CN109281443A - A kind of building roof parapet flashing structure and construction method - Google Patents

A kind of building roof parapet flashing structure and construction method Download PDF

Info

Publication number
CN109281443A
CN109281443A CN201811326489.6A CN201811326489A CN109281443A CN 109281443 A CN109281443 A CN 109281443A CN 201811326489 A CN201811326489 A CN 201811326489A CN 109281443 A CN109281443 A CN 109281443A
Authority
CN
China
Prior art keywords
flashing
wall
reinforced frame
parapet
waterproof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811326489.6A
Other languages
Chinese (zh)
Inventor
夏进
胡宝明
李文祥
王文玮
杜峰
孔宪勇
王聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Construction Engineering Co Ltd
Original Assignee
Wuhan Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Construction Engineering Co Ltd filed Critical Wuhan Construction Engineering Co Ltd
Priority to CN201811326489.6A priority Critical patent/CN109281443A/en
Publication of CN109281443A publication Critical patent/CN109281443A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/14Junctions of roof sheathings to chimneys or other parts extending above the roof
    • E04D13/1407Junctions of roof sheathings to chimneys or other parts extending above the roof for flat roofs
    • E04D13/1415Junctions to walls extending above the perimeter of the roof

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Building Environments (AREA)

Abstract

The present invention relates to kind of a building roof parapets, the flashing wall being integrated including building roof structure sheaf, it is cast in the waterproof protective layer of the reinforced concrete structure of daughter's wall outer side, in flashing wall top surface, daughter's wall is connected with the flashing wall by the interior bar construction set, the thickness of daughter's wall is greater than flashing wall, vertical waterproof protective layer is extended downwardly out based on bottom of daughter's wall far from flashing wall side, facade is affixed with waterproof roll above the building roof structure sheaf and in flashing wall, waterproof roll is pressed on flashing wall by metal bead and steel nail, it is filled using sealant in gap in the waterproof roll apical margin and flashing wall between facade.It invention enhances the overall performance of the tensile property of waterproof protective layer and waterproof protective layer and parapet, avoids because the cohesive force between waterproof protective layer and waterproof roll is insufficient, and cracking occurs and fall off, lose protective effect.

Description

A kind of building roof parapet flashing structure and construction method
Technical field
The present invention relates to a kind of building engineering construction decoration technique fields, are related to a kind of building roof parapet flashing knot Structure is more particularly to a kind of building roof parapet flashing structure construction method.
Background technique
Parapet of roofing flashing refers to the water proof structure between roof waterproof layer and parapet, parapet of roofing wall surface and room The junction on top extends to roof waterproof layer on these vertical planes, forms the water proof structure of vertical paving.Currently, building roof female The construction method of youngster's wall flashing is as follows: the parapet of brick setting is built on reinforced concrete structure roofing, then in parapet Upper paving waterproof roll brushes protective layer of the one layer of mortar as waterproof layer as waterproof layer on waterproof roll.This construction party The flashing that method is made constructs in the long-term use, due to the temperature of reinforced concrete structure roofing and brick setting flashing construction Expansion coefficient difference is larger, and flashing wall (parapet) is caused to be easy cracking, and flashing wall crazing can cause waterproof roll to go out Drum, cracking, obscission are now played, waterproof failure, roof leakage are eventually led to.Meanwhile protective layer is attached to smooth waterproof roll Material surface, the cohesive force between protective layer and waterproof roll is insufficient, and protective layer is easy cracking, falls off, and loses protective effect, so that anti- Water coiled material is exposed, and waterproof roll aging accelerates under solar exposure and temperature cataclysm, gradually loses waterproof action, therefore industry A kind of building roof daughter wall construction method is inside needed, has been easy to rouse solving waterproof roll, crack, has fallen off, eventually led to anti- The problem of water fails.Meanwhile can crack and fall off to avoid waterproof protective layer, lose protective effect.
Summary of the invention
The purpose of the present invention is to provide a kind of building roof daughter wall construction methods, compared with prior art, can keep away Waterproof roll caused by exempting from because of flashing wall crazing plays drum, cracking, obscission, eventually leads to waterproof failure, roof leakage.Together When, parapet and flashing wall waterproof protective layer are all made of reinforced concrete structure.The tensile property of waterproof protective layer is enhanced, It avoids because the cohesive force between waterproof protective layer and waterproof roll is insufficient, and cracking occurs and fall off, lose protective effect.
The present invention in order to overcome the above-mentioned deficiencies of the prior art, proposes following scheme:
A kind of building roof parapet flashing structure, including it is vertically arranged in the first reinforced frame in building roof structure sheaf, And the flashing wall being integrated with building roof structure sheaf, the waterproof for being cast in the reinforced concrete structure of daughter's wall outer side are protected Sheath, the flashing wall is reinforced concrete structure, in flashing wall top surface, daughter's wall and the flashing wall Body is by the interior bar construction linking set, and the thickness of daughter's wall is greater than flashing wall, with daughter's wall far from flashing wall Vertical waterproof protective layer is extended downwardly out based on the bottom of body side, above the building roof structure sheaf and flashing wall Interior facade is affixed with waterproof roll, and waterproof roll is pressed on flashing wall by metal bead and steel nail, the waterproof roll It is filled using sealant in gap in apical margin and flashing wall between facade.
Further, the bar construction includes that flashing wall is stretched out in one end, and the other end is embedded in flashing wall intracorporal the One reinforced frame;It is connected in parapet with the second reinforced frame of parapet and waterproofing protection interlayer, the first reinforced frame top Second reinforced frame, the second reinforced frame thickness are greater than flashing wall, the bottom with the second reinforced frame far from flashing wall side Based on weld third reinforced frame.
Further, setting diameter in the junction of the flashing wall and building roof structure sheaf is 5cm circular arc.
Further, the first reinforced frame specification is double two-way 8@200 of Φ, and higher than flashing wall.
Further, the waterproof roll top edge is compacted using metal bead, along metal bead horizontal direction to be greater than Spacing equal to 250mm and less than or equal to 500mm squeezes into steel nail, is fixed on waterproof roll on flashing wall.
Further, the second reinforced frame specification is double two-way 8@200 of Φ.
Further, the third reinforced frame specification is single two-way 8@200 of Φ.
A kind of building roof daughter wall construction method, the specific steps are as follows:
Step 1: flashing wall construction
The flashing wall that one-piece casting goes out vertical plane at building roof structure sheaf edge makes flashing wall in casting process Circular arc junction is formed with building roof structure sheaf;To be close to flashing wall when waterproof roll paving;In the flashing wall Embedded first reinforced frame, the vertical stretching flashing wall 50cm of the first reinforced frame, so as to the second reinforced frame for being set to parapet It is overlapped, the specification of first reinforced frame is double two-way 8@200 of Φ, and first reinforced frame is in building roof structure sheaf With joint bar before 1 one-piece casting of flashing wall;
Step 2: waterproof roll paving and receipts head processing
The paving waterproof roll on facade in building roof structure sheaf and flashing wall forms waterproof layer, and along waterproof roll Material top edge horizontal direction arranges metal bead, and steel nail is squeezed into metal bead, waterproof roll is pressed abd fixed on flashing wall On, finally waterproof roll top edge is received using sealant and is covered at head;Sealant is caused for filling up to receive in head processing Gap, the metal bead width be not less than 20mm, the steel nail along metal bead horizontal direction be more than or equal to 250mm and Spacing equidistant placement less than or equal to 500mm.
Step 3: parapet and waterproof protective layer construction
The second reinforced frame is welded at the top of flashing wall, the second reinforced frame thickness is greater than flashing wall, with the second steel Third reinforced frame is welded based on bottom of the ledges far from flashing wall side, installs wall for the second reinforced frame and third reinforced frame Template pours C20 pea gravel concreten, last shape in the parapet and waterproofing protection sheaf space that wall form and flashing wall are formed It is integrated reinforced concrete structure at parapet and flashing and waterproof protective layer, the second reinforced frame specification is double two-way Φ 8@200, the third reinforced frame specification are single two-way 8@200 of Φ.
Compared with prior art, parapet of the invention and waterproof protective layer use reinforced concrete structure, and pour together Construction is built, rather than builds daughter's wall brick at the top of flashing wall, wall brick is protected in the inside paving in waterproof roll, in protection wall Weather-proof sealing compound is filled between brick and parapet, the side hanging steel wire outside protection wall brick and parapet applies plastering outside steel wire Layer.
The beneficial effects of the present invention are: flashing wall and building roof structure are all made of reinforced concrete structure, avoid Temperature expansion co-efficient difference it is different it is larger caused by flashing wall crazing, thus waterproof caused by also avoiding because of flashing wall crazing Has there is drum, cracking, obscission in coiled material, eventually leads to waterproof failure, roof leakage.Parapet and flashing wall waterproofing protection Layer is all made of reinforced concrete structure, and pours simultaneously.Enhance tensile property and waterproof protective layer and the female of waterproof protective layer The overall performance of youngster's wall is avoided because the cohesive force between waterproof protective layer and waterproof roll is insufficient, and cracking is occurred and fallen off, and is lost Protective effect.Waterproof protective layer, parapet and flashing wall, building roof structure form overall structure, avoid because of temperature expansion Difference of coefficients causes parapet and waterproof protective layer to crack.In terms of constructing operation, structure of the invention has easily unimaginable Effect is used only on when flashing wall body structure pours and is inserted into reinforcing bar, repaves waterproof roll such as and carries out receiving head processing, finally in flashing The framework of steel reinforcement of parapet and waterproof protective layer is built in the intracorporal reinforcing bar external welding of wall, and direct one-piece casting parapet and waterproof are protected Sheath, construction procedure is simple, easily operated.
Detailed description of the invention
Fig. 1 is to be formed by building roof parapet flashing structure using construction method of the present invention;
Fig. 2 is that waterproof roll receives drawing at head;
Fig. 3 is that waterproof roll receives metal bead and steel nail detail drawing at head;
In figure, 1- flashing wall, 2- building roof structure, 3- circular arc, 4- waterproof roll, the first reinforced frame of 5-, daughter 6- Wall, 7- metal bead, 8- steel nail, 9- sealant, 10- waterproof protective layer, the second reinforced frame of 11-, 12- third reinforced frame.
Specific embodiment
The following further describes the present invention with reference to the drawings.
As shown in Figure 1, building roof parapet flashing structure, including be vertically arranged in first in building roof structure sheaf 2 Reinforced frame, and the flashing wall 1 being integrated with building roof structure sheaf 2 are cast in the armored concrete knot in 6 outside of daughter's wall The waterproof protective layer 10 of structure, the flashing wall 1 is reinforced concrete structure, in 1 top surface of flashing wall, the parapet Body 6 is connected with the flashing wall 1 by the interior bar construction set, and the thickness of daughter's wall 6 is greater than flashing wall 1, with Daughter's wall 6 extends downwardly out vertical waterproof protective layer 10, the building based on the bottom far from 1 side of flashing wall Facade is affixed with waterproof roll 4 to face structure sheaf 2 above and in flashing wall 1, and waterproof roll 4 is pressed by metal bead 7 and steel nail 8 Tightly on flashing wall 1, the gap in 4 apical margin of waterproof roll and flashing wall 1 between facade is filled using sealant 9.
The bar construction includes that the first reinforced frame that 1 other end of flashing wall is embedded in flashing wall 1 is stretched out in one end 5;The second reinforced frame 11 in parapet 1 between parapet 1 and waterproof protective layer 10 is connected at the top of first reinforced frame 5 Second reinforced frame 11, the second reinforced frame thickness is greater than flashing wall 1, with the second reinforced frame 11 far from 1 side of flashing wall Bottom based on weld third reinforced frame 12.
The flashing wall 1 is highly 2 or more 250mm of roof building face structure sheaf, the flashing wall with a thickness of 140mm The junction of body 1 and building roof structure sheaf 2 setting diameter is 5cm circular arc 3, and 5 specification of the first reinforced frame is double two-way 8@of Φ 200, and it is 50cm higher than flashing height, to be welded with the second reinforced frame.
As Figure 2-3,4 top edge of waterproof roll is compacted using 20mm wide metal bead 7, to be greater than on metal bead Spacing equal to 250mm and less than or equal to 500mm squeezes into steel nail to be fixed on flashing wall 1, and in the top of waterproof roll 4 Edge is received and is covered at head using sealant 9, receives gap caused by head processing to fill up.
In Fig. 1-2, parapet 6 is with a thickness of 200mm, and with a thickness of 60mm, the two is adopted for waterproof roll 4 and waterproof protective layer 10 The concrete for being C20 with intensity pours together.Second reinforced frame, 11 specification is double two-way 8@200 of Φ, with general first reinforced frame 5 Welding.12 specification of third reinforced frame is single two-way 8@200 of Φ, protrudes into waterproof protective layer for two-way concrete slab single on the inside of parapet Formed in.
Specific step is as follows for a kind of building roof parapet flashing construction method:
Step 1: flashing wall construction
Make flashing wall in casting process in the flashing wall 1 that 2 edge one-piece casting of building roof structure sheaf goes out vertical plane Body 1 and building roof structure sheaf 2 form 3 junction of circular arc;To be close to flashing wall 1 when 4 paving of waterproof roll;The flashing Bury the first reinforced frame 5 in wall 1, the vertical stretching flashing wall 50cm of the first reinforced frame 5, so as to be set to parapet 6 Second reinforced frame 11 is overlapped, and the specification of the reinforcing bar 5 is double two-way 8@200 of Φ, and first reinforced frame 5 is in building Joint bar before face structure sheaf 2 and 1 one-piece casting of flashing wall.
Step 2: waterproof roll paving and receipts head processing
The paving waterproof roll 4 on facade in building roof structure sheaf 2 and flashing wall 1 forms waterproof layer, and along waterproof 4 top edge horizontal direction of coiled material arranges metal bead 7, and steel nail 8 is squeezed into metal bead 7, waterproof roll 4 is pressed abd fixed on general On waterwall body 1, finally 4 top edge of waterproof roll is received using sealant 9 and is covered at head;Sealant 9 is for filling up receipts head Gap caused by processing, 7 width of metal bead are not less than 20mm, and the steel nail 8 is along 7 horizontal direction of metal bead with big In equal to 250mm and less than or equal to the spacing equidistant placement of 500mm.
Step 3: parapet and waterproof protective layer construction
Weld the second reinforced frame 11 at the top of flashing wall 1, the second reinforced frame thickness is greater than flashing wall 1, with the Third reinforced frame 12 is welded based on two bottoms of the reinforced frame 11 far from 1 side of flashing wall, is the second reinforced frame 11 and third Reinforced frame 12 installs wall form, and it is thin to pour C20 in the parapet and waterproofing protection sheaf space that wall form and flashing wall are formed Stone concrete, eventually forms parapet and flashing and waterproof protective layer is integrated reinforced concrete structure, second reinforced frame 11 specifications are double two-way 8@200 of Φ, and 12 specification of third reinforced frame is single two-way 8@200 of Φ.
Construction method of the present invention is easy to operate and quick, substantially reduces the construction period, reduces construction cost, has simultaneously There is the advantages of crack resistence, anti-dropout and extended shelf-life.

Claims (8)

1. a kind of building roof parapet flashing structure, which is characterized in that including being vertically arranged in building roof structure sheaf One reinforced frame, and the flashing wall being integrated with building roof structure sheaf, are cast in the armored concrete knot of daughter's wall outer side The waterproof protective layer of structure, the flashing wall be reinforced concrete structure, in flashing wall top surface, daughter's wall with The flashing wall is by the interior bar construction linking set, and the thickness of daughter's wall is greater than flashing wall, with daughter's wall Vertical waterproof protective layer is extended downwardly out based on bottom far from flashing wall side, above the building roof structure sheaf And facade is affixed with waterproof roll in flashing wall, waterproof roll is pressed on flashing wall by metal bead and steel nail, institute The gap in waterproof roll apical margin and flashing wall between facade is stated to fill using sealant.
2. parapet flashing structure according to claim 1, which is characterized in that the bar construction includes that one end stretching is general Waterwall body, the other end are embedded in intracorporal first reinforced frame of flashing wall;In parapet and parapet and waterproofing protection interlayer The second reinforced frame, the second reinforced frame being connected at the top of the first reinforced frame, the second reinforced frame thickness is greater than flashing wall, with Third reinforced frame is welded based on bottom of second reinforced frame far from flashing wall side.
3. parapet flashing structure according to claim 1, which is characterized in that the flashing wall and building roof structure The junction setting diameter of layer is 5cm circular arc.
4. parapet flashing structure according to claim 1, which is characterized in that the waterproof roll top edge uses metal Press strip compacting, is more than or equal to 250mm along metal bead horizontal direction and the spacing less than or equal to 500mm squeezes into steel nail, makes to prevent Water coiled material is fixed on flashing wall.
5. parapet flashing structure according to claim 2, which is characterized in that the first reinforced frame specification is double double To 8@200 of Φ, and it is higher than flashing wall.
6. parapet flashing structure according to claim 2, which is characterized in that the second reinforced frame specification is double double To 8@200 of Φ.
7. parapet flashing structure according to claim 2, which is characterized in that the third reinforced frame specification is single double To 8@200 of Φ.
8. a kind of construction method of building roof parapet flashing structure, which is characterized in that described in the Claims 1 to 4 The construction method of parapet flashing structure, comprising the following steps:
Step 1, flashing wall construction
The flashing wall that one-piece casting goes out vertical plane at building roof structure sheaf edge makes flashing wall and builds in casting process It builds roof construction layer and forms circular arc junction;The first reinforced frame, the vertical stretching of the first reinforced frame are buried in the flashing wall The specification of flashing wall 50cm, first reinforced frame are double two-way 8@200 of Φ, and first reinforced frame is in building roof knot Joint bar before structure layer and flashing wall one-piece casting;
Step 2, waterproof roll paving and receipts head processing
The paving waterproof roll on facade in building roof structure sheaf and flashing wall forms waterproof layer, and along waterproof roll Edge horizontal direction arranges metal bead, and steel nail is squeezed into metal bead, waterproof roll is pressed abd fixed on flashing wall, most Waterproof roll top edge is received using sealant afterwards and is covered at head;Sealant receives seam caused by head processing for filling up Gap, the metal bead width are not less than 20mm, and the steel nail is more than or equal to 250mm along metal bead horizontal direction and is less than Spacing equidistant placement equal to 500mm;
Step 3, parapet and waterproof protective layer construction
The second reinforced frame is welded at the top of flashing wall, the second reinforced frame thickness is greater than flashing wall, with the second reinforced frame Third reinforced frame is welded based on bottom far from flashing wall side, installs wall mould for the second reinforced frame and third reinforced frame Plate pours C20 pea gravel concreten in the parapet and waterproofing protection sheaf space that wall form and flashing wall are formed, eventually forms Parapet and flashing and waterproof protective layer are integrated reinforced concrete structure, and the second reinforced frame specification is double two-way 8@of Φ 200, the third reinforced frame specification is single two-way 8@200 of Φ.
CN201811326489.6A 2018-11-08 2018-11-08 A kind of building roof parapet flashing structure and construction method Pending CN109281443A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811326489.6A CN109281443A (en) 2018-11-08 2018-11-08 A kind of building roof parapet flashing structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811326489.6A CN109281443A (en) 2018-11-08 2018-11-08 A kind of building roof parapet flashing structure and construction method

Publications (1)

Publication Number Publication Date
CN109281443A true CN109281443A (en) 2019-01-29

Family

ID=65175744

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811326489.6A Pending CN109281443A (en) 2018-11-08 2018-11-08 A kind of building roof parapet flashing structure and construction method

Country Status (1)

Country Link
CN (1) CN109281443A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113463854A (en) * 2021-07-12 2021-10-01 上海宝冶集团南京建筑有限公司 Waterproof construction method for joint of parapet root and roof concrete structure
CN113833272A (en) * 2021-09-23 2021-12-24 中国二十冶集团有限公司 Roof waterproof closing construction method
CN114135042A (en) * 2021-08-31 2022-03-04 上海宝冶集团有限公司 Arc integral type pouring method for roof waterproof construction
CN114482424A (en) * 2022-03-15 2022-05-13 南通新华建筑集团有限公司 Secondary pouring construction method for parapet wall with hidden rabbet

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100062393A (en) * 2008-12-02 2010-06-10 한본인더스트리 주식회사 Roof structure system for improvement quality of roof waterproofing
CN206174319U (en) * 2016-10-27 2017-05-17 奥意建筑工程设计有限公司 Head structure is received to flashing of parapet
CN106906962A (en) * 2017-03-14 2017-06-30 中冶建工集团有限公司 A kind of building roof parapet flashing construction technology
CN206545334U (en) * 2017-03-14 2017-10-10 中冶建工集团有限公司 A kind of building roof parapet flashing construction
CN209114751U (en) * 2018-11-08 2019-07-16 武汉建工集团股份有限公司 A kind of building roof parapet flashing structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100062393A (en) * 2008-12-02 2010-06-10 한본인더스트리 주식회사 Roof structure system for improvement quality of roof waterproofing
CN206174319U (en) * 2016-10-27 2017-05-17 奥意建筑工程设计有限公司 Head structure is received to flashing of parapet
CN106906962A (en) * 2017-03-14 2017-06-30 中冶建工集团有限公司 A kind of building roof parapet flashing construction technology
CN206545334U (en) * 2017-03-14 2017-10-10 中冶建工集团有限公司 A kind of building roof parapet flashing construction
CN209114751U (en) * 2018-11-08 2019-07-16 武汉建工集团股份有限公司 A kind of building roof parapet flashing structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113463854A (en) * 2021-07-12 2021-10-01 上海宝冶集团南京建筑有限公司 Waterproof construction method for joint of parapet root and roof concrete structure
CN114135042A (en) * 2021-08-31 2022-03-04 上海宝冶集团有限公司 Arc integral type pouring method for roof waterproof construction
CN113833272A (en) * 2021-09-23 2021-12-24 中国二十冶集团有限公司 Roof waterproof closing construction method
CN114482424A (en) * 2022-03-15 2022-05-13 南通新华建筑集团有限公司 Secondary pouring construction method for parapet wall with hidden rabbet

Similar Documents

Publication Publication Date Title
CN109281443A (en) A kind of building roof parapet flashing structure and construction method
CN106906962B (en) A kind of building roof parapet flashing construction technology
CN106677440A (en) Roofing parapet water-floating structure and construction method thereof
CN206616585U (en) One kind splits element precast formula pipe gallery
CN205557856U (en) Leakage structure is prevented at building expansion joint
CN107059917A (en) One kind splits element precast formula pipe gallery and its construction method
CN106120870A (en) The advanced enclosed construction of poured band of outer wall of basement and construction method
CN110905219A (en) Frame structure and filler wall interface combined anti-crack structure and construction method
CN112411901B (en) Waterproof and heat-insulating construction process for roof deformation joint
CN103410173A (en) Construction method for vertical post pouring belt plugging of underground structural outer wall
CN104405065A (en) Wallboard structure provided with non-dismantling formwork and construction method of wallboard structure
CN209114751U (en) A kind of building roof parapet flashing structure
CN109208830A (en) A kind of construction method and structure of parapet of roofing flashing
CN110080308A (en) A kind of novel late poured band structure and its construction method
CN107503450A (en) A kind of cast-in-place hollow armored concrete filling wall and its construction technology
CN205712204U (en) A kind of multiple waterstop and waterproof construction thereof
CN105780940B (en) building expansion joint anti-leakage structure
CN102912945A (en) Roof compound seepage-proofing steam exhausting hole detail treatment technology
CN104989100B (en) Construction method for crack prevention on connecting portion of masonry wall and concrete wall column
CN114482135A (en) Advanced water stop structure of basement exterior wall post-cast strip and construction method
CN106978809A (en) A kind of construction method of casing off concrete protective reserved steel bar
CN110158542A (en) The Lossless connection structure and construction method of cut-pff wall and nut cap concrete
CN108240045A (en) A kind of compound late poured band structure of outer wall precast slab and its construction method
CN103669746B (en) The construction method of inverted roof heat-insulation system
CN205954707U (en) Leading enclosed construction in basement outer wall post -cast strip

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination