CN109441113A - Roof waterproof engineering construction method - Google Patents

Roof waterproof engineering construction method Download PDF

Info

Publication number
CN109441113A
CN109441113A CN201811599470.9A CN201811599470A CN109441113A CN 109441113 A CN109441113 A CN 109441113A CN 201811599470 A CN201811599470 A CN 201811599470A CN 109441113 A CN109441113 A CN 109441113A
Authority
CN
China
Prior art keywords
engineering construction
construction method
waterproof engineering
roof waterproof
coiled material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811599470.9A
Other languages
Chinese (zh)
Inventor
高昭宗
石磊
吴刚
熊家强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shougang Shuicheng Iron And Steel (group) Saide Construction Co Ltd
Original Assignee
Shougang Shuicheng Iron And Steel (group) Saide Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shougang Shuicheng Iron And Steel (group) Saide Construction Co Ltd filed Critical Shougang Shuicheng Iron And Steel (group) Saide Construction Co Ltd
Priority to CN201811599470.9A priority Critical patent/CN109441113A/en
Publication of CN109441113A publication Critical patent/CN109441113A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Roof Covering Using Slabs Or Stiff Sheets (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention provides a kind of roof waterproof engineering construction methods, belong to the realm of building construction.This roof waterproof engineering construction method, using rubber coiled material, comprising the following steps: S1. clears up roof surface;S2. the connection structure for protruding from roof surface is pre-processed;S3. paving rubber coiled material.In step s 2, pretreatment refers to, between connection structure and roof surface, carries out chamfered.When construction, by the way that chamfering is arranged at the connection structure for protruding from roofing so that between connection structure and roofing can smooth transition guarantee waterproof effect so that rubber coiled material be enable smoothly to be bonded near connection structure.

Description

Roof waterproof engineering construction method
Technical field
The present invention relates to the realm of building construction, in particular to a kind of roof waterproof engineering construction method.
Background technique
During building construction, it is often necessary to carry out water-proofing treatment to roofing.It is in roofing large area bond capacity One of roof waterproof method.
For protruding from the connection structure of roofing, due to surface irregularity, during bond capacity, it is easy hair The phenomenon that raw edge tilts, influences waterproof effect.
Summary of the invention
The present invention provides a kind of roof waterproof engineering construction methods, it is intended to solve roof waterproof engineering in the prior art and apply The above problem existing for work method.
The present invention is implemented as follows:
A kind of roof waterproof engineering construction method, using rubber coiled material, comprising the following steps:
S1. roof surface is cleared up;
S2. the connection structure for protruding from roof surface is pre-processed;
S3. paving rubber coiled material.
In step s 2, pretreatment refers to, between connection structure and roof surface, carries out chamfered.
In preferred embodiment of the invention, in step s 2, chamfered obtuse angle for rounded corner or.
It is further comprising the steps of in preferred embodiment of the invention:
S4. brushing protective layer.
It is further comprising the steps of in preferred embodiment of the invention:
S5. water-storing test is carried out;
Step S5 is carried out after step s 4 is completed.
In preferred embodiment of the invention, in step sl, specifically includes the following steps:
S11. the processing of the dust of roofing, sundries and remaining mortar lump is clean;
S12. roofing is made to keep drying, moisture content is not more than 9%.
In preferred embodiment of the invention, in step s3, comprising the following steps:
S31. rubber coiled material connector is handled;
S32. the paving of rubber coiled material is carried out.
In preferred embodiment of the invention, in step S31, comprising:
S311. the brushing of butyl binder is bonded after waiting default drying time in rubber coiled material joint surface.
It is further comprising the steps of in step S31 in preferred embodiment of the invention:
S312. bonding part is rolled using iron roll.
In preferred embodiment of the invention, at rubber water-proofing coiled multiple-layer overlapped, using polyurethane sealant Sealing.
In preferred embodiment of the invention, rubber coiled material connector is closed using Polymer Mortar tooled joint.
The beneficial effects of the present invention are: the roof waterproof engineering construction method that the present invention obtains by above-mentioned design, construction When, by the connection structure for protruding from roofing be arranged chamfering so that between connection structure and roofing can smooth transition, from And rubber coiled material is enable smoothly to be bonded near connection structure, guarantee waterproof effect.
Specific embodiment
To keep the purposes, technical schemes and advantages of embodiment of the present invention clearer, implement below in conjunction with the present invention The technical solution in embodiment of the present invention is clearly and completely described in content in mode, it is clear that described reality The mode of applying is some embodiments of the invention, rather than whole embodiments.Based on the embodiment in the present invention, ability Domain those of ordinary skill every other embodiment obtained without creative efforts, belongs to the present invention The range of protection.Therefore, the detailed description of embodiments of the present invention presented below is not intended to limit claimed The range of invention, but it is merely representative of selected embodiment of the invention.Based on the embodiment in the present invention, this field is common Technical staff's every other embodiment obtained without creative efforts belongs to what the present invention protected Range.
Embodiment
Present embodiments provide a kind of roof waterproof engineering construction method, this roof waterproof engineering construction method include with Lower step:
S1. roof surface is cleared up;
S2. the connection structure for protruding from roof surface is pre-processed;
S3. paving rubber coiled material.
In step s 2, pretreatment refers to, between connection structure and roof surface, carries out chamfered.
Further, in the present embodiment, in step s 2, chamfered is rounded corner, and fillet size range is 100mm-150mm.In other embodiments of the invention, Taoism processing is it is also an option that the processing of falling obtuse angle.
Further, further comprising the steps of:
S4. brushing protective layer.The protective layer used rubber coiled material surface in brushing at exposed one layer.The concrete operations of step S4 Process is: exposed one layer of the rubber coiled material surface of cleaning, then the brushing protective layer on rubber coiled material surface.
Further, further comprising the steps of:
S5. water-storing test is carried out;
Step S5 is carried out after step s 4 is completed.After step s 4 is completed, water-storing test is carried out, is able to verify that roof waterproof Whether engineering is up to standard.
Further, in step sl, specifically includes the following steps:
S11. the processing of the dust of roofing, sundries and remaining mortar lump is clean;
S12. roofing is made to keep drying, moisture content is not more than 9%.
In step 1, carry out above-mentioned roofing processing, roofing made to keep dry and clean, can be avoided sundries, dust and Extra moisture has an adverse effect to bond effect.
Further, in step s3, comprising the following steps:
S31. rubber coiled material connector is handled;
S32. the paving of rubber coiled material is carried out.
Further, in step S31, comprising:
S311. the brushing of butyl binder is bonded after waiting default drying time in rubber coiled material joint surface. In above-mentioned steps, the range for presetting drying time is 15 minutes to 30 minutes, in use, can be selected according to environment temperature It selects.During the bonding process, air is squeezed out on one side with hand pressing since one end, avoid the generation of bubble.
Further, further comprising the steps of in step S31:
S312. bonding part is rolled using iron roll.After bonding is good, bonding part is rolled with iron roll, can guarantee adhesion strength.
Further, it at rubber water-proofing coiled multiple-layer overlapped, is sealed using polyurethane sealant.
Further, rubber coiled material connector is closed using Polymer Mortar tooled joint.In above-mentioned steps, the weight of Polymer Mortar Proportion is cement: sand: 107 glue=1:3:0.15.
The foregoing is merely the preferred embodiment of the present invention, are not intended to restrict the invention, for this field For technical staff, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any Modification, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of roof waterproof engineering construction method, which is characterized in that use rubber coiled material, comprising the following steps:
S1. roof surface is cleared up;
S2. the connection structure for protruding from roof surface is pre-processed;
S3. paving rubber coiled material;
In the step S2, the pretreatment refers to, between connection structure and roof surface, carries out chamfered.
2. roof waterproof engineering construction method according to claim 1, which is characterized in that described in the step S2 Chamfered obtuse angle for rounded corner or.
3. roof waterproof engineering construction method according to claim 1, which is characterized in that further comprising the steps of:
S4. brushing protective layer.
4. roof waterproof engineering construction method according to claim 3, which is characterized in that further comprising the steps of:
S5. water-storing test is carried out;
The step S5 is carried out after the completion of the step S4.
5. roof waterproof engineering construction method according to claim 1, which is characterized in that in the step S1, specifically The following steps are included:
S11. the processing of the dust of roofing, sundries and remaining mortar lump is clean;
S12. roofing is made to keep drying, moisture content is not more than 9%.
6. roof waterproof engineering construction method according to claim 1, which is characterized in that in the step S3, including Following steps:
S31. rubber coiled material connector is handled;
S32. the paving of rubber coiled material is carried out.
7. roof waterproof engineering construction method according to claim 6, which is characterized in that in the step S31, packet It includes:
S311. the brushing of butyl binder is bonded after waiting default drying time in rubber coiled material joint surface.
8. roof waterproof engineering construction method according to claim 7, which is characterized in that in the step S31, also wrap Include following steps:
S312. bonding part is rolled using iron roll.
9. roof waterproof engineering construction method according to claim 8, which is characterized in that in rubber water-proofing coiled multilayer Overlapping is sealed using polyurethane sealant.
10. roof waterproof engineering construction method according to claim 9, which is characterized in that sealed using Polymer Mortar tooled joint Close rubber coiled material connector.
CN201811599470.9A 2018-12-26 2018-12-26 Roof waterproof engineering construction method Pending CN109441113A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811599470.9A CN109441113A (en) 2018-12-26 2018-12-26 Roof waterproof engineering construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811599470.9A CN109441113A (en) 2018-12-26 2018-12-26 Roof waterproof engineering construction method

Publications (1)

Publication Number Publication Date
CN109441113A true CN109441113A (en) 2019-03-08

Family

ID=65538138

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811599470.9A Pending CN109441113A (en) 2018-12-26 2018-12-26 Roof waterproof engineering construction method

Country Status (1)

Country Link
CN (1) CN109441113A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110512750A (en) * 2019-09-09 2019-11-29 安徽法莱科技有限公司 A kind of Polymeric water repellent material manufacture craft for building
CN110512805A (en) * 2019-07-24 2019-11-29 江苏茂盛建设集团有限公司 Using the roof covering water-proof structure of TPO waterproof roll
CN111335559A (en) * 2020-03-03 2020-06-26 北京华泰龙城防腐工程有限公司 Roof drying device and roof waterproof construction process using same

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58123957A (en) * 1982-01-16 1983-07-23 荻野 初太郎 Cushion, heat insulating and sheet waterproofing execution of concrete floor panel in rooftop or roof
CN101994399A (en) * 2010-10-30 2011-03-30 河南国基建设集团有限公司 Method for repairing leaked coiled-material water-proof roof
CN103774797A (en) * 2012-10-25 2014-05-07 陕西龙海工程建设有限公司 Construction technology of bituminous waterproof sheet materials
CN104251042A (en) * 2013-06-27 2014-12-31 张玲玲 Roof waterproof construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58123957A (en) * 1982-01-16 1983-07-23 荻野 初太郎 Cushion, heat insulating and sheet waterproofing execution of concrete floor panel in rooftop or roof
CN101994399A (en) * 2010-10-30 2011-03-30 河南国基建设集团有限公司 Method for repairing leaked coiled-material water-proof roof
CN103774797A (en) * 2012-10-25 2014-05-07 陕西龙海工程建设有限公司 Construction technology of bituminous waterproof sheet materials
CN104251042A (en) * 2013-06-27 2014-12-31 张玲玲 Roof waterproof construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
中国建筑工业出版社: "《现行防水材料标准及施工规范汇编》", 30 September 1999, 中国建筑工业出版社 *
李捍元: "《建筑施工组织设计》", 30 September 2002, 西安地图出版社 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110512805A (en) * 2019-07-24 2019-11-29 江苏茂盛建设集团有限公司 Using the roof covering water-proof structure of TPO waterproof roll
CN110512750A (en) * 2019-09-09 2019-11-29 安徽法莱科技有限公司 A kind of Polymeric water repellent material manufacture craft for building
CN111335559A (en) * 2020-03-03 2020-06-26 北京华泰龙城防腐工程有限公司 Roof drying device and roof waterproof construction process using same
CN111335559B (en) * 2020-03-03 2021-08-17 北京华泰龙城防腐工程有限公司 Roof drying device and roof waterproof construction process using same

Similar Documents

Publication Publication Date Title
CN109441113A (en) Roof waterproof engineering construction method
KR101468017B1 (en) The Outer Wall Repair Method of Brick Building
KR100744727B1 (en) Expoused double waterproof plus film of paint and sheet in the building and construction method of the same
CN103410331B (en) The wet combining technique of vitrified tile
CN104763111B (en) A kind of construction technology of waterproof and insulation integrated system
CN110984406A (en) Waterproof leakage-repairing construction method using non-cured rubber asphalt waterproof coating
CN104251042A (en) Roof waterproof construction method
CN112227755A (en) Waterproof repairing structure and method for old roof
CN107780627A (en) A kind of exterior wall heat-insulating paint construction method
CN106193485A (en) A kind of building wall exempts from cracking resistance technique of plastering
CN108193862A (en) Building wall plastering construction method
CN111441391A (en) CBF reaction bonding macromolecule waterproof coiled material construction method
CN111395410B (en) Construction method for pre-paving asphalt-based waterproof coiled material through welding and bonding combined construction
CN103015643A (en) Waterproof and heat insulation processing system for metal roof
CN104947902A (en) Anti-hollowing paving process of vitrified tiles
CN107299728A (en) A kind of construction method of waterproof and insulation integrated plate
KR101571999B1 (en) Construction Method Of Wallpaper Using Lining Paper
CN109881864A (en) A kind of joining method and structure on floor and stone material or ceramic tile
CN104532968B (en) Prevent concrete structure from building the method for filling wall connecting portion crack with rear
CN216380282U (en) Sand face waterproofing membrane that wet shop was used
WO2022127094A1 (en) Method for overlapping different waterproofing materials of side wall and roof
CN205976015U (en) Waterproof construction of basement outer wall
CN210067247U (en) Rigid-flexible composite waterproof structure
KR101338583B1 (en) Water resistant constructing method for roof and water resistant roof constructed by the same
CN208730686U (en) A kind of embedded colored stone watt bridging arrangement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190308