CN111125814A - BIM-based project supervision and supervision method and system - Google Patents

BIM-based project supervision and supervision method and system Download PDF

Info

Publication number
CN111125814A
CN111125814A CN201911204344.3A CN201911204344A CN111125814A CN 111125814 A CN111125814 A CN 111125814A CN 201911204344 A CN201911204344 A CN 201911204344A CN 111125814 A CN111125814 A CN 111125814A
Authority
CN
China
Prior art keywords
construction
model
project
progress
models
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201911204344.3A
Other languages
Chinese (zh)
Inventor
顾客
刘军
李爽
李恒超
费永胜
戴卫惠
陈献奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Co Construction Project Supervision Consulting Co ltd
Original Assignee
Shanghai Co Construction Project Supervision Consulting Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Co Construction Project Supervision Consulting Co ltd filed Critical Shanghai Co Construction Project Supervision Consulting Co ltd
Priority to CN201911204344.3A priority Critical patent/CN111125814A/en
Publication of CN111125814A publication Critical patent/CN111125814A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Primary Health Care (AREA)

Abstract

The invention relates to the technical field of building construction supervision management, and discloses a project supervision method and a project supervision system based on BIM, wherein the method comprises the following steps: building a project BIM model according to the national building design standard, wherein the project has subunits; acquiring construction information to construct a three-level model, compiling a construction progress plan and generating four-dimensional progress simulation with the three-level model; generating a plurality of sub-models for the four-dimensional progress simulation, comparing the sub-models with the sub-units one by one, and evaluating whether the construction scheme of the construction party is reasonable or not according to the time consumption of the comparison result; judging the place with the evaluation value larger than the set occupation ratio as the area to be optimized, submitting the area to be optimized to a designer, a proctoring party and a construction party for approval, attaching a plurality of approval results to the area to be optimized, and finally pushing the approval results to the designer according to the time sequence generated by the approval results, wherein the generated results are pushed first and then the system obtains the approval results obtained by the designer after being pushed; the real-time performance of the supervision system and the effectiveness of the result obtained by analysis and discussion are ensured.

Description

BIM-based project supervision and supervision method and system
Technical Field
The invention relates to the technical field of building construction supervision management, in particular to a project supervision method and system based on BIM.
Background
The construction supervision and management of the house construction project is an important link of the house construction project management, and the traditional supervision and management method is low in informatization degree and seriously restricts the level of the project supervision and management development. The building information model, BIM for short, BIM technology has the characteristics of informatization, visualization and the like, and the application of the BIM-based construction progress informatization management mode in the engineering has important significance for improving the management level of the engineering and further improving the overall value of the engineering.
With the popularization of BIM in China, BIM is gradually applied to supervision work. For example, chinese patent with publication number CN105844380A discloses a BIM-based management method and system for BIM engineering project elements, which is implemented by integrating a BIM database, a progress management subsystem, a cost management subsystem, a contract management subsystem, a quality management subsystem and a mobile terminal into a set of system, so that five major elements of an engineering project can be managed by using a set of system, and the management cost is reduced.
However, because the units and departments involved in engineering supervision are numerous, the traditional methods such as meeting, sending documents and the like need to call many people to the scene for analysis and discussion, and the efficiency of information verification is low. After the BIM system is used, required data and information are sent point to point, and although the timeliness of analysis and discussion is highlighted, the effectiveness of information verification is reduced because interaction communication cannot be carried out among multiple points.
Disclosure of Invention
In view of the above technical problems, an object of the present invention is to provide a project supervision and supervision method based on BIM, which ensures real-time performance of a supervision system and validity of results obtained by analysis and discussion. The invention also aims to provide a BIM-based project supervision and supervision system, which ensures the real-time performance of the supervision system and the effectiveness of the analysis and discussion results.
In order to achieve the first purpose, the invention provides the following technical scheme:
a project supervision and supervision method based on BIM comprises the following steps:
building a project BIM model according to the national building design standard, wherein the project is provided with subunits, and data is prepared for each subunit;
acquiring construction information to construct a three-level model, wherein the three-level model comprises a macroscopic model of an integral project, a mesoscopic model of an auxiliary building and a microscopic model of a building component;
compiling a construction progress plan, and linking the construction progress with the three-level model to generate a four-dimensional progress simulation;
generating a plurality of sub-models for the four-dimensional progress simulation, comparing the sub-models with the subunits one by one, comparing the sub-models in the four-dimensional progress simulation with the subunits in the project BIM model, setting a plurality of threads, simultaneously comparing a plurality of groups of corresponding sub-models with the subunits, and evaluating whether the construction scheme of the construction side is reasonable or not according to the ratio of the time consumption of the comparison result and the size of the four-dimensional progress simulation;
guiding the construction progress of the project according to the four-dimensional construction simulation model, and displaying each work in the construction process by a visual building element virtual construction process;
judging the place with the occupation ratio larger than the set occupation ratio as the area to be optimized, submitting the area to be optimized to a designer, a supervisor and a constructor for approval, generating approval results after unilateral approval, attaching a plurality of approval results beside the corresponding area to be optimized to represent, finally pushing the approval results to the designer according to the time sequence generated by the approval results, pushing the generated results first, and enabling the system to obtain the approval results obtained by the designer after pushing;
and correspondingly optimizing and modifying the four-dimensional progress simulation, and finally finishing the adjustment of the construction scheme.
Through the technical scheme, the BIM-based three-level model is built step by step, in actual modeling, a time dimension is added, BIM auxiliary technology is applied for cooperative management, time consumption of comparison results and the proportion of the four-dimensional progress simulation size are utilized to inspect design files of a builder, submodels and subunits which are wrong, leaked, collided and lacked in drawings are reminded quickly, then results obtained by the designer, the supervisor and the constructor are displayed in a centralized mode according to a later-output result which is displayed first, the later-output result can be closer to the actual progress in the construction progress, the method has the advantages of high information checking efficiency and good quality, detailed supervision and control are achieved really, the real-time performance of a supervision system is guaranteed, and meanwhile the effectiveness of the analyzed and discussed results is guaranteed.
Further, the construction information includes first to third model data, the three-level model is built by adopting a step-by-step modeling method, and the building method includes:
according to the first model data, the third model data, the macro model, the mesoscopic model and the micro model are respectively built;
stacking and arranging the auditing results obtained by the pushed design party according to the positions of the models corresponding to the areas to be optimized, wherein the auditing results of the macroscopic models are positioned on the outermost layer, the auditing results of the mesoscopic models are positioned on the middle layer, the auditing results of the microscopic models are positioned on the innermost layer, the outermost layer covers the middle layer, and the middle layer covers the innermost layer;
clicking the outermost layer and displaying the middle layer; clicking the middle layer to display the innermost layer; clicking the innermost layer and displaying the outermost layer;
and saving the macroscopic model, the mesoscopic model and the microscopic model.
Through the technical scheme, the newly added audit results are reflected from the integral, local and terminal dimensions, and the display method does not need to display all information, so that the burden of the audit results is not increased, the information can not be displayed in a missing manner, and the review is convenient.
Further, the first model data includes: building project 3D model, integral construction progress and engineering information;
the second model data includes: simplified 3D models and corresponding construction progress and construction information;
the third model data includes: all members including the self-defined construction time family and the detailed associated construction progress and construction information;
and newly adding components, wherein each component is defined with an installation specification expression, and an auditing result positioned in the innermost layer is distributed to the installation specification expressions.
Through the technical scheme, the installation steps of the newly added components need to be audited, so that the audit result of the innermost layer is independently distributed, the newly added components can be prevented from being overhauled, and the construction plan is prevented from being inaccurate.
Further, the method also comprises the following steps: the duty ratio is amplified to a duty ratio greater than 1.
Through the technical scheme, the method can be compared with 1, and the judgment of a plurality of duty ratios in the later period is facilitated.
Further, the compiling the construction progress plan includes:
acquiring schedule task arrangement to create engineering tasks, corresponding to the schedule task arrangement and a construction object in the three-layer model, and making a Gantt chart for guiding the construction progress of the engineering according to each engineering task in the three-layer model;
the four-dimensional construction simulation model forming method comprises the following steps:
and formulating the construction task and the progress plan according to the project content, wherein the construction task and the progress plan are obtained by performing simulation analysis on construction site arrangement, mechanical equipment arrangement, construction scheme arrangement and other auxiliary projects.
By the technical scheme, factors of other dimensions of construction operation can be fully considered by simulation analysis, and the integrity of construction progress is reflected.
In order to achieve the second purpose, the invention provides the following technical scheme:
a BIM-based project supervision and administration system comprising:
the building unit is used for building a project BIM model according to the national building design standard, the project is provided with subunits, and data are prepared for each subunit;
an acquisition unit configured to acquire construction information;
the construction unit is used for constructing and storing a three-level model according to the construction information, wherein the three-level model comprises a macroscopic model of an integral project, a mesoscopic model of an auxiliary building and a microscopic model of a building component;
the compiling unit is used for compiling a construction progress plan;
a linking unit for linking a construction progress with the three-level model to generate a four-dimensional progress simulation;
the comparison unit is used for generating a plurality of sub-models for the four-dimensional progress simulation, comparing the sub-models with the sub-units one by one, comparing the sub-models in the four-dimensional progress simulation with the sub-units in the project BIM model, setting a plurality of threads, comparing a plurality of groups of corresponding sub-models with the sub-units, and evaluating whether the construction scheme of the construction party is reasonable or not according to the ratio of the time consumption of the comparison result and the size of the four-dimensional progress simulation;
the prediction unit is used for guiding the construction progress of the project according to the four-dimensional construction simulation model and displaying each work of the construction process in a virtual construction process of a visual building element;
the submitting and pushing unit is used for judging the place with the occupation ratio larger than the set occupation ratio value as the area to be optimized, submitting the area to be optimized to a designer, a proctoring party and a construction party for approval, generating approval results after the approval by a single party, attaching a plurality of approval results beside the corresponding area to be optimized, representing the approval results, pushing the approval results to the designer according to the time sequence generated by the approval results, pushing the generated results first and then pushing the results, and enabling the system to obtain the approval results obtained by the designer after the pushing;
and the adjusting unit is used for correspondingly optimizing and modifying the four-dimensional progress simulation and finally completing the adjustment of the construction scheme.
Through the technical scheme, the BIM-based three-level model is built step by step, in actual modeling, a time dimension is added, BIM auxiliary technology is applied for cooperative management, the design file of a builder is examined by utilizing the proportion of time consumption of comparison results and the simulation size of a four-dimensional progress, submodels and subunits which are wrong, missed, collided and lacked in a drawing are reminded quickly, then results obtained by a designer, a supervisor and a constructor are displayed in a centralized mode according to a later-output result which is displayed first, the later-output result can be closer to the actual progress in the construction progress, the method has the advantages of high information checking efficiency and good quality, detailed supervision and control are really achieved, the real-time performance of a supervision system is guaranteed, and meanwhile the effectiveness of the analyzed and discussed results is guaranteed.
Further, the submission pushing unit further includes:
the building subunit is used for building a macroscopic model, a mesoscopic model and a microscopic model according to the first model data, the second model data and the third model data;
the arrangement subunit is used for superposing and arranging the audit results obtained by the pushed design party according to the positions of the models corresponding to the areas to be optimized, wherein the audit results of the macroscopic models are positioned on the outermost layer, the audit results of the mesoscopic models are positioned on the middle layer, the audit results of the microscopic models are positioned on the innermost layer, the outermost layer covers the middle layer, and the middle layer covers the innermost layer;
a click subunit, configured to perform the following operations: clicking the outermost layer and displaying the middle layer; clicking the middle layer to display the innermost layer; clicking the innermost layer and displaying the outermost layer;
and the holding subunit is used for storing the macroscopic model, the mesoscopic model and the microscopic model.
Through the technical scheme, the newly added audit results are reflected from the integral, local and terminal dimensions, and the display method does not need to display all information, so that the burden of the audit results is not increased, the information can not be displayed in a missing manner, and the review is convenient.
Further, the compiling unit includes:
the creating subunit is used for acquiring schedule task arrangement and creating engineering tasks;
the corresponding subunit is used for arranging the corresponding progress task and the constructed object in the three-level model;
and the formulating subunit is used for formulating a Gantt chart for guiding the construction progress of the engineering according to each engineering task in the three-level model.
Further, the system further comprises:
and the newly-added unit is used for newly adding components, wherein each component is defined with an installation standard expression, and an auditing result positioned in the innermost layer is distributed to the installation standard expression.
Through the technical scheme, the installation steps of the newly added components need to be audited, so that the audit result of the innermost layer is independently distributed, the newly added components can be prevented from being overhauled, and the construction plan is prevented from being inaccurate.
Further, the system further comprises:
and the amplifying unit is used for amplifying the occupation ratio to be more than 1.
Through the technical scheme, the method can be compared with 1, and the judgment of a plurality of duty ratios in the later period is facilitated.
The technical scheme of the invention at least comprises the following beneficial effects: the method comprises the steps of gradually establishing a BIM-based three-level model, adding a time dimension in actual modeling, applying BIM auxiliary technology for cooperative management, examining a design file of a construction party by utilizing the proportion of time consumption of a comparison result and the simulation size of a four-dimensional progress, quickly reminding sub-models and sub-units of errors, omissions, collisions and defects possibly appearing in a drawing, then intensively displaying results obtained by the design party, a supervisor and a construction party according to a mode that the later-output results are displayed first, enabling the later-output results to be closer to the actual progress in the construction progress, having the advantages of high information checking efficiency and good quality, really realizing detailed supervision and control, ensuring the real-time performance of a supervision system and simultaneously ensuring the effectiveness of the results obtained by analysis and discussion.
Drawings
FIG. 1 is a schematic flow chart of a method according to a first embodiment of the present invention;
fig. 2 is a flowchart illustrating a method S100 according to an embodiment of the present invention;
fig. 3 is a flowchart illustrating a method S200 according to an embodiment of the present invention;
fig. 4 is a flowchart illustrating a method S300 according to an embodiment of the present invention;
FIG. 5 is a block diagram of a system according to a second embodiment of the present invention;
FIG. 6 is a block diagram of a compiling unit according to a second embodiment of the invention;
FIG. 7 is a block diagram of a prediction unit according to a second embodiment of the present invention;
FIG. 8 is a block diagram of a second commit pushing unit according to an embodiment of the present invention.
Reference numerals: 000. a building unit; 100. an acquisition unit; 200. a building unit; 300. a compiling unit; 301. creating a subunit; 302. a corresponding subunit; 303. formulating a subunit; 400. a linking unit; 500. a comparison unit; 600. an amplifying unit; 700. a prediction unit; 701. a virtual subunit; 702. an additional subunit; 703. an association subunit; 800. submitting a pushing unit; 801. building sub-units; 802. arranging the subunits; 8021. Clicking a subunit; 803. a holding subunit; 900. an adjustment unit; 1000. and adding a unit.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention.
The first embodiment is as follows:
a project supervision and supervision method based on BIM, as shown in fig. 1, includes:
step S000: and establishing a BIM (building information modeling) model of the project according to the national building design standard, wherein the project is provided with subunits, and data is prepared for each subunit.
Step S100: and acquiring construction information to construct a three-level model, wherein the three-level model comprises a macroscopic model of the whole project, a mesoscopic model of the auxiliary building and a microscopic model of the building component.
And acquiring all construction information related to the project according to the content of the construction project, and importing the information into the BIM system to build a project model. The information is divided into first to third model data according to the degree of refinement of the information content thereof. The first model data comprise a 3D model of a construction project, the whole construction progress and engineering information, and different material colors are adopted in the modeling to represent each block, wall, road, equipment and the like. The second model data includes a simplified 3D model and corresponding construction progress and construction information, wherein the simplified 3D model may not include detail components such as indoor equipment and pipes according to actual design construction needs. The third model data comprises all components including a self-defined construction time family, detailed associated construction progress and construction information, and can be used for fine management of buildings.
As shown in fig. 2, step S100 further includes step S101 and step S102.
Step S101: according to the first model data, the third model data, the macro model, the middle view model and the micro model are respectively built;
step S102: and stacking and arranging the auditing results obtained by the pushed design party according to the positions of the models corresponding to the areas to be optimized, wherein the auditing results of the macroscopic models are positioned on the outermost layer, the auditing results of the mesoscopic models are positioned on the middle layer, the auditing results of the microscopic models are positioned on the innermost layer, the outermost layer covers the middle layer, and the middle layer covers the innermost layer.
Step S103: clicking the outermost layer and displaying the middle layer; clicking the middle layer to display the innermost layer; clicking the innermost layer and displaying the outermost layer.
Step S104: and storing the macroscopic model, the mesoscopic model and the microscopic model.
The newly added audit results are reflected from the overall, local and terminal dimensions, and the display method does not need to display all information, so that the burden of the audit results is not increased, the information can not be displayed in a missing manner, and the review is convenient.
And establishing a macroscopic model of the whole project according to the first model data, establishing a mesoscopic model of the auxiliary building according to the second model data and establishing a microscopic model of the building component according to the third model data by adopting a step-by-step modeling method. The macroscopic model, the mesoscopic model and the microscopic model form a three-level model. The construction model established based on the three layers is actually a sub-model forming a complete BIM model of the whole building construction project, and the models are mutually related and communicated with each other. The model construction information of different dimensions of each level comprises related progress, engineering quantity, safety quality indexes, cost and the like. In order to avoid the problems that information conflicts and repeated creation exist when models of different layers are easily encountered during modeling, the technical scheme of the invention adopts a step-by-step modeling method from macro to mesoscopic to micro step-by-step modeling.
After the three-level model is established, the step S200 is carried out: and compiling a construction progress plan, and linking the construction progress with the three-level model to generate a four-dimensional progress simulation. The step S200 further includes amplifying the occupation ratio until the occupation ratio is greater than 1, and comparing the occupation ratio with 1, so as to facilitate the judgment of a plurality of occupation ratios in the later period. .
Four-dimensional progress simulation is achieved by linking the progress plan file with a three-level model. The key is that the scheduling task and scheduling must be divided in sufficient detail. Activities such as previous grading, equipment approach, material approach and scaffolding require detailed partitioning. Meanwhile, the factors of space, time and the like need to be fully considered when reasonable sequence and schedule plan are compiled. The technical scheme of the invention uses Project management software to create engineering tasks, sets the relationship among all the work tasks and formulates a Gantt chart. The schedule task arrangement corresponds to the component object of the three-level model, the subdivided activities are displayed in the four-dimensional schedule simulation by using a BIM tool, the complete butt joint of the tasks, the Gantt chart and the three-level model is realized, and the whole schedule is all contents required to be displayed by the four-dimensional schedule simulation. In order to achieve better effect, animation can be added to the appearance of the component, and the task type, the playing time and the like can be set. So far, the four-dimensional progress simulation is established and completed, and the process comprises the following steps: (1) the created four-dimensional progress simulation takes day, week and month as time units, and the progress of the construction can be simulated in a positive sequence or in a negative sequence according to different time intervals, so that the progress of the whole construction is reflected vividly. (2) And the date and the finished and unfinished project amount of the current day are displayed at the upper right corner while playing, so that the project amount can be conveniently checked at any time. (3) The system updates the progress database in real time after changing the construction time and the current state, and adjusts Project progress plans. (4) Different colors on the three-dimensional model represent different processes.
The BIM technology is used as a tool, the building is used as an engineering background, the Navisthroks software is used for dynamically demonstrating the whole and local construction process and the construction site arrangement condition of the BIM model and the construction progress plan Project file of the building, the structure and the electromechanical equipment, which are established by the Revit software, and the Navisthroks software is used for establishing a corresponding four-dimensional progress simulation model. Compared with the traditional construction progress management method, the BIM-based four-dimensional progress simulation has the following characteristics: (1) the four-dimensional progress simulation can intuitively show the whole construction process, so that a three-dimensional visual platform is provided for project managers, and visual management of the construction process becomes possible. (2) The 3D parameterized model is completely butted with data in the Project file, so that the coordination of construction site management and construction progress in time and space is ensured, a Project manager is effectively helped to reasonably arrange the construction progress and the construction site arrangement, and various resources such as people, materials, machines and the like are optimally distributed according to the progress requirement. (3) The four-dimensional progress simulation can simulate the construction process of the whole project, can also simulate the construction process and progress of a complex technical scheme, realizes the visual intersection of the construction scheme, and avoids the problems of comprehension divergence, information omission and the like caused by the intersection of language characters and two-dimensional drawings. (4) By using the technology, the communication level of the building information is improved, the communication among all the participating parties is convenient, the influence of the construction project caused by information overload or information loss is reduced, the working efficiency and the management capacity of a building construction manager are improved, and a new way and a new method are created for the management of the large-scale construction project.
Step S300: and generating a plurality of sub models for the four-dimensional progress simulation, comparing the sub models with the subunits one by one, comparing the sub models in the four-dimensional progress simulation with the subunits in the project BIM model, setting a plurality of threads, simultaneously comparing a plurality of groups of corresponding sub models and subunits, and evaluating whether the construction scheme of the construction party is reasonable or not according to the ratio of the time consumption of the comparison result and the size of the four-dimensional progress simulation.
And establishing a construction task decomposition structure according to the four-dimensional progress simulation to make construction plans of different levels, and gradually adding the construction tasks and the progress plans into the construction plans according to the project content to form a four-dimensional construction simulation model.
As shown in fig. 4, step S300 includes step S301: and gradually adding construction tasks and progress plans into the construction plan according to the project content to form a four-dimensional construction simulation model of the project. The construction task and the progress plan are obtained by performing simulation analysis on construction site arrangement, mechanical equipment arrangement, construction scheme arrangement and other auxiliary projects.
After the four-dimensional progress simulation is completed, the construction project establishes a construction task decomposition structure according to a 4D-BIM system, and formulates construction plans of different levels, wherein the mesoscopic and microscopic models create custom families to represent various objects such as construction time, lines, pipelines and the like. And the BIM model created by using Revit software is led into a 4D-BIM system created by Navisvarks in an automatic association mode, wherein the one-to-one corresponding association relationship is automatically established between the construction task decomposition structure and each part of the model, and a four-dimensional construction simulation model frame is formed.
Then, step S400 is performed: and guiding the construction progress of the project according to the four-dimensional construction simulation model, and displaying each work of the construction process in a virtual building element construction process of a visual image.
Step S500: and judging the place with the occupation ratio larger than the set occupation ratio as the area to be optimized, submitting the area to be optimized to a designer, a proctoring party and a construction party for approval, generating approval results after unilateral approval, attaching a plurality of approval results beside the corresponding area to be optimized, representing, finally pushing the approval results to the designer according to the time sequence generated by the approval results, pushing the generated results first, and enabling the system to obtain the approval results obtained by the designer after pushing.
Step S600: and correspondingly optimizing and modifying the four-dimensional progress simulation, and finally finishing the adjustment of the construction scheme. Further comprising: and newly adding components, wherein each component is defined with an installation specification expression, and an auditing result positioned in the innermost layer is distributed to the installation specification expressions. The installation steps of the newly added components need to be checked, so that the checking result of the innermost layer is independently distributed, the newly added components can be prevented from being checked in a missing mode, and the inaccurate construction plan is prevented.
The traditional construction scheme is mainly based on the experience of technicians and experts, cannot be quantitatively described, cannot be intuitively compared, checked and optimized, and cannot predict the possible emergency in construction. The building of the BIM construction model maps the whole process of the construction scheme into a virtual environment, and the observation, tracking, control and guidance of the whole construction process are realized through the operation of the virtual environment, so that the aims of verifying, optimizing, adjusting and optimizing the construction scheme are finally fulfilled. In the construction stage, the simulation of the construction scheme based on the BIM virtual construction can find the possible risks in the construction process in the virtual environment, and adjust and modify the model and the plan aiming at the risks to guide the actual construction, thereby ensuring the smooth construction of the project. The method comprises the steps of gradually establishing a BIM-based three-level model, adding a time dimension in actual modeling, applying BIM auxiliary technology for cooperative management, examining a design file of a construction party by utilizing the proportion of time consumption of a comparison result and the simulation size of a four-dimensional progress, quickly reminding sub-models and sub-units of errors, omissions, collisions and defects possibly appearing in a drawing, then intensively displaying results obtained by the design party, a supervisor and a construction party according to a mode that the later-output results are displayed first, enabling the later-output results to be closer to the actual progress in the construction progress, having the advantages of high information checking efficiency and good quality, really realizing detailed supervision and control, ensuring the real-time performance of a supervision system and simultaneously ensuring the effectiveness of the results obtained by analysis and discussion. The construction method can visually reflect all the construction procedures, is convenient for construction units to coordinate the construction sequence of each specialty, and organizes the entrance construction of professional teams and groups, prepare equipment, fields, turnover materials and the like in advance; meanwhile, the four-dimensional construction simulation model also has strong intuitiveness, and the leader of an owner who is not the birth of engineering technology can quickly and accurately master the progress of the engineering.
Example two:
in combination with the above inventive idea of the technical solution of the present invention, a project supervision and administration system based on BIM, as shown in fig. 5, includes:
and the establishing unit 000 is used for establishing a BIM (building information modeling) model of the project according to the national building design standard, wherein the project is provided with subunits, and data is prepared for each subunit.
An acquisition unit 100 for acquiring construction information.
And the construction unit 200 is used for constructing and storing a three-level model according to the construction information, wherein the three-level model comprises a macroscopic model of the whole project, a mesoscopic model of the auxiliary building and a microscopic model of the building component.
And the compiling unit 300 is used for compiling a construction progress plan. As shown in FIG. 6, the orchestration unit 300 comprises a creation subunit 301, a corresponding subunit 302, and an enactment subunit 303.
The creation subunit 301 is used to obtain scheduling task scheduling and create engineering tasks.
The corresponding subunit 302 is used for corresponding scheduling tasks and building objects in the three-level model.
The stator making unit 303 is used for making a gantt chart for guiding the construction progress of the project according to each project task in the three-level model.
And a linking unit 400 for linking the construction progress with the three-level model to generate a four-dimensional progress simulation.
And the comparison unit 500 is used for generating a plurality of sub-models for the four-dimensional progress simulation, comparing the sub-models in the four-dimensional progress simulation with the sub-units in the project BIM model one by one, setting up a plurality of threads, comparing a plurality of groups of corresponding sub-models and sub-units, and evaluating whether the construction scheme of the construction party is reasonable according to the time consumption of the comparison result and the proportion of the size of the four-dimensional progress simulation. The comparison unit 500 is connected with an amplifying unit 600 for amplifying the ratio to a ratio greater than 1.
And the prediction unit 700 is used for guiding the construction progress of the project according to the four-dimensional construction simulation model, and displaying each work of the construction process in a virtual construction process of the building components with visual images. As shown in fig. 7, the prediction unit 700 further includes a virtual sub-unit 701, an additional sub-unit 702, and an associated sub-unit 703.
The virtual subunit 701 is configured to establish a 3D model by using computer software, and then perform virtual description on the item content through a visualization device.
An additional subunit 702 is used to add a time dimension to the item content.
The association subunit 703 is configured to associate the project content with the construction progress plan through the construction task decomposition structure.
And the submitting and pushing unit 800 is used for judging the place with the occupation ratio larger than the set occupation ratio value as the area to be optimized, submitting the design party, the supervision party and the construction party for approval, generating approval results after unilateral approval, attaching a plurality of approval results beside the corresponding area to be optimized, representing the approval results, pushing the approval results to the design party according to the time sequence generated by the approval results, pushing the generated results first and then pushing the results, and enabling the system to obtain the approval results obtained by the design party after pushing. As shown in fig. 8, the commit pushing unit 800 further includes:
and the establishing subunit 801 is configured to establish a macro model, a mesoscopic model and a micro model according to the first to third model data.
The arrangement subunit 802 is configured to perform superposition arrangement on the audit results obtained by the design party after pushing according to the positions in the models corresponding to the areas to be optimized, where the audit results of the macroscopic models are located on the top layer, the audit results of the mesoscopic models are located on the middle layer, the audit results of the microscopic models are located on the innermost layer, the top layer covers the middle layer, and the middle layer covers the innermost layer.
Click subunit 8021, configured to perform the following operations: clicking the outermost layer and displaying the middle layer; clicking the middle layer to display the innermost layer; clicking the innermost layer and displaying the outermost layer.
A holding subunit 803 for holding the macroscopic model, the mesoscopic model and the microscopic model.
The adjusting unit 900 is configured to perform corresponding optimization and modification on the four-dimensional progress simulation, and finally complete the adjustment of the construction scheme.
As shown in fig. 7, the system further includes an adding unit 1000, configured to add new components, where each component has an installation specification expression defined therein, and assign an audit result located at the innermost layer to the installation specification expression. The above description is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments, and all technical solutions belonging to the idea of the present invention belong to the protection scope of the present invention. It should be noted that modifications and embellishments within the scope of the invention may occur to those skilled in the art without departing from the principle of the invention, and are considered to be within the scope of the invention.

Claims (10)

1. A project supervision and supervision method based on BIM is characterized by comprising the following steps:
building a project BIM model according to the national building design standard, wherein the project is provided with subunits, and data is prepared for each subunit;
acquiring construction information to construct a three-level model, wherein the three-level model comprises a macroscopic model of an integral project, a mesoscopic model of an auxiliary building and a microscopic model of a building component;
compiling a construction progress plan, and linking the construction progress with the three-level model to generate a four-dimensional progress simulation;
generating a plurality of sub-models for the four-dimensional progress simulation, comparing the sub-models with the subunits one by one, comparing the sub-models in the four-dimensional progress simulation with the subunits in the project BIM model, setting a plurality of threads, simultaneously comparing a plurality of groups of corresponding sub-models with the subunits, and evaluating whether the construction scheme of the construction side is reasonable or not according to the ratio of the time consumption of the comparison result and the size of the four-dimensional progress simulation;
guiding the construction progress of the project according to the four-dimensional construction simulation model, and displaying each work in the construction process by a visual building element virtual construction process;
judging the place with the occupation ratio larger than the set occupation ratio as the area to be optimized, submitting the area to be optimized to a designer, a supervisor and a constructor for approval, generating approval results after unilateral approval, attaching a plurality of approval results beside the corresponding area to be optimized to represent, finally pushing the approval results to the designer according to the time sequence generated by the approval results, pushing the generated results first, and enabling the system to obtain the approval results obtained by the designer after pushing;
and correspondingly optimizing and modifying the four-dimensional progress simulation, and finally finishing the adjustment of the construction scheme.
2. The method of claim 1, wherein the construction information includes first to third model data, and the three-level model is built by a step-by-step modeling method, the building method including:
according to the first model data, the third model data, the macro model, the mesoscopic model and the micro model are respectively built;
stacking and arranging the auditing results obtained by the pushed design party according to the positions of the models corresponding to the areas to be optimized, wherein the auditing results of the macroscopic models are positioned on the outermost layer, the auditing results of the mesoscopic models are positioned on the middle layer, the auditing results of the microscopic models are positioned on the innermost layer, the outermost layer covers the middle layer, and the middle layer covers the innermost layer;
clicking the outermost layer and displaying the middle layer; clicking the middle layer to display the innermost layer; clicking the innermost layer and displaying the outermost layer;
and saving the macroscopic model, the mesoscopic model and the microscopic model.
3. The method of claim 2, wherein the first model data comprises: building project 3D model, integral construction progress and engineering information;
the second model data includes: simplified 3D models and corresponding construction progress and construction information;
the third model data includes: all members including the self-defined construction time family and the detailed associated construction progress and construction information;
and newly adding components, wherein each component is defined with an installation specification expression, and an auditing result positioned in the innermost layer is distributed to the installation specification expressions.
4. The method of claim 1, further comprising: the duty ratio is amplified to a duty ratio greater than 1.
5. The method of claim 1, wherein said compiling a construction schedule comprises:
acquiring schedule task arrangement to create engineering tasks, corresponding to the schedule task arrangement and a construction object in the three-layer model, and making a Gantt chart for guiding the construction progress of the engineering according to each engineering task in the three-layer model;
the four-dimensional construction simulation model forming method comprises the following steps:
and formulating the construction task and the progress plan according to the project content, wherein the construction task and the progress plan are obtained by performing simulation analysis on construction site arrangement, mechanical equipment arrangement, construction scheme arrangement and other auxiliary projects.
6. A BIM-based project supervision and administration system, comprising:
the building unit (000) is used for building a project BIM model according to the national building design standard, the project is provided with subunits, and data are prepared for each subunit;
an acquisition unit (100) for acquiring construction information;
the construction unit (200) is used for constructing and storing a three-level model according to the construction information, wherein the three-level model comprises a macroscopic model of the whole project, a mesoscopic model of the auxiliary building and a microscopic model of the building component;
a compiling unit (300) for compiling a construction progress plan;
a linking unit (400) for linking a construction progress with the three-level model to produce a four-dimensional progress simulation;
the comparison unit (500) is used for generating a plurality of sub models for four-dimensional progress simulation, comparing the sub models with the sub units one by one, comparing the sub models in the four-dimensional progress simulation with the sub units in the project BIM model, setting a plurality of threads, simultaneously comparing a plurality of groups of corresponding sub models with the sub units, and evaluating whether the construction scheme of a construction party is reasonable or not according to the ratio of the time consumption of the comparison result and the size of the four-dimensional progress simulation;
a prediction unit (700) for guiding the construction progress of the project according to the four-dimensional construction simulation model, and displaying each work of the construction process as a virtual construction process of a building element with a visual image;
the submitting and pushing unit (800) is used for judging the place with the occupation ratio larger than the set occupation ratio value as the area to be optimized, submitting the area to be optimized to a designer, a proctoring party and a construction party for approval, generating approval results after unilateral approval, attaching a plurality of approval results to the corresponding area to be optimized, representing the approval results, pushing the approval results to the designer according to the time sequence generated by the approval results, pushing the generated results first and then pushing the results, and enabling the system to obtain the approval results obtained by the designer after pushing;
and the adjusting unit (900) is used for correspondingly optimizing and modifying the four-dimensional progress simulation and finally completing the adjustment of the construction scheme.
7. The system according to claim 6, wherein the commit pushing unit (800) further comprises:
a construction subunit (801) for constructing a macroscopic model, a mesoscopic model and a microscopic model from the first to third model data;
the arrangement subunit (802) is used for stacking and arranging the audit results obtained by the pushed design party according to the positions of the models corresponding to the areas to be optimized, wherein the audit results of the macroscopic models are located on the outermost layer, the audit results of the mesoscopic models are located on the middle layer, the audit results of the microscopic models are located on the innermost layer, the outermost layer covers the middle layer, and the middle layer covers the innermost layer;
a click subunit (8021) for performing the following operations: clicking the outermost layer and displaying the middle layer; clicking the middle layer to display the innermost layer; clicking the innermost layer and displaying the outermost layer;
a holding subunit (803) for saving the macroscopic model, the mesoscopic model and the microscopic model.
8. The system according to claim 7, characterized in that the compilation unit (300) comprises:
a creating subunit (301) for obtaining schedule task arrangement and creating an engineering task;
a corresponding subunit (302) for arranging a corresponding scheduled task with a build object in the three-level model;
and the formulating subunit (303) is used for formulating a Gantt chart for guiding the construction progress of the project according to each project task in the three-level model.
9. The system of claim 7, further comprising:
and the adding unit (1000) is used for adding components, wherein each component is defined with an installation specification expression, and an auditing result positioned in the innermost layer is distributed to the installation specification expressions.
10. The system of claim 7, further comprising:
and an amplifying unit (900) for amplifying the duty ratio to a duty ratio greater than 1.
CN201911204344.3A 2019-11-29 2019-11-29 BIM-based project supervision and supervision method and system Withdrawn CN111125814A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911204344.3A CN111125814A (en) 2019-11-29 2019-11-29 BIM-based project supervision and supervision method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911204344.3A CN111125814A (en) 2019-11-29 2019-11-29 BIM-based project supervision and supervision method and system

Publications (1)

Publication Number Publication Date
CN111125814A true CN111125814A (en) 2020-05-08

Family

ID=70497109

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911204344.3A Withdrawn CN111125814A (en) 2019-11-29 2019-11-29 BIM-based project supervision and supervision method and system

Country Status (1)

Country Link
CN (1) CN111125814A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111833016A (en) * 2020-07-08 2020-10-27 惠州市筑成工程管理有限公司 Infrastructure building supervision method based on BIM
CN112016908A (en) * 2020-10-22 2020-12-01 广东恩胜科技有限公司 BIM-based construction progress monitoring method and system, electronic equipment and storage medium
CN112084761A (en) * 2020-09-02 2020-12-15 董萍 Hydraulic engineering information management method and device
CN112381943A (en) * 2020-11-13 2021-02-19 杭州绿锦建筑设计咨询有限公司 Building construction quality monitoring method, system, device and storage medium
CN112733239A (en) * 2021-01-15 2021-04-30 广州市新誉工程咨询有限公司 Building engineering quality monitoring method and system based on BIM model
CN113673899A (en) * 2021-08-28 2021-11-19 江苏苏科建设项目管理有限公司 Road engineering progress management method based on supervision cloud system
CN114943494A (en) * 2022-07-26 2022-08-26 如皋市规划建筑设计院有限公司 Building design progress supervisory systems based on BIM technique
CN116308152A (en) * 2023-02-28 2023-06-23 北京洛斯达科技发展有限公司 BIM and laser point cloud data-based transmission line engineering progress assessment method
CN116824107A (en) * 2023-07-13 2023-09-29 北京万物镜像数据服务有限公司 Processing method, device and equipment for three-dimensional model review information

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111833016A (en) * 2020-07-08 2020-10-27 惠州市筑成工程管理有限公司 Infrastructure building supervision method based on BIM
CN112084761A (en) * 2020-09-02 2020-12-15 董萍 Hydraulic engineering information management method and device
CN112016908A (en) * 2020-10-22 2020-12-01 广东恩胜科技有限公司 BIM-based construction progress monitoring method and system, electronic equipment and storage medium
CN112381943A (en) * 2020-11-13 2021-02-19 杭州绿锦建筑设计咨询有限公司 Building construction quality monitoring method, system, device and storage medium
CN112733239A (en) * 2021-01-15 2021-04-30 广州市新誉工程咨询有限公司 Building engineering quality monitoring method and system based on BIM model
CN113673899A (en) * 2021-08-28 2021-11-19 江苏苏科建设项目管理有限公司 Road engineering progress management method based on supervision cloud system
CN114943494A (en) * 2022-07-26 2022-08-26 如皋市规划建筑设计院有限公司 Building design progress supervisory systems based on BIM technique
CN116308152A (en) * 2023-02-28 2023-06-23 北京洛斯达科技发展有限公司 BIM and laser point cloud data-based transmission line engineering progress assessment method
CN116308152B (en) * 2023-02-28 2024-01-26 广东电网有限责任公司 BIM and laser point cloud data-based transmission line engineering progress assessment method
CN116824107A (en) * 2023-07-13 2023-09-29 北京万物镜像数据服务有限公司 Processing method, device and equipment for three-dimensional model review information
CN116824107B (en) * 2023-07-13 2024-03-19 北京万物镜像数据服务有限公司 Processing method, device and equipment for three-dimensional model review information

Similar Documents

Publication Publication Date Title
CN111125814A (en) BIM-based project supervision and supervision method and system
Han et al. Automated post-simulation visualization of modular building production assembly line
CN107480370A (en) A kind of construction speed Forecasting Methodology and system based on BIM models
Alizadehsalehi et al. BIM/MR-Lean construction project delivery management system
Ku et al. Building interactive modeling for construction education in virtual worlds
Getuli et al. A BIM-based construction supply chain framework for monitoring progress and coordination of site activities
Messner et al. Using advanced visualization tools to improve construction education
CN111105080A (en) Construction progress prediction method and system based on BIM (building information modeling)
CN115860499A (en) Multi-professional work-type coordination construction management system based on BIM technology
Fernandes Advantages and disadvantages of BIM platforms on construction site
Balakina et al. 4D modeling in high-rise construction
Zhang et al. A reference system of smart manufacturing talent education (SMTE) in China
Tayeh et al. Developing construction information systems courses based on collaboration between industry and academia
Lee et al. The development of the virtual construction simulator 3: an interactive simulation environment for construction management education
Feng [Retracted] The Influence Mechanism of BIM on Green Building Engineering Project Management under the Background of Big Data
Amer Architectural design in the light of AI concepts and applications
Sinenko et al. Digital transformation of the organization of construction production
Su et al. A graphical planning method for workspace-aware, four-dimensional modeling to assist effective construction planning.
Blanco Caballero et al. Implementation of BIM in the subject technical industrial projects—Degree in industrial technologies engineering—University of Valladolid
Tarar et al. Impact of 4D modeling on construction planning process
Grishina et al. Monitoring of the construction site using an information model
Olugboyega Specific Roles of Builders in Building Information Modelling Processes
TUDublin et al. The potential impact of BIM on early design stages of Residential Apartment Construction in Ireland: A Computational Design Approach
Lehtinen Increasing integration in construction projects: A case study on a PPP project adopting BIM
Joseph et al. Application of Building Information Modeling for an Institutional Building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20200508