CN109703694B - 一种锚台整体的单分段预装方法 - Google Patents

一种锚台整体的单分段预装方法 Download PDF

Info

Publication number
CN109703694B
CN109703694B CN201811652994.XA CN201811652994A CN109703694B CN 109703694 B CN109703694 B CN 109703694B CN 201811652994 A CN201811652994 A CN 201811652994A CN 109703694 B CN109703694 B CN 109703694B
Authority
CN
China
Prior art keywords
anchor
layer
subsection
section
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811652994.XA
Other languages
English (en)
Other versions
CN109703694A (zh
Inventor
张棚
高志刚
尉燕
高军连
李剑博
韩宏宇
王宏波
刘崇臻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghaiguan Shipbuilding Industry Co ltd
Original Assignee
Shanghaiguan Shipbuilding Industry Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghaiguan Shipbuilding Industry Co ltd filed Critical Shanghaiguan Shipbuilding Industry Co ltd
Priority to CN201811652994.XA priority Critical patent/CN109703694B/zh
Publication of CN109703694A publication Critical patent/CN109703694A/zh
Application granted granted Critical
Publication of CN109703694B publication Critical patent/CN109703694B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

一种锚台整体的单分段预装方法,包括以下步骤:第一步,将艏部的船体划分为上层分段和下层分段,其中上层分段包括艏楼甲板以及锚台整体安装所通过的位置,下层分段包括去除锚台整体安装位置后的主甲板;同时将锚台、锚唇和锚链筒组装为锚台整体;上层分段和下层分段对应锚台整体安装所在位置的外板分段缝为等腰梯形;第二步,分别对上层分段和下层分段进行建造,其中锚台整体安装在上层分段上;第三步:对上层分段和下层分段进行正态总组。本发明将锚台、锚唇、锚链筒在分段阶段预装到一个分段里,避免跨分段合拢口施工,即分段划分阶段将锚台、锚唇、锚链筒及部分主甲板结构一起划分到一个分段里,具有定位精确、安装难度低和缩短总组周期的优点。

Description

一种锚台整体的单分段预装方法
技术领域
本发明涉及船舶建造技术领域,具体的说是一种锚台整体的单分段预装方法。
背景技术
锚台、锚唇和锚链筒统称为锚台整体。其中,锚链筒在船舶起、抛锚时作为锚链的通道,锚链筒由甲板链孔、舷边链孔和筒体组成。锚台是位于锚链筒外板出口处的凸台结构,作用是起、抛锚时防止锚对外板的碰撞,锚台前端安装锚唇。锚唇是位于锚链筒外板出口处,承受锚的碰撞力和摩擦并使锚稳定服帖地处于收藏位置的椭圆形环状结构。
缩短船舶建造总组及搭载周期是各大船厂研究的大课题,针对锚台、锚唇、锚链筒安装阶段的问题,目前有两种方案:
一种是传统的施工工艺,将艏部的艏楼甲板和主甲板分别划分为上下层两个分段,这两个分段分别底部朝上进行反向建造,同时将锚台、锚唇和锚链筒单独建造为一个整体,待这两个分段分别翻身后进行正向总组,在坞内合拢前将两个分段提前预合拢形成一个大的总段。完成后,再将锚台整体带锚链筒从下向上倒插入艏部外板进行定位安装,此工艺需要考虑总段总组时的整体高度以便锚台带锚链筒能够插入分段,通常情况下需要将分段整体架高才能满足要求。
另一种是改进后的工艺方案,将艏部的艏楼甲板和主甲板分别划分为上下层两个分段,将锚链筒从中间断开,上部分在分段阶段安装到上层分段,锚台和下部分锚链筒安装到下层分段,两个分段再进行正向总组,对接锚链筒。此工艺需要将锚链筒断开,锚链筒在总组阶段对接施工极为不方便,且对于锚台定位及锚链筒精度控制较为困难。
发明内容
本发明需要解决的技术问题是提供一种定位精确、安装难度低并能缩短总组周期的锚台整体的单分段预装方法。
为解决上述技术问题,本发明所采用的技术方案是:
一种锚台整体的单分段预装方法,包括以下步骤:
第一步,将艏部的船体划分为上层分段和下层分段,其中上层分段包括艏楼甲板以及锚台整体的安装位置,下层分段包括去除锚台整体安装位置后的主甲板;同时将锚台、锚唇和锚链筒组装为锚台整体;
第二步,分别对上层分段和下层分段进行建造,其中锚台整体安装在上层分段上;
第三步:对上层分段和下层分段进行总组。
上述锚台整体的单分段预装方法,其进一步改进在于:所述第一步中上层分段和下层分段对应锚台整体所在安装位置的分段缝为等腰梯形。
上述锚台整体的单分段预装方法,其进一步改进在于:所述第二步中,上层分段和下层分段的建造方式为反向建造,下层分段以主甲板面为胎板,上层分段以艏楼甲板为胎板,锚台整体安装在上层分段上。
上述锚台整体的单分段预装方法,其进一步改进在于:所述第三步中,上层分段和下层分段的总组方式为正态总组:首先将完成建造的下层分段后翻身为主甲板向上,正放于地面上;然后将完成建造的上层分段翻身后落于下层分段上方,进行正态总组。
本发明在采用上述技术方案后,具有如下技术进步的效果:
本发明将锚台、锚唇、锚链筒在分段阶段预装到一个分段里,避免跨分段合拢口施工,即分段划分阶段将锚台、锚唇、锚链筒及部分主甲板结构一起划分到一个分段里。先将锚台、锚唇及锚链筒进行组合装配为一个整体,在分段反向建造阶段,再将锚链筒带锚台和锚唇一起从上向下由外板穿入分段内,实现安装。总组阶段,上层分段带锚台区域的外板及主甲板,整体插入下层分段,合拢完成。本发明可以应用于所有有锚台的船舶建造,如原油轮、散货船、化学品船、各类工程船等。
本发明锚台整体在单个分段预装具有以下优点:1、方便锚台在分段预装时精确定位;2、分段反向安装锚台,降低锚台安装难度;3、锚台安装工序前移,缩短总组周期;4、避免锚台区域外板油漆的破坏。
附图说明
图1为本发明外板分段缝划分的侧视图;
图2为本发明主甲板分段缝划分的俯视图;
图3为本发明下层分段反向建造的示意图;
图4为本发明上层分段反向建造的示意图;
图5是本发明上层分段和下层分段正态组装的示意图。
图中各标号分别表示为:1、上层分段,2、下层分段,3、锚台整体,4、艏楼甲板,5、主甲板,6、分段缝。
具体实施方式
下面结合附图及实施例对本发明做进一步详细说明:
本发明涉及一种锚台整体的单分段预装方法,包括以下步骤:
第一步,将艏部的船体划分为上层分段1和下层分段2。同时将锚台、锚唇和锚链筒组装为锚台整体3。上层分段1包括艏楼甲板4以及锚台整体3安装时所对应的位置,其中锚台整体3的安装位置包括上部与艏楼甲板4连接的地方,还包括与艏楼甲板4下方的主甲板5部分连接的地方。下层分段2包括去除锚台整体安装位置的主甲板5。如图1和图2所示,上层分段1和下层分段2的分段缝6整体为直线,对应锚台整体3所在安装位置的分段缝6为等腰梯形。
第二步,分别对上层分段1和下层分段2进行反向建造,下层分段2以主甲板5面为胎板,反向建造如图3所示,上层分段1以艏楼甲板4为胎板,将锚台整体3全部都安装在上层分段上,反向建造如图4所示。
第三步:对上层分段1和下层分段2进行正态总组。如图5所示,首先将完成建造的下层分段2后翻身为主甲板5向上,正放于地面上;然后将完成建造的上层分段1翻身后落于下层分段2上方,进行正态总组。

Claims (1)

1.一种锚台整体的单分段预装方法,其特征在于,包括以下步骤:
第一步,将艏部的船体划分为上层分段(1)和下层分段(2),其中上层分段(1)包括艏楼甲板(4)以及锚台整体(3)的安装位置,下层分段(2)包括去除锚台整体安装位置后的主甲板(5);同时将锚台、锚唇和锚链筒组装为锚台整体(3);
第二步,分别对上层分段(1)和下层分段(2)进行建造,其中锚台整体(3)安装在上层分段(1)上;
第三步:对上层分段(1)和下层分段(2)进行总组;
所述第二步中,上层分段(1)和下层分段(2)的建造方式为反向建造,下层分段以主甲板(5)面为胎板,上层分段以艏楼甲板(4)为胎板;锚台整体(3)安装在上层分段(1)上;
所述第一步中上层分段(1)和下层分段(2)对应锚台整体(3)所在安装位置的外板分段缝为等腰梯形;
所述第三步中,上层分段(1)和下层分段(2)的总组方式为正态总组:首先将完成建造的下层分段(2)后翻身为主甲板(5)向上,正放于地面上;然后将完成建造的上层分段(1)翻身后落于下层分段(2)上方,进行正态总组;
将锚台、锚唇、锚链筒在分段阶段预装到一个分段里,避免跨分段合拢口施工,即分段划分阶段将锚台、锚唇、锚链筒及部分主甲板结构一起划分到一个分段里;先将锚台、锚唇及锚链筒进行组合装配为一个整体,在分段反向建造阶段,再将锚链筒带锚台和锚唇一起从上向下由外板穿入分段内,实现安装;总组阶段,上层分段带锚台区域的外板及主甲板,整体插入下层分段,合拢完成。
CN201811652994.XA 2018-12-30 2018-12-30 一种锚台整体的单分段预装方法 Active CN109703694B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811652994.XA CN109703694B (zh) 2018-12-30 2018-12-30 一种锚台整体的单分段预装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811652994.XA CN109703694B (zh) 2018-12-30 2018-12-30 一种锚台整体的单分段预装方法

Publications (2)

Publication Number Publication Date
CN109703694A CN109703694A (zh) 2019-05-03
CN109703694B true CN109703694B (zh) 2021-08-06

Family

ID=66260573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811652994.XA Active CN109703694B (zh) 2018-12-30 2018-12-30 一种锚台整体的单分段预装方法

Country Status (1)

Country Link
CN (1) CN109703694B (zh)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112407189A (zh) * 2020-11-26 2021-02-26 江南造船(集团)有限责任公司 超大型船舶艏部锚链筒和锚台的精度建造工艺
CN115320804A (zh) * 2021-05-11 2022-11-11 江南造船(集团)有限责任公司 一种船舶机舱分段建造方法
CN115370201A (zh) * 2021-05-19 2022-11-22 南通振华重型装备制造有限公司 一种换流站上部组块模块化建造工艺
CN113148063A (zh) * 2021-06-03 2021-07-23 江南造船(集团)有限责任公司 一种船锚穴建造方法
CN113998072B (zh) * 2021-11-30 2023-11-07 沪东中华造船(集团)有限公司 一种标准锚台的制造与安装方法

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1455726A (en) * 1972-11-16 1976-11-17 Ijsselveer Bv Method and apparatus for building a ship on a slipway and launching same in the longitudinal direction of the ship
JPS624689A (ja) * 1985-06-29 1987-01-10 Mitsui Eng & Shipbuild Co Ltd 船首上部ブロツクの建造方法
CN101407246A (zh) * 2008-11-14 2009-04-15 大连船舶重工集团有限公司 船舶锚台锚链筒线型光顺与安装方法
CN103010402A (zh) * 2012-12-13 2013-04-03 沪东中华造船(集团)有限公司 一种散货轮锚链筒在分段预装的安装方法
CN103979073A (zh) * 2014-05-26 2014-08-13 上海江南长兴重工有限责任公司 锚台、锚唇及锚链筒分段预装的安装方法
CN104071301A (zh) * 2014-06-12 2014-10-01 沪东中华造船(集团)有限公司 一种散货轮锚唇在分段阶段的预装方法
CN104071300A (zh) * 2014-07-11 2014-10-01 广州文冲船厂有限责任公司 锚台锚唇地面整体预制的安装方法
CN105644714A (zh) * 2015-12-21 2016-06-08 广船国际有限公司 一种锚台部件的制作安装方法
CN107458540A (zh) * 2017-07-31 2017-12-12 上海江南长兴重工有限责任公司 一种船舶锚链筒安装定位方法

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1455726A (en) * 1972-11-16 1976-11-17 Ijsselveer Bv Method and apparatus for building a ship on a slipway and launching same in the longitudinal direction of the ship
JPS624689A (ja) * 1985-06-29 1987-01-10 Mitsui Eng & Shipbuild Co Ltd 船首上部ブロツクの建造方法
CN101407246A (zh) * 2008-11-14 2009-04-15 大连船舶重工集团有限公司 船舶锚台锚链筒线型光顺与安装方法
CN103010402A (zh) * 2012-12-13 2013-04-03 沪东中华造船(集团)有限公司 一种散货轮锚链筒在分段预装的安装方法
CN103979073A (zh) * 2014-05-26 2014-08-13 上海江南长兴重工有限责任公司 锚台、锚唇及锚链筒分段预装的安装方法
CN104071301A (zh) * 2014-06-12 2014-10-01 沪东中华造船(集团)有限公司 一种散货轮锚唇在分段阶段的预装方法
CN104071300A (zh) * 2014-07-11 2014-10-01 广州文冲船厂有限责任公司 锚台锚唇地面整体预制的安装方法
CN105644714A (zh) * 2015-12-21 2016-06-08 广船国际有限公司 一种锚台部件的制作安装方法
CN107458540A (zh) * 2017-07-31 2017-12-12 上海江南长兴重工有限责任公司 一种船舶锚链筒安装定位方法

Also Published As

Publication number Publication date
CN109703694A (zh) 2019-05-03

Similar Documents

Publication Publication Date Title
CN109703694B (zh) 一种锚台整体的单分段预装方法
US6450734B1 (en) Transportation underwater tunnel system
US5609442A (en) Offshore apparatus and method for oil operations
US4059065A (en) Semisubmersible loading mooring and storage facility
JPS61294015A (ja) オフシヨ−プラツトホ−ムの建設工法
JP7266447B2 (ja) セミサブ浮体、及びセミサブ浮体を用いた風車の洋上設置方法
US9446825B1 (en) Self-propelled, catamaran-type, dual-application, semisubmersible ship with hydrodynamic hulls and columns
US11377175B2 (en) Modular ramp system for a landing craft
US3841254A (en) Vessel with removable sections
KR100507853B1 (ko) 자항 바지선
CN1605485A (zh) 能够兼具浅滩靠岸和高速行驶的变形船
US6968795B2 (en) Very large vessel construction
US20080196655A1 (en) Vessels
CN111188324A (zh) 一种海上风电安装平台升降系统水上合拢工艺
CN107187554B (zh) 用于半潜式钻井平台干拖运输的双体半潜驳船及作业方法
KR100785479B1 (ko) 선박용 stl 모듈화 설치방법 및 구조
KR20100123438A (ko) 부유식 항구 및 이를 이용한 선박 화물 하역 방법
KR102376885B1 (ko) 스폰손을 탑재한 코퍼댐의 부력구조
WO2008118082A1 (en) A method of manufacturing a hull of a ship and a hull manufactured in accordance with the method
US5909715A (en) Method of conversion of a vessel from single to double hull
KR20060096761A (ko) 대형 탑재 블록의 대차 탑재에 의한 경사선대에서의 선박건조 공법
JP7436347B2 (ja) 浮体構造物の製造方法
CN205396468U (zh) 一种过闸专用浮力式载驳船
BG98954A (bg) Метод за свързване на модули на плавателни съдове
CN112937781B (zh) 一种快速拼装的机动浮式驳船及拼装方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant