CN109235914A - Structure construction protective device is got rid of after a kind of building - Google Patents

Structure construction protective device is got rid of after a kind of building Download PDF

Info

Publication number
CN109235914A
CN109235914A CN201811332402.6A CN201811332402A CN109235914A CN 109235914 A CN109235914 A CN 109235914A CN 201811332402 A CN201811332402 A CN 201811332402A CN 109235914 A CN109235914 A CN 109235914A
Authority
CN
China
Prior art keywords
column
protective plate
ground
protective
upper layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811332402.6A
Other languages
Chinese (zh)
Inventor
张迎松
张海鸣
张凯华
曹峰
李娟�
张厚起
杨继波
翟书青
樊兆鹏
王保同
王志鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG GOLD REAL ESTATE TOURISM GROUP Co Ltd
China Construction Eighth Engineering Division Co Ltd
Original Assignee
SHANDONG GOLD REAL ESTATE TOURISM GROUP Co Ltd
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG GOLD REAL ESTATE TOURISM GROUP Co Ltd, China Construction Eighth Engineering Division Co Ltd filed Critical SHANDONG GOLD REAL ESTATE TOURISM GROUP Co Ltd
Priority to CN201811332402.6A priority Critical patent/CN109235914A/en
Publication of CN109235914A publication Critical patent/CN109235914A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • E04G21/3204Safety or protective measures for persons during the construction of buildings against falling down
    • E04G21/3219Means supported by the building wall, e.g. security consoles

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Types And Forms Of Lifts (AREA)

Abstract

Structure construction protective device is got rid of after building of the invention, is made of column, protective plate, turnover panel and pulley, and the lower end of column is located in lower floor;It is characterized in that: offering the hole to be provided passed through for column on upper layer ground to be poured, protective plate is fixed on the column of upper layer above the ground, and pulley and turnover panel are provided on four sides of protective plate, and turnover panel is located at the top of pulley;It is connected between adjacent columns between lower floor and upper layer ground by dismountable connecting rod.Structure construction protective device is got rid of after building of the invention, it can effectively avoid top junk to pound to the staff on the ground of upper layer, it ensure that staff carries out the reinforcing bar binding on upper layer ground, concrete pouring operation in the secure state, it improves work efficiency, labor intensity is reduced, beneficial effect is significant.

Description

Structure construction protective device is got rid of after a kind of building
Technical field
The present invention relates to getting rid of structure construction protective device after a kind of building, more specifically, more particularly to one kind be suitable for Structure construction protective device is got rid of after the building that the escalator ground later period builds.
Background technique
During the construction of skyscraper, used tower crane device has by being fixed on building body There is self-service function of climbing;This tower crane with self-service function of climbing is usually fixed in escalator channel, this results in elevator Between the mattess needs of each layer delay and pour, the region that this later period builds is referred to as " getting rid of structure afterwards ".Such as electric During getting rid of structure building behind ground between ladder, upper part exists simultaneously main body and builds operation, this results in falling on tower crane Object, the worker for building escalator ground to lower section cause very big security risk.Usual way is not poured in 2 layers or 3 layers The top fixed protection plate on escalator ground is built, to realize the protective effect to lower section worker, but this protective plate is needed every 2 Layer or 3 layers need to build again primary, build not only time-consuming and laborious, but also will affect project progress, if one kind can be invented It can be with the protective device for building highly automated lifting, it will be resolved this problem.
Summary of the invention
The present invention in order to overcome the shortcomings of the above technical problems, provide it is a kind of suitable for the escalator ground later period build Structure construction protective device is got rid of after building.
Structure construction protective device is got rid of after building of the invention, is made of column, protective plate, turnover panel and pulley, column Quantity is 3 or 3 or more, and the lower end of column is located at concrete and has poured in the lower floor of completion;It is characterized by: to be poured The hole to be provided passed through for column is offered on the upper layer ground built, protective plate is fixed on the column of upper layer above the ground, is prevented Backplate is at horizontality, for preventing the staff on the ground of upper layer from being injured by a crashing object by top falling objects;On four sides of protective plate It is provided with the pulley being in contact in protective device uphill process with surrounding metope, is provided on four sides of protective plate pair The turnover panel that sealing between protective plate and wall is blocked, turnover panel are located at the top of pulley;Lower floor and upper layer ground it Between adjacent columns between be connected by dismountable connecting rod.
Structure construction protective device is got rid of after building of the invention, including the promotion being made of pedestal, lifting motor and lifting rope Device, pedestal are fixed on the wall above protective plate through anchor pole, and lifting motor is fixed on pedestal, and the upper end of lifting rope is wound in On the output shaft of lifting motor, the hanging ring mutually fixed with the lower end of lifting rope is fixed on the upper surface of protective plate.
Structure construction protective device is got rid of after building of the invention, is provided with above the protective plate on protective plate The slanting baffle that is protected of cleaning personnel, column passes through protective plate, and slanting baffle is fixed on the top of column;It is opened up on protective plate There is the channel above and below for personnel, lower section ladder is provided in channel;It is provided on protective plate convenient for being torn open to lifting device The top ladder of dress.
Structure construction protective device is got rid of after building of the invention, the lower end that column is placed in the lower floor carries out The backing plate of support, the periphery above the hole to be provided are provided with the rectangular gear mud cylinder that height is higher than steel reinforcement cage upper surface.
The application method of structure construction protective device is got rid of after building of the invention, which is characterized in that by following steps come It realizes:
A) ground pours, and under the protection of protective plate and turnover panel, can effectively avoid top falling objects and pounds to the work on the ground of upper layer Make personnel, by setting up supporting frame in lower floor, then places plank sheathing and banding steel cage on supporting frame, work Personnel pour it after steel reinforcement cage is bound;B) installs lifting device, and staff climbs top ladder the bottom of for Seat is installed on wall, then lifting motor is fixed on pedestal, finally by hanging on the lifting rope protective plate on lifting motor Ring is fixedly connected;C) dismantling connection bar disassembles the connecting rod between column after ground maintenance to be poured, with Just column can be gone up and down in hole to be provided;D) elevating protective device is mentioned entire protective device by starting lifting motor It rises, stops being promoted after the lower end of column passes through hole to be provided, then block hole to be provided and pad upper padding plate, and column is made to fall in backing plate On, and connected column using connecting rod;E) steel reinforcement cage is bound, the banding steel cage on upper one layer of ground, and is reserved The hole to be provided that column passes through pours to carry out this layer of ground concrete;So circulation, gets rid of the safe structure of structure after can be realized It builds.,
The beneficial effects of the present invention are: get rid of structure construction protective device after building of the invention, by column, protective plate, turnover panel and Pulley composition, the lower end of column are supported by lower floor, and the hole to be provided that column passes through is offered on the ground of upper layer, are protected Plate is fixed on the column of upper layer above the ground, by protective plate and its top turnover panel protective action, can effectively avoid Square junk, which is pounded, ensure that staff carries out the reinforcing bar on upper layer ground in the secure state and ties up to the staff on the ground of upper layer It pricks, concrete pouring operation.Entire protective device can be promoted under the drive of lifting device, to carry out next layer of ground The building operation in face improves work efficiency the drawbacks of avoiding in the past every 2 layers or 3 layers with regard to that need to set up a protective device, Labor intensity is reduced, beneficial effect is significant.
Detailed description of the invention
Fig. 1 is to get rid of the structural schematic diagram of structure construction protective device after building of the invention;
Fig. 2 is the cross-sectional view of Section A-A in Fig. 1;
Fig. 3 is the cross-sectional view of section B-B in Fig. 1;
Fig. 4 is the cross-sectional view in the section C-C in Fig. 1;
Fig. 5 is the structural schematic diagram when turnover panel in Fig. 4 is translated on protective plate.
In figure: 1 escalator channel, 2 walls, 3 from climbing tower crane, 4 lower floors, 5 upper layer ground, 6 columns, 7 protective plates, 8 connecting rods, 9 turnover panels, 10 pulleys, 11 struts, 12 hole to be provided, 13 lifting motors, 14 lifting ropes, 15 hanging rings, 16 pedestals, 17 anchor poles, 18 backing plates, 19 gear mud cylinders, 20 lower section ladders, 21 top ladders, 22 channels, 23 slanting baffles, 24 supporting frames, 25 plank sheathings, 26 Steel reinforcement cage, 27 elevator regions, 28 shafts, 29 support rods.
Specific embodiment
The invention will be further described with embodiment with reference to the accompanying drawing.
As shown in Figure 1, getting rid of the structural schematic diagram of structure construction protective device after giving building of the invention, built in high level In the process of construction built, tower crane device by be arranged in escalator channel 1, in order to not influence from climb tower crane 3 climb and It uses, this results in the passageway between elevator region 27 that the later period is needed to build, and the structure that this later period builds is referred to as " getting rid of afterwards " Structure.Since " getting rid of afterwards " structure is during construction, top also carries out main body and builds operation, in this cross-operation ring Under border, in order to protect the safety of lower work personnel, need to set up protective device.
The cross-sectional view in the section A-A, B-B, C-C in Fig. 1 is set forth in Fig. 2, Fig. 3 and Fig. 4, shown in build after get rid of structure Construction protection device is made of column 6, protective plate 7, connecting rod 8, turnover panel 9, pulley 10 and lifting device, and the quantity of column 6 is 3 Root or 3 or more use 4 root posts 6 in figure, the lower section of column 6 is placed in lower floor 4, in order to realize the firm of column 6 Support does not destroy lower floor 4 again, can place backing plate 18 in the lower section of column 6.4 are offered on upper layer ground 5 to be built Hole to be provided 12, column 6 are passed through from hole to be provided 12.In order to guarantee the stability of column 6, and do not influence vertical when protective device rises Column 6 is passed through from hole to be provided 12, is connected between the adjacent columns 6 of shown 5 lower section of upper layer ground by dismountable connecting rod 8 It connects.It is fixed with protective plate 7 on the column 6 of 5 top of upper layer ground, protective plate 7 is at horizontality, for realizing on upper layer ground The protective action of staff on 5 avoids top from falling object and pounds staff, is conducive to worker and carries out reinforcing bar binding, coagulation Soil pours operation.In order to guarantee the stability of protective plate 7, the support rod 29 reinforced to protective plate 7 is fixed on column 6.
During protective device rises, in order to avoid the surrounding of protective plate 7 and the metope of wall 2 collide or rub It wipes, is provided with pulley 10 on four sides of shown protective plate 7, pulley 10 is fixed on protective plate 7 through strut 11, in this way, During protective plate 7 rises, by sliding of the pulley on metope, frictional force is both reduced, in turn avoids breaking metope It is bad, it ensure that the safe and stable promotion of protective plate 7.It, will between the surrounding and wall of protective plate 7 due to being provided with pulley 10 There are certain gaps, in order to be sealed to gap, are provided with turnover panel 9 on four sides of protective plate 7, turnover panel 9 is through shaft 28 are set on the upper surface of protective plate 7, and turnover panel 9 is located at the top of pulley 10.When carrying out protective action, turnover panel 9 is turned to The position contacted with wall 2 is fallen in the gap between protective plate 7 and wall 2 to avoid object is fallen;When protective plate 7 rises When, turnover panel 9 is turned to the position being bonded with protective plate 7, to avoid the friction of turnover panel 9 and metope.
Protective device can carry out allocation and transportation promotion by tower crane, may also set up the lifting device of oneself.As shown in fig. 1, The lifting device of itself is made of lifting motor 13, pedestal 16, lifting rope 14, and pedestal 16 is fixed on 7 top of protective plate through anchor pole 17 Wall 2 on, lifting motor 13 is fixed on pedestal 16, and the upper end of lifting rope 14 is fixed on the output shaft of lifting motor 13, prevent The hanging ring 15 being connected with the lower end of lifting rope 14 is fixed on the upper surface of backplate 7.The quantity of lifting device is 2, right respectively The both ends of protective plate 7 are promoted, in use, protective device can be driven to rise by the remote controler of operation lifting device.For Convenient for dismounting to pedestal 16, be provided with top ladder 21 on protective plate 7, staff by by top ladder 21, It is convenient that pedestal 16 is dismounted.
In the long-term use process, some falling objects can be inevitably saved bit by bit on the upper surface of protective plate 7, in order to realize to falling The cleaning of junk offers the channel 22 being pierced by convenient for personnel on shown protective plate 7, can be arranged in channel 22 below ladder 20, so that personnel are risen on protective plate 7 by upper layer ground 5.In order to realize the protection of the worker of rubbish on cleaning protective plate 7, The top of shown protective plate 7 is additionally provided with slanting baffle 23, and the area of slanting baffle 23 is less than protective plate 7, when falling objects fall on oblique gear After on plate 23, and it can be slipped on the protective plate 7 of lower section.
The application method that structure construction protective device is got rid of after building of the invention is realized by following steps:
A) ground pours, and under the protection of protective plate (7) and turnover panel (9), can effectively avoid top falling objects and pounds to upper layer ground (5) staff on by erection supporting frame (24) on lower floor (4), then places plank sheathing on supporting frame (25) and banding steel cage (26), staff pour it after steel reinforcement cage (26) are bound;
B) installs lifting device, and staff climbs top ladder (21) and pedestal (16) is installed on wall (2), then will Lifting motor (13) is fixed on pedestal, finally that the hanging ring (15) on lifting rope (14) protective plate (7) on lifting motor is fixed Connection;
C) dismantling connection bar disassembles the connecting rod (8) between column, after ground maintenance to be poured to stand Column can the lifting in hole to be provided (12);
D) elevating protective device is promoted entire protective device by starting lifting motor (13), under column (6) End stops being promoted across hole to be provided (12) afterwards, then blocks hole to be provided and pads upper padding plate (18), and column is made to fall in backing plate (18) On, and connected column using connecting rod;
E) steel reinforcement cage is bound, the banding steel cage on upper one layer of ground, and reserves the hole to be provided (12) that column passes through, so as to This layer of ground concrete is carried out to pour;So circulation gets rid of the safety building of structure after can be realized.

Claims (5)

1. getting rid of structure construction protective device after a kind of building, it is made of column (6), protective plate (7), turnover panel (9) and pulley (10), The quantity of column is 3 or 3 or more, and the lower end of column is located at concrete and has poured in the lower floor (4) of completion;Its feature It is: offers the hole to be provided (12) passed through for column (6) on upper layer ground (5) to be poured, protective plate is fixed on upper layer On column above the ground, protective plate is at horizontality, for preventing the staff on the ground of upper layer from being pounded by top falling objects Wound;It is provided with the pulley (10) being in contact in protective device uphill process with surrounding metope on four sides of protective plate, prevents The turnover panel (9) blocked to the sealing between protective plate and wall is provided on four sides of backplate, turnover panel is located at pulley Top;It is connected between adjacent columns (6) between lower floor and upper layer ground by dismountable connecting rod (8).
2. getting rid of structure construction protective device after building according to claim 1, it is characterised in that: including by pedestal (16), The lifting device of lifting motor (13) and lifting rope (14) composition, pedestal are fixed on the wall above protective plate (7) through anchor pole (17) On, lifting motor is fixed on pedestal, and the upper end of lifting rope is wound on the output shaft of lifting motor, solid on the upper surface of protective plate Surely there is the hanging ring (15) mutually fixed with the lower end of lifting rope (14).
3. getting rid of structure construction protective device after building according to claim 1 or 2, it is characterised in that: the protective plate (7) Top be provided with to the slanting baffle (23) that is protected of cleaning personnel being located on protective plate, column (6) passes through protective plate, tiltedly Baffle is fixed on the top of column;The channel (22) above and below for personnel is offered on protective plate (7), channel is provided in (22) Lower section ladder (20);The top ladder (21) convenient for being dismounted to lifting device is provided on protective plate.
4. getting rid of structure construction protective device after building according to claim 1 or 2, it is characterised in that: the lower floor (4) backing plate (18) that the lower end of column (6) is supported is placed on, the periphery above the hole to be provided (12) is provided with height Degree is higher than the rectangular gear mud cylinder (19) of steel reinforcement cage (26) upper surface.
5. a kind of based on the application method for getting rid of structure construction protective device after building described in claim 1, which is characterized in that logical Following steps are crossed to realize:
A) ground pours, and under the protection of protective plate (7) and turnover panel (9), can effectively avoid top falling objects and pounds to upper layer ground (5) staff on by erection supporting frame (24) on lower floor (4), then places plank sheathing on supporting frame (25) and banding steel cage (26), staff pour it after steel reinforcement cage (26) are bound;
B) installs lifting device, and staff climbs top ladder (21) and pedestal (16) is installed on wall (2), then will Lifting motor (13) is fixed on pedestal, finally that the hanging ring (15) on lifting rope (14) protective plate (7) on lifting motor is fixed Connection;
C) dismantling connection bar disassembles the connecting rod (8) between column, after ground maintenance to be poured to stand Column can the lifting in hole to be provided (12);
D) elevating protective device is promoted entire protective device by starting lifting motor (13), under column (6) End stops being promoted across hole to be provided (12) afterwards, then blocks hole to be provided and pads upper padding plate (18), and column is made to fall in backing plate (18) On, and connected column using connecting rod;
E) steel reinforcement cage is bound, the banding steel cage on upper one layer of ground, and reserves the hole to be provided (12) that column passes through, so as to This layer of ground concrete is carried out to pour;So circulation gets rid of the safety building of structure after can be realized.
CN201811332402.6A 2018-11-09 2018-11-09 Structure construction protective device is got rid of after a kind of building Pending CN109235914A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811332402.6A CN109235914A (en) 2018-11-09 2018-11-09 Structure construction protective device is got rid of after a kind of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811332402.6A CN109235914A (en) 2018-11-09 2018-11-09 Structure construction protective device is got rid of after a kind of building

Publications (1)

Publication Number Publication Date
CN109235914A true CN109235914A (en) 2019-01-18

Family

ID=65077813

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811332402.6A Pending CN109235914A (en) 2018-11-09 2018-11-09 Structure construction protective device is got rid of after a kind of building

Country Status (1)

Country Link
CN (1) CN109235914A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203626278U (en) * 2013-12-21 2014-06-04 中国建筑第四工程局有限公司 Protective structure for construction of internal core tube of high-rise building
CN204112692U (en) * 2014-09-24 2015-01-21 中建一局集团建设发展有限公司 Simple and easy lift-type wellbore operations platform
CN205314595U (en) * 2015-10-16 2016-06-15 北京博大经开建设有限公司 Elevartor shaft protection frame
GB201615286D0 (en) * 2016-09-08 2016-10-26 Ischebeck Titan Ltd Climbing screen
CN207092583U (en) * 2017-08-22 2018-03-13 浙江宏超建设集团有限公司 A kind of lift protection canopy
CN209145319U (en) * 2018-11-09 2019-07-23 中国建筑第八工程局有限公司 Structure construction protective device is got rid of after a kind of building

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203626278U (en) * 2013-12-21 2014-06-04 中国建筑第四工程局有限公司 Protective structure for construction of internal core tube of high-rise building
CN204112692U (en) * 2014-09-24 2015-01-21 中建一局集团建设发展有限公司 Simple and easy lift-type wellbore operations platform
CN205314595U (en) * 2015-10-16 2016-06-15 北京博大经开建设有限公司 Elevartor shaft protection frame
GB201615286D0 (en) * 2016-09-08 2016-10-26 Ischebeck Titan Ltd Climbing screen
CN207092583U (en) * 2017-08-22 2018-03-13 浙江宏超建设集团有限公司 A kind of lift protection canopy
CN209145319U (en) * 2018-11-09 2019-07-23 中国建筑第八工程局有限公司 Structure construction protective device is got rid of after a kind of building

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
瞿义勇: "混凝土结构工程施工便携手册", 31 January 2006, 北京:中国计划出版社, pages: 174 *

Similar Documents

Publication Publication Date Title
CN103635643B (en) The construction method of nigh-level synthesis steel bar concrete cylindrical shell
CN108331336A (en) The integrated lifting steel plateform system and its construction method of floor synchronous construction
CN207048345U (en) Construction discharge platform device
CN209145319U (en) Structure construction protective device is got rid of after a kind of building
CN205955160U (en) Antiskid lattice formula elevartor shaft removes operation platform
CN202954552U (en) Steel tube concrete column high-altitude construction safety protection system
CN202451040U (en) Perpendicular high-altitude crawling ladder
CN106869479A (en) Bailey bracket sliding formwork system construction method
CN205654127U (en) Portable operation protective platform of assembly type structure stairwell
CN109235914A (en) Structure construction protective device is got rid of after a kind of building
CN216662305U (en) Super high-rise tower crane bottom attached hydraulic self-climbing hard protection platform
CN211714541U (en) Special handling frame for installing shear wall template in elevator shaft
CN216810895U (en) Elevator shaft operation platform
CN206886484U (en) One kind circulation building hoist system
CN202023149U (en) Hanging basket used in construction
CN105060124B (en) Intra-frame portal crane system and hoisting use method thereof
CN111392589B (en) Application method of attached lifting and transporting device for dismantling concrete support beam
CN210767838U (en) Large-section inclined column template construction structure for constructional engineering
CN202831591U (en) Special-shaped truss operation platform capable of hoisting to super high space
CN207003989U (en) External hanging type scaffold is climbed in one kind
CN215212258U (en) Safe and reliable elevator shaft protection operation platform convenient to layer-by-layer turnover use
CN216276806U (en) Novel integral lifting type operation platform for elevator shaft construction
CN110387824A (en) A kind of Sarasota creeping formwork becomes rail construction method in the air
CN212836618U (en) A integral operation platform in capital for prefabricated stand concrete placement
CN107806238A (en) Construction of lift well hydraulic climbing protection system and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination