CN109518556A - The Prefabricated road plate and its manufacturing method and Joining Technology of a kind of bolt with one end bent back connection - Google Patents

The Prefabricated road plate and its manufacturing method and Joining Technology of a kind of bolt with one end bent back connection Download PDF

Info

Publication number
CN109518556A
CN109518556A CN201811562328.7A CN201811562328A CN109518556A CN 109518556 A CN109518556 A CN 109518556A CN 201811562328 A CN201811562328 A CN 201811562328A CN 109518556 A CN109518556 A CN 109518556A
Authority
CN
China
Prior art keywords
plate
bolt
prefabricated
bent back
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811562328.7A
Other languages
Chinese (zh)
Other versions
CN109518556B (en
Inventor
张耀东
王岳平
阚卫明
安秀山
刘祥玉
石啸
宋军港
宫云增
刘军其
刘志军
孙宗津
薛顶勇
王也枫
李宝闯
李龙
郑中华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hsiung Hsiung An Investment Co Ltd
TIANJIN PORT ENGINEERING DESIGN&CONSULTING Co Ltd OF CCCC FIRST HARBOR ENGINEERING Co Ltd
China Xiongan Group Infrastructure Co Ltd
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
Hsiung Hsiung An Investment Co Ltd
TIANJIN PORT ENGINEERING DESIGN&CONSULTING Co Ltd OF CCCC FIRST HARBOR ENGINEERING Co Ltd
China Xiongan Group Infrastructure Co Ltd
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hsiung Hsiung An Investment Co Ltd, TIANJIN PORT ENGINEERING DESIGN&CONSULTING Co Ltd OF CCCC FIRST HARBOR ENGINEERING Co Ltd, China Xiongan Group Infrastructure Co Ltd, CCCC First Harbor Engineering Co Ltd, No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical Hsiung Hsiung An Investment Co Ltd
Priority to CN201811562328.7A priority Critical patent/CN109518556B/en
Publication of CN109518556A publication Critical patent/CN109518556A/en
Application granted granted Critical
Publication of CN109518556B publication Critical patent/CN109518556B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C5/00Pavings made of prefabricated single units
    • E01C5/06Pavings made of prefabricated single units made of units with cement or like binders
    • E01C5/08Reinforced units with steel frames
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/08Producing shaped prefabricated articles from the material by vibrating or jolting
    • B28B1/093Producing shaped prefabricated articles from the material by vibrating or jolting by means directly acting on the material, e.g. by cores wholly or partly immersed in the material or elements acting on the upper surface of the material
    • B28B1/0935Producing shaped prefabricated articles from the material by vibrating or jolting by means directly acting on the material, e.g. by cores wholly or partly immersed in the material or elements acting on the upper surface of the material using only elements wholly or partly immersed in the material, e.g. cores
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/0056Means for inserting the elements into the mould or supporting them in the mould
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0002Auxiliary parts or elements of the mould
    • B28B7/0014Fastening means for mould parts, e.g. for attaching mould walls on mould tables; Mould clamps
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0002Auxiliary parts or elements of the mould
    • B28B7/0014Fastening means for mould parts, e.g. for attaching mould walls on mould tables; Mould clamps
    • B28B7/002Fastening means for mould parts, e.g. for attaching mould walls on mould tables; Mould clamps using magnets
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0029Moulds or moulding surfaces not covered by B28B7/0058 - B28B7/36 and B28B7/40 - B28B7/465, e.g. moulds assembled from several parts
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention provides the Prefabricated road plate and its manufacturing method and Joining Technology of a kind of connection of bolt with one end bent back, including roads plate main body, roads plate body top is equipped with horseshoe slot, arcuate socket is equipped in roads plate main body, steps are as follows for Specific construction: being carried using first artificial assembling reinforcement mesh sheet, then entirety into mould working procedure;Template construction is placed in dedicated steel platform after side form is assembled and enters to avoid release agent to pollute prefabricated board reinforcing bar in mold process;Installation of embedded parts, Prefabricated road plate need pre-buried horseshoe slot before pouring, and horseshoe slot makes to be fixed by bolts on position-limited rack;Pre-buried convex, recessed iron plate is distinguished on four side of prefab-form;Concrete construction vibrates to use and manually vibrate, uniform jolt ramming;Concrete curing, molding Prefabricated road plate is placed into steam-cured slot using elevator carry out it is steam-cured.The beneficial effects of the present invention are: first, cost is relatively low.Second, safety coefficient is high.Third, construction efficiency are high.4th, construction quality is guaranteed.5th, environmental pollution is small.

Description

The Prefabricated road plate and its manufacturing method and Joining Technology of a kind of bolt with one end bent back connection
Technical field
The present invention relates to the Prefabricated road plates that Prefabricated road plate technology field more particularly to a kind of bolt with one end bent back connect And its manufacturing method and Joining Technology.
Background technique
Currently, temporary road mostly uses the way of traditional concrete cast-in-situ road surface technique, such pavement construction time compared with It is long, and consume a large amount of manpower;Construction period all can be to construction to the passage that material and other vehicles are transported in construction site Duration brings adverse effect.Moreover, it after to temporary road use, also needs to abolish place road surface, not only need A large amount of manpowers are put into, and will cause material and environment, do not meet the requirement of green construction and sustainable development.In addition, Traditional work mode open work, process are intersected, and there are some potential safety problemss.
Summary of the invention
Present invention seek to address that the deficiencies in the prior art, and the Prefabricated road plate and its system of a kind of bolt with one end bent back connection are provided Make method and Joining Technology.
The present invention to achieve the above object, using following technical scheme:
A kind of Prefabricated road plate of bolt with one end bent back connection, the roads plate main body including prolate cube, roads plate body top Equipped with several horseshoe slots, equipped with several arcuate sockets passed through for elbow connection bolt, the both ends of arcuate socket in roads plate main body It is connected respectively with the side wall of roads plate main body and horseshoe slot, the two neighboring side of roads plate main body is installed with noseiron plate, road The adjacent side of the another two of plate main body is equipped with recessed iron plate, and noseiron plate and recessed iron plate are respectively positioned on the arc in roads plate main body wall At shape hole, noseiron plate and recessed iron plate are equipped with the through-hole to match with arcuate socket, and noseiron plate is equipped with convex block, and recessed iron plate is equipped with The groove to match with the convex block on noseiron plate, roads plate body top, which is fixedly provided with, several hangs nail.
Preferably, noseiron plate and recessed iron plate are in the equal spaced set in roads plate main body two sides and both ends, roads plate main body two The noseiron plate of side and recessed iron plate position are corresponding, and the noseiron plate at roads plate main body both ends and recessed iron plate position are corresponding.
Preferably, roads plate main body includes concrete segment and two blocks of prefabricated board reinforcing bars being embedded in concrete segment, Prefabricated board reinforcing bar includes reinforced mesh, and reinforced mesh includes several transverse bars and several vertical muscle of binding together, reinforced mesh four Angle is installed with the radiation tendon for reinforced steel mesh sheet.
A kind of manufacturing method of the Prefabricated road plate of bolt with one end bent back connection, the specific steps are as follows:
Step 1, reinforcing bar binding
Prefabricated board reinforcing bar is integrally carried into mould working procedure, reinforcing bar uses when binding using first artificial assembling reinforcement mesh sheet Position-limited rack controls spacing between vertical muscle between transverse bar, and galvanized wire will securely when binding, and binding galvanized wire head should be pressed to reinforcing bar side , galvanized wire button is some tripping bindings in blossom type interval when assembling reinforcement mesh sheet;Cover to reinforcement is controlled using plastic cushion, Prefabricated board reinforcing bar bottom plastic cushion block spacing is 1m;
Step 2, template construction
Prefab-form uses set shaped steel formwork, and set shaped steel formwork includes four side forms, is placed on after side form is assembled dedicated It in steel platform, is bolted between side form and side form, magnetic holder Joining Technology is used between side form and steel platform;It is wanted in construction Guarantee all bolt fastening connections, all magnetic holders all press securely;Before assembled prefab-form will lime-ash to prefab-form surface, Sundries is cleared up, while using angle grinder polishing prefab-form, guaranteeing that its any surface finish is rustless, then uniform brushing release agent, Prefabricated board reinforcing bar clears up prefabricated board reinforcing bar using cleaning platform before entering mould, enters to avoid release agent pollution pre- in mold process Making sheet reinforcing bar;
Step 3, installation of embedded parts
Prefabricated road plate suspension centre hangs nail technique using pre-buried, before concreting using with hang the matched ball of nail and fix Nail is hung, then makes to be fixed by bolts on position-limited rack by ball, prevents from being subjected to displacement when concreting;After concrete formation Ball is deducted, concrete component is then hoisted to component storage area using duckbilled hanging ring;
Prefabricated road plate needs pre-buried horseshoe box before pouring, connection of the horseshoe slot formed after pouring as bolt with one end bent back Bore ends, horseshoe box make to be fixed by bolts on position-limited rack;Pre-buried noseiron plate, recessed iron plate and curved are distinguished on four side of prefab-form Pipe, noseiron plate and recessed iron plate are used to increase the bonding strength between adjacent road plate, and bend pipe is for arcuate socket reserved when pouring;
Step 4, concrete construction
The slump of concrete is controlled within the scope of 130-150mm, vibrates to use and manually vibrate, prefab-form edge It is manually vibrated using 50 poker vibrator of Ф, vibrates sequence since at nearly prefab-form, first outside and then inside, moving distance No more than 550mm, the distance of vibrator to template is not more than 150mm, avoids vibrator collision prefab-form and prefabricated board reinforcing bar, It is inserted perpendicularly into concrete when vibrating, and inserts pull out slowly fastly, twitched up and down, with the uniform jolt ramming of benefit;
Step 5, concrete curing
After the completion of concreting, molding Prefabricated road plate is placed into steam-cured slot using elevator carry out it is steam-cured.
Preferably, the reinforcing bar model HRB400 Φ 14 that the reinforced mesh in step 1 uses.
Preferably, vibrating time is 15-20s in step 4.
Preferably, steam curing process process in step 5 are as follows: 2 hours first are stood, 20-25 DEG C of dwell temperature, then it is warming up to 50- 55 DEG C are kept for 2 hours, are finally cooled to 20-25 DEG C and are kept for 2 hours.
Preferably, temperature-rise period and temperature-fall period are 2 hours.
Preferably, when placing plastic cushion in step 1, three pieces are placed along prefabricated board reinforcing bar length direction, width direction is put Set two pieces.
A kind of Joining Technology of the Prefabricated road plate of bolt with one end bent back connection, the specific steps are as follows:
Several blocks of Prefabricated road plates are stitched together by step a, one piece of Prefabricated road in two blocks of adjacent Prefabricated road plates The convex block on noseiron plate on plate is inserted in the groove of the recessed iron plate on another block of Prefabricated road plate, is made in two blocks of Prefabricated road plates Two opposite arcuate sockets dock and constitute a U-shaped hole;
Bolt with one end bent back is penetrated from one end of U-shaped hole and is pierced by from the other end by step b, and the bolt head of bolt with one end bent back resists U The horseshoe slot inner wall of shape hole one end;
Step c makes it resist the horseshoe slot inner wall of the U-shaped hole other end by nut tightening in the tail portion of bolt with one end bent back, adjacent Two Prefabricated road plates can be linked together by bolt with one end bent back.
Compared with prior art the beneficial effects of the present invention are:
First, cost is relatively low.The investment for reducing live reinforcing bar, template, manpower, substantially reduces production cost.
Second, safety coefficient is high.Prefabricated road plate is by the prefabricated unified production of batch production, and construction site is unified to install, technique Simply, security risk is reduced.
Third, construction efficiency are high.Reduce the transport of live material, improves construction efficiency.
4th, construction quality is guaranteed.Batch production is prefabricated, can preferably control concrete pouring quality, reduces concrete Hidden danger of quality caused by crack.
5th, environmental pollution is small.The environmental pollutions such as air, noise caused by site operation are reduced, greenization is met Demand for development.
Detailed description of the invention
Fig. 1 is the main view of the Prefabricated road plate of bolt with one end bent back connection;
Fig. 2 is the top view of the Prefabricated road plate of bolt with one end bent back connection;
Fig. 3 is the cross-sectional view in Fig. 2 at A-A;
Fig. 4 is the structural schematic diagram of prefabricated board reinforcing bar;
In figure: 1- roads plate main body;2- horseshoe slot;3- arcuate socket;4- noseiron plate;The recessed iron plate of 5-;6- hangs nail;7- is prefabricated Slab muscle;71- transverse bar;72- indulges muscle;73- radiation tendon;
It is described in detail below with reference to the embodiment of the present invention referring to attached drawing.
Specific embodiment
Below with reference to embodiment, the invention will be further described:
A kind of Prefabricated road plate of bolt with one end bent back connection, the roads plate main body 1 including prolate cube, roads plate main body 1 are pushed up Portion is equipped with several horseshoe slots 2, and several arcuate sockets 3 passed through for elbows connection bolt, arcuate socket 3 are equipped in roads plate main body 1 Both ends be connected respectively with the side wall of roads plate main body 1 and horseshoe slot 2, the two neighboring side of roads plate main body 1 is installed with convex Iron plate 4, the adjacent side of the another two of roads plate main body 1 are equipped with recessed iron plate 5, and noseiron plate 4 and recessed iron plate 5 are respectively positioned on roads plate At arcuate socket 3 on 1 side wall of main body, noseiron plate 4 and recessed iron plate 5 are equipped with the through-hole to match with arcuate socket 3, on noseiron plate 4 Equipped with convex block, recessed iron plate 5 is equipped with the groove to match with the convex block on noseiron plate 4, if being fixedly provided at the top of roads plate main body 1 It is dry to hang nail 6.
Preferably, noseiron plate 4 and recessed iron plate 5 are in the equal spaced set in 1 two sides of roads plate main body and both ends, roads plate main body The noseiron plate 4 of 1 two sides and 5 position of recessed iron plate are corresponding, and the noseiron plate 4 at 1 both ends of roads plate main body is opposite with recessed 5 position of iron plate It answers.
Preferably, roads plate main body 1 includes concrete segment and two blocks of prefabricated board reinforcing bars being embedded in concrete segment 7, prefabricated board reinforcing bar 7 includes reinforced mesh, and reinforced mesh includes several transverse bars 71 and several vertical muscle 72 of binding together, steel Muscle mesh sheet quadrangle is installed with the radiation tendon 73 for reinforced steel mesh sheet.
A kind of manufacturing method of the Prefabricated road plate of bolt with one end bent back connection, the specific steps are as follows:
Step 1, reinforcing bar binding
Prefabricated board reinforcing bar 7 is integrally carried into mould working procedure, reinforcing bar uses when binding using first artificial assembling reinforcement mesh sheet Position-limited rack controls spacing between vertical muscle 72 between transverse bar 71, and galvanized wire will securely when binding, and binding galvanized wire head should be to reinforcing bar side Face is pushed down, and galvanized wire button is that some trippings in blossom type interval are bound when assembling reinforcement mesh sheet;Reinforcing bar guarantor is controlled using plastic cushion Sheath, 7 bottom plastic cushion block spacing of prefabricated board reinforcing bar is 1m;
Step 2, template construction
Prefab-form uses set shaped steel formwork, and set shaped steel formwork includes four side forms, is placed on after side form is assembled dedicated It in steel platform, is bolted between side form and side form, magnetic holder Joining Technology is used between side form and steel platform;It is wanted in construction Guarantee all bolt fastening connections, all magnetic holders all press securely;Before assembled prefab-form will lime-ash to prefab-form surface, Sundries is cleared up, while using angle grinder polishing prefab-form, guaranteeing that its any surface finish is rustless, then uniform brushing release agent, Prefabricated board reinforcing bar 7 clears up prefabricated board reinforcing bar 7 using cleaning platform before entering mould, and entering in mold process will avoid release agent from polluting Prefabricated board reinforcing bar 7;
Step 3, installation of embedded parts
Prefabricated road plate suspension centre hangs 6 techniques of nail using pre-buried, before concreting using with to hang 6 matched balls of nail solid Surely nail 6 is hung, then makes to be fixed by bolts on position-limited rack by ball, prevents from being subjected to displacement when concreting;Concrete at Ball is deducted after type, concrete component is then hoisted to component storage area using duckbilled hanging ring;
Prefabricated road plate needs pre-buried horseshoe box before pouring, company of the horseshoe slot 2 formed after pouring as bolt with one end bent back Bore ends are connect, horseshoe box makes to be fixed by bolts on position-limited rack;Pre-buried noseiron plate 4,5 and of recessed iron plate are distinguished on four side of prefab-form Bend pipe, noseiron plate 4 and recessed iron plate 5 are used to increase the bonding strength between adjacent road plate, and bend pipe is for arc reserved when pouring Hole 3;
Step 4, concrete construction
The slump of concrete is controlled within the scope of 130-150mm, vibrates to use and manually vibrate, prefab-form edge It is manually vibrated using 50 poker vibrator of Ф, vibrates sequence since at nearly prefab-form, first outside and then inside, moving distance No more than 550mm, the distance of vibrator to template is not more than 150mm, avoids vibrator collision prefab-form and prefabricated board reinforcing bar 7, it is inserted perpendicularly into concrete when vibrating, and insert pull out slowly fastly, twitches up and down, with the uniform jolt ramming of benefit;
Step 5, concrete curing
After the completion of concreting, molding Prefabricated road plate is placed into steam-cured slot using elevator carry out it is steam-cured.
Preferably, the reinforcing bar model HRB400 Φ 14 that the reinforced mesh in step 1 uses.
Preferably, vibrating time is 15-20s in step 4.
Preferably, steam curing process process in step 5 are as follows: 2 hours first are stood, 20-25 DEG C of dwell temperature, then it is warming up to 50- 55 DEG C are kept for 2 hours, are finally cooled to 20-25 DEG C and are kept for 2 hours.
Preferably, temperature-rise period and temperature-fall period are 2 hours.
Preferably, when placing plastic cushion in step 1, three pieces are placed along 7 length direction of prefabricated board reinforcing bar, width direction Place two pieces.
A kind of Joining Technology of the Prefabricated road plate of bolt with one end bent back connection, the specific steps are as follows:
Several blocks of Prefabricated road plates are stitched together by step a, one piece of Prefabricated road in two blocks of adjacent Prefabricated road plates The convex block on noseiron plate 4 on plate is inserted in the groove of the recessed iron plate 5 on another block of Prefabricated road plate, makes two blocks of Prefabricated road plates In opposite two arcuate sockets 3 dock and constitute a U-shaped hole;
Bolt with one end bent back is penetrated from one end of U-shaped hole and is pierced by from the other end by step b, and the bolt head of bolt with one end bent back resists U 2 inner wall of horseshoe slot of shape hole one end;
Step c makes it resist 2 inner wall of horseshoe slot of the U-shaped hole other end, phase by nut tightening in the tail portion of bolt with one end bent back Two adjacent Prefabricated road plates can be linked together by bolt with one end bent back.
Embodiment one
A kind of Prefabricated road plate of bolt with one end bent back connection, the roads plate main body 1 including prolate cube, roads plate main body 1 are pushed up Portion is equipped with several horseshoe slots 2, and several arcuate sockets 3 passed through for elbows connection bolt, arcuate socket 3 are equipped in roads plate main body 1 Both ends be connected respectively with the side wall of roads plate main body 1 and horseshoe slot 2, the two neighboring side of roads plate main body 1 is installed with convex Iron plate 4, the adjacent side of the another two of roads plate main body 1 are equipped with recessed iron plate 5, and noseiron plate 4 and recessed iron plate 5 are respectively positioned on roads plate At arcuate socket 3 on 1 side wall of main body, noseiron plate 4 and recessed iron plate 5 are equipped with the through-hole to match with arcuate socket 3, on noseiron plate 4 Equipped with convex block, recessed iron plate 5 is equipped with the groove to match with the convex block on noseiron plate 4, if being fixedly provided at the top of roads plate main body 1 It is dry to hang nail 6.
Preferably, noseiron plate 4 and recessed iron plate 5 are in the equal spaced set in 1 two sides of roads plate main body and both ends, roads plate main body The noseiron plate 4 of 1 two sides and 5 position of recessed iron plate are corresponding, and the noseiron plate 4 at 1 both ends of roads plate main body is opposite with recessed 5 position of iron plate It answers.
Preferably, roads plate main body 1 includes concrete segment and two blocks of prefabricated board reinforcing bars being embedded in concrete segment 7, prefabricated board reinforcing bar 7 includes reinforced mesh, and reinforced mesh includes several transverse bars 71 and several vertical muscle 72 of binding together, reinforcing bar Mesh sheet quadrangle is installed with the radiation tendon 73 for reinforced steel mesh sheet.
A kind of manufacturing method of the Prefabricated road plate of bolt with one end bent back connection, the specific steps are as follows:
Step 1, reinforcing bar binding
Prefabricated board reinforcing bar 7 is integrally carried into mould working procedure, reinforcing bar uses when binding using first artificial assembling reinforcement mesh sheet Position-limited rack controls spacing between vertical muscle 72 between transverse bar 71, and galvanized wire will securely when binding, and binding galvanized wire head should be to reinforcing bar side Face is pushed down, and galvanized wire button is that some trippings in blossom type interval are bound when assembling reinforcement mesh sheet;Reinforcing bar guarantor is controlled using plastic cushion Sheath, 7 bottom plastic cushion block spacing of prefabricated board reinforcing bar is 1m;
Step 2, template construction
Prefab-form uses set shaped steel formwork, and set shaped steel formwork includes four side forms, is placed on after side form is assembled dedicated It in steel platform, is bolted between side form and side form, magnetic holder Joining Technology is used between side form and steel platform;It is wanted in construction Guarantee all bolt fastening connections, all magnetic holders all press securely;Before assembled prefab-form will lime-ash to prefab-form surface, Sundries is cleared up, while using angle grinder polishing prefab-form, guaranteeing that its any surface finish is rustless, then uniform brushing release agent, Prefabricated board reinforcing bar 7 clears up prefabricated board reinforcing bar 7 using cleaning platform before entering mould, and entering in mold process will avoid release agent from polluting Prefabricated board reinforcing bar 7;
Step 3, installation of embedded parts
Prefabricated road plate suspension centre hangs 6 techniques of nail using pre-buried, before concreting using with to hang 6 matched balls of nail solid Surely nail 6 is hung, then makes to be fixed by bolts on position-limited rack by ball, prevents from being subjected to displacement when concreting;Concrete at Ball is deducted after type, concrete component is then hoisted to component storage area using duckbilled hanging ring;
Prefabricated road plate needs pre-buried horseshoe box before pouring, company of the horseshoe slot 2 formed after pouring as bolt with one end bent back Bore ends are connect, horseshoe box makes to be fixed by bolts on position-limited rack;Pre-buried noseiron plate 4,5 and of recessed iron plate are distinguished on four side of prefab-form Bend pipe, noseiron plate 4 and recessed iron plate 5 are used to increase the bonding strength between adjacent road plate, and bend pipe is for arc reserved when pouring Hole 3;
Step 4, concrete construction
The slump of concrete is controlled within the scope of 130mm, is vibrated using manually vibrating, prefab-form edge uses 50 poker vibrator of Ф is manually vibrated, and vibrates sequence since at nearly prefab-form, first outside and then inside, moving distance is little It is not more than 150mm in the distance of 550mm, vibrator to template, avoids vibrator collision prefab-form and prefabricated board reinforcing bar 7, vibration It is inserted perpendicularly into concrete when smashing, and inserts pull out slowly fastly, twitched up and down, with the uniform jolt ramming of benefit;
Step 5, concrete curing
After the completion of concreting, molding Prefabricated road plate is placed into steam-cured slot using elevator carry out it is steam-cured.
Preferably, the reinforcing bar model HRB400 Φ 14 that the reinforced mesh in step 1 uses.
Preferably, vibrating time is 15s in step 4.
Preferably, steam curing process process in step 5 are as follows: 2 hours first are stood, 20 DEG C of dwell temperature, then it is warming up to 50 DEG C of guarantors It holds 2 hours, is finally cooled to 20 DEG C and is kept for 2 hours.
Preferably, temperature-rise period and temperature-fall period are 2 hours.
Preferably, when placing plastic cushion in step 1, three pieces are placed along 7 length direction of prefabricated board reinforcing bar, width direction Place two pieces.
A kind of Joining Technology of the Prefabricated road plate of bolt with one end bent back connection, the specific steps are as follows:
Several blocks of Prefabricated road plates are stitched together by step a, one piece of Prefabricated road in two blocks of adjacent Prefabricated road plates The convex block on noseiron plate 4 on plate is inserted in the groove of the recessed iron plate 5 on another block of Prefabricated road plate, makes two blocks of Prefabricated road plates In opposite two arcuate sockets 3 dock and constitute a U-shaped hole;
Bolt with one end bent back is penetrated from one end of U-shaped hole and is pierced by from the other end by step b, and the bolt head of bolt with one end bent back resists U 2 inner wall of horseshoe slot of shape hole one end;
Step c makes it resist 2 inner wall of horseshoe slot of the U-shaped hole other end, phase by nut tightening in the tail portion of bolt with one end bent back Two adjacent Prefabricated road plates can be linked together by bolt with one end bent back.
Embodiment two
A kind of Prefabricated road plate of bolt with one end bent back connection, the roads plate main body 1 including prolate cube, roads plate main body 1 are pushed up Portion is equipped with several horseshoe slots 2, and several arcuate sockets 3 passed through for elbows connection bolt, arcuate socket 3 are equipped in roads plate main body 1 Both ends be connected respectively with the side wall of roads plate main body 1 and horseshoe slot 2, the two neighboring side of roads plate main body 1 is installed with convex Iron plate 4, the adjacent side of the another two of roads plate main body 1 are equipped with recessed iron plate 5, and noseiron plate 4 and recessed iron plate 5 are respectively positioned on roads plate At arcuate socket 3 on 1 side wall of main body, noseiron plate 4 and recessed iron plate 5 are equipped with the through-hole to match with arcuate socket 3, on noseiron plate 4 Equipped with convex block, recessed iron plate 5 is equipped with the groove to match with the convex block on noseiron plate 4, if being fixedly provided at the top of roads plate main body 1 It is dry to hang nail 6.
Preferably, noseiron plate 4 and recessed iron plate 5 are in the equal spaced set in 1 two sides of roads plate main body and both ends, roads plate main body The noseiron plate 4 of 1 two sides and 5 position of recessed iron plate are corresponding, and the noseiron plate 4 at 1 both ends of roads plate main body is opposite with recessed 5 position of iron plate It answers.
Preferably, roads plate main body 1 includes concrete segment and two blocks of prefabricated board reinforcing bars being embedded in concrete segment 7, prefabricated board reinforcing bar 7 includes reinforced mesh, and reinforced mesh includes several transverse bars 71 and several vertical muscle 72 of binding together, steel Muscle mesh sheet quadrangle is installed with the radiation tendon 73 for reinforced steel mesh sheet.
A kind of manufacturing method of the Prefabricated road plate of bolt with one end bent back connection, the specific steps are as follows:
Step 1, reinforcing bar binding
Prefabricated board reinforcing bar 7 is integrally carried into mould working procedure, reinforcing bar uses when binding using first artificial assembling reinforcement mesh sheet Position-limited rack controls spacing between vertical muscle 72 between transverse bar 71, and galvanized wire will securely when binding, and binding galvanized wire head should be to reinforcing bar side Face is pushed down, and galvanized wire button is that some trippings in blossom type interval are bound when assembling reinforcement mesh sheet;Reinforcing bar guarantor is controlled using plastic cushion Sheath, 7 bottom plastic cushion block spacing of prefabricated board reinforcing bar is 1m;
Step 2, template construction
Prefab-form uses set shaped steel formwork, and set shaped steel formwork includes four side forms, is placed on after side form is assembled dedicated It in steel platform, is bolted between side form and side form, magnetic holder Joining Technology is used between side form and steel platform;It is wanted in construction Guarantee all bolt fastening connections, all magnetic holders all press securely;Before assembled prefab-form will lime-ash to prefab-form surface, Sundries is cleared up, while using angle grinder polishing prefab-form, guaranteeing that its any surface finish is rustless, then uniform brushing release agent, Prefabricated board reinforcing bar 7 clears up prefabricated board reinforcing bar 7 using cleaning platform before entering mould, and entering in mold process will avoid release agent from polluting Prefabricated board reinforcing bar 7;
Step 3, installation of embedded parts
Prefabricated road plate suspension centre hangs 6 techniques of nail using pre-buried, before concreting using with to hang 6 matched balls of nail solid Surely nail 6 is hung, then makes to be fixed by bolts on position-limited rack by ball, prevents from being subjected to displacement when concreting;Concrete at Ball is deducted after type, concrete component is then hoisted to component storage area using duckbilled hanging ring;
Prefabricated road plate needs pre-buried horseshoe box before pouring, company of the horseshoe slot 2 formed after pouring as bolt with one end bent back Bore ends are connect, horseshoe box makes to be fixed by bolts on position-limited rack;Pre-buried noseiron plate 4,5 and of recessed iron plate are distinguished on four side of prefab-form Bend pipe, noseiron plate 4 and recessed iron plate 5 are used to increase the bonding strength between adjacent road plate, and bend pipe is for arc reserved when pouring Hole 3;
Step 4, concrete construction
The slump of concrete is controlled within the scope of 150mm, is vibrated using manually vibrating, prefab-form edge uses 50 poker vibrator of Ф is manually vibrated, and vibrates sequence since at nearly prefab-form, first outside and then inside, moving distance is little It is not more than 150mm in the distance of 550mm, vibrator to template, avoids vibrator collision prefab-form and prefabricated board reinforcing bar 7, vibration It is inserted perpendicularly into concrete when smashing, and inserts pull out slowly fastly, twitched up and down, with the uniform jolt ramming of benefit;
Step 5, concrete curing
After the completion of concreting, molding Prefabricated road plate is placed into steam-cured slot using elevator carry out it is steam-cured.
Preferably, the reinforcing bar model HRB400 Φ 14 that the reinforced mesh in step 1 uses.
Preferably, vibrating time is 20s in step 4.
Preferably, steam curing process process in step 5 are as follows: 2 hours first are stood, 25 DEG C of dwell temperature, then it is warming up to 55 DEG C of guarantors It holds 2 hours, is finally cooled to 25 DEG C and is kept for 2 hours.
Preferably, temperature-rise period and temperature-fall period are 2 hours.
Preferably, when placing plastic cushion in step 1, three pieces are placed along 7 length direction of prefabricated board reinforcing bar, width direction Place two pieces.
A kind of Joining Technology of the Prefabricated road plate of bolt with one end bent back connection, the specific steps are as follows:
Several blocks of Prefabricated road plates are stitched together by step a, one piece of Prefabricated road in two blocks of adjacent Prefabricated road plates The convex block on noseiron plate 4 on plate is inserted in the groove of the recessed iron plate 5 on another block of Prefabricated road plate, makes two blocks of Prefabricated road plates In opposite two arcuate sockets 3 dock and constitute a U-shaped hole;
Bolt with one end bent back is penetrated from one end of U-shaped hole and is pierced by from the other end by step b, and the bolt head of bolt with one end bent back resists U 2 inner wall of horseshoe slot of shape hole one end;
Step c makes it resist 2 inner wall of horseshoe slot of the U-shaped hole other end, phase by nut tightening in the tail portion of bolt with one end bent back Two adjacent Prefabricated road plates can be linked together by bolt with one end bent back.
Embodiment three
A kind of Prefabricated road plate of bolt with one end bent back connection, the roads plate main body 1 including prolate cube, roads plate main body 1 are pushed up Portion is equipped with several horseshoe slots 2, and several arcuate sockets 3 passed through for elbows connection bolt, arcuate socket 3 are equipped in roads plate main body 1 Both ends be connected respectively with the side wall of roads plate main body 1 and horseshoe slot 2, the two neighboring side of roads plate main body 1 is installed with convex Iron plate 4, the adjacent side of the another two of roads plate main body 1 are equipped with recessed iron plate 5, and noseiron plate 4 and recessed iron plate 5 are respectively positioned on roads plate At arcuate socket 3 on 1 side wall of main body, noseiron plate 4 and recessed iron plate 5 are equipped with the through-hole to match with arcuate socket 3, on noseiron plate 4 Equipped with convex block, recessed iron plate 5 is equipped with the groove to match with the convex block on noseiron plate 4, if being fixedly provided at the top of roads plate main body 1 It is dry to hang nail 6.
Preferably, noseiron plate 4 and recessed iron plate 5 are in the equal spaced set in 1 two sides of roads plate main body and both ends, roads plate main body The noseiron plate 4 of 1 two sides and 5 position of recessed iron plate are corresponding, and the noseiron plate 4 at 1 both ends of roads plate main body is opposite with recessed 5 position of iron plate It answers.
Preferably, roads plate main body 1 includes concrete segment and two blocks of prefabricated board reinforcing bars being embedded in concrete segment 7, prefabricated board reinforcing bar 7 includes reinforced mesh, and reinforced mesh includes several transverse bars 71 and several vertical muscle 72 of binding together, steel Muscle mesh sheet quadrangle is installed with the radiation tendon 73 for reinforced steel mesh sheet.
A kind of manufacturing method of the Prefabricated road plate of bolt with one end bent back connection, the specific steps are as follows:
Step 1, reinforcing bar binding
Prefabricated board reinforcing bar 7 is integrally carried into mould working procedure, reinforcing bar uses when binding using first artificial assembling reinforcement mesh sheet Position-limited rack controls spacing between vertical muscle 72 between transverse bar 71, and galvanized wire will securely when binding, and binding galvanized wire head should be to reinforcing bar side Face is pushed down, and galvanized wire button is that some trippings in blossom type interval are bound when assembling reinforcement mesh sheet;Reinforcing bar guarantor is controlled using plastic cushion Sheath, 7 bottom plastic cushion block spacing of prefabricated board reinforcing bar is 1m;
Step 2, template construction
Prefab-form uses set shaped steel formwork, and set shaped steel formwork includes four side forms, is placed on after side form is assembled dedicated It in steel platform, is bolted between side form and side form, magnetic holder Joining Technology is used between side form and steel platform;It is wanted in construction Guarantee all bolt fastening connections, all magnetic holders all press securely;Before assembled prefab-form will lime-ash to prefab-form surface, Sundries is cleared up, while using angle grinder polishing prefab-form, guaranteeing that its any surface finish is rustless, then uniform brushing release agent, Prefabricated board reinforcing bar 7 clears up prefabricated board reinforcing bar 7 using cleaning platform before entering mould, and entering in mold process will avoid release agent from polluting Prefabricated board reinforcing bar 7;
Step 3, installation of embedded parts
Prefabricated road plate suspension centre hangs 6 techniques of nail using pre-buried, before concreting using with to hang 6 matched balls of nail solid Surely nail 6 is hung, then makes to be fixed by bolts on position-limited rack by ball, prevents from being subjected to displacement when concreting;Concrete at Ball is deducted after type, concrete component is then hoisted to component storage area using duckbilled hanging ring;
Prefabricated road plate needs pre-buried horseshoe box before pouring, company of the horseshoe slot 2 formed after pouring as bolt with one end bent back Bore ends are connect, horseshoe box makes to be fixed by bolts on position-limited rack;Pre-buried noseiron plate 4,5 and of recessed iron plate are distinguished on four side of prefab-form Bend pipe, noseiron plate 4 and recessed iron plate 5 are used to increase the bonding strength between adjacent road plate, and bend pipe is for arc reserved when pouring Hole 3;
Step 4, concrete construction
The slump of concrete is controlled within the scope of 140mm, is vibrated using manually vibrating, prefab-form edge uses 50 poker vibrator of Ф is manually vibrated, and vibrates sequence since at nearly prefab-form, first outside and then inside, moving distance is little It is not more than 150mm in the distance of 550mm, vibrator to template, avoids vibrator collision prefab-form and prefabricated board reinforcing bar 7, vibration It is inserted perpendicularly into concrete when smashing, and inserts pull out slowly fastly, twitched up and down, with the uniform jolt ramming of benefit;
Step 5, concrete curing
After the completion of concreting, molding Prefabricated road plate is placed into steam-cured slot using elevator carry out it is steam-cured.
Preferably, the reinforcing bar model HRB400 Φ 14 that the reinforced mesh in step 1 uses.
Preferably, vibrating time is 16s in step 4.
Preferably, steam curing process process in step 5 are as follows: 2 hours first are stood, 22 DEG C of dwell temperature, then it is warming up to 53 DEG C of guarantors It holds 2 hours, is finally cooled to 21 DEG C and is kept for 2 hours.
Preferably, temperature-rise period and temperature-fall period are 2 hours.
Preferably, when placing plastic cushion in step 1, three pieces are placed along 7 length direction of prefabricated board reinforcing bar, width direction Place two pieces.
A kind of Joining Technology of the Prefabricated road plate of bolt with one end bent back connection, the specific steps are as follows:
Several blocks of Prefabricated road plates are stitched together by step a, one piece of Prefabricated road in two blocks of adjacent Prefabricated road plates The convex block on noseiron plate 4 on plate is inserted in the groove of the recessed iron plate 5 on another block of Prefabricated road plate, makes two blocks of Prefabricated road plates In opposite two arcuate sockets 3 dock and constitute a U-shaped hole;
Bolt with one end bent back is penetrated from one end of U-shaped hole and is pierced by from the other end by step b, and the bolt head of bolt with one end bent back resists U 2 inner wall of horseshoe slot of shape hole one end;
Step c makes it resist 2 inner wall of horseshoe slot of the U-shaped hole other end, phase by nut tightening in the tail portion of bolt with one end bent back Two adjacent Prefabricated road plates can be linked together by bolt with one end bent back.
The present invention is exemplarily described above in conjunction with specific embodiment, it is clear that the present invention implements not by upper The limitation of mode is stated, as long as using the various improvement that the inventive concept and technical scheme of the present invention carry out, or not improved straight It scoops out for other occasions, it is within the scope of the present invention.

Claims (10)

1. a kind of Prefabricated road plate of bolt with one end bent back connection, the roads plate main body (1) including prolate cube, which is characterized in that road It is equipped with several horseshoe slots (2) at the top of road plate main body (1), several elbow connection bolts that are used for are equipped in roads plate main body (1) and are passed through Arcuate socket (3), the both ends of arcuate socket (3) are connected with the side wall of roads plate main body (1) and horseshoe slot (2) respectively, roads plate master Body (1) two neighboring side is installed with noseiron plate (4), and the side that the another two of roads plate main body (1) is adjacent is equipped with recessed iron Plate (5), noseiron plate (4) and recessed iron plate (5) are respectively positioned at the arcuate socket (3) on roads plate main body (1) side wall, noseiron plate (4) and Recessed iron plate (5) is equipped with the through-hole to match with arcuate socket (3), and noseiron plate (4) is equipped with convex block, recessed iron plate (5) be equipped with The groove that convex block on noseiron plate (4) matches is fixedly provided at the top of roads plate main body (1) and several hangs nail (6).
2. the Prefabricated road plate of bolt with one end bent back connection according to claim 1, which is characterized in that noseiron plate (4) and recessed iron Plate (5) is in the equal spaced set in roads plate main body (1) two sides and both ends, the noseiron plate (4) and recessed iron of roads plate main body (1) two sides Plate (5) position is corresponding, and the noseiron plate (4) at roads plate main body (1) both ends is corresponding with recessed iron plate (5) position.
3. the Prefabricated road plate of bolt with one end bent back connection according to claim 2, which is characterized in that roads plate main body (1) packet The two pieces of prefabricated board reinforcing bars (7) for including concrete segment and being embedded in concrete segment, prefabricated board reinforcing bar (7) includes steel mesh Piece, reinforced mesh include several transverse bars (71) and several vertical muscle (72) of binding together, and reinforced mesh quadrangle, which is installed with, to be used for The radiation tendon (73) of reinforced steel mesh sheet.
4. a kind of manufacturing method of the Prefabricated road plate of bolt with one end bent back connection as claimed in claim 3, which is characterized in that specific step It is rapid as follows:
Step 1, reinforcing bar binding
Prefabricated board reinforcing bar (7) is integrally carried into mould working procedure using first artificial assembling reinforcement mesh sheet, limit is used when reinforcing bar is bound Spacing vertical muscle (72) between position frame control transverse bar (71), galvanized wire will securely when binding, and binding galvanized wire head should be to reinforcing bar Side is pushed down, and galvanized wire button is that some trippings in blossom type interval are bound when assembling reinforcement mesh sheet;Reinforcing bar is controlled using plastic cushion Protective layer, prefabricated board reinforcing bar (7) bottom plastic cushion block spacing is 1m;
Step 2, template construction
Prefab-form uses set shaped steel formwork, and set shaped steel formwork includes four side forms, and it is flat to be placed on dedicated steel after side form is assembled It on platform, is bolted between side form and side form, magnetic holder Joining Technology is used between side form and steel platform;To guarantee in construction All bolt fastening connections, all magnetic holders all press securely;It will lime-ash, sundries to prefab-form surface before assembled prefab-form It is cleared up, while using angle grinder polishing prefab-form, guaranteeing that its any surface finish is rustless, then uniform brushing release agent, it is prefabricated Slab muscle (7) clears up prefabricated board reinforcing bar (7) using cleaning platform before entering mould, and entering in mold process will avoid release agent from polluting Prefabricated board reinforcing bar (7);
Step 3, installation of embedded parts
Prefabricated road plate suspension centre hangs nail (6) technique using pre-buried, before concreting using with hang the matched ball of nail (6) and consolidate Surely nail (6) are hung, then make to be fixed by bolts on position-limited rack by ball, prevent from being subjected to displacement when concreting;Concrete Ball is deducted after molding, concrete component is then hoisted to component storage area using duckbilled hanging ring;
Prefabricated road plate needs pre-buried horseshoe box before pouring, connection of the horseshoe slot (2) formed after pouring as bolt with one end bent back Bore ends, horseshoe box make to be fixed by bolts on position-limited rack;Pre-buried noseiron plate (4), recessed iron plate (5) are distinguished on four side of prefab-form And bend pipe, noseiron plate (4) and recessed iron plate (5) are used to increase the bonding strength between adjacent road plate, bend pipe is for pre- when pouring Stay arcuate socket (3);
Step 4, concrete construction
The slump of concrete is controlled within the scope of 130-150mm, is vibrated using manually vibrating, prefab-form edge uses 50 poker vibrator of Ф is manually vibrated, and vibrates sequence since at nearly prefab-form, first outside and then inside, moving distance is little It is not more than 150mm in the distance of 550mm, vibrator to template, avoids vibrator collision prefab-form and prefabricated board reinforcing bar (7), It is inserted perpendicularly into concrete when vibrating, and inserts pull out slowly fastly, twitched up and down, with the uniform jolt ramming of benefit;
Step 5, concrete curing
After the completion of concreting, molding Prefabricated road plate is placed into steam-cured slot using elevator carry out it is steam-cured.
5. the manufacturing method of the Prefabricated road plate of bolt with one end bent back connection according to claim 4, which is characterized in that step 1 In reinforced mesh use reinforcing bar model HRB400 Φ 14.
6. the manufacturing method of the Prefabricated road plate of bolt with one end bent back connection according to claim 5, which is characterized in that step 4 Middle vibrating time is 15-20s.
7. the manufacturing method of the Prefabricated road plate of bolt with one end bent back connection according to claim 6, which is characterized in that step 5 Middle steam curing process process are as follows: 2 hours first are stood, 20-25 DEG C of dwell temperature, then be warming up to 50-55 DEG C and kept for 2 hours, finally drop Temperature to 20-25 DEG C keep 2 hours.
8. the manufacturing method of the Prefabricated road plate of bolt with one end bent back connection according to claim 7, which is characterized in that heated up Journey and temperature-fall period are 2 hours.
9. the manufacturing method of the Prefabricated road plate of bolt with one end bent back connection according to claim 8, which is characterized in that step 1 When middle placement plastic cushion, three pieces are placed along prefabricated board reinforcing bar (7) length direction, width direction places two pieces.
10. a kind of Joining Technology of the Prefabricated road plate of bolt with one end bent back connection as claimed in claim 3, which is characterized in that specific Steps are as follows:
Several blocks of Prefabricated road plates are stitched together by step a, in two blocks of adjacent Prefabricated road plates on one block of Prefabricated road plate Noseiron plate (4) on convex block be inserted in the groove of the recessed iron plate (5) on another block of Prefabricated road plate, make two blocks of Prefabricated road plates In opposite two arcuate sockets (3) dock and constitute a U-shaped hole;
Bolt with one end bent back is penetrated from one end of U-shaped hole and is pierced by from the other end by step b, and the bolt head of bolt with one end bent back resists U-shaped hole Horseshoe slot (2) inner wall of one end;
Step c makes it resist horseshoe slot (2) inner wall of the U-shaped hole other end by nut tightening in the tail portion of bolt with one end bent back, adjacent Two Prefabricated road plates can be linked together by bolt with one end bent back.
CN201811562328.7A 2018-12-20 2018-12-20 Prefabricated road plate connected by elbow bolts, manufacturing method thereof and connecting process Active CN109518556B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811562328.7A CN109518556B (en) 2018-12-20 2018-12-20 Prefabricated road plate connected by elbow bolts, manufacturing method thereof and connecting process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811562328.7A CN109518556B (en) 2018-12-20 2018-12-20 Prefabricated road plate connected by elbow bolts, manufacturing method thereof and connecting process

Publications (2)

Publication Number Publication Date
CN109518556A true CN109518556A (en) 2019-03-26
CN109518556B CN109518556B (en) 2024-04-05

Family

ID=65796777

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811562328.7A Active CN109518556B (en) 2018-12-20 2018-12-20 Prefabricated road plate connected by elbow bolts, manufacturing method thereof and connecting process

Country Status (1)

Country Link
CN (1) CN109518556B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110405905A (en) * 2019-07-10 2019-11-05 中交一航局第一工程有限公司 It is a kind of to hang nail construction method for the pre-buried of precast slab
CN110593043A (en) * 2019-08-08 2019-12-20 安徽瑞澳混凝土有限公司 Concrete road easy to assemble
CN110886176A (en) * 2019-12-17 2020-03-17 山东汇通建设集团有限公司 Multifunctional assembled road fender foundation roadbed concrete side mold
CN111002443A (en) * 2019-12-24 2020-04-14 中建三局集团有限公司 Duct piece elbow bolt hole mold and implementation method thereof
CN114193600A (en) * 2022-01-24 2022-03-18 上海三一重机股份有限公司 Counterweight integrated forming manufacturing method and operation machine
CN114477875A (en) * 2022-02-28 2022-05-13 铭际建筑科技(泰兴)有限公司 High-strength concrete and prefabricated road slab prepared from same

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101097995B1 (en) * 2011-08-04 2011-12-23 콘비젼스 주식회사 Concrete modular panels for rigid paving and fast construction method
KR101389704B1 (en) * 2013-07-25 2014-04-28 김근택 Precast concrete panel for pavement and its construction method
CN206736662U (en) * 2017-05-08 2017-12-12 西京学院 A kind of job site pin-connected panel precast concrete temporary road
CN108130837A (en) * 2017-12-05 2018-06-08 上海建工七建集团有限公司 A kind of prefabricated road plate and its construction method
CN209619780U (en) * 2018-12-20 2019-11-12 中国雄安集团基础建设有限公司 A kind of Prefabricated road plate of bolt with one end bent back connection

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101097995B1 (en) * 2011-08-04 2011-12-23 콘비젼스 주식회사 Concrete modular panels for rigid paving and fast construction method
KR101389704B1 (en) * 2013-07-25 2014-04-28 김근택 Precast concrete panel for pavement and its construction method
CN206736662U (en) * 2017-05-08 2017-12-12 西京学院 A kind of job site pin-connected panel precast concrete temporary road
CN108130837A (en) * 2017-12-05 2018-06-08 上海建工七建集团有限公司 A kind of prefabricated road plate and its construction method
CN209619780U (en) * 2018-12-20 2019-11-12 中国雄安集团基础建设有限公司 A kind of Prefabricated road plate of bolt with one end bent back connection

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110405905A (en) * 2019-07-10 2019-11-05 中交一航局第一工程有限公司 It is a kind of to hang nail construction method for the pre-buried of precast slab
CN110593043A (en) * 2019-08-08 2019-12-20 安徽瑞澳混凝土有限公司 Concrete road easy to assemble
CN110886176A (en) * 2019-12-17 2020-03-17 山东汇通建设集团有限公司 Multifunctional assembled road fender foundation roadbed concrete side mold
CN111002443A (en) * 2019-12-24 2020-04-14 中建三局集团有限公司 Duct piece elbow bolt hole mold and implementation method thereof
CN114193600A (en) * 2022-01-24 2022-03-18 上海三一重机股份有限公司 Counterweight integrated forming manufacturing method and operation machine
CN114193600B (en) * 2022-01-24 2023-09-12 上海三一重机股份有限公司 Counterweight integrated forming manufacturing method and working machine
CN114477875A (en) * 2022-02-28 2022-05-13 铭际建筑科技(泰兴)有限公司 High-strength concrete and prefabricated road slab prepared from same

Also Published As

Publication number Publication date
CN109518556B (en) 2024-04-05

Similar Documents

Publication Publication Date Title
CN109518556A (en) The Prefabricated road plate and its manufacturing method and Joining Technology of a kind of bolt with one end bent back connection
CN207669500U (en) A kind of fixed production line of prestressing force superimposed sheet long-line pedestal
CN106150001B (en) A kind of fabricated assembly overall stair construction method
CN209619780U (en) A kind of Prefabricated road plate of bolt with one end bent back connection
CN207959612U (en) A kind of frame, shear wall cast-in-place structural fill wall with assembled light
CN109049294A (en) A kind of concrete prefabricated wallboard and its production technology
CN107268878A (en) The fabrication and installation method of prefabricated sandwich wallboard
CN1461372A (en) Concrete building construction form unit and manufacturing device therefor, and concrete building constructed by using concrete building construction form
CN105298015B (en) The architectural surface light-weight aseismatic partition plate integrated with wall and preparation method
CN206144031U (en) Assembled reinforced concrete constructional column and utilize system of this post
CN107740574A (en) A kind of more curved surface architectural concrete template construct methods
CN109083365A (en) A kind of production of the European high-strength cement base artificial stone moulding of assembled and mounting means
CN205444590U (en) Cast -in -place compound incubation concrete shear force wall
KR20100007009A (en) A panel block and this manufacturing and construction equipment
US3767153A (en) Platform structure
CN109676764A (en) A kind of assembly concrete out-hung panel prepares mold and preparation method
CN210011144U (en) Construction site fence prefabricated foundation
CN211566369U (en) Exempt from to receive a sandwich outer wall construction formwork
CN211850319U (en) Laminated plate
CN106182362A (en) A kind of die assembly for making concrete slit floor and application thereof
CN206123901U (en) Mould for prefabricated staircase
JP3310893B2 (en) Surface treatment method for concrete products and manufacturing formwork used for it
CN207974469U (en) A kind of European high-strength cement base artificial stone of assembled
CN207619999U (en) Cap mold
CN110405905A (en) It is a kind of to hang nail construction method for the pre-buried of precast slab

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant