CN109403200A - 一种隔板后浇的小箱梁桥的施工方法及其小箱梁桥 - Google Patents
一种隔板后浇的小箱梁桥的施工方法及其小箱梁桥 Download PDFInfo
- Publication number
- CN109403200A CN109403200A CN201811401711.4A CN201811401711A CN109403200A CN 109403200 A CN109403200 A CN 109403200A CN 201811401711 A CN201811401711 A CN 201811401711A CN 109403200 A CN109403200 A CN 109403200A
- Authority
- CN
- China
- Prior art keywords
- small box
- box girder
- several
- girder bridge
- partition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
- E01D2/04—Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开一种隔板后浇的小箱梁桥的施工方法及其小箱梁桥,包括:步骤S1:预制若干不具备横隔板的小箱梁,每一所述小箱梁内预埋有若干机械套筒和若干第一钢筋,同时进行小箱梁桥下部结构的施工;步骤S2:将若干所述小箱梁吊装就位,使若干所述小箱梁之间形成后浇带;步骤S3:绑扎若干第二钢筋,搭设隔板;步骤S4:进行所述后浇带的混凝土浇筑;在所述步骤S3中,若干所述第二钢筋分别与若干所述第一钢筋机械连接。本发明加快了小箱梁的预制速度,减少了材料的浪费,减小了吊装重量,使得施工更加方便快捷,缩短了工程周期。
Description
技术领域
本发明涉及预制装配式桥梁的技术领域,尤其涉及一种隔板后浇的小箱梁桥的施工方法及其小箱梁桥。
背景技术
小箱梁,桥梁工程中梁的一种,内部为空心状,上部两侧有翼缘,类似箱子,因而得名。小箱梁由于其桥梁结构整体性较好,架设也很便利,现在已经在桥梁工程中得到了广泛的应用。
但是,现有技术中小箱梁横隔板通常采用部分现浇部分预制的施工方式,即预制小箱梁中带有部分横隔板,待小箱梁吊装就位后,绑扎现浇部分横隔板钢筋、搭设模板,进行现浇部分横隔板混凝土浇筑,待混凝土达到规定强度继续进行后续施工步骤。这种结构形式中预制小箱梁模板较为复杂,影响了小箱梁的预制速度,且不同项目横隔板尺寸差异较大,模板不能通用,会造成材料的浪费。小箱梁带有部分预制横隔板,加大了吊装的重量,且横隔板强度较低,增大了吊装的难度。
发明内容
针对现有的小箱梁桥存在的上述问题,现提供一种旨在加快了小箱梁的预制速度,减少了材料的浪费和提高了施工的便捷性的隔板后浇的小箱梁桥的施工方法及其小箱梁桥。
具体技术方案如下:
一种隔板后浇的小箱梁桥的施工方法,包括:
步骤S1:预制若干不具备横隔板的小箱梁,每一所述小箱梁内预埋有若干机械套筒和若干第一钢筋,同时进行小箱梁桥下部结构的施工;
步骤S2:将若干所述小箱梁吊装就位,使若干所述小箱梁之间形成后浇带;
步骤S3:绑扎若干第二钢筋,搭设隔板;
步骤S4:进行所述后浇带的混凝土浇筑;
若干所述第二钢筋分别与若干所述第一钢筋机械连接。
上述的隔板后浇的小箱梁桥的施工方法,其中,若干所述第二钢筋分别与若干所述第一钢筋通过钢筋机械连接接头相连接。
上述的隔板后浇的小箱梁桥的施工方法,其中,所述钢筋机械连接接头为镦粗直螺纹套筒或滚轧直螺纹套筒。
上述的隔板后浇的小箱梁桥的施工方法,其中,所述钢筋机械连接接头为挤压套筒。
上述的隔板后浇的小箱梁桥的施工方法,其中,所述钢筋机械连接接头为I级钢筋机械连接接头或II级钢筋机械连接接头。
上述的隔板后浇的小箱梁桥的施工方法,其中,所述钢筋机械连接接头的保护层厚度大于或等于20mm。
上述的隔板后浇的小箱梁桥的施工方法,其中,两相邻的所述钢筋机械连接接头之间、所述钢筋机械连接接头与所述第一钢筋之间、或所述钢筋机械连接接头与所述第二钢筋之间的横向净距大于或等于25mm。
一种隔板后浇的小箱梁桥,其中,包括上述的任意一项所述的隔板后浇的小箱梁桥的施工方法得到。
上述技术方案与现有技术相比具有的积极效果是:
本发明采用隔板后浇的形式,简化了小箱梁的模板的制作工艺,加快了小箱梁的预制速度,减少了材料的浪费,减小了吊装重量,使得施工更加方便快捷,缩短了工程周期。
附图说明
图1为本发明一种隔板后浇的小箱梁桥的施工方法及其小箱梁桥的整体结构示意图;
附图中:1、小箱梁;2、后浇带。
具体实施方式
下面结合附图和具体实施例对本发明作进一步说明,但不作为本发明的限定。
图1为本发明一种隔板后浇的小箱梁桥的施工方法及其小箱梁桥的整体结构示意图,如图1所示,示出了一种较佳实施例的隔板后浇的小箱梁桥的施工方法,包括:
步骤S1:预制若干不具备横隔板的小箱梁1,每一小箱梁1内预埋有若干机械套筒和若干第一钢筋,同时进行小箱梁桥下部结构的施工;
步骤S2:将若干小箱梁1吊装就位,使若干小箱梁1之间形成后浇带2;
步骤S3:绑扎若干第二钢筋,搭设隔板;
步骤S4:进行后浇带2的混凝土浇筑。
进一步,作为一种较佳的实施例,在步骤S3中,若干第二钢筋分别与若干第一钢筋机械连接。
进一步,作为一种较佳的实施例,在步骤S3中,若干第二钢筋分别与若干第一钢筋通过钢筋机械连接接头相连接。
进一步,作为一种较佳的实施例,钢筋机械连接接头为镦粗直螺纹套筒或滚轧直螺纹套筒。
进一步,作为一种较佳的实施例,钢筋机械连接接头为挤压套筒。
以上仅为本发明较佳的实施例,并非因此限制本发明的实施方式及保护范围。
本发明在上述基础上还具有如下实施方式:
本发明的进一步实施例中,请继续参见图1所示,钢筋机械连接接头为I级钢筋机械连接接头或II级钢筋机械连接接头。
本发明的进一步实施例中,钢筋机械连接接头的保护层厚度大于或等于20mm。
本发明的进一步实施例中,两相邻的钢筋机械连接接头之间、钢筋机械连接接头与第一钢筋之间、或钢筋机械连接接头与第二钢筋之间的横向净距大于或等于25mm。
一种隔板后浇的小箱梁桥,包括隔板后浇的小箱梁桥的施工方法得到。
优选地,机械连接接头的材料、制作、安装施工及质量检验和验收,应符合相关现行行业标准的规定。
优选地,连接套筒、锁母、丝头等安装材料在运输和储存过程中应采取防护措施,防止雨淋、玷污和损伤。
本发明采用隔板后浇的形式,简化了小箱梁1对的模板的制作工艺,加快了小箱梁1的预制速度,减少了材料的浪费。减小了吊装重量,使得施工更加方便快捷,缩短了工程周期。
以上所述仅为本发明较佳的实施例,并非因此限制本发明的实施方式及保护范围,对于本领域技术人员而言,应当能够意识到凡运用本发明说明书及图示内容所作出的等同替换和显而易见的变化所得到的方案,均应当包含在本发明的保护范围内。
Claims (8)
1.一种隔板后浇的小箱梁桥的施工方法,其特征在于,包括:
步骤S1:预制若干不具备横隔板的小箱梁,每一所述小箱梁内预埋有若干机械套筒和若干第一钢筋,同时进行小箱梁桥下部结构的施工;
步骤S2:将若干所述小箱梁吊装就位,使若干所述小箱梁之间形成后浇带;
步骤S3:绑扎若干第二钢筋,搭设隔板;
步骤S4:进行所述后浇带的混凝土浇筑;
在所述步骤S3中,若干所述第二钢筋分别与若干所述第一钢筋机械连接。
2.根据权利要求1所述隔板后浇的小箱梁桥的施工方法,其特征在于,在所述步骤S3中,若干所述第二钢筋分别与若干所述第一钢筋通过钢筋机械连接接头相连接。
3.根据权利要求2所述隔板后浇的小箱梁桥的施工方法,其特征在于,所述钢筋机械连接接头为镦粗直螺纹套筒或滚轧直螺纹套筒。
4.根据权利要求2所述隔板后浇的小箱梁桥的施工方法,其特征在于,所述钢筋机械连接接头为挤压套筒。
5.根据权利要求2所述隔板后浇的小箱梁桥的施工方法,其特征在于,所述钢筋机械连接接头为I级钢筋机械连接接头或II级钢筋机械连接接头。
6.根据权利要求2所述隔板后浇的小箱梁桥的施工方法,其特征在于,所述钢筋机械连接接头的保护层厚度大于或等于20mm。
7.根据权利要求2所述隔板后浇的小箱梁桥的施工方法,其特征在于,两相邻的所述钢筋机械连接接头之间、所述钢筋机械连接接头与所述第一钢筋之间、或所述钢筋机械连接接头与所述第二钢筋之间的横向净距大于或等于25mm。
8.一种隔板后浇的小箱梁桥,其特征在于,由权利要求1至7中任意一项所述的隔板后浇的小箱梁桥的施工方法得到。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811401711.4A CN109403200A (zh) | 2018-11-22 | 2018-11-22 | 一种隔板后浇的小箱梁桥的施工方法及其小箱梁桥 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811401711.4A CN109403200A (zh) | 2018-11-22 | 2018-11-22 | 一种隔板后浇的小箱梁桥的施工方法及其小箱梁桥 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109403200A true CN109403200A (zh) | 2019-03-01 |
Family
ID=65474663
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811401711.4A Pending CN109403200A (zh) | 2018-11-22 | 2018-11-22 | 一种隔板后浇的小箱梁桥的施工方法及其小箱梁桥 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109403200A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109837838A (zh) * | 2019-03-09 | 2019-06-04 | 北京市市政二建设工程有限责任公司 | 一种钢混箱梁的施工方法 |
CN111730738A (zh) * | 2020-06-30 | 2020-10-02 | 中国一冶集团有限公司 | 一种预制箱梁横隔板连接结构及其施工方法 |
CN112627033A (zh) * | 2020-12-04 | 2021-04-09 | 中国葛洲坝集团第一工程有限公司 | 一种弯桥上预制梁的横隔板浇筑模板及浇筑方法 |
CN114622492A (zh) * | 2022-04-02 | 2022-06-14 | 中国水利水电第七工程局有限公司 | 一种超高空心薄壁墩大断面横隔板及施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105064202A (zh) * | 2015-07-17 | 2015-11-18 | 安徽省交通建设有限责任公司 | 型钢与钢筋混凝土板装配式轻型组合梁桥及其施工方法 |
CN206800173U (zh) * | 2017-05-03 | 2017-12-26 | 中铁第四勘察设计院集团有限公司 | 一种铁路后浇桥面板预应力混凝土i型梁 |
CN206800165U (zh) * | 2017-04-13 | 2017-12-26 | 中铁第四勘察设计院集团有限公司 | 一种公路桥梁 |
CN107938504A (zh) * | 2017-10-18 | 2018-04-20 | 重庆大学 | 一种采用t头钢筋的桥面板湿接缝结构及其施工方法 |
CN108277733A (zh) * | 2018-01-31 | 2018-07-13 | 重庆交通大学 | 能抵御铰缝劣化影响的装配式小箱梁桥及其制作方法 |
CN209555748U (zh) * | 2018-11-22 | 2019-10-29 | 上海市政交通设计研究院有限公司 | 一种隔板后浇的小箱梁桥 |
-
2018
- 2018-11-22 CN CN201811401711.4A patent/CN109403200A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105064202A (zh) * | 2015-07-17 | 2015-11-18 | 安徽省交通建设有限责任公司 | 型钢与钢筋混凝土板装配式轻型组合梁桥及其施工方法 |
CN206800165U (zh) * | 2017-04-13 | 2017-12-26 | 中铁第四勘察设计院集团有限公司 | 一种公路桥梁 |
CN206800173U (zh) * | 2017-05-03 | 2017-12-26 | 中铁第四勘察设计院集团有限公司 | 一种铁路后浇桥面板预应力混凝土i型梁 |
CN107938504A (zh) * | 2017-10-18 | 2018-04-20 | 重庆大学 | 一种采用t头钢筋的桥面板湿接缝结构及其施工方法 |
CN108277733A (zh) * | 2018-01-31 | 2018-07-13 | 重庆交通大学 | 能抵御铰缝劣化影响的装配式小箱梁桥及其制作方法 |
CN209555748U (zh) * | 2018-11-22 | 2019-10-29 | 上海市政交通设计研究院有限公司 | 一种隔板后浇的小箱梁桥 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109837838A (zh) * | 2019-03-09 | 2019-06-04 | 北京市市政二建设工程有限责任公司 | 一种钢混箱梁的施工方法 |
CN111730738A (zh) * | 2020-06-30 | 2020-10-02 | 中国一冶集团有限公司 | 一种预制箱梁横隔板连接结构及其施工方法 |
CN112627033A (zh) * | 2020-12-04 | 2021-04-09 | 中国葛洲坝集团第一工程有限公司 | 一种弯桥上预制梁的横隔板浇筑模板及浇筑方法 |
CN114622492A (zh) * | 2022-04-02 | 2022-06-14 | 中国水利水电第七工程局有限公司 | 一种超高空心薄壁墩大断面横隔板及施工方法 |
CN114622492B (zh) * | 2022-04-02 | 2023-11-10 | 中国水利水电第七工程局有限公司 | 一种超高空心薄壁墩大断面横隔板及施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109403200A (zh) | 一种隔板后浇的小箱梁桥的施工方法及其小箱梁桥 | |
CN105256713B (zh) | 半装配式钢混凝土组合梁及其建造方法 | |
CN103883051B (zh) | 一种装配式板-梁连接节点及其施工方法 | |
CN104912321B (zh) | 一种用于悬空结构的钢桁架模板支撑结构及其安装方法 | |
CN103938549B (zh) | 装配式波形钢斜腹板组合梁的施工方法 | |
CN101748682A (zh) | 采用波形钢腹板的钢-混凝土叠合板组合梁及其施工方法 | |
CN206784913U (zh) | 一种两段式叠合板接缝吊模工具 | |
CN106013565A (zh) | 3d打印桁架空心楼板单元的制作方法 | |
CN104805960B (zh) | 一种免拆模混凝土梁及其施工方法 | |
CN107514083B (zh) | 侧悬钢筋带抗剪键混凝土叠合楼板结构及连接方法 | |
CN104532953A (zh) | 基于3d打印的装配式异形柱框架结构及其施工方法 | |
CN103410265A (zh) | 一种叠合楼板的拼接构造 | |
CN114770706B (zh) | 一种轻型t梁预制装备及预制安装施工方法 | |
CN109779114A (zh) | 一种整体式叠合板组合梁 | |
CN208105008U (zh) | 一种城市高架桥预应力钢束布置结构 | |
CN103669665A (zh) | 钢筋桁架楼承板施工的标高差节点施工工艺 | |
CN105155836B (zh) | 建筑用铝合金模板及其使用方法 | |
CN104499430A (zh) | 用于全预制拼装桥梁间的湿接段连接结构 | |
CN208280454U (zh) | 双钢板钢筋混凝土组合梁 | |
CN209555748U (zh) | 一种隔板后浇的小箱梁桥 | |
CN110042947A (zh) | 一种基于3d打印的墙体结构及其打印方法 | |
CN110042743A (zh) | 双肢薄壁空心墩的液压爬模系统和同步爬升施工工艺 | |
CN107152112A (zh) | 一种用于降板区域的模块化预制叠合楼板及其施工方法 | |
CN208668274U (zh) | 一种钢混组合梁桥 | |
CN210134588U (zh) | 一种混凝土柱拼装结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |