CN109537819A - A kind of integrate draining pipe roof leakage control method - Google Patents

A kind of integrate draining pipe roof leakage control method Download PDF

Info

Publication number
CN109537819A
CN109537819A CN201811457935.7A CN201811457935A CN109537819A CN 109537819 A CN109537819 A CN 109537819A CN 201811457935 A CN201811457935 A CN 201811457935A CN 109537819 A CN109537819 A CN 109537819A
Authority
CN
China
Prior art keywords
draining pipe
integrate draining
pipe
laid
integrate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811457935.7A
Other languages
Chinese (zh)
Inventor
史路辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201811457935.7A priority Critical patent/CN109537819A/en
Publication of CN109537819A publication Critical patent/CN109537819A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D11/00Roof covering, as far as not restricted to features covered by only one of groups E04D1/00 - E04D9/00; Roof covering in ways not provided for by groups E04D1/00 - E04D9/00, e.g. built-up roofs, elevated load-supporting roof coverings
    • E04D11/02Build-up roofs, i.e. consisting of two or more layers bonded together in situ, at least one of the layers being of watertight composition
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/04Roof drainage; Drainage fittings in flat roofs, balconies or the like
    • E04D13/08Down pipes; Special clamping means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/16Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

A kind of integrate draining pipe roof leakage control method, it is characterised in that the following steps are included: a, prefabricated integrate draining pipe, b, are laid with prefabricated integrate draining pipe; c, it is laid with insulating layer; d, it is laid with roof protecting layer, insulating layer is laid on prefabricated integrate draining pipe, integrate draining pipe is completed and is laid with.The advantages of integrate draining pipe roof leakage control method of the invention has integrate draining pipe structure simple, easy to make, and construction quality is safe and reliable, seepage prevention and treatment is had excellent performance, and integrate draining pipe is low in cost, reduces engineering cost.

Description

A kind of integrate draining pipe roof leakage control method
Technical field
The present invention relates to a kind of prevention and treatments of roof leakage, specifically, being a kind of integrate draining pipe roof leakage control method.
Background technique
Roof leakage is the rainy humid area of one of construction quality common fault, especially south China, according to government's dependent part Door and the enterprises such as construction, exploitation, property with big data investigation statistics, in 3 term of new building roof leakage rate up to 40% with On, this makes country and enterprise seep the overall expenses and its huge of building maintenance and rectification for roofing, it can be seen that, solve roofing Leakage problems have become civil buildings one of important topic urgently to be resolved, according to market survey and my company's Cost Management data It has been shown that, waterproofing work and waterproof correlation engineering, only account for total cost 1%-5% or so, but to engineering total quality, especially subsequent to make It is that cannot be neglected with influence, according to the business data statistics display such as our company maintenance data and other constructions, exploitation, building matter It measures the defect problem frequency of occurrences and complains in quantity sum, leakage problem accounting is up to 70%, and wherein roof leakage accounting 40% is The defective in quality middle complaint ratio of institute is maximum, therefore in society, for top layer house type, by discrimination in Consumer groups.
Therefore known roofing internal structure cause percolating water there are problems that it is above-mentioned various inconvenient and.
Summary of the invention
The purpose of the present invention is to propose a kind of safe and reliable integrate draining pipe roof leakage control method.
To achieve the above object, the technical solution of the invention is as follows:
A kind of integrate draining pipe roof leakage control method, it is characterised in that the following steps are included:
A, prefabricated integrate draining pipe
Prefabricated integrate draining pipe: integrate draining pipe is made using 50 specification pvc pipes, production method: according to roofing size, by 50 specifications PVC is cut into the length of needs, drills along pvc pipe axis, pvc pipe is finally cut into two semicanals along axis, is put into semicanal It uses;
B, it is laid with prefabricated integrate draining pipe
According to Roof Design, roofing screed-coat, the laying water-proof coiled material on roofing screed-coat, anti-are laid on roof construction layer It is horizontal on water coiled material to be laid with integrate draining pipe, so that the end face with half bore of integrate draining pipe is contacted waterproof roll, integrate draining pipe downwards Other side arc surface is in top, makes one end of integrate draining pipe in waterproof roll, and other end stretching waterproof roll enters overboard In bucket;
C, it is laid with insulating layer
It is laid with insulating layer on prefabricated integrate draining pipe, the thermal insulation material of insulating layer is made all to wrap up covering integrate draining pipe;
D, it is laid with roof protecting layer
It is laid with insulating layer on prefabricated integrate draining pipe, completes integrate draining pipe and is laid with.
Integrate draining pipe roof leakage control method of the invention can also be further achieved by the following technical measures.
Method above-mentioned, wherein the outer diameter of the pvc pipe is >=50mm, thickness 2.5mm.
Method above-mentioned, wherein the length of the pvc pipe is 2500-1800mm.
Method above-mentioned, wherein the pore diameter of the pvc pipe is 10-15mm.
Method above-mentioned, wherein the pore adjacent spacing of the pvc pipe is 100-150mm.
Method above-mentioned, wherein one end of the stretching waterproof roll of the integrate draining pipe is arranged to >=45oBackslash cuts the gradient, Roofing layer is entered by integrate draining pipe with rainwater-proof.
After adopting the above technical scheme, integrate draining pipe roof leakage control method of the invention has the advantage that
1, integrate draining pipe structure is simple, easy to make;
2, construction quality is safe and reliable, seepage prevention and treatment is had excellent performance;
3, integrate draining pipe is low in cost, reduces engineering cost.
Detailed description of the invention
Fig. 1 is the pvc pipe manufacturing process schematic diagram of the embodiment of the present invention, will be cut into along axis to cutting secant in pvc pipe Two semicanals;
Fig. 2 is the structural schematic diagram under the pvc pipe use state of the embodiment of the present invention, and it is 45 that backslash, which cuts angle of slope,o
Fig. 3 is position view of the pvc pipe of the embodiment of the present invention in roof construction layer;
Fig. 4 is the use state diagram of the pvc pipe of the embodiment of the present invention.
In figure: 1PVC pipe, 2 pores, 3 axis are to cutting secant, 4 roof construction layers, 5 screed-coats, 6 waterproof rolls, 7 heat preservations Layer, 8 protective layers, 9 downpipes, 10 gutter spout funnels.
Specific embodiment
With reference to embodiments and its attached drawing further explains the present invention.
Embodiment 1
Integrate draining pipe roof leakage control method of the invention, comprising the following steps:
A, prefabricated integrate draining pipe.Referring now to Fig. 1, Fig. 1 is the pvc pipe manufacturing process schematic diagram of the embodiment of the present invention, by pvc pipe It is middle that two semicanals are cut into cutting secant along axis.As shown, the prefabricated integrate draining pipe: integrate draining pipe is using outer diameter The pvc pipe production of 50mm, thickness 2.5mm, production method: according to roofing size, are cut into 1800mm length for pvc pipe, along PVC Pipe axis brill/punching, bore dia are preferably 15mm, and two pitchs of holes are preferably 150mm, and pvc pipe is finally cut into two and half along axis Pipe.
B, it is laid with prefabricated integrate draining pipe.Fig. 2 is the structural schematic diagram under 1 use state of pvc pipe of the embodiment of the present invention, It is 45 that backslash, which cuts angle of slope,o.According to Roof Design, roofing screed-coat 5 is laid on roof construction layer 4, on roofing screed-coat Laying water-proof coiled material 6, it is horizontal on waterproof roll to be laid with integrate draining pipe, contact the end face with half bore of integrate draining pipe downwards Waterproof roll, integrate draining pipe other side arc surface are in top, make one end of integrate draining pipe in waterproof roll, and the other end stretches out Waterproof roll enters in gutter spout funnel 10, overboard warp.One end of the stretching waterproof roll of the integrate draining pipe is arranged to 45oBackslash is cut The gradient enters roofing layer by integrate draining pipe with rainwater-proof.
C, it is laid with insulating layer: being laid with insulating layer on prefabricated integrate draining pipe, wrap up the thermal insulation material of insulating layer all and cover Lid integrate draining pipe downpipe 9 is drained.
D, it is laid with roof protecting layer: in prefabricated integrate draining pipe, i.e., being laid with insulating layer 7 on pvc pipe 1, be arranged on insulating layer Protective layer 8 is completed integrate draining pipe and is laid with.
It should be noted that collector pipe is placed in waterproof layer in integrate draining pipe roof leakage control method implementation process of the invention On, in insulating layer, wherein one section extends at drain gully, expose to outside each techonosphere of roofing;Adhesive tape can be used in the placement of integrate draining pipe Etc. being fixed temporarily, every collector pipe, which is fixed temporarily, to be a little no less than at three;Roof slope making layer answers firm, damaged without loose, draining The gradient should be correct, no adverse slope phenomenon;Roof waterproof layer construction should meet code requirement, and no breakage, drainage grade should be correct, connector Act in accordance with drainage direction.
The present invention has substantive distinguishing features and significant technological progress, integrate draining pipe roof leakage prevention and treatment side of the invention Method, integrate draining pipe structure are simple, easy to make.
Integrate draining pipe roof leakage control method of the invention is in Hexi Area, Nanjing lotus flower village Low Cost Residence projects Middle utilization, method is simple, low in cost, significant effect.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field Member, without departing from the spirit and scope of the present invention, can also make various transformation or variation.Therefore, all equivalent Technical solution also should belong to scope of the invention, should be limited by each claim.

Claims (6)

1. a kind of integrate draining pipe roof leakage control method, it is characterised in that the following steps are included:
A, prefabricated integrate draining pipe
Prefabricated integrate draining pipe: integrate draining pipe is made using 50 specification pvc pipes, production method: according to roofing size, by 50 specifications PVC is cut into the length of needs, drills along pvc pipe axis, pvc pipe is finally cut into two semicanals along axis, is put into semicanal It uses;
B, it is laid with prefabricated integrate draining pipe
According to Roof Design, roofing screed-coat, the laying water-proof coiled material on roofing screed-coat, anti-are laid on roof construction layer It is horizontal on water coiled material to be laid with integrate draining pipe, so that the end face with half bore of integrate draining pipe is contacted waterproof roll, integrate draining pipe downwards Other side arc surface is in top, makes one end of integrate draining pipe in waterproof roll, and other end stretching waterproof roll enters overboard In bucket;
C, it is laid with insulating layer
It is laid with insulating layer on prefabricated integrate draining pipe, the thermal insulation material of insulating layer is made all to wrap up covering integrate draining pipe;
D, it is laid with roof protecting layer
It is laid with insulating layer on prefabricated integrate draining pipe, completes integrate draining pipe and is laid with.
2. integrate draining pipe roof leakage control method as described in claim 1, which is characterized in that the outer diameter of the pvc pipe is >=50mm, thickness 2.5mm.
3. integrate draining pipe roof leakage control method as described in claim 1, which is characterized in that the length of the pvc pipe is 2500-1800mm。
4. integrate draining pipe roof leakage control method as described in claim 1, which is characterized in that the pore of the pvc pipe is straight Diameter is 10-15mm.
5. integrate draining pipe roof leakage control method as described in claim 1, which is characterized in that the pore phase of the pvc pipe Adjacent spacing is 100-150mm.
6. integrate draining pipe roof leakage control method as described in claim 1, which is characterized in that the stretching of the integrate draining pipe One end of waterproof roll is arranged to >=45oBackslash cuts the gradient, enters roofing layer by integrate draining pipe with rainwater-proof.
CN201811457935.7A 2018-11-30 2018-11-30 A kind of integrate draining pipe roof leakage control method Pending CN109537819A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811457935.7A CN109537819A (en) 2018-11-30 2018-11-30 A kind of integrate draining pipe roof leakage control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811457935.7A CN109537819A (en) 2018-11-30 2018-11-30 A kind of integrate draining pipe roof leakage control method

Publications (1)

Publication Number Publication Date
CN109537819A true CN109537819A (en) 2019-03-29

Family

ID=65851901

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811457935.7A Pending CN109537819A (en) 2018-11-30 2018-11-30 A kind of integrate draining pipe roof leakage control method

Country Status (1)

Country Link
CN (1) CN109537819A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0943747B1 (en) * 1998-03-20 2002-05-29 Wolfgang Dipl.-Ing. Vahlbrauk Waterdraining method and apparatus for a substantially plane surface
CN2758354Y (en) * 2004-12-14 2006-02-15 万科企业股份有限公司 Inversion type roof surface having blind drain
CN101148932A (en) * 2007-11-13 2008-03-26 贵州中建建筑科研设计院 Thermal insulation waterproof roof covering gas-guiding drainage system and construction method thereof
CN203008251U (en) * 2012-11-28 2013-06-19 广西建工集团第三建筑工程有限责任公司 Comprehensive drainage and exhaust system with guide pipe embedded into inverted roof insulating layer

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0943747B1 (en) * 1998-03-20 2002-05-29 Wolfgang Dipl.-Ing. Vahlbrauk Waterdraining method and apparatus for a substantially plane surface
CN2758354Y (en) * 2004-12-14 2006-02-15 万科企业股份有限公司 Inversion type roof surface having blind drain
CN101148932A (en) * 2007-11-13 2008-03-26 贵州中建建筑科研设计院 Thermal insulation waterproof roof covering gas-guiding drainage system and construction method thereof
CN203008251U (en) * 2012-11-28 2013-06-19 广西建工集团第三建筑工程有限责任公司 Comprehensive drainage and exhaust system with guide pipe embedded into inverted roof insulating layer

Similar Documents

Publication Publication Date Title
CN201695580U (en) Inverted roof structure
CN206337739U (en) A kind of heat insulating and water proof structure of parapet root
CN205712797U (en) A kind of drainage system on building roof
CN102912945B (en) Roof compound seepage-proofing steam exhausting hole detail treatment technology
CN208396162U (en) A kind of thermal isolation by water storage roofing
CN109537819A (en) A kind of integrate draining pipe roof leakage control method
CN210713558U (en) A prevent arranging integrative waterproof system, building for house roof
CN217128772U (en) Inverted roof drainage structure
CN205894523U (en) Roof drainage mouth waterproof insulation structure
CN204715638U (en) A kind of roof covering water-proof structure
CN206128463U (en) Flat roof deck heat insulative and water -proof structure
CN211396308U (en) Waterproof structure of pitched roof eaves gutter
CN211037568U (en) Plant vegetation roof waterproof construction
CN217500838U (en) Sloping tile roofing pipe shaft structure
CN202787726U (en) Anti-leakage roof drainage gutter
CN206408645U (en) A kind of pipe gallery guard system structure
CN220550770U (en) Antiseep device for roof of high-rise building
CN212534233U (en) Basement roof waterproof construction
CN217079425U (en) Water accumulation preventing drainage guide structure in roof
CN216740416U (en) A antiseep structure that is used for severe cold district to reform transform flat roofing
CN220686540U (en) Leakage-free structure of flat slope roof
CN220620749U (en) Building roof structure
CN204531210U (en) Open valley crosses water-bound
CN217128760U (en) Roof waterproof structure
CN202689366U (en) Double-drain-pipe structure of building roof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190329