CN111535588A - System for selecting optimal pouring scheme based on BIM technology - Google Patents
System for selecting optimal pouring scheme based on BIM technology Download PDFInfo
- Publication number
- CN111535588A CN111535588A CN202010527542.XA CN202010527542A CN111535588A CN 111535588 A CN111535588 A CN 111535588A CN 202010527542 A CN202010527542 A CN 202010527542A CN 111535588 A CN111535588 A CN 111535588A
- Authority
- CN
- China
- Prior art keywords
- bim
- pouring
- construction
- parameters
- module
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Engineering & Computer Science (AREA)
- Geometry (AREA)
- Structural Engineering (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- Mining & Mineral Resources (AREA)
- Computational Mathematics (AREA)
- Paleontology (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mechanical Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The invention discloses a system for selecting an optimal pouring scheme based on a BIM (building information modeling) technology, and belongs to the technical field of concrete construction. The system comprises a system information input module, a data processing module and a data processing module, wherein the system information input module is used for inputting and setting various parameters in the simulated pouring process of the large-volume concrete; the system data processing module is used for simulating data processing and integration of the system and establishing association between various parameters and the BIM by utilizing secondary development software; the BIM construction simulation module is used for simulating the large-volume concrete pouring process by a method of changing parameter settings for multiple times through a BIM model, so that the optimal pouring scheme is selected; and the system information output module is used for simulating information output of data and is associated with the BIM through a preset data processing program. The invention simulates the field construction process by the BIM technology, can find the problems in different pouring processes in time, and improves the simulation construction process by continuously adjusting the construction simulation parameters, thereby determining the optimal pouring construction scheme.
Description
Technical Field
The invention relates to the technical field of concrete construction, in particular to a system for selecting an optimal pouring scheme based on a BIM (building information modeling) technology.
Background
The construction method has the advantages that the construction method is widely applied to large-volume concrete structure construction engineering, different pouring schemes of large-volume concrete play a critical role in the large-volume concrete quality, the selection of parameters such as the number of pouring layers, the pouring sequence, the number of vibrating rods and the like has a great influence on the large-volume concrete construction quality, the on-site large-volume pouring construction is generally arranged by experience, and various construction problems caused by unreasonable selection of the construction method, such as unreasonable pouring sequence, insufficient configuration of the vibrating rods, unmatched pouring speed and concrete supply speed and the like, are often found in the construction engineering.
Disclosure of Invention
Aiming at the defects and shortcomings in the prior art, the invention provides a system for selecting the optimal pouring scheme based on the BIM technology, which has the advantages of accurately simulating the pouring process of the large-volume concrete, and can find the advantages and disadvantages of each pouring scheme in time to correct and adjust the simulated construction parameters, thereby determining the optimal large-volume concrete simulated construction scheme for guiding the site construction.
In order to achieve the purpose, the invention provides the following technical scheme: a system for selecting an optimal pouring scheme based on a BIM technology comprises four modules, namely a system information input module, a system data processing module, a BIM construction simulation module and a system information output module, wherein: the system information input module comprises construction data such as pouring modes and sequences, pouring equipment construction parameters, single layered pouring thickness, single pouring width, pouring layer concrete vibration parameters and the like; the system data processing module is used for simulating data processing and integration of the system, establishing association between various parameters and the BIM by utilizing secondary development software, and changing dynamic change of the BIM through setting the parameters so as to simulate a concrete pouring process; the BIM construction simulation module adopts BIM modeling software to carry out modeling according to a construction structure entity, and simulates the large-volume concrete pouring process by a method of changing parameter setting for multiple times through a BIM model, so as to select an optimal pouring scheme; and the system information output module is used for simulating information output of data, is associated with the BIM through a preset data processing program, and outputs different construction parameters in different simulation processes, such as total concrete amount, continuous pouring time, concrete pouring amount in unit time, the using amount of vibration equipment, the using amount of labor force and other related parameters.
Furthermore, the output parameters of the BIM pouring simulation process are associated with the BIM simulation model by adopting a secondary development program, and the viewable construction parameters are automatically generated after the simulation process is finished.
Compared with the prior art, the invention has the following beneficial effects:
according to the system for selecting the optimal pouring scheme based on the BIM technology, the BIM technology is used for simulating the field construction process, so that the problems in different pouring processes can be found in time, and the simulation construction process is improved by continuously adjusting the construction simulation parameters, so that the optimal pouring construction scheme is determined.
Drawings
FIG. 1 is a schematic structural diagram of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1, a system for selecting an optimal casting scheme based on a BIM technique includes four modules, namely a system information input module, a system data processing module, a BIM construction simulation module, and a system information output module.
The system information input module enables input parameters to be related to parameters of the model through secondary development, relevant parameters of the model are changed through changes of the input parameters, and the input parameters mainly comprise construction data such as pouring sequence, single layered pouring thickness, single pouring width, pouring layer concrete vibration parameters and the like.
The system data processing module is used for simulating data of a system and associating the data with the BIM, establishing association between various parameters and the BIM by utilizing secondary development software, and changing dynamic change of the BIM through setting of the parameters so as to simulate a concrete pouring process;
the BIM construction simulation module is a core module of the system, large-volume concrete modeling is carried out through Revit, simulation construction is carried out by combining display animation setting of BIM related software (Fuzor \ Navisvarks), and a large-volume concrete pouring process is simulated through a method of changing parameter setting for multiple times through a BIM model, so that an optimal pouring scheme is selected;
the system information output module is an information output window of simulation data, is associated with the BIM through a preset data processing program, and outputs different construction parameters in different simulation processes, such as total concrete amount, continuous pouring time, concrete pouring amount in unit time, vibrating equipment amount, labor force amount and other related parameters.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (2)
1. A system for selecting an optimal pouring scheme based on a BIM technology is characterized in that: including system information input module, system data processing module, BIM construction simulation module and system information output module four major modules, wherein: the system information input module comprises construction data such as pouring modes and sequences, pouring equipment construction parameters, single layered pouring thickness, single pouring width, pouring layer concrete vibration parameters and the like; the system data processing module is used for simulating data processing and integration of the system, establishing association between various parameters and the BIM by utilizing secondary development software, and changing dynamic change of the BIM through setting the parameters so as to simulate a concrete pouring process; the BIM construction simulation module adopts BIM modeling software to carry out modeling according to a construction structure entity, and simulates the large-volume concrete pouring process by a method of changing parameter setting for multiple times through a BIM model, so as to select an optimal pouring scheme; and the system information output module is used for simulating information output of data, is associated with the BIM through a preset data processing program, and outputs different construction parameters in different simulation processes, such as total concrete amount, continuous pouring time, concrete pouring amount in unit time, the using amount of vibration equipment, the using amount of labor force and other related parameters.
2. The BIM technology-based system for selecting an optimal casting solution according to claim 1, wherein: the BIM pouring simulation process output parameters are associated with the BIM simulation model by adopting a secondary development program, and the viewable construction parameters are automatically generated after the simulation process is finished.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010527542.XA CN111535588A (en) | 2020-06-11 | 2020-06-11 | System for selecting optimal pouring scheme based on BIM technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010527542.XA CN111535588A (en) | 2020-06-11 | 2020-06-11 | System for selecting optimal pouring scheme based on BIM technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111535588A true CN111535588A (en) | 2020-08-14 |
Family
ID=71979761
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010527542.XA Pending CN111535588A (en) | 2020-06-11 | 2020-06-11 | System for selecting optimal pouring scheme based on BIM technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111535588A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114351541A (en) * | 2021-09-27 | 2022-04-15 | 广西北投交通养护科技集团有限公司 | Automatic pouring system for foam lightweight concrete |
CN115952589A (en) * | 2023-03-14 | 2023-04-11 | 中国建筑第二工程局有限公司 | Ring beam joint BIM auxiliary construction method capable of avoiding concrete pouring obstruction |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20140337286A1 (en) * | 2010-03-09 | 2014-11-13 | Autodesk, Inc. | Systems and Methods for Construction Field Management and Operations with Building Information Modeling |
CN107299762A (en) * | 2017-07-28 | 2017-10-27 | 成都智建新业建筑设计咨询有限公司 | A kind of concrete pouring procedure based on BIM |
CN110978204A (en) * | 2019-12-20 | 2020-04-10 | 万翼科技有限公司 | BIM-based intelligent concrete pouring method and related product |
-
2020
- 2020-06-11 CN CN202010527542.XA patent/CN111535588A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20140337286A1 (en) * | 2010-03-09 | 2014-11-13 | Autodesk, Inc. | Systems and Methods for Construction Field Management and Operations with Building Information Modeling |
CN107299762A (en) * | 2017-07-28 | 2017-10-27 | 成都智建新业建筑设计咨询有限公司 | A kind of concrete pouring procedure based on BIM |
CN110978204A (en) * | 2019-12-20 | 2020-04-10 | 万翼科技有限公司 | BIM-based intelligent concrete pouring method and related product |
Non-Patent Citations (2)
Title |
---|
刘军生: "BIM 技术在大体积筏板混凝土浇筑过程中的探索应用", 《土木建筑工程信息技术》 * |
谢宏: "BIM技术在大体积筏板混凝土浇筑施工中的应用", 《广西科技大学学报》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114351541A (en) * | 2021-09-27 | 2022-04-15 | 广西北投交通养护科技集团有限公司 | Automatic pouring system for foam lightweight concrete |
CN114351541B (en) * | 2021-09-27 | 2023-11-07 | 广西北投交通养护科技集团有限公司 | Automatic pouring system for foam lightweight concrete |
CN115952589A (en) * | 2023-03-14 | 2023-04-11 | 中国建筑第二工程局有限公司 | Ring beam joint BIM auxiliary construction method capable of avoiding concrete pouring obstruction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105888248B (en) | A kind of construction method based on BIM technology tutorial message prefabricated components | |
CN110826130B (en) | Application method of BIM modeling in design and construction of special-shaped curved surface structural body | |
CN105488301A (en) | Three-dimensional reinforcing steel bar lofting method | |
CN111062081A (en) | Underground continuous wall construction method based on BIM technology | |
CN110119516B (en) | Reinforcing steel bar sample turning method based on BIM technology | |
CN111535588A (en) | System for selecting optimal pouring scheme based on BIM technology | |
CN107292038A (en) | A kind of parametric modeling production method for overlapping plate prefabricated member | |
CN107391862A (en) | A kind of prefabricated concrete structure Digital Collaborative Design Method | |
CN104850709A (en) | Three-dimensional simulation method for construction of architectural decoration project | |
CN107273640A (en) | Hydraulic and Hydro-Power Engineering Schedule monitoring method based on three-dimensional digital model | |
CN107299762B (en) | Concrete pouring method based on BIM | |
WO2021244667A1 (en) | Ultra-real-time calculation method for axial power deviation, electronic device, and storage medium | |
CN107545080A (en) | A kind of virtual pre-assembly method of steel bridge based on BIM models | |
CN113158320B (en) | Three-dimensional modeling system based on building plane design | |
CN112182727A (en) | Method and device for automatically laying supporting pieces of building engineering and readable storage medium | |
CN108416076A (en) | A kind of assembled architecture design method based on BIM technology | |
CN112257150A (en) | Refined calculation amount method of raft foundation slab band reinforcing ribs based on BIM modeling | |
CN109376395A (en) | A kind of architectural design management method and system | |
Miller | The Hangzhou tennis center: a case study in integrated parametric design | |
Raspall | A procedural framework for design to fabrication | |
CN106354933B (en) | A kind of ultra-large type waste heat boiler pipeline pressure test method based on BIM technology | |
CN107134007A (en) | The three-dimensional fast modeling method of traffic infrastructure | |
CN1275154C (en) | Continuous cast logistic simulation system based on computer | |
Hongyan et al. | Comparative analysis of civil engineering quantity calculation based on glodon gtj and revit | |
CN114077765A (en) | Dynamo project data management method and device and computer equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200814 |
|
RJ01 | Rejection of invention patent application after publication |