influence of blasting on the finished secondary lining is completely avoided;
(4) excavating the upper section of the bottom right pilot tunnel, the upper section of the bottom left pilot tunnel, the lower section of the bottom right pilot tunnel and the lower section of the bottom left pilot tunnel by using a step method, performing crossed construction on the left side and the right side, performing secondary lining pouring operation on the arch part of the bottom when the construction length is more than 10m, then carrying out two-lining waterproof, reinforcing steel bar and pouring operation of the side wall at the bottom of the single side, wherein the two-lining pouring operation is staggered from front to back, namely, after the current casting strength reaches 70%, the two-lining casting operation of the bottom side wall at the other side is carried out, the casting adopts an integral casting mode, the construction process is carried out by a sequential method, the casting length is controlled within 10 meters, when the joint of the two-lining concrete is encountered in the excavation process, weak blasting excavation of the middle groove is firstly carried out, and the side wall adopts the construction processes of weak blasting, carbon dioxide presplitting and cold cracking, so that the protection of the grouted rubble is enhanced, and the influence of blasting on the finished secondary lining is completely avoided.
CN201910049724.8A 2019-01-18 2019-01-18 A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork Active CN109736843B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910049724.8A CN109736843B (en) 2019-01-18 2019-01-18 A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910049724.8A CN109736843B (en) 2019-01-18 2019-01-18 A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork

Publications (2)

Publication Number Publication Date
CN109736843A CN109736843A (en) 2019-05-10
CN109736843B true CN109736843B (en) 2020-06-19

Family

ID=66365300

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910049724.8A Active CN109736843B (en) 2019-01-18 2019-01-18 A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork

Country Status (1)

Country Link
CN (1) CN109736843B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593893B (en) * 2019-11-01 2024-04-12 中建八局轨道交通建设有限公司 Main body structure construction method and system at intersection of main tunnel and construction transverse channel

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1563671A (en) * 2004-03-19 2005-01-12 刘昌用 Dormant digging and separating construction method for underground two layers and multilayer composite lining structure
CN101067374A (en) * 2007-02-13 2007-11-07 铁道第二勘察设计院 Single-hole double-layer overlapping tunnel structure and its construction method
CN104806251B (en) * 2015-04-27 2017-05-17 北京市轨道交通建设管理有限公司 Subsidiary inverted excavation construction method for urban subway station under complex environment
CN108005660A (en) * 2017-11-16 2018-05-08 党文华 A kind of Optimization of Expressway Tunnel Construction method

Also Published As

Publication number Publication date
CN109736843A (en) 2019-05-10

Similar Documents

Publication Publication Date Title
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN105041349B (en) A kind of excavating construction method that station is digged on the basis of Subway Tunnel shield tunnel
CN106761778B (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
JP7394252B1 (en) Protruding type wind duct structure perpendicular to the vertical direction and construction method at deep subway station
CN108412501B (en) Under wear oil pipeline shallow depth loess tunnels construction method
CN110905530B (en) Stability control construction method for water-rich soft rock tunnel penetrating fault fracture zone
CN105003272B (en) Reversed construction method for expanding and excavating stations on sectional shield tunnel foundations of subways
CN105064397B (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN105201516B (en) A kind of main structure of subway station and its tetrad arch PBA excavating construction methods
CN105156121A (en) Construction method of large-cross section loess tunnel cave entering shallow buried section
CN101929340A (en) Construction technology of pre-grouting and advance support for pipe shed in horizontal inclined roadway in coal mine
CN106703814A (en) Mined metro station hole pile construction method
CN111677520A (en) Construction method of excavating station structure by tunnel first and then station pipe curtain hole pile method
CN107939415A (en) Stay the micro- two step constructions method of Core Soil in the soft plastic clay tunnel of Shallow-buried Large-span
CN107905814A (en) Large span loess tunnel top bar CD construction methods
CN207033463U (en) Mine shield handing-over tunnel folded type joint design in the middle part of marine site
CN112443331B (en) Disturbance sensitive stratum ultra-small clear distance large section group-hole parallel subway tunnel construction method
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure
CN114412509A (en) A support method suitable for large deformation of mudstone tunnel
CN114542086A (en) Construction method of large-span section underground excavation tunnel influenced by underground water
CN111911169B (en) A shallow buried deep tunnel construction method and structure under an existing railway line
CN109736843B (en) A kind of retrograde waterproofing method of assembling and pouring secondary lining with small formwork
CN205036388U (en) Block of four encircles knot hunch construction structures that PBA secretly dug subway station
CN105178355B (en) The stratum pre-reinforcement processing method of underground space construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant