Prior art keywords
construction
model
bim
data
flat face
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510028780.5A
Other languages
Chinese (zh)
Inventor
周培珊
汪芦金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201510028780.5A priority Critical patent/CN104631826A/en
Publication of CN104631826A publication Critical patent/CN104631826A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a construction general layout based on a BIM. The method comprises the following steps that firstly, a project to be constructed is modeled according to a general layout, and boundary data of a building line and a foundation pit side boundary are input to a model; secondly, data of an outdoor pipe network, a road and ancillary facilities of the project to be constructed are input to a model; thirdly, data of a pipeline and ancillary temporary construction facilitates in the construction process are input to a model; fourthly, the models are overlaid through a data processing module, and rationality checking is carried out; fifthly, if irrationality is found out during checking, related data in the first step, the second step and the third step are adjusted, and the fourth step is executed again till rationality occurs; in the construction process, the construction general layout is strictly constructed according to the models. The construction general layout has the advantages of being visual, fast and capable of improving the construction efficiency and increasing the field utilization rate, and the project net pipe construction is not affected through reasonable arrangement of the temporary facility pipe network.

Description

A kind of construction main flat face method for arranging based on BIM model
Technical field
The present invention relates to a kind of construction main flat face method for arranging, in particular, relate to a kind of construction main flat face method for arranging based on BIM model.
Background technology
BIM (Building Information Modeling is called for short BIM), being the new technology greatly developed in the world, represent the developing direction of building trade, is a kind of revolutionary engineering.Started in current China building trade to be progressively familiar with, to accept and start to apply this technology, that applies at home along with BIM technology progressively carries out, and the work such as the design to construction work, construction are produced far-reaching influence by it.
Building Trade in China is huge, and for a long time, the construction mode of extensive style causes becoming a mere formality to the various management constraints of each unit of taking part in building in process of construction.Example is arranged as with construction main flat face, usually traditional CAD two dimension drawing is adopted at present, as run into the situation of construction plant around, CAD two dimension drawing is difficult to show complete construction plant, adds in construction plant the layout of facing and building pipe network, temporary construction facility, rely on separately two-dimentional drawing and rely on the experience of constructor to be constructed, cause difficulty of construction large, cause some projects construction main flat face to be arranged unreasonable, bring difficulty to subsequent construction, cause unnecessary loss.
Summary of the invention
The present invention is directed to the deficiencies in the prior art, and a kind of efficiency of construction that improves is provided, reduce construction cost, improve a kind of construction main flat face method for arranging based on BIM model of utilization of area rate.
A kind of construction main flat face method for arranging based on BIM model of the present invention, comprises the following steps:
Step 1: modeling is carried out to the engineering that will construct according to overall construction site plan, and by the data boundary input model in building line, foundation ditch sideline;
Step 2: by the tube net outside of construction project to be built, road, ancillary facility data input model;
Step 3: pipeline, supporting facing in work progress are built facility data input model;
Step 4: step 1,2, the model of 3 carries out overlap-add procedure by data processing module, and carries out reasonableness check;
Step 5: finding that work progress data are unreasonable as checked, returning step 4 after the related data of set-up procedure 1,2,3, until rationally;
Step 6: in work progress, construction main flat face is arranged and is strictly pressed model construction.
The model that described step 1 is set up is the threedimensional model carried out based on BIM platform.
The input of tube net outside in described step 2, road, ancillary facility data be threedimensional model based on BIM platform.
Pipeline in described step 3, supporting to face what build facility data input be threedimensional model based on BIM platform.
Carrying out superposition by data processing module in described step 4 is be superimposed as on-site actual situations model in construction process.
The invention has the beneficial effects as follows: (1) is directly perceived, quick, improves efficiency of construction; (2) improve utilization of area rate, the reasonable setting of temporory structure pipe network, does not affect Engineering Network pipe construction.
Accompanying drawing explanation
Fig. 1 is process flow diagram of the present invention.
Detailed description of the invention
Below in conjunction with accompanying drawing, the invention will be further described.
In the drawings, a kind of construction main flat face method for arranging based on BIM model of the present invention, comprises the following steps:
Step 1: modeling is carried out to the engineering that will construct according to overall construction site plan, the model of foundation is the threedimensional model carried out based on BIM platform, and by the data boundary input model in building line, foundation ditch sideline;
Step 2: by the tube net outside of construction project to be built, road, ancillary facility data input model, data input be threedimensional model based on BIM platform;
Step 3: pipeline, supporting facing in work progress are built facility data input model, data input be threedimensional model based on BIM platform;
Step 4: step 1,2, the model of 3 superposed by data processing module, be superimposed as on-site actual situations model in construction process and process, and carry out reasonableness check;
Step 5: finding that work progress data are unreasonable as checked, returning step 4 after the related data of set-up procedure 1,2,3, until rationally;
Step 6: in work progress, construction main flat face is arranged and is strictly pressed model construction.
Construction manager reasonable Arrangement job site can be helped by the construction main flat face method for arranging of this example, accomplish in good order, as temporary road is tried one's best and permanent roads position consistency, permanent roads roadbed can be done and use, reduce construction cost; The reasonable setting of temporory structure pipe network, does not affect Engineering Network pipe construction; Improving utilization of area rate, is engineering construction better services.

Claims (5)

1., based on a construction main flat face method for arranging for BIM model, it is characterized in that, comprise the following steps:
Step 1: modeling is carried out to the engineering that will construct according to overall construction site plan, and by the data boundary input model in building line, foundation ditch sideline;
Step 2: by the tube net outside of construction project to be built, road, ancillary facility data input model;
Step 3: pipeline, supporting facing in work progress are built facility data input model;
Step 4: step 1,2, the model of 3 carries out overlap-add procedure by data processing module, and carries out reasonableness check;
Step 5: finding that work progress data are unreasonable as checked, returning step 4 after the related data of set-up procedure 1,2,3, until rationally;
Step 6: in work progress, construction main flat face is arranged and is strictly pressed model construction.
2. a kind of construction main flat face method for arranging based on BIM model according to claim 1, is characterized in that, the model that described step 1 is set up is the threedimensional model carried out based on BIM platform.
3. a kind of construction main flat face method for arranging based on BIM model according to claim 1, is characterized in that, the input of tube net outside in described step 2, road, ancillary facility data be threedimensional model based on BIM platform.
4. a kind of construction main flat face method for arranging based on BIM model according to claim 1, is characterized in that, pipeline in described step 3, supporting to face what build facility data input be threedimensional model based on BIM platform.
5. a kind of construction main flat face method for arranging based on BIM model according to claim 1, is characterized in that, carrying out superposition by data processing module in described step 4 is be superimposed as on-site actual situations model in construction process.
CN201510028780.5A 2015-01-21 2015-01-21 Construction general layout method based on BIM Pending CN104631826A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510028780.5A CN104631826A (en) 2015-01-21 2015-01-21 Construction general layout method based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510028780.5A CN104631826A (en) 2015-01-21 2015-01-21 Construction general layout method based on BIM

Publications (1)

Publication Number Publication Date
CN104631826A true CN104631826A (en) 2015-05-20

Family

ID=53211021

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510028780.5A Pending CN104631826A (en) 2015-01-21 2015-01-21 Construction general layout method based on BIM

Country Status (1)

Country Link
CN (1) CN104631826A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104912340A (en) * 2015-06-09 2015-09-16 华鼎建筑装饰工程有限公司 Construction method for double-curve triangular aluminum plate unit type hanging ceiling
CN105678006A (en) * 2016-01-25 2016-06-15 中建一局集团第三建筑有限公司 Method for drawing foundation pit excavation drawing
CN105701282A (en) * 2016-01-08 2016-06-22 中建三局第建设工程有限责任公司 Multi-pipe group mounting frame and prefabricating construction method thereof based on BIM (Building Information Modeling)
CN106202825A (en) * 2016-07-29 2016-12-07 上海宝冶集团有限公司 Underground pipe gallery method for designing based on BIM
CN106327045A (en) * 2015-06-30 2017-01-11 上海宝冶集团有限公司 Method for creating metallurgical steelmaking production line building information model
CN106639162A (en) * 2016-12-28 2017-05-10 江苏中南建筑产业集团有限责任公司 BIM-based environment-friendly cushion block standardized construction method
CN107609237A (en) * 2017-08-29 2018-01-19 中国三冶集团有限公司 The interim layout drawing in technical bid job site based on BIM quickly goes out drawing method
CN108038265A (en) * 2017-11-17 2018-05-15 上海二十冶建设有限公司 A kind of Mountainous Building group's construction temporary road method for arranging based on BIM
CN108959824A (en) * 2018-08-06 2018-12-07 上海营邑城市规划设计股份有限公司 A kind of city of battalion plans pipeline BIM design section figure layer secondaryization generation method
CN109711076A (en) * 2018-12-29 2019-05-03 江苏龙腾数字建造技术研究院有限公司 The application method of BIM model in the construction process
CN109933900A (en) * 2019-03-13 2019-06-25 上海理工大学 A kind of construction three dimensional field cloth modeling method based on BIM technology
CN111368437A (en) * 2020-03-05 2020-07-03 中铁二院工程集团有限责任公司 Railway roadbed engineering design method based on BIM technology
CN111432197A (en) * 2020-03-19 2020-07-17 上海建工四建集团有限公司 Construction monitoring method and system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09268760A (en) * 1996-03-28 1997-10-14 Shimizu Corp Schedule control support system
JPH11311023A (en) * 1998-04-30 1999-11-09 Sekisui House Ltd Computer processing system for building construction starting work
CN202167021U (en) * 2011-06-10 2012-03-14 上海市电力公司 System device capable of establishing BIM model
CN102884532A (en) * 2010-03-09 2013-01-16 欧特克公司 Systems and methods for construction field management and operations with building information modeling

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09268760A (en) * 1996-03-28 1997-10-14 Shimizu Corp Schedule control support system
JPH11311023A (en) * 1998-04-30 1999-11-09 Sekisui House Ltd Computer processing system for building construction starting work
CN102884532A (en) * 2010-03-09 2013-01-16 欧特克公司 Systems and methods for construction field management and operations with building information modeling
CN202167021U (en) * 2011-06-10 2012-03-14 上海市电力公司 System device capable of establishing BIM model

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
宋盈莹: "BIM系统在城市超高层建筑中的应用研究", 《环渤海经济瞭望》 *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104912340A (en) * 2015-06-09 2015-09-16 华鼎建筑装饰工程有限公司 Construction method for double-curve triangular aluminum plate unit type hanging ceiling
CN106327045A (en) * 2015-06-30 2017-01-11 上海宝冶集团有限公司 Method for creating metallurgical steelmaking production line building information model
CN105701282A (en) * 2016-01-08 2016-06-22 中建三局第建设工程有限责任公司 Multi-pipe group mounting frame and prefabricating construction method thereof based on BIM (Building Information Modeling)
CN105678006B (en) * 2016-01-25 2020-02-18 中建一局集团第三建筑有限公司 Foundation pit excavation map drawing method
CN105678006A (en) * 2016-01-25 2016-06-15 中建一局集团第三建筑有限公司 Method for drawing foundation pit excavation drawing
CN106202825A (en) * 2016-07-29 2016-12-07 上海宝冶集团有限公司 Underground pipe gallery method for designing based on BIM
CN106639162A (en) * 2016-12-28 2017-05-10 江苏中南建筑产业集团有限责任公司 BIM-based environment-friendly cushion block standardized construction method
CN107609237A (en) * 2017-08-29 2018-01-19 中国三冶集团有限公司 The interim layout drawing in technical bid job site based on BIM quickly goes out drawing method
CN108038265A (en) * 2017-11-17 2018-05-15 上海二十冶建设有限公司 A kind of Mountainous Building group's construction temporary road method for arranging based on BIM
CN108959824A (en) * 2018-08-06 2018-12-07 上海营邑城市规划设计股份有限公司 A kind of city of battalion plans pipeline BIM design section figure layer secondaryization generation method
CN108959824B (en) * 2018-08-06 2020-10-02 上海营邑城市规划设计股份有限公司 BIM design section layer layering generation method for Ying Yi planning pipeline
CN109711076A (en) * 2018-12-29 2019-05-03 江苏龙腾数字建造技术研究院有限公司 The application method of BIM model in the construction process
CN109933900A (en) * 2019-03-13 2019-06-25 上海理工大学 A kind of construction three dimensional field cloth modeling method based on BIM technology
CN111368437A (en) * 2020-03-05 2020-07-03 中铁二院工程集团有限责任公司 Railway roadbed engineering design method based on BIM technology
CN111432197A (en) * 2020-03-19 2020-07-17 上海建工四建集团有限公司 Construction monitoring method and system

Similar Documents

Publication Publication Date Title
CN104631826A (en) Construction general layout method based on BIM
Xu Research on application of BIM 5D technology in central grand project
WO2017219921A1 (en) Building co-construction system and method based on member classification and combination
CN105488301A (en) Three-dimensional reinforcing steel bar lofting method
CN112257160B (en) BIM-based standardized forward design method for garbage incineration power plant
CN105781064A (en) Floor tile laying construction method based on building information modeling (BIM)
CN104156544A (en) Automatic beam and column steel bar joint arranging and constructing simulation method based on BIM technology
CN110080114A (en) A kind of visualization prefabricated stand column construction method based on BIM technology
CN107299762B (en) Concrete pouring method based on BIM
CN110889160A (en) Municipal pipeline construction method based on BIM technology
CN106650053A (en) USRAMS-based optimization design method of rainwater pipe network
CN111177824A (en) Aluminum alloy formwork construction method based on BIM technology
CN110837670A (en) BIM bidirectional deepening design method
CN107194112A (en) The method being laid out based on BIM to garden landscape
CN110990933A (en) Modeling method for shield tunnel
CN108875167A (en) A kind of construction site three dimensional arrangement optimization method based on BIM technology
CN110502834A (en) Depot of urban railway transit vehicles design method based on BIM
CN109920036A (en) A kind of arc steel structure construction method based on BIM technology
CN113626911A (en) Concrete 3D printing path optimization method based on first principal stress vector distribution
CN108984876A (en) A kind of service sleeve automation modeling method and system based on BIM
CN105631135A (en) Rapid modeling analysis system based on ABAQUS foundation pit excavation and application system thereof
CN108589725A (en) A kind of built-in fitting construction method based on BIM technology
CN107292058A (en) A kind of brickwork method based on BIM technology
CN106354933A (en) BIM (building information modeling) technology based ultra-large steel making exhausted heat boiler pipeline pressure testing method
CN111612433A (en) Assembly type building cooperative cloud platform based on BIM

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150520