CN109441113A - Roof waterproof engineering construction method - Google Patents
Roof waterproof engineering construction method Download PDFInfo
- Publication number
- CN109441113A CN109441113A CN201811599470.9A CN201811599470A CN109441113A CN 109441113 A CN109441113 A CN 109441113A CN 201811599470 A CN201811599470 A CN 201811599470A CN 109441113 A CN109441113 A CN 109441113A
- Authority
- CN
- China
- Prior art keywords
- engineering construction
- construction method
- waterproof engineering
- roof waterproof
- coiled material
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Roof Covering Using Slabs Or Stiff Sheets (AREA)
- Road Paving Structures (AREA)
Abstract
The present invention provides a kind of roof waterproof engineering construction methods, belong to the realm of building construction.This roof waterproof engineering construction method, using rubber coiled material, comprising the following steps: S1. clears up roof surface;S2. the connection structure for protruding from roof surface is pre-processed;S3. paving rubber coiled material.In step s 2, pretreatment refers to, between connection structure and roof surface, carries out chamfered.When construction, by the way that chamfering is arranged at the connection structure for protruding from roofing so that between connection structure and roofing can smooth transition guarantee waterproof effect so that rubber coiled material be enable smoothly to be bonded near connection structure.
Description
Technical field
The present invention relates to the realm of building construction, in particular to a kind of roof waterproof engineering construction method.
Background technique
During building construction, it is often necessary to carry out water-proofing treatment to roofing.It is in roofing large area bond capacity
One of roof waterproof method.
For protruding from the connection structure of roofing, due to surface irregularity, during bond capacity, it is easy hair
The phenomenon that raw edge tilts, influences waterproof effect.
Summary of the invention
The present invention provides a kind of roof waterproof engineering construction methods, it is intended to solve roof waterproof engineering in the prior art and apply
The above problem existing for work method.
The present invention is implemented as follows:
A kind of roof waterproof engineering construction method, using rubber coiled material, comprising the following steps:
S1. roof surface is cleared up;
S2. the connection structure for protruding from roof surface is pre-processed;
S3. paving rubber coiled material.
In step s 2, pretreatment refers to, between connection structure and roof surface, carries out chamfered.
In preferred embodiment of the invention, in step s 2, chamfered obtuse angle for rounded corner or.
It is further comprising the steps of in preferred embodiment of the invention:
S4. brushing protective layer.
It is further comprising the steps of in preferred embodiment of the invention:
S5. water-storing test is carried out;
Step S5 is carried out after step s 4 is completed.
In preferred embodiment of the invention, in step sl, specifically includes the following steps:
S11. the processing of the dust of roofing, sundries and remaining mortar lump is clean;
S12. roofing is made to keep drying, moisture content is not more than 9%.
In preferred embodiment of the invention, in step s3, comprising the following steps:
S31. rubber coiled material connector is handled;
S32. the paving of rubber coiled material is carried out.
In preferred embodiment of the invention, in step S31, comprising:
S311. the brushing of butyl binder is bonded after waiting default drying time in rubber coiled material joint surface.
It is further comprising the steps of in step S31 in preferred embodiment of the invention:
S312. bonding part is rolled using iron roll.
In preferred embodiment of the invention, at rubber water-proofing coiled multiple-layer overlapped, using polyurethane sealant
Sealing.
In preferred embodiment of the invention, rubber coiled material connector is closed using Polymer Mortar tooled joint.
The beneficial effects of the present invention are: the roof waterproof engineering construction method that the present invention obtains by above-mentioned design, construction
When, by the connection structure for protruding from roofing be arranged chamfering so that between connection structure and roofing can smooth transition, from
And rubber coiled material is enable smoothly to be bonded near connection structure, guarantee waterproof effect.
Specific embodiment
To keep the purposes, technical schemes and advantages of embodiment of the present invention clearer, implement below in conjunction with the present invention
The technical solution in embodiment of the present invention is clearly and completely described in content in mode, it is clear that described reality
The mode of applying is some embodiments of the invention, rather than whole embodiments.Based on the embodiment in the present invention, ability
Domain those of ordinary skill every other embodiment obtained without creative efforts, belongs to the present invention
The range of protection.Therefore, the detailed description of embodiments of the present invention presented below is not intended to limit claimed
The range of invention, but it is merely representative of selected embodiment of the invention.Based on the embodiment in the present invention, this field is common
Technical staff's every other embodiment obtained without creative efforts belongs to what the present invention protected
Range.
Embodiment
Present embodiments provide a kind of roof waterproof engineering construction method, this roof waterproof engineering construction method include with
Lower step:
S1. roof surface is cleared up;
S2. the connection structure for protruding from roof surface is pre-processed;
S3. paving rubber coiled material.
In step s 2, pretreatment refers to, between connection structure and roof surface, carries out chamfered.
Further, in the present embodiment, in step s 2, chamfered is rounded corner, and fillet size range is
100mm-150mm.In other embodiments of the invention, Taoism processing is it is also an option that the processing of falling obtuse angle.
Further, further comprising the steps of:
S4. brushing protective layer.The protective layer used rubber coiled material surface in brushing at exposed one layer.The concrete operations of step S4
Process is: exposed one layer of the rubber coiled material surface of cleaning, then the brushing protective layer on rubber coiled material surface.
Further, further comprising the steps of:
S5. water-storing test is carried out;
Step S5 is carried out after step s 4 is completed.After step s 4 is completed, water-storing test is carried out, is able to verify that roof waterproof
Whether engineering is up to standard.
Further, in step sl, specifically includes the following steps:
S11. the processing of the dust of roofing, sundries and remaining mortar lump is clean;
S12. roofing is made to keep drying, moisture content is not more than 9%.
In step 1, carry out above-mentioned roofing processing, roofing made to keep dry and clean, can be avoided sundries, dust and
Extra moisture has an adverse effect to bond effect.
Further, in step s3, comprising the following steps:
S31. rubber coiled material connector is handled;
S32. the paving of rubber coiled material is carried out.
Further, in step S31, comprising:
S311. the brushing of butyl binder is bonded after waiting default drying time in rubber coiled material joint surface.
In above-mentioned steps, the range for presetting drying time is 15 minutes to 30 minutes, in use, can be selected according to environment temperature
It selects.During the bonding process, air is squeezed out on one side with hand pressing since one end, avoid the generation of bubble.
Further, further comprising the steps of in step S31:
S312. bonding part is rolled using iron roll.After bonding is good, bonding part is rolled with iron roll, can guarantee adhesion strength.
Further, it at rubber water-proofing coiled multiple-layer overlapped, is sealed using polyurethane sealant.
Further, rubber coiled material connector is closed using Polymer Mortar tooled joint.In above-mentioned steps, the weight of Polymer Mortar
Proportion is cement: sand: 107 glue=1:3:0.15.
The foregoing is merely the preferred embodiment of the present invention, are not intended to restrict the invention, for this field
For technical staff, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any
Modification, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.
Claims (10)
1. a kind of roof waterproof engineering construction method, which is characterized in that use rubber coiled material, comprising the following steps:
S1. roof surface is cleared up;
S2. the connection structure for protruding from roof surface is pre-processed;
S3. paving rubber coiled material;
In the step S2, the pretreatment refers to, between connection structure and roof surface, carries out chamfered.
2. roof waterproof engineering construction method according to claim 1, which is characterized in that described in the step S2
Chamfered obtuse angle for rounded corner or.
3. roof waterproof engineering construction method according to claim 1, which is characterized in that further comprising the steps of:
S4. brushing protective layer.
4. roof waterproof engineering construction method according to claim 3, which is characterized in that further comprising the steps of:
S5. water-storing test is carried out;
The step S5 is carried out after the completion of the step S4.
5. roof waterproof engineering construction method according to claim 1, which is characterized in that in the step S1, specifically
The following steps are included:
S11. the processing of the dust of roofing, sundries and remaining mortar lump is clean;
S12. roofing is made to keep drying, moisture content is not more than 9%.
6. roof waterproof engineering construction method according to claim 1, which is characterized in that in the step S3, including
Following steps:
S31. rubber coiled material connector is handled;
S32. the paving of rubber coiled material is carried out.
7. roof waterproof engineering construction method according to claim 6, which is characterized in that in the step S31, packet
It includes:
S311. the brushing of butyl binder is bonded after waiting default drying time in rubber coiled material joint surface.
8. roof waterproof engineering construction method according to claim 7, which is characterized in that in the step S31, also wrap
Include following steps:
S312. bonding part is rolled using iron roll.
9. roof waterproof engineering construction method according to claim 8, which is characterized in that in rubber water-proofing coiled multilayer
Overlapping is sealed using polyurethane sealant.
10. roof waterproof engineering construction method according to claim 9, which is characterized in that sealed using Polymer Mortar tooled joint
Close rubber coiled material connector.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811599470.9A CN109441113A (en) | 2018-12-26 | 2018-12-26 | Roof waterproof engineering construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811599470.9A CN109441113A (en) | 2018-12-26 | 2018-12-26 | Roof waterproof engineering construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109441113A true CN109441113A (en) | 2019-03-08 |
Family
ID=65538138
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811599470.9A Pending CN109441113A (en) | 2018-12-26 | 2018-12-26 | Roof waterproof engineering construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109441113A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110512750A (en) * | 2019-09-09 | 2019-11-29 | 安徽法莱科技有限公司 | A kind of Polymeric water repellent material manufacture craft for building |
CN110512805A (en) * | 2019-07-24 | 2019-11-29 | 江苏茂盛建设集团有限公司 | Using the roof covering water-proof structure of TPO waterproof roll |
CN111335559A (en) * | 2020-03-03 | 2020-06-26 | 北京华泰龙城防腐工程有限公司 | Roof drying device and roof waterproof construction process using same |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS58123957A (en) * | 1982-01-16 | 1983-07-23 | 荻野 初太郎 | Cushion, heat insulating and sheet waterproofing execution of concrete floor panel in rooftop or roof |
CN101994399A (en) * | 2010-10-30 | 2011-03-30 | 河南国基建设集团有限公司 | Method for repairing leaked coiled-material water-proof roof |
CN103774797A (en) * | 2012-10-25 | 2014-05-07 | 陕西龙海工程建设有限公司 | Construction technology of bituminous waterproof sheet materials |
CN104251042A (en) * | 2013-06-27 | 2014-12-31 | 张玲玲 | Roof waterproof construction method |
-
2018
- 2018-12-26 CN CN201811599470.9A patent/CN109441113A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS58123957A (en) * | 1982-01-16 | 1983-07-23 | 荻野 初太郎 | Cushion, heat insulating and sheet waterproofing execution of concrete floor panel in rooftop or roof |
CN101994399A (en) * | 2010-10-30 | 2011-03-30 | 河南国基建设集团有限公司 | Method for repairing leaked coiled-material water-proof roof |
CN103774797A (en) * | 2012-10-25 | 2014-05-07 | 陕西龙海工程建设有限公司 | Construction technology of bituminous waterproof sheet materials |
CN104251042A (en) * | 2013-06-27 | 2014-12-31 | 张玲玲 | Roof waterproof construction method |
Non-Patent Citations (2)
Title |
---|
中国建筑工业出版社: "《现行防水材料标准及施工规范汇编》", 30 September 1999, 中国建筑工业出版社 * |
李捍元: "《建筑施工组织设计》", 30 September 2002, 西安地图出版社 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110512805A (en) * | 2019-07-24 | 2019-11-29 | 江苏茂盛建设集团有限公司 | Using the roof covering water-proof structure of TPO waterproof roll |
CN110512750A (en) * | 2019-09-09 | 2019-11-29 | 安徽法莱科技有限公司 | A kind of Polymeric water repellent material manufacture craft for building |
CN111335559A (en) * | 2020-03-03 | 2020-06-26 | 北京华泰龙城防腐工程有限公司 | Roof drying device and roof waterproof construction process using same |
CN111335559B (en) * | 2020-03-03 | 2021-08-17 | 北京华泰龙城防腐工程有限公司 | Roof drying device and roof waterproof construction process using same |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109441113A (en) | Roof waterproof engineering construction method | |
KR101468017B1 (en) | The Outer Wall Repair Method of Brick Building | |
KR100744727B1 (en) | Expoused double waterproof plus film of paint and sheet in the building and construction method of the same | |
CN103410331B (en) | The wet combining technique of vitrified tile | |
CN104763111B (en) | A kind of construction technology of waterproof and insulation integrated system | |
CN110984406A (en) | Waterproof leakage-repairing construction method using non-cured rubber asphalt waterproof coating | |
CN104251042A (en) | Roof waterproof construction method | |
CN112227755A (en) | Waterproof repairing structure and method for old roof | |
CN107780627A (en) | A kind of exterior wall heat-insulating paint construction method | |
CN106193485A (en) | A kind of building wall exempts from cracking resistance technique of plastering | |
CN108193862A (en) | Building wall plastering construction method | |
CN111441391A (en) | CBF reaction bonding macromolecule waterproof coiled material construction method | |
CN111395410B (en) | Construction method for pre-paving asphalt-based waterproof coiled material through welding and bonding combined construction | |
CN103015643A (en) | Waterproof and heat insulation processing system for metal roof | |
CN104947902A (en) | Anti-hollowing paving process of vitrified tiles | |
CN107299728A (en) | A kind of construction method of waterproof and insulation integrated plate | |
KR101571999B1 (en) | Construction Method Of Wallpaper Using Lining Paper | |
CN109881864A (en) | A kind of joining method and structure on floor and stone material or ceramic tile | |
CN104532968B (en) | Prevent concrete structure from building the method for filling wall connecting portion crack with rear | |
CN216380282U (en) | Sand face waterproofing membrane that wet shop was used | |
WO2022127094A1 (en) | Method for overlapping different waterproofing materials of side wall and roof | |
CN205976015U (en) | Waterproof construction of basement outer wall | |
CN210067247U (en) | Rigid-flexible composite waterproof structure | |
KR101338583B1 (en) | Water resistant constructing method for roof and water resistant roof constructed by the same | |
CN208730686U (en) | A kind of embedded colored stone watt bridging arrangement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190308 |