CN109397523A - A kind of deformed bar tensioning tooling and its application method - Google Patents

A kind of deformed bar tensioning tooling and its application method Download PDF

Info

Publication number
CN109397523A
CN109397523A CN201811593487.3A CN201811593487A CN109397523A CN 109397523 A CN109397523 A CN 109397523A CN 201811593487 A CN201811593487 A CN 201811593487A CN 109397523 A CN109397523 A CN 109397523A
Authority
CN
China
Prior art keywords
deformed bar
tensioning
equipment
tooling
bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811593487.3A
Other languages
Chinese (zh)
Inventor
张剑
王雅明
徐雷
周涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chenzhou Yuanda Residence Industry Co Ltd
Original Assignee
Chenzhou Yuanda Residence Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chenzhou Yuanda Residence Industry Co Ltd filed Critical Chenzhou Yuanda Residence Industry Co Ltd
Priority to CN201811593487.3A priority Critical patent/CN109397523A/en
Publication of CN109397523A publication Critical patent/CN109397523A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • B28B23/043Wire anchoring or tensioning means for the reinforcements

Abstract

A kind of deformed bar tensioning tooling, including anchorage, tensioning equipment and equipment is put, the side put equipment and be arranged in trolley, the tensioning equipment installation is on the car, and it is located at the two sides of prefabricated components, the positioning for deformed bar both ends anchorage in prefabricated components is fixed;The trolley is additionally provided with protective device far from the one end for putting equipment is opened;The tensioning equipment is located at protective device and puts between equipment.The invention also discloses the application methods of above-mentioned tooling.The structure of the deformed bar tensioning tooling is simple, easy to use, it can be achieved that mould standard, reduces the labor intensity of the processes such as mold design, production and mold installation, improve production efficiency, reduce die cost, keep mold tooling reusable.

Description

A kind of deformed bar tensioning tooling and its application method
Technical field
The present invention relates to architectural engineering construction technique fields, more particularly, to a kind of deformed bar tensioning tooling and its make Use method.
Background technique
Pre-tensioning system is cracking resistance in order to improve reinforced concrete precast member and avoids reinforced concrete member too early There is crack, and stress is previously applied to it in prefabrication process to improve a kind of method of component performance.It is usually mixed in pouring The production method of tension reinforcing steel bar is also referred to as pre-tensioning system before solidifying soil, it plays an important role in engineering construction.
After pre-tensioning system stretching wire, when steel wire there are enough cohesive forces with concrete, is opened by putting, unclamp steel Silk, by means of the bonding of concrete and steel wire, guarantees that prefabricated components reach design requirement.It develops now a kind of using force-transmitting pole The pre-stress construction pedestal of stress, including pedestal and the force-transmitting pole for being arranged in pedestal two sides, pedestal both ends are provided with fixation Gooseneck, one end are additionally provided with movable gooseneck, and anchoring has steel between the activity gooseneck and the fixation gooseneck of opposite side Silk, is provided between ipsilateral fixation gooseneck and puts equipment, the effect of the fixation gooseneck at pedestal both ends in tension stress Under, it is pressed in power transmission column end, puts and opens while to realize steel wire on the pedestal, that is, guarantees that steel wire puts the synchronism opened, needs It wants matched and puts a constructing device.
Floor deformed bar tensioning prestressed reinforcement of tensioning before floor concrete casting.Due to pre-stress floor size It is different, and different floor set aside pre-embeddeds position is different, causes prestressed stretch-draw mold design specification more, installation is troublesome in poeration, It is easy error.
Summary of the invention
The technical problem to be solved by the present invention is it is simple to overcome the deficiencies of the prior art and provide a kind of structure, user Just, the application method of the good deformed bar tensioning tooling of security performance and the tooling.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of deformed bar tensioning tooling, including anchorage, tensioning equipment and equipment is put, the equipment of putting is arranged in trolley Side;The tensioning equipment installation on the car, and is located at the two sides of prefabricated components, for deformed bar in prefabricated components The positioning of both ends anchorage is fixed;The trolley is additionally provided with protective device far from the one end for putting equipment is opened;The tensioning equipment is located at It protective device and puts between equipment.
In a certain example embodiment, the tensioning equipment is L-shaped, and the vertical portion of the tensioning equipment is equidistantly evenly equipped with Deformed bar through-hole, the spacing between adjacent deformed bar through-hole are 50mm ~ 100mm, can be according to same Tai Monei floor Equal prefabricated components actual conditions adjust arrangement prestress reinforcing bar, so that its deformed bar arrangement is met design requirement, avoid difference Prestress steel in the prefabricated components such as floor is quickly and easily realized in interference of the set aside pre-embedded of the prefabricated components such as floor to arrangement Muscle tensioning.
It is preferred that tensioning equipment is angle bar, the spacing between adjacent deformed bar through-hole is 50mm.
In a certain example embodiment, the distance of the centre distance trolley of the deformed bar through-hole is equal to prestress steel The sum of thickness and the radius of deformed bar of tendon protective layer, play deformed bar preferably to prestress steel tendon protective layer Protective effect.
In a certain example embodiment, the angle bar back side is equipped at intervals with stiffener plate;Between between adjacent said rib plate Away from >=500m, it is preferable that the spacing between adjacent said rib plate is the mm of 500 mm ~ 800.
In a certain example embodiment, the angle bar is equal angle iron.
The protective device is equal angle iron, and the back side of equal angle iron is equipped at intervals with stiffener plate.
The equipment of putting is hydraulic tensioning mechanism.
A kind of application method of deformed bar tensioning tooling of the invention, comprising the following steps:
1) when deformed bar tensioning tooling is used for single trolley, the rib mold to prefabricated components (such as floor), which is installed, to be fixed After in place, in the tensioning equipment that deformed bar tensioning tooling is welded and fixed not less than 300mm away from trolley end, guarantee tooling peace Fixation is filled, keeps deformed bar through-hole and mold fluting hole location concentric, reduces deformed bar tensioning work in stretching process Fill the resistance to deformed bar;
2) within the scope of the outside 150-200mm of the tensioning equipment for fastening deformed bar away from deformed bar tensioning tooling Protective device is welded and fixed, is broken rebound after preventing certain deformed bar tensioning, personnel is damaged.
3) intert deformed bar, deformed bar sequentially passes through fastening for prestressing force for deformed bar tensioning tooling Deformed bar through-hole on tensioning equipment and the U-lag on mold are then passed through deformed bar tensioning tooling close to Zhang Fangshe Deformed bar through-hole on the tensioning equipment of standby one end, then respectively with anchorage to through deformed bar tensioning tooling both ends Deformed bar carries out installation fixation, guarantees that deformed bar is generally flat;
4) reinforcing bar is placed, assembling reinforcement, last prestressed reinforcement of tensioning, close, trolley puts equipment one end as stretching end, separately One end is as prestressing force fastening end, and since centre, successively symmetrical prestressed reinforcement of tensioning, reaches the tensioning of design requirement Value.
When multiple trolleys that deformed bar tensioning tooling is used to successively arrange, then welded at most end trolley end face both ends Connect the tensioning equipment and protective device in deformed bar tensioning tooling.
A kind of deformed bar tensioning tooling of the present invention the utility model has the advantages that its structure is simple, it is easy to use, it can be achieved that mold Standardization, reduce mold design, production and mold installation etc. processes labor intensity, improve production efficiency, reduce mold at This, keeps mold tooling reusable.
The vertical portion of the angle bar is equidistantly evenly equipped with deformed bar through-hole, between adjacent deformed bar through-hole between Away from for 50mm ~ 100mm, arrangement prestress reinforcing bar can be adjusted according to prefabricated components actual conditions such as same Tai Monei floors, make it Deformed bar arrangement meets design requirement, and can avoid interference of the set aside pre-embedded to arrangement.
By the way that protective device is arranged in the prestressing force fastening end of trolley, presstressed reinforcing steel can be effectively prevent to be broken suddenly to artificial Phenomena such as at injury, improve the safety of deformed bar stretching process.
Detailed description of the invention
Fig. 1-uses schematic diagram for a kind of deformed bar tensioning tooling;
Fig. 2-is a kind of main view of tensioning equipment in deformed bar tensioning tooling in Fig. 1;
Fig. 3-is a kind of side view of tensioning equipment in deformed bar tensioning tooling in Fig. 1.
In figure: 1-protective device, 2-tensioning equipments, 21-angle bar, 22-reinforcing ribs, 23-deformed bar through-holes, 3-trolleys, 4-prefabricated components, 5-rib molds, 6-deformed bars, 7-anchorages, 8-put equipment.
Specific embodiment
The invention will be further described with reference to the accompanying drawings and embodiments.
Referring to Fig.1: a kind of deformed bar tensioning tooling, including anchorage 7, tensioning equipment 2 and equipment 8 is put, it is described to put Open the side that equipment 8 is arranged in trolley 3;The tensioning equipment 2 is mounted on trolley 3, and is located at the two sides of prefabricated components 4, is used The positioning of 6 both ends anchorage 7 of deformed bar is fixed in prefabricated components 4;The trolley 3 is also set far from the one end for putting equipment 8 is opened There is protective device 1;The tensioning equipment 2 is located at protective device 1 and puts between equipment 8.
The tensioning equipment 2 is angle bar 21, and L-shaped, the vertical portion of the angle bar 21 is equidistantly evenly equipped with deformed bar Through-hole 23, the spacing between adjacent deformed bar through-hole 23 are 50mm, can be according to same 4 actual conditions of Tai Monei prefabricated components Arrangement prestress reinforcing bar 6 is adjusted, so that its deformed bar 6 arrangement is met design requirement, avoids the reserved pre- of different prefabricated components 4 Bury the interference to arrangement, quickly and easily realize prefabricated components 4(such as floor) in deformed bar 6 tensioning.
It should be noted that can spacing according to the prefabricated components structure such as floor, between adjacent deformed bar through-hole 23 For can also be 60mm, 70mm, 80mm or 100mm, and then according to the prefabricated components actual conditions such as same Tai Monei floor adjust Arrangement prestress reinforcing bar makes its deformed bar arrangement meet design requirement, and can avoid interference of the set aside pre-embedded to arrangement.
21 back side of angle bar is equipped at intervals with stiffener plate 22;Spacing >=500 mm between adjacent said rib plate 22 lead to It crosses and stiffener plate 22 is set at 21 back side of angle bar, improve the stress intensity of tensioning equipment 2.It is preferred that between adjacent said rib plate 22 Spacing be the mm of 500 mm ~ 800.According to the force request of tensioning equipment 2, between appropriate adjustment stiffener plate 22 Away from the lower stress intensity for improving tensioning equipment 2 and making main material angle bar 21 of realization low cost, it is ensured that the stress performance of tensioning equipment 2 Meet force request when 6 tensioning of deformed bar.
The angle bar 21 is equal angle iron 21.
The distance of the centre distance trolley 3 of the deformed bar through-hole 23 is equal to the thickness of 6 protective layer of deformed bar The sum of with the radius of deformed bar 6, deformed bar 6 is made to play preferable protective effect to prestress steel tendon protective layer.
The protective device 1 is equal angle iron 21, and the back side of equal angle iron 21 is equipped at intervals with stiffener plate 22.
A kind of application method of deformed bar tensioning tooling of the invention, comprising the following steps:
1) when deformed bar tensioning tooling is used for single trolley, to prefabricated components 4(such as floor) the installation of rib mold 5 it is solid After determining in place, in the tensioning equipment 2 that deformed bar tensioning tooling is welded and fixed not less than 300mm away from trolley end, guarantee work Dress installation fixation keeps deformed bar through-hole 23 and mold fluting hole location concentric, reduces deformed bar in stretching process Resistance of the tensioning tooling to deformed bar 6;
2) it is welded within the scope of 150-200mm on the outside of the tensioning equipment for fastening deformed bar away from deformed bar tensioning tooling Fixing protector 1 is connect, rebound is broken after preventing certain 6 tensioning of deformed bar, personnel is damaged.
3) intert deformed bar 6, deformed bar 6 sequentially passes through the tight for prestressing force of deformed bar tensioning tooling Solid tensioning equipment on deformed bar through-hole 23 and mold on U-lag, it is close to be then passed through deformed bar tensioning tooling The deformed bar through-hole 23 put on the tensioning equipment of equipment one end is opened, then respectively with anchorage 7 to through deformed bar tensioning The deformed bar 6 at tooling both ends carries out installation fixation, guarantees that deformed bar 6 is generally flat;
4) place reinforcing bar, assembling reinforcement, last prestressed reinforcement of tensioning 6, trolley close to putting one end of equipment as stretching end, The other end is as prestressing force fastening end, and since centre, successively symmetrical prestressed reinforcement of tensioning 6, reaches design requirement Tensioning value.
When multiple trolleys that deformed bar tensioning tooling is used to successively arrange, then welded at most end trolley end face both ends The tensioning equipment 2 and protective device 1 in deformed bar tensioning tooling are connect, other steps are identical as single trolley.

Claims (10)

1. a kind of deformed bar tensioning tooling, including anchorage, tensioning equipment and equipment is put, the equipment of putting is arranged in platform The side of vehicle;It is characterized in that, the tensioning equipment installation is on the car, and it is located at the two sides of prefabricated components, is used for prefabricated structure The positioning of deformed bar both ends anchorage is fixed in part;The trolley is additionally provided with protective device far from the one end for putting equipment is opened;Institute Tensioning equipment is stated to be located at protective device and put between equipment.
2. a kind of deformed bar tensioning tooling as described in claim 1, which is characterized in that the tensioning equipment is L-shaped, described The vertical portion of tensioning equipment is equidistantly evenly equipped with deformed bar through-hole, and the spacing between adjacent deformed bar through-hole is 50mm ~100mm。
3. a kind of deformed bar tensioning tooling as claimed in claim 2, which is characterized in that the tensioning equipment is angle bar, phase Spacing between adjacent deformed bar through-hole is 50mm.
4. a kind of deformed bar tensioning tooling as claimed in claim 2, which is characterized in that in the deformed bar through-hole Distance of the heart apart from trolley is equal to the sum of thickness and radius of deformed bar of prestress steel tendon protective layer.
5. a kind of deformed bar tensioning tooling as claimed in claim 2, which is characterized in that be equipped at intervals with reinforcement on the angle bar Gusset;Spacing >=500 mm between adjacent said rib plate.
6. a kind of deformed bar tensioning tooling as claimed in claim 5, which is characterized in that the spacing between adjacent said rib plate For the mm of 500 mm ~ 800.
7. such as a kind of any one of claim 1 ~ 6 deformed bar tensioning tooling, which is characterized in that the protective device is The back side of equal angle iron, equal angle iron is equipped at intervals with stiffener plate.
8. such as a kind of any one of claim 1 ~ 6 deformed bar tensioning tooling, which is characterized in that the equipment of putting is Hydraulic tensioning mechanism.
9. a kind of such as a kind of any one of claim 1 ~ 8 application method of deformed bar tensioning tooling, which is characterized in that The following steps are included:
1) after the installation of the rib mold of prefabricated components is secured in position, away from separate unit trolley end or positioned at more trolley most ends Trolley the fixed deformed bar tensioning tooling in end tensioning equipment, keep deformed bar through-hole and mold fluting hole location same The heart;
2) within the scope of the outside 150-200mm of the tensioning equipment for fastening deformed bar away from deformed bar tensioning tooling Protective device is welded and fixed;
3) intert deformed bar, deformed bar sequentially passes through for prestressing force fastening of deformed bar tensioning tooling Deformed bar through-hole on drawing device and the U-lag on mold are then passed through the close Zhang Fangshe of deformed bar tensioning tooling Deformed bar through-hole on the tensioning equipment of standby one end, then respectively with anchorage to through deformed bar tensioning tooling both ends Deformed bar carries out installation fixation, guarantees that deformed bar is generally flat;
4) reinforcing bar is placed, assembling reinforcement, last prestressed reinforcement of tensioning, close, trolley puts equipment one end as stretching end, separately One end is as prestressing force fastening end, and since centre, successively symmetrical prestressed reinforcement of tensioning, reaches the tensioning of design requirement Value.
10. a kind of application method of deformed bar tensioning tooling as claimed in claim 9, which is characterized in that the tensioning dress The distance apart from the end of trolley is set not less than 300mm.
CN201811593487.3A 2018-12-25 2018-12-25 A kind of deformed bar tensioning tooling and its application method Pending CN109397523A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811593487.3A CN109397523A (en) 2018-12-25 2018-12-25 A kind of deformed bar tensioning tooling and its application method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811593487.3A CN109397523A (en) 2018-12-25 2018-12-25 A kind of deformed bar tensioning tooling and its application method

Publications (1)

Publication Number Publication Date
CN109397523A true CN109397523A (en) 2019-03-01

Family

ID=65461267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811593487.3A Pending CN109397523A (en) 2018-12-25 2018-12-25 A kind of deformed bar tensioning tooling and its application method

Country Status (1)

Country Link
CN (1) CN109397523A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109894547A (en) * 2019-04-03 2019-06-18 贵州长通集团有限公司 A kind of prestressing force pull-up structure

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130174503A1 (en) * 2012-01-06 2013-07-11 Clark Pacific Corporation Composite panel including pre-stressed concrete with support frame, and method for making same
CN203792513U (en) * 2014-01-30 2014-08-27 上海柘中建设股份有限公司 Construction facility for producing prestress hollow slab beams in batches
CN204339983U (en) * 2014-12-08 2015-05-20 中国十七冶集团有限公司 Pre-tensioning system precast plate girder rod-pulling type integral tension device
CN104908159A (en) * 2015-06-01 2015-09-16 江苏山海建设工程有限公司 Operation equipment for industrial large-scale solid square pile production line
CN107599158A (en) * 2017-09-26 2018-01-19 汤始建华建材(苏州)有限公司 A kind of process for prestressed component two directions tension
CN207240472U (en) * 2017-09-26 2018-04-17 汤始建华建材(苏州)有限公司 A kind of tension ground tackle for prestressed component production
CN207267290U (en) * 2017-09-01 2018-04-24 中天建设集团有限公司 Compressor wire tensioning equipment
CN207273541U (en) * 2017-09-01 2018-04-27 中天建设集团有限公司 Prestressing force mortar Decorative hanging board molding die
CN209533783U (en) * 2018-12-25 2019-10-25 郴州远大住宅工业有限公司 A kind of deformed bar tensioning tooling

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130174503A1 (en) * 2012-01-06 2013-07-11 Clark Pacific Corporation Composite panel including pre-stressed concrete with support frame, and method for making same
CN203792513U (en) * 2014-01-30 2014-08-27 上海柘中建设股份有限公司 Construction facility for producing prestress hollow slab beams in batches
CN204339983U (en) * 2014-12-08 2015-05-20 中国十七冶集团有限公司 Pre-tensioning system precast plate girder rod-pulling type integral tension device
CN104908159A (en) * 2015-06-01 2015-09-16 江苏山海建设工程有限公司 Operation equipment for industrial large-scale solid square pile production line
CN207267290U (en) * 2017-09-01 2018-04-24 中天建设集团有限公司 Compressor wire tensioning equipment
CN207273541U (en) * 2017-09-01 2018-04-27 中天建设集团有限公司 Prestressing force mortar Decorative hanging board molding die
CN107599158A (en) * 2017-09-26 2018-01-19 汤始建华建材(苏州)有限公司 A kind of process for prestressed component two directions tension
CN207240472U (en) * 2017-09-26 2018-04-17 汤始建华建材(苏州)有限公司 A kind of tension ground tackle for prestressed component production
CN209533783U (en) * 2018-12-25 2019-10-25 郴州远大住宅工业有限公司 A kind of deformed bar tensioning tooling

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109894547A (en) * 2019-04-03 2019-06-18 贵州长通集团有限公司 A kind of prestressing force pull-up structure

Similar Documents

Publication Publication Date Title
CN208543603U (en) Precast prestressed floor production mould and production equipment
CN106677069A (en) Construction method for overall formwork one-time forming structure of pier
CN109707173B (en) Construction method of assembly type laminated beam plate installation auxiliary device
KR101195516B1 (en) Pier Cap Installation Structure Using Precast Concrete Shell And Construction Method Thereof
CN108505448A (en) Pier cap beam anchor ear girder steel template system and its construction method
CN105649213B (en) A kind of construction method of intensive cloth muscle area large-scale steel structure built-in fitting
CN208668279U (en) Pier cap beam anchor ear girder steel template system
CN107984610B (en) A kind of prestressing force small box girder production method
CN209533783U (en) A kind of deformed bar tensioning tooling
CN205630974U (en) Pre -tensioning system precast beam pedestal
CN109397523A (en) A kind of deformed bar tensioning tooling and its application method
CN207812307U (en) The construction system of Cable stayed Bridge Main Tower and steel anchor beam
CN102251481A (en) Railway pier layered construction method and construction device
CN207392430U (en) A kind of modular architectural structural
CN106284997B (en) The big punching block construction method for lifting whole of reinforced concrete chimney
CN201511439U (en) System for integrally binding and hoisting box girder steel reinforcement framework
CN110158770A (en) A kind of assembled architecture beam column anchor plate type attachment device and its construction method
CN205024584U (en) Pre -stressed reinforcement's segmentation anchor structure in case roof beam
CN109024685A (en) A kind of mass concrete invert reinforcing steel support system and its construction method
KR100841387B1 (en) Non-support type prestressed form for constructing beam
CN110318557B (en) Prestressed concrete hollow slab reinforcing device and method
CN210529735U (en) Building steel structure platform base
CN202247681U (en) Layered construction device for railway bridge piers
CN110154228A (en) A kind of cast-in-place pre-buried board positioning method of face bracket
CN216810955U (en) Cantilever beam type external climbing frame embedded part connecting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination