CN107984610B - A prestressed small box girder manufacturing method - Google Patents
A prestressed small box girder manufacturing method Download PDFInfo
- Publication number
- CN107984610B CN107984610B CN201711175269.3A CN201711175269A CN107984610B CN 107984610 B CN107984610 B CN 107984610B CN 201711175269 A CN201711175269 A CN 201711175269A CN 107984610 B CN107984610 B CN 107984610B
- Authority
- CN
- China
- Prior art keywords
- prestressed
- section
- open channel
- tension
- open
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
- B28B23/04—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
- B28B23/043—Wire anchoring or tensioning means for the reinforcements
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
- E01D2/04—Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/28—Concrete reinforced prestressed
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Rod-Shaped Construction Members (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
本发明公开了一种预应力小箱梁制作方法,将该预应力小箱梁分为中间的明槽段和位于两端的锚固段,首先浇筑明槽段,在明槽段的腹板上预留用于布置预应力筋的明槽,并在明槽底部间隔一段距离预设两个用于张拉预应力筋的张拉孔;将预应力筋在明槽段预留的明槽内穿束,将穿束后的预应力筋与两端的锚固段的钢筋笼固定相连,并浇筑位于两端的锚固段,锚固段浇筑固化后,通过明槽底部的两个横张孔用张拉设备将预应力筋往下张拉,检查预应力筋达的张拉值和伸长值满足要求;对明槽段中的明槽进行浇筑,完成第三次浇筑,固化后拆除张拉设备,完成整个预应力小箱梁的制作。本发明制作小箱梁预应力张拉中压浆更加密实,同时提高了预应力筋的利用率。
The invention discloses a method for manufacturing a prestressed small box girder. The prestressed small box girder is divided into an open channel section in the middle and anchor sections located at both ends. Reserve the open slots for arranging the prestressed tendons, and preset two tension holes for tensioning the prestressed tendons at the bottom of the open slots at a certain distance; The prestressed tendons after beam penetration are fixedly connected to the reinforcement cages of the anchorage sections at both ends, and the anchorage sections at both ends are poured. After the anchorage sections are poured and solidified, they are drawn by tensioning equipment through the two transverse tension holes at the bottom of the open groove. The prestressed tendons are stretched downward, and the tension and elongation values of the prestressed tendons are checked to meet the requirements; the open grooves in the open groove section are poured, and the third pouring is completed. After curing, the tensioning equipment is removed to complete the entire prestressed tendons. Fabrication of stressed small box girders. The invention makes the grout more compact in the prestressed stretching of the small box girder, and improves the utilization rate of the prestressed tendons at the same time.
Description
技术领域technical field
本发明涉及桥梁建造领域,涉及一种小箱梁制作方法,具体涉及一种预应力小箱梁制作方法。The invention relates to the field of bridge construction, and relates to a method for manufacturing a small box girder, in particular to a method for manufacturing a prestressed small box girder.
背景技术Background technique
预制连续小箱梁因其结构简单、施工简便、造价低廉、节省工期等优点,在我国的中小跨径桥梁中运用十分广泛。在该类预制梁中,预应力筋是必不可少的组成部分。现阶段预应力施工中较为成熟的张拉方法是后张法和先张法。根据预应力筋与混凝土接触与否,又分为有粘结预应力混凝土和无粘结预应力混凝土。在连续小箱梁的预制中,预应力筋采用后张法,粘结形式为有粘结。但是采用后张法,以现有的施工技术会出现以下问题:(1)预应力筋端部张拉力较大,而跨中部位的张拉力往往较小;(2)预应力筋张拉后,存在孔道压浆不密实的情况,影响梁的质量。Prefabricated continuous small box girders are widely used in small and medium-span bridges in my country because of their simple structure, convenient construction, low cost, and time-saving construction. In this type of prefabricated beams, prestressed tendons are an essential component. The relatively mature tensioning methods in prestressed construction at this stage are post-tensioning and pre-tensioning. According to whether the prestressed tendon is in contact with concrete, it can be divided into bonded prestressed concrete and unbonded prestressed concrete. In the prefabrication of continuous small box girders, the post-tensioning method is adopted for the prestressed tendons, and the bonded form is bonded. But adopt the post-tensioning method, the following problems will occur with the existing construction technology: (1) the tension force at the end of the prestressed tendon is relatively large, while the tension force at the mid-span is often small; (2) after the prestressed tendon is stretched , there is a situation where the channel grouting is not dense, which affects the quality of the beam.
发明内容Contents of the invention
针对现有预应力预制小箱梁施工技术,本发明的目的在于为了避免现有技术张拉方法带来的不利影响,在综合先张法与后张法、体外束与体内束、有粘结与无粘结预应力混凝土各自优势的基础上,提出一种新型的预应力张拉技术——横张法预应力施工。Aiming at the existing prestressed prefabricated small box girder construction technology, the purpose of the present invention is to avoid the adverse effects brought by the tensioning method of the prior art, and integrate pre-tensioning and post-tensioning, external beam and internal beam, and bonding Based on the respective advantages of unbonded prestressed concrete, a new type of prestressed tensioning technology—transverse tension method prestressed construction is proposed.
本发明的另一目的在于提供了一种结构简单、施工安全的横张法预应力小箱梁施工制作方法。Another object of the present invention is to provide a method for constructing a prestressed small box girder with a simple structure and safe construction.
为了解决上述技术问题,本发明采用的技术方案是:In order to solve the problems of the technologies described above, the technical solution adopted in the present invention is:
一种预应力小箱梁制作方法,其特征在于:将该预应力小箱梁分为中间的明槽段和位于明槽段两端的锚固段,整个预应力小箱梁分三次浇筑完成,具体如下:A method for manufacturing a prestressed small box girder, characterized in that: the prestressed small box girder is divided into an open channel section in the middle and anchor sections located at both ends of the open channel section, and the entire prestressed small box girder is poured in three times to complete, specifically as follows:
步骤一、首先浇筑明槽段,在明槽段的预应力小箱梁腹板上预留用于布置预应力筋的明槽,并在明槽底部间隔一段距离预设两个用于张拉预应力筋的张拉孔;Step 1. First pour the open channel section, reserve an open channel for arranging prestressed tendons on the prestressed small box girder web of the open channel section, and preset two at the bottom of the open channel for tensioning Tension holes for prestressed tendons;
步骤二、将预应力筋在明槽段预留的明槽内穿束,将穿束后的预应力筋与两端的锚固段的钢筋笼固定相连,并浇筑位于两端的锚固段,完成第二次浇筑;Step 2. Thread the prestressed tendons in the open grooves reserved in the open groove section, connect the prestressed tendons after the bundles with the reinforcement cages of the anchorage sections at both ends, and pour the anchorage sections at both ends to complete the second secondary pouring;
步骤三、第二次浇筑固化后,通过明槽底部的两个横张孔用张拉设备将预应力筋往下张拉,检查预应力筋达的张拉值和伸长值满足要求;Step 3. After the second pouring and solidification, stretch the prestressed tendons downward with tensioning equipment through the two transverse stretching holes at the bottom of the open groove, and check that the tension and elongation values of the prestressed tendons meet the requirements;
步骤四、对明槽段中的明槽进行浇筑,完成第三次浇筑,固化后拆除张拉设备,完成整个预应力小箱梁的制作。Step 4: Concrete the open channel in the open channel section, complete the third pouring, remove the tensioning equipment after solidification, and complete the production of the entire prestressed small box girder.
作为改进,所述明槽段浇筑工艺为:先绑扎明槽段的底板和腹板钢筋,将钢筋笼吊入外模板中,并装入预留明槽的气囊,气囊充气达到要求气压后,安装内模板,绑扎顶板钢筋,同时在顶板钢筋处每隔一段距离用管道设置预留的孔洞用于明槽的第三次浇筑及安装张拉设备,在明槽的底板处预留两个用于预应力筋横向张拉的张拉孔,检查钢筋模板无误后,浇筑第一次混凝土,完成明槽段浇筑。As an improvement, the pouring process of the open channel section is as follows: first bind the bottom plate and web steel bars of the open channel section, hang the steel cage into the outer formwork, and put it into the air bag reserved for the open channel, after the air bag is inflated to the required air pressure, Install the inner formwork, tie the roof steel bars, and set reserved holes with pipes at intervals between the roof steel bars for the third pouring of the open channel and the installation of tensioning equipment, and reserve two holes at the bottom plate of the open channel In the tension hole where the prestressed tendon is stretched horizontally, after checking that the steel formwork is correct, the first concrete is poured to complete the pouring of the open channel section.
作为改进,步骤二中,在与明槽段相接处的锚固段设置将预应力筋定位的定位钢板,具体为,按照预应力筋的设计要求,在定位钢板上设置多个对应的定位孔,每根预应力筋从其中一个定位孔中穿过,定位钢板与锚固段的钢筋笼焊接在一起。As an improvement, in step 2, a positioning steel plate for positioning the prestressed tendon is provided at the anchorage section at the junction with the open groove section, specifically, according to the design requirements of the prestressed tendon, a plurality of corresponding positioning holes are provided on the positioning steel plate , each prestressed tendon passes through one of the positioning holes, and the positioning steel plate and the reinforcement cage of the anchorage section are welded together.
作为改进,步骤二中,在锚固段从梁顶下定位钢筋勾住预应力筋,使锚固段内预应力筋保持平直状态,并将预应力筋绑扎在锚固段的钢筋笼,之后对锚固段进行浇筑,完成第二次浇筑。As an improvement, in step 2, locate the steel bars from the top of the beam in the anchorage section to hook the prestressed tendons, keep the prestressed tendons in the anchorage section in a straight state, and tie the prestressed tendons to the reinforcement cage of the anchorage section. Section pouring, complete the second pouring.
作为改进,所述明槽段上张拉孔四周的底板和腹板上分别设有加强钢筋网。As an improvement, the bottom plate and the web around the tension hole on the open channel section are respectively provided with reinforcing steel mesh.
作为改进,绑扎明槽段钢筋笼时,在明槽段顶板钢筋上用管道预留的孔洞间距为1.5-3m,其中两个预留的孔洞与底板上的两个张拉孔对应。As an improvement, when binding the reinforcement cage of the open channel section, the distance between the holes reserved by pipes on the roof reinforcement of the open channel section is 1.5-3m, and the two reserved holes correspond to the two tension holes on the bottom plate.
作为改进,在锚固段浇筑前,预应力筋穿束后,在明槽内每隔一段距离用临时定位钢筋支撑预应力筋,锚固段浇筑固化后拆除临时定位钢筋。As an improvement, before the anchoring section is poured, after the prestressed tendons pass through, the prestressed tendons are supported by temporary positioning steel bars at intervals in the open groove, and the temporary positioning steel bars are removed after the anchoring section is poured and solidified.
作为改进,对预应力筋横向张拉后,预应力筋在明槽内分为倾斜段和平直段,其中预应力筋横向张拉的下行距离与倾斜段长度的比值范围为1:4.5~1:6。As an improvement, after the prestressed tendon is stretched horizontally, the prestressed tendon is divided into an inclined section and a straight section in the open groove, and the ratio of the descending distance of the prestressed tendon to the length of the inclined section is in the range of 1:4.5~1 :6.
作为改进,第三次浇筑明槽的混凝土为比前两次浇筑明槽段和锚固段混凝土强度高一个等级的微膨胀细石混凝土。As an improvement, the concrete for the third pouring of the open channel is micro-expansion fine stone concrete with a grade higher than the strength of the concrete for the first two pouring of the open channel section and the anchor section.
作为改进,所述张拉设备包括张拉杆、承压板、锚具和千斤顶,先将张拉杆顶部与承压板固定相连,然后将张拉杆从明槽顶部往下放,张拉杆至少两个,且对称分布在预应力筋两侧,张拉杆下端从明槽底部的张拉孔伸出,之后在承压板与预应力筋之间放置钢垫片,将张拉杆底部与千斤顶安装好,在千斤顶与明槽段底板之间设置楔形承压板,楔形承压板上表面与明槽段底板平行,下表面与张拉杆垂直,最后启动千斤顶对预应力筋进行横向张拉,对预应力筋张拉达到要求后,浇筑明槽,明槽浇筑固化后拆除千斤顶和楔形承压板,将伸出底板外的张拉杆割除,并封闭张拉孔。As an improvement, the tensioning equipment includes a tensioning rod, a pressure bearing plate, an anchor and a jack. First, the top of the tensioning rod is fixedly connected to the pressure bearing plate, and then the tensioning rod is lowered from the top of the open groove. There are at least two tensioning rods. And symmetrically distributed on both sides of the prestressed tendons, the lower end of the tension rod protrudes from the tension hole at the bottom of the open groove, and then a steel gasket is placed between the pressure bearing plate and the prestressed tendon, and the bottom of the tension rod and the jack are installed. A wedge-shaped pressure bearing plate is set between the jack and the bottom plate of the open groove section. The upper surface of the wedge-shaped pressure bearing plate is parallel to the bottom plate of the open groove section, and the lower surface is perpendicular to the tension rod. After the tension meets the requirements, pour the open groove, remove the jack and wedge-shaped pressure bearing plate after the open groove is poured and solidified, cut off the tension rod protruding from the bottom plate, and close the tension hole.
本发明的有益效果是:The beneficial effects of the present invention are:
(1)后张法施工的最大缺陷在于管道压浆易出现不密实现象,从而影响梁的质量。因此横张法改管道压浆为预留明槽浇筑混凝土,以使梁的质量得到更好的控制。(1) The biggest defect of post-tensioning construction is that the pipeline grouting is prone to non-compacting, which affects the quality of the beam. Therefore, the horizontal tension method is changed to pipe grouting to reserve open grooves to pour concrete, so that the quality of the beams can be better controlled.
(2)采用后张法,预应力筋较长时存在张拉力不均、中部预应力筋利用率低的问题,而采用横张法张拉,预应力筋在梁跨中部仍有较好的张拉效果,经实验证明,预应力筋的利用率可以高达80%~90%。(2) When the post-tensioning method is used, the prestressed tendons are uneven in tension and the utilization rate of the central prestressed tendons is low when the prestressed tendons are long, while the transverse tension method is used to stretch the prestressed tendons in the middle of the beam span. Tensile effect, it has been proved by experiments that the utilization rate of prestressed tendons can be as high as 80% to 90%.
(3)后张法需要锚具对预应力筋进行固定,而横张法借鉴了先张法的粘结自锚,节省了锚具;同时,横张法所需的张拉力远小于后张法的张拉力,可以选用较小吨数的千斤顶;横张法从箱梁下部张拉,两端预应力束无需伸出梁体来获得张拉操作空间,节省了一定数量的预应力筋。(3) The post-tensioning method requires anchors to fix the prestressed tendons, while the transverse-tensioning method uses the bonded self-anchor of the pre-tensioning method to save anchors; at the same time, the tension required by the transverse-tensioning method is much smaller than that of post-tensioning Jacks with a smaller tonnage can be used for the tensile force of the method; the horizontal tension method is used to stretch from the lower part of the box girder, and the prestressed beams at both ends do not need to extend out of the beam body to obtain a tensioning operation space, saving a certain amount of prestressed tendons.
(3)本发明解决了现有小箱梁预应力张拉中压浆不密实的问题,同时降低了预应力筋的应力损失、提高了预应力筋的利用率、有效地降低了张拉力。本发明结构简单,施工安全,主要用于在梁底进行预应力张拉的预应力小箱梁施工。(3) The present invention solves the problem of insufficient grouting in the prestressed stretching of the existing small box girder, reduces the stress loss of the prestressed tendons, improves the utilization rate of the prestressed tendons, and effectively reduces the tension force. The invention has simple structure and safe construction, and is mainly used for the construction of prestressed small box girders with prestressed tension at the bottom of the beams.
附图说明Description of drawings
图1是预应力小箱梁俯视图。Figure 1 is a top view of the prestressed small box girder.
图2是图1中预应力小箱梁截面图;Fig. 2 is a sectional view of the prestressed small box girder in Fig. 1;
其中A-A为图1中锚固段截面图,B-B为图1中明槽段截面图。Among them, A-A is the cross-sectional view of the anchoring section in Figure 1, and B-B is the cross-sectional view of the open groove section in Figure 1.
图3是预应力小箱梁预应力筋穿束并张拉示意图。Fig. 3 is a schematic diagram of the prestressed tendons of the prestressed small box girder passing through and stretched.
图4是预应力小箱梁明槽段加强钢筋网分布示意图。Figure 4 is a schematic diagram of the distribution of reinforcing steel mesh in the open channel section of a prestressed small box girder.
图5是张拉设备使用示意图。Figure 5 is a schematic diagram of the use of tensioning equipment.
图6是预应力小箱左半段上预留孔设置俯视图示意图。Fig. 6 is a schematic top view of the reserved holes on the left half of the prestressed small box.
图7是预应力小箱左半段上张拉孔设置仰视图示意图。Fig. 7 is a bottom view schematic diagram of the setting of the tension holes on the left half of the prestressed small box.
1-明槽段,2-锚固段,3-预应力筋,4-明槽段顶板,5-明槽段腹板,6-明槽段底板,7-锚固段顶板,8-锚固段底板,9-锚固段腹板,10-定位钢板,11-腹板加强钢筋网,12-底板加强钢筋网,13-明槽,14-张拉孔,15-孔洞,16-P锚挤压套,17-承压板,18-钢垫片,19-张拉杆,20-楔形承压板,21-锚具,22-千斤顶,23-锚固段加强钢筋。1-open channel section, 2-anchor section, 3-prestressed tendons, 4-top plate of open channel section, 5-web plate of open channel section, 6-bottom plate of open channel section, 7-top plate of anchor section, 8-bottom plate of anchor section , 9-web plate of anchor section, 10-positioning steel plate, 11-web reinforcement mesh, 12-bottom plate reinforcement mesh, 13-open groove, 14-tension hole, 15-hole, 16-P anchor extrusion sleeve , 17-pressure bearing plate, 18-steel gasket, 19-tension rod, 20-wedge bearing plate, 21-anchor, 22-jack, 23-reinforcing steel bar for anchorage section.
具体实施方式Detailed ways
下面通过非限定性的实施例对本发明作进一步说明:The present invention will be further described below by non-limiting embodiment:
一种预应力小箱梁制作方法,如图1所示,将该预应力小箱梁分为中间的明槽段1和位于明槽段1两端的锚固段2,整个预应力小箱梁分三次浇筑完成,具体如下:A kind of prestressed small box girder manufacturing method, as shown in Figure 1, this prestressed small box girder is divided into the open groove section 1 in the middle and the anchorage section 2 that is positioned at the open groove section 1 two ends, and the whole prestressed small box girder is divided into The pouring was completed three times, as follows:
步骤一、首先浇筑明槽段1,在明槽段1的预应力小箱梁腹板上预留用于布置预应力筋3的明槽13,并在明槽13底部间隔一段距离预设两个用于张拉预应力筋3的张拉孔14;Step 1. First pour the open channel section 1, reserve the open channel 13 for arranging the prestressed ribs 3 on the prestressed small box girder web of the open channel section 1, and preset two holes at the bottom of the open channel 13 at a distance. A tension hole 14 for tensioning the prestressed tendons 3;
步骤二、将预应力筋3在明槽段1预留的明槽13内穿束,将穿束后的预应力筋3与两端的锚固段2的钢筋笼固定相连,并浇筑位于两端的锚固段2,完成第二次浇筑;Step 2, thread the prestressed tendons 3 in the open groove 13 reserved in the open groove section 1, connect the threaded prestressed tendons 3 with the reinforcement cages of the anchorage sections 2 at both ends, and pour the anchorage bars at both ends. Section 2, complete the second pouring;
步骤三、第二次浇筑固化后,通过明槽13底部的两个横张孔用张拉设备将预应力筋3往下张拉,检查预应力筋3达的张拉值和伸长值满足要求;Step 3. After the second pouring and solidification, stretch the prestressed tendons 3 downward through the two horizontal stretching holes at the bottom of the open groove 13, and check that the tension and elongation values of the prestressed tendons 3 meet the requirements. ;
步骤四、对明槽段1中的明槽13进行浇筑,完成第三次浇筑,固化后拆除张拉设备,完成整个预应力小箱梁的制作。Step 4: Concrete the open channel 13 in the open channel section 1, complete the third pouring, remove the tensioning equipment after curing, and complete the production of the entire prestressed small box girder.
所述明槽段1浇筑工艺为:先绑扎明槽段1的底板和腹板钢筋,将钢筋笼吊入外模板中,并装入预留明槽13的气囊,气囊充气达到要求气压后,安装内模板,绑扎顶板钢筋,同时在顶板钢筋处每隔一段2m距离用PVC管道设置预留的孔洞15用于明槽13的第三次浇筑及安装张拉设备,在明槽13的底板处预留两个用于预应力筋3横向张拉的张拉孔14,检查钢筋模板无误后,浇筑第一次混凝土,完成明槽段1浇筑,浇筑后,将气囊放气取出即形成明槽13。The pouring process of the open channel section 1 is as follows: first bind the bottom plate and web steel bars of the open channel section 1, hoist the reinforcement cage into the outer formwork, and put the air bag reserved for the open channel 13 into it, and after the air bag is inflated to the required air pressure, Install the inner formwork, bind the steel bars of the roof, and set reserved holes 15 with PVC pipes at intervals of 2m at the steel bars of the roof for the third pouring of the open channel 13 and the installation of tensioning equipment, at the bottom plate of the open channel 13 Two tension holes 14 are reserved for the transverse tension of the prestressed tendons 3. After checking that the steel formwork is correct, the first concrete is poured, and the pouring of the open channel section 1 is completed. After pouring, the air bag is deflated and taken out to form the open channel 13.
步骤二中,在与明槽段1相接处的锚固段2设置将预应力筋3定位的定位钢板10,具体为,按照预应力筋3的设计要求,在定位钢板10上设置多个对应的定位孔,每根预应力筋3从其中一个定位孔中穿过,以保证预应力筋3定位准确,定位钢板10与锚固段2的腹板钢筋笼焊接在一起或绑在一起,定位钢板10厚度为30mm左右,相邻预应力筋3的间距要求满足规范要求。In step 2, a positioning steel plate 10 for positioning the prestressed tendons 3 is provided at the anchorage section 2 at the junction with the open channel section 1, specifically, according to the design requirements of the prestressed tendons 3, multiple corresponding Each prestressed tendon 3 passes through one of the positioning holes to ensure accurate positioning of the prestressed tendons 3. The positioning steel plate 10 is welded or tied together with the web steel cage of the anchorage section 2, and the positioning steel plate 10. The thickness is about 30 mm, and the distance between adjacent prestressed tendons 3 meets the specification requirements.
步骤二中,在锚固段2从梁顶下定位钢筋勾住预应力筋3,使锚固段2内预应力筋3保持平直状态,并将预应力筋3绑扎在锚固段2的钢筋笼,之后对锚固段2进行浇筑,完成第二次浇筑。In step 2, locate the steel bars under the beam top in the anchorage section 2 to hook the prestressed tendons 3, keep the prestressed tendons 3 in the anchorage section 2 in a straight state, and bind the prestressed tendons 3 to the reinforcement cage of the anchorage section 2, After that, the anchorage section 2 is poured to complete the second pouring.
所述明槽段1上张拉孔14四周的底板和腹板上分别设有底板加强钢筋网12和腹板加强钢筋网11,以保证预应力筋3横向张拉时底板和腹板混凝土表面不出现裂缝。The bottom plate and the web around the tension hole 14 on the open channel section 1 are respectively provided with a bottom plate reinforcing steel mesh 12 and a web strengthening steel mesh 11, so as to ensure that the concrete surface of the bottom plate and the web when the prestressed tendons 3 are stretched transversely Cracks do not appear.
绑扎明槽段1钢筋笼时,在明槽段顶板4钢筋上用管道预留的孔洞15间距为1.5-3m,本实施例为2m,其中两个预留的孔洞15与底板上的两个张拉孔14对应。When binding the open channel section 1 reinforcement cage, on the open channel section top plate 4 steel bars, the hole 15 spacing reserved with the pipeline is 1.5-3m, and the present embodiment is 2m, wherein two of the reserved holes 15 are connected with the two holes on the bottom plate. Tension holes 14 correspond.
在锚固段2浇筑前,预应力筋3穿束后,在明槽13内每隔4m距离用临时定位钢筋支撑预应力筋3,以确保预应力筋3在张拉前满足设计所要求的直线位置,锚固段2浇筑固化后拆除临时定位钢筋,预应力筋3两端绑在锚固段腹板9钢筋笼上。Before the anchorage section 2 is poured, after the prestressed tendons 3 are threaded, use temporary positioning steel bars to support the prestressed tendons 3 at intervals of 4m in the open groove 13, so as to ensure that the prestressed tendons 3 meet the straight line required by the design before tensioning position, after the anchor section 2 is poured and solidified, the temporary positioning reinforcement is removed, and the two ends of the prestressed tendon 3 are tied to the reinforcement cage of the anchor section web 9 .
对预应力筋3横向张拉后,预应力筋3在明槽13内分为倾斜段和平直段,其中预应力筋3横向张拉的下行距离与倾斜段长度的比值范围为1:4.5~1:6。After the prestressed tendon 3 is stretched transversely, the prestressed tendon 3 is divided into an inclined section and a straight section in the open groove 13, wherein the ratio of the descending distance of the prestressed tendon 3 transversely stretched to the length of the inclined section ranges from 1:4.5 to 1:6.
第三次浇筑明槽13的混凝土为比前两次浇筑明槽段1和锚固段2混凝土强度高一个等级的微膨胀细石混凝土。The concrete for the third pouring of the open channel 13 is micro-expansion fine stone concrete one level higher than the strength of the concrete for the first two pouring of the open channel section 1 and the anchor section 2 .
上述横张法预应力小箱梁制作方法采用的张拉设备包括张拉杆19、承压板17、锚具21和千斤顶22,先将张拉杆19顶部与承压板17通过P锚挤压套16固定相连,然后将张拉杆19从明槽13顶部往下放,张拉杆19至少两个,且对称分布在预应力筋3两侧,张拉杆19下端从明槽13底部的张拉孔14伸出,之后在承压板17与预应力筋3之间放置钢垫片18,将张拉杆19底部与千斤顶22安装好,在千斤顶22与明槽段底板6之间设置楔形承压板20,楔形承压板20上表面与明槽段底板6平行,下表面与张拉杆19垂直,最后启动千斤顶22对预应力筋3进行横向张拉,对预应力筋3张拉达到要求后,浇筑明槽13,明槽13浇筑固化后拆除千斤顶22和楔形承压板20,将伸出明槽段底板6外的张拉杆19割除,并封闭张拉孔14。The tensioning equipment used in the above-mentioned transverse tension method prestressed small box girder manufacturing method includes a tension rod 19, a pressure bearing plate 17, an anchor 21 and a jack 22. First, the top of the tension rod 19 and the pressure bearing plate 17 are passed through the P anchor extrusion sleeve 16 are fixedly connected, and then the tension rod 19 is lowered from the top of the open groove 13. There are at least two tension rods 19, and they are symmetrically distributed on both sides of the prestressed tendon 3. The lower end of the tension rod 19 extends from the tension hole 14 at the bottom of the open groove 13. Afterwards, a steel gasket 18 is placed between the pressure-bearing plate 17 and the prestressed tendon 3, the bottom of the tension rod 19 and the jack 22 are installed, and a wedge-shaped pressure-bearing plate 20 is set between the jack 22 and the bottom plate 6 of the open groove section. The upper surface of the wedge-shaped pressure bearing plate 20 is parallel to the bottom plate 6 of the open groove section, and the lower surface is perpendicular to the tension rod 19. Finally, the jack 22 is started to stretch the prestressed tendons 3 transversely. After the groove 13 and the open groove 13 are poured and solidified, the jack 22 and the wedge-shaped pressure bearing plate 20 are removed, the tension rods 19 protruding from the bottom plate 6 of the open groove section are cut off, and the tension holes 14 are closed.
所述锚固段2长度要满足预应力筋3黏结锚固所需最小长度的要求,具体尺寸根据梁体构造确定,明槽段1长度为梁长减去梁两端锚固段2后的剩余长度。箱梁施工完成前后对施工质量进行实时监管。本实施例的其他部分采用现有技术。The length of the anchoring section 2 should meet the minimum length required for the bonding and anchoring of the prestressed tendon 3. The specific size is determined according to the structure of the beam body. The length of the open groove section 1 is the remaining length after subtracting the anchoring sections 2 at both ends of the beam. Real-time supervision of the construction quality before and after the box girder construction is completed. Other parts of this embodiment adopt the prior art.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711175269.3A CN107984610B (en) | 2017-11-22 | 2017-11-22 | A prestressed small box girder manufacturing method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711175269.3A CN107984610B (en) | 2017-11-22 | 2017-11-22 | A prestressed small box girder manufacturing method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107984610A CN107984610A (en) | 2018-05-04 |
CN107984610B true CN107984610B (en) | 2019-10-25 |
Family
ID=62032021
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711175269.3A Active CN107984610B (en) | 2017-11-22 | 2017-11-22 | A prestressed small box girder manufacturing method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107984610B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106592839A (en) * | 2017-03-03 | 2017-04-26 | 沈阳建筑大学 | Horizontal tensioning and external pre-stressing profiled steel sheet composite floor |
CN109695322A (en) * | 2019-02-01 | 2019-04-30 | 蔡君 | Prestressed prefabricated stringer type stairway of one kind and preparation method thereof |
CN111622079A (en) * | 2020-05-26 | 2020-09-04 | 中交路桥建设有限公司 | Separated construction method for prestressed cast-in-situ box beam end and beam |
CN112695633A (en) * | 2020-12-17 | 2021-04-23 | 中国能源建设集团安徽电力建设第一工程有限公司 | Prefabricated small box girder prestress engineering construction method for intelligent express way |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1061121C (en) * | 1995-09-08 | 2001-01-24 | 周志祥 | Method for construction of transverse tension prestress concrete beam |
CN2350429Y (en) * | 1998-11-08 | 1999-11-24 | 周志祥 | Transverse tension prestress hollow concrete slab bridge |
CN102182146B (en) * | 2011-03-29 | 2012-07-04 | 中国铁道科学研究院铁道建筑研究所 | Prestress rib tensioning equipment, system and method and concrete continuous box girder |
-
2017
- 2017-11-22 CN CN201711175269.3A patent/CN107984610B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN107984610A (en) | 2018-05-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107984610B (en) | A prestressed small box girder manufacturing method | |
CN106638313B (en) | A kind of large size half prefabricated construction technical method of bent cap | |
KR101394193B1 (en) | Incremental launching apparatus for launching concrete slab for composite bridge using form of buried type | |
CN102587267A (en) | Tension-fabricated bridge with prestressed hollow-plate-girders and middle transverse partitions and construction method of tension-fabricated bridge with prestressed hollow-plate-girder and middle transverse partitions | |
CN106522561A (en) | Long-span concrete frame beam bonded prestressed post-cast strip inside stretching construction method | |
CN104727441A (en) | Prestress assembled concrete beam column joint structure and construction method thereof | |
CN104762871A (en) | Prestressed concrete-steel tank beam bond beam continuous beam bridge | |
CN103774565B (en) | A kind of longitudinal prestressing reinforcement means of Hollow Slab Beam Bridge | |
CN108951399A (en) | A kind of Single-box multi-chamber box beam bridge and its construction method | |
CN108442227A (en) | One kind preventing deck crack hollow slab bridge structure and attaching method thereof | |
CN102561591A (en) | Retarded adhesive prestressed steel reinforced concrete beam | |
CN105735099B (en) | Construction time uses the simple supported-to-continuous girder bridge and its construction method of external prestressing | |
CN106087692A (en) | A kind of Simply supported non-uniform T negative moment of girder section structure and construction method | |
CN102747678B (en) | Unequal-height V-shaped bridge pier | |
CN106607989A (en) | Rail transit post-stressed U-shaped beam construction technique | |
CN108411801A (en) | One kind reinforcing the old hollow slab bridge construction of single hole and construction method by real abdomen Bars In Poured Concrete Slab | |
CN208362941U (en) | One kind reinforcing the old hollow slab bridge construction of single hole by real abdomen Bars In Poured Concrete Slab | |
CN107100095A (en) | A kind of T-shaped rigid frame bridge oblique pull ruggedized construction and its construction method | |
CN204626264U (en) | A kind of ruggedized construction of reinforced concrete arch bridge main arch ring | |
CN209114299U (en) | A single box multi-chamber box girder bridge | |
CN117754722A (en) | A two-stage symmetrical tensioning process for prefabricating box beams of highway bridges | |
CN107012986A (en) | Multilayer steel-enclosed concrete members composite coupling beams | |
CN113719152B (en) | Steel member externally-wrapped prestressed precast concrete reinforced structure and construction method | |
CN206693055U (en) | Super-long prestressed steel tendon staggered anchor arrangement structure | |
CN116674079A (en) | A construction method of prefabricated small box girder |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |