CN109635339A - PCF system simulation link method and system based on BIM - Google Patents

PCF system simulation link method and system based on BIM Download PDF

Info

Publication number
CN109635339A
CN109635339A CN201811346092.3A CN201811346092A CN109635339A CN 109635339 A CN109635339 A CN 109635339A CN 201811346092 A CN201811346092 A CN 201811346092A CN 109635339 A CN109635339 A CN 109635339A
Authority
CN
China
Prior art keywords
bim
pcf
bim technology
construction
dimension model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811346092.3A
Other languages
Chinese (zh)
Inventor
夏静平
施忠平
施智亮
孙鹏飞
刘坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Priority to CN201811346092.3A priority Critical patent/CN109635339A/en
Publication of CN109635339A publication Critical patent/CN109635339A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation

Abstract

The PCF system simulation link method and system based on BIM that the present invention provides a kind of, the present invention gives the effect after the completion of project by the visualization function of BIM technology, unit in charge of construction modifies and multivariant selection on this basis, it is able to solve the problem of PCF system on-site hoisting, installation inconvenience, construction quality is improved, is accelerated construction progress.The present invention can optimize prefabricated components construction and installation process, component error rate when reducing construction, reduce component heap field time at the construction field (site).The present invention can be improved the construction site level of informatization, reduce it is artificial, shorten the construction period.

Description

PCF system simulation link method and system based on BIM
Technical field
The PCF system simulation link method and system based on BIM that the present invention relates to a kind of.
Background technique
Overlapped shear wall (PCF) system is precast facade mould (containing exterior finish, exterior wall overlapping)+cast-in-place shear wall.It is existing PCF system on-site hoisting, installation are inconvenient.
Summary of the invention
The PCF system simulation link method and system based on BIM that the purpose of the present invention is to provide a kind of, are able to solve existing The inconvenient problem of some PCF system on-site hoistings, installation.
To solve the above problems, the present invention provides a kind of PCF system simulation link method based on BIM, comprising:
Step 1 carries out the assembling scheme selection of PCF system by BIM technology when approving and initiate a project;
Step 2 carries out Deepen Design to selected assembling scheme by BIM technology, with selected PCF and concrete knot The assembly of structure is combined;
The assembly combination of selected PCF and concrete structure is carried out STRUCTURE DECOMPOSITION by BIM technology, with right by step 3 Each prefabricated member carries out setting-out in the assembly combination, obtains dimension model;
Step 4 carries out pre-simulated to work progress according to the dimension model, and by BIM technology, judges described pre- Whether simulation has collision problem, if nothing,
Step 5 tell somebody what one's real intentions are and guiding according to the dimension model, and by BIM technology to the assembly construction at scene.
Further, in the above-mentioned methods, the assembly construction at scene tell somebody what one's real intentions are and guiding by BIM technology, comprising:
By BIM technology and mobile terminal, the assembly construction at scene tell somebody what one's real intentions are and guiding.
Further, in the above-mentioned methods, step 4, according to the dimension model, and by BIM technology to work progress Pre-simulated is carried out, after judging whether the pre-simulated has collision problem, further includes:
If so, step 6, optimizes the dimension model according to the collision problem found out, and according to the ruler after optimization Very little model, and the assembly construction at scene tell somebody what one's real intentions are and guiding by BIM technology.
Further, in the above-mentioned methods, the dimension model is optimized according to the collision problem found out, comprising:
Again the step 1 is sequentially carried out to step 4.
Further, in the above-mentioned methods, according to the dimension model after the dimension model or optimization, and pass through BIM skill After art tell somebody what one's real intentions are and and guides to the assembly construction at scene, further includes:
It tells somebody what one's real intentions are and instructs according to described, carry out the on-site hoisting of the PCF system.
Another side according to the present invention provides a kind of PCF system simulation link system based on BIM, comprising:
First device, for carrying out the assembling scheme selection of PCF system when approving and initiate a project by BIM technology;
Second device with selected PCF and is mixed for carrying out Deepen Design to selected assembling scheme by BIM technology The assembly of Xtah Crude Clay structure is combined;
3rd device, for the assembly combination of selected PCF and concrete structure to be carried out structure point by BIM technology Solution obtains dimension model to carry out setting-out to each prefabricated member in assembly combination;
4th device, for carrying out pre-simulated, judgement to work progress according to the dimension model, and by BIM technology Whether the pre-simulated has collision problem;
5th device according to the dimension model, and passes through BIM technology pair if being used for the pre-simulated Lothrus apterus problem The assembly construction at scene tell somebody what one's real intentions are and guiding.
Further, in above system, the 5th device, for passing through BIM technology and mobile terminal, to scene Assembly construction tell somebody what one's real intentions are and guiding.
It further, further include the 6th device in above system, if having collision problem for the pre-simulated, according to The collision problem found out optimizes the dimension model, and according to the dimension model after optimization, and by BIM technology to existing The assembly construction of field tell somebody what one's real intentions are and guiding.
Further, in above system, the 6th device, for first device described in sequential start again to the 4th Device.
It further, further include the 7th device in above system, for telling somebody what one's real intentions are and instructing according to, described in progress The on-site hoisting of PCF system.
Compared with prior art, the present invention gives the effect after the completion of project by the visualization function of BIM technology, applies Work order position is modified and multivariant selection on this basis, is able to solve PCF system on-site hoisting, is installed inconvenient ask Topic improves construction quality, accelerates construction progress.The present invention can optimize prefabricated components construction and installation process, structure when reducing construction Part error rate reduces component heap field time at the construction field (site).The present invention can be improved the construction site level of informatization, reduce people Work shortens the construction period.
Detailed description of the invention
Fig. 1 is the flow chart of the PCF system simulation link method based on BIM of one embodiment of the invention.
Specific embodiment
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing and specific real Applying mode, the present invention is described in further detail.
As shown in Figure 1, the present invention provides a kind of PCF system simulation link method based on BIM, comprising:
Step 1 is carried out the assembling scheme selection of PCF system when approving and initiate a project by BIM technology, provided directly for owner The reference frame of sight;
Step 2 carries out Deepen Design to selected assembling scheme by BIM technology, with selected PCF and concrete knot The assembly of structure is combined;
The assembly combination of selected PCF and concrete structure is carried out STRUCTURE DECOMPOSITION by BIM technology, with right by step 3 Each prefabricated member carries out setting-out in the assembly combination, obtains dimension model;
Step 4 carries out pre-simulated to work progress according to the dimension model, and by BIM technology, judges described pre- Whether simulation has collision problem,
Here, the dimension model can be fining dimension model;
If nothing, step 5 tells somebody what one's real intentions are simultaneously to the assembly construction at scene according to the dimension model, and by BIM technology Guidance.
Here, BIM is the abbreviation of Building Infortion Modeling, which is pushed away from 2002 in North America After wide, the fashionable whole world;Its main line has shaken the traditional two-dintension CAD drawing epoch, will build to the technology subversiveness All relevant informations of project are built all to be integrated among three-dimensional visualization model, and each participant of project exists in each stage of project Formula management and perfect is interacted to the model on particular platform, realizes the seamless handover of each link and the real time information of each side It is shared;Efficiency can be improved using BIM technology, reduce repetition and ineffective labor, promotion fining degree, reduce energy consumption.
The present invention gives the effect after the completion of project by the visualization function of BIM technology, and unit in charge of construction is basic herein On modify and multivariant selection, be able to solve the inconvenient problem of PCF system on-site hoisting, installation, improve construction quality, It accelerates construction progress.The present invention can optimize prefabricated components construction and installation process, and component error rate when reducing construction reduces component Heap field time at the construction field (site).The present invention can be improved the construction site level of informatization, reduce it is artificial, shorten the construction period.
In PCF system simulation one embodiment of link method based on BIM of the invention, by BIM technology to the dress at scene Tell somebody what one's real intentions are and guiding with construction, comprising:
By BIM technology and mobile terminal, the assembly construction at scene tell somebody what one's real intentions are and guiding, with the assembly at the scene of improving Construction tell somebody what one's real intentions are the convenience and guided.
In PCF system simulation one embodiment of link method based on BIM of the invention, step 4, according to the size mould Type, and pre-simulated is carried out to work progress by BIM technology, after judging whether the pre-simulated has collision problem, further includes:
If so, step 6, optimizes the dimension model according to the collision problem found out, and according to the ruler after optimization Very little model, and the assembly construction at scene tell somebody what one's real intentions are and guiding by BIM technology, to improve the accuracy of dimension model.
In PCF system simulation one embodiment of link method based on BIM of the invention, according to the collision problem found out to institute Dimension model is stated to optimize, comprising:
Again the step 1 is sequentially carried out to step 4, to improve setting-out and the dimension model of each prefabricated member Effect of optimization.
In PCF system simulation one embodiment of link method based on BIM of the invention, according to the dimension model or optimization Dimension model afterwards, and after the assembly construction at scene tell somebody what one's real intentions are and and guided by BIM technology, further includes:
It tells somebody what one's real intentions are and instructs according to described, carry out the on-site hoisting of the PCF system, to improve the convenience of on-site hoisting.
The present invention also provides another kinds to simulate link system based on the PCF system of BIM, comprising:
First device is owner for carrying out the assembling scheme selection of PCF system when approving and initiate a project by BIM technology Intuitive reference frame is provided;
Second device with selected PCF and is mixed for carrying out Deepen Design to selected assembling scheme by BIM technology The assembly of Xtah Crude Clay structure is combined;
3rd device, for the assembly combination of selected PCF and concrete structure to be carried out structure point by BIM technology Solution obtains dimension model to carry out setting-out to each prefabricated member in assembly combination;
4th device, for carrying out pre-simulated, judgement to work progress according to the dimension model, and by BIM technology Whether the pre-simulated has collision problem;
5th device according to the dimension model, and passes through BIM technology pair if being used for the pre-simulated Lothrus apterus problem The assembly construction at scene tell somebody what one's real intentions are and guiding.
Here, BIM is the abbreviation of Building Infortion Modeling, which is pushed away from 2002 in North America After wide, the fashionable whole world;Its main line has shaken the traditional two-dintension CAD drawing epoch, will build to the technology subversiveness All relevant informations of project are built all to be integrated among three-dimensional visualization model, and each participant of project exists in each stage of project Formula management and perfect is interacted to the model on particular platform, realizes the seamless handover of each link and the real time information of each side It is shared;Efficiency can be improved using BIM technology, reduce repetition and ineffective labor, promotion fining degree, reduce energy consumption.
The present invention gives the effect after the completion of project by the visualization function of BIM technology, and unit in charge of construction is basic herein On modify and multivariant selection, be able to solve the inconvenient problem of PCF system on-site hoisting, installation, improve construction quality, It accelerates construction progress.The present invention can optimize prefabricated components construction and installation process, and component error rate when reducing construction reduces component Heap field time at the construction field (site).The present invention can be improved the construction site level of informatization, reduce it is artificial, shorten the construction period.
Further, in above system, the 5th device, for passing through BIM technology and mobile terminal, to scene Assembly construction tell somebody what one's real intentions are and guiding, and is constructed and tell somebody what one's real intentions are the convenience and guided with the assembly at the scene of improving.
It further, further include the 6th device in above system, if having collision problem for the pre-simulated, according to The collision problem found out optimizes the dimension model, and according to the dimension model after optimization, and by BIM technology to existing The assembly construction of field tell somebody what one's real intentions are and guiding, to improve the accuracy of dimension model.
Further, in above system, the 6th device, for first device described in sequential start again to the 4th Device, to improve the setting-out of each prefabricated member and the effect of optimization of dimension model.
It further, further include the 7th device in above system, for telling somebody what one's real intentions are and instructing according to, described in progress The on-site hoisting of PCF system, to improve the convenience of on-site hoisting.
Compared with prior art, the present invention gives the effect after the completion of project by the visualization function of BIM technology, applies Work order position is modified and multivariant selection on this basis, is able to solve PCF system on-site hoisting, is installed inconvenient ask Topic improves construction quality, accelerates construction progress.The present invention can optimize prefabricated components construction and installation process, structure when reducing construction Part error rate reduces component heap field time at the construction field (site).The present invention can be improved the construction site level of informatization, reduce people Work shortens the construction period.
Each embodiment in this specification is described in a progressive manner, the highlights of each of the examples are with other The difference of embodiment, the same or similar parts in each embodiment may refer to each other.
Professional further appreciates that, unit described in conjunction with the examples disclosed in the embodiments of the present disclosure And algorithm steps, can be realized with electronic hardware, computer software, or a combination of the two, in order to clearly demonstrate hardware and The interchangeability of software generally describes each exemplary composition and step according to function in the above description.These Function is implemented in hardware or software actually, the specific application and design constraint depending on technical solution.Profession Technical staff can use different methods to achieve the described function each specific application, but this realization is not answered Think beyond the scope of this invention.
Obviously, those skilled in the art can carry out various modification and variations without departing from spirit of the invention to invention And range.If in this way, these modifications and changes of the present invention belong to the claims in the present invention and its equivalent technologies range it Interior, then the invention is also intended to include including these modification and variations.

Claims (10)

1. a kind of PCF system based on BIM simulates link method characterized by comprising
Step 1 carries out the assembling scheme selection of PCF system by BIM technology when approving and initiate a project;
Step 2 carries out Deepen Design to selected assembling scheme by BIM technology, to select PCF and concrete structure Assembly combination;
The assembly combination of selected PCF and concrete structure is carried out STRUCTURE DECOMPOSITION by BIM technology, to described by step 3 Each prefabricated member carries out setting-out in assembly combination, obtains dimension model;
Step 4 carries out pre-simulated to work progress according to the dimension model, and by BIM technology, judges the pre-simulated Whether collision problem is had, if nothing,
Step 5 tell somebody what one's real intentions are and guiding according to the dimension model, and by BIM technology to the assembly construction at scene.
2. the PCF system based on BIM simulates link method as described in claim 1, which is characterized in that pass through BIM technology pair The assembly construction at scene tell somebody what one's real intentions are and guiding, comprising:
By BIM technology and mobile terminal, the assembly construction at scene tell somebody what one's real intentions are and guiding.
3. the PCF system based on BIM simulates link method as described in claim 1, which is characterized in that step 4, according to institute State dimension model, and pre-simulated carried out to work progress by BIM technology, judge the pre-simulated whether have collision problem it Afterwards, further includes:
If so, step 6, optimizes the dimension model according to the collision problem found out, and according to the size mould after optimization Type, and the assembly construction at scene tell somebody what one's real intentions are and guiding by BIM technology.
4. the PCF system based on BIM simulates link method as claimed in claim 3, which is characterized in that according to the conflict found out Problem optimizes the dimension model, comprising:
Again the step 1 is sequentially carried out to step 4.
5. the PCF system based on BIM simulates link method as claimed in claim 3, which is characterized in that according to the size mould Dimension model after type or optimization, and after the assembly construction at scene tell somebody what one's real intentions are and and guided by BIM technology, further includes:
It tells somebody what one's real intentions are and instructs according to described, carry out the on-site hoisting of the PCF system.
6. a kind of PCF system based on BIM simulates link system characterized by comprising
First device, for carrying out the assembling scheme selection of PCF system when approving and initiate a project by BIM technology;
Second device, for carrying out Deepen Design to selected assembling scheme by BIM technology, with selected PCF and concrete The assembly of structure is combined;
3rd device, for the assembly combination of selected PCF and concrete structure to be carried out STRUCTURE DECOMPOSITION by BIM technology, with Setting-out is carried out to each prefabricated member in assembly combination, obtains dimension model;
4th device carries out pre-simulated to work progress for according to the dimension model, and by BIM technology, described in judgement Whether pre-simulated has collision problem;
5th device, if being used for the pre-simulated Lothrus apterus problem, according to the dimension model, and by BIM technology to scene Assembly construction tell somebody what one's real intentions are and guiding.
7. the PCF system based on BIM simulates link system as claimed in claim 6, which is characterized in that the 5th device, For tell somebody what one's real intentions are and guiding to the assembly construction at scene by BIM technology and mobile terminal.
8. the PCF system based on BIM simulates link system as claimed in claim 6, which is characterized in that further include the 6th dress It sets, if having collision problem for the pre-simulated, the dimension model is optimized according to the collision problem found out, and according to Dimension model after optimization, and the assembly construction at scene tell somebody what one's real intentions are and guiding by BIM technology.
9. the PCF system based on BIM simulates link system as claimed in claim 8, which is characterized in that the 6th device, For first device described in sequential start again to the 4th device.
10. the PCF system based on BIM simulates link system as claimed in claim 8, which is characterized in that further include the 7th dress It sets, for telling somebody what one's real intentions are and instructing according to, carries out the on-site hoisting of the PCF system.
CN201811346092.3A 2018-11-13 2018-11-13 PCF system simulation link method and system based on BIM Pending CN109635339A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811346092.3A CN109635339A (en) 2018-11-13 2018-11-13 PCF system simulation link method and system based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811346092.3A CN109635339A (en) 2018-11-13 2018-11-13 PCF system simulation link method and system based on BIM

Publications (1)

Publication Number Publication Date
CN109635339A true CN109635339A (en) 2019-04-16

Family

ID=66067823

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811346092.3A Pending CN109635339A (en) 2018-11-13 2018-11-13 PCF system simulation link method and system based on BIM

Country Status (1)

Country Link
CN (1) CN109635339A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107958101A (en) * 2017-11-07 2018-04-24 山东住工装配建筑有限公司 A kind of assembled architecture Information Management System and method based on BIM
CN107967399A (en) * 2017-12-19 2018-04-27 广东建远建筑装配工业有限公司 A kind of assembled architecture Deepen Design method based on BIM softwares
CN107977487A (en) * 2017-11-07 2018-05-01 山东住工装配建筑有限公司 A kind of assembly concrete architectural design method based on BIM technology
CN108108510A (en) * 2017-10-27 2018-06-01 广东星层建筑科技股份有限公司 A kind of assembled architecture design method and equipment based on BIM
CN108133107A (en) * 2017-12-23 2018-06-08 中冶建筑研究总院有限公司 A kind of FRP- concrete assembly methods based on BIM models
CN108453884A (en) * 2017-12-15 2018-08-28 上海建工五建集团有限公司 Prefabricated components information updating method and system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108108510A (en) * 2017-10-27 2018-06-01 广东星层建筑科技股份有限公司 A kind of assembled architecture design method and equipment based on BIM
CN107958101A (en) * 2017-11-07 2018-04-24 山东住工装配建筑有限公司 A kind of assembled architecture Information Management System and method based on BIM
CN107977487A (en) * 2017-11-07 2018-05-01 山东住工装配建筑有限公司 A kind of assembly concrete architectural design method based on BIM technology
CN108453884A (en) * 2017-12-15 2018-08-28 上海建工五建集团有限公司 Prefabricated components information updating method and system
CN107967399A (en) * 2017-12-19 2018-04-27 广东建远建筑装配工业有限公司 A kind of assembled architecture Deepen Design method based on BIM softwares
CN108133107A (en) * 2017-12-23 2018-06-08 中冶建筑研究总院有限公司 A kind of FRP- concrete assembly methods based on BIM models

Similar Documents

Publication Publication Date Title
Tan et al. Construction-oriented design for manufacture and assembly guidelines
Kim et al. Applicability of 4D CAD in civil engineering construction: Case study of a cable-stayed bridge project
CN104631826A (en) Construction general layout method based on BIM
CN111125814A (en) BIM-based project supervision and supervision method and system
CN107516161A (en) A kind of project progress management-control method based on BIM
CN112257150B (en) BIM modeling-based raft foundation slab band reinforcing rib refined calculation method
CN110991882A (en) Project construction fine management method based on BIM5D
CN106844840A (en) A kind of method that subway station rapid modeling is realized based on BIM
CN115048699A (en) Construction management method based on BIM
CN109635339A (en) PCF system simulation link method and system based on BIM
Rybakova et al. Opportunities to improve the efficiency of design and construction
Chau et al. 4D dynamic construction management and visualization software: 2. Site trial
CN109034551B (en) Resource balancing method for construction planning
CN111535588A (en) System for selecting optimal pouring scheme based on BIM technology
CN116150872A (en) Modeling method, system, equipment and storage medium of complex system digital function prototype
CN114077765B (en) Dynamo project data management method and device based on Dynamo project data management method and device, and computer equipment
CN108846220A (en) A kind of visualization building illumination design method and its system
Huang et al. System development for non-unit based repetitive project scheduling
CN109472084A (en) Assembled architecture design method and system, computer equipment and storage medium
CN114037817A (en) Three-dimensional simulation drilling system and construction method thereof
CN1997191A (en) A method for animation display in the mobile communication terminal
Thabet Design/construction integration thru virtual construction for improved constructability
Yusof et al. Industrialised building system (IBS)/Off-Site project management life cycle
Al-Assaf et al. Representing the Aesthetics of Richard Meier’s Houses Using Building Information Modeling
Fernando et al. A review of simulation applications for varying demands in tunneling

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190416