CN108999570A - Tunnel drill carriage - Google Patents

Tunnel drill carriage Download PDF

Info

Publication number
CN108999570A
CN108999570A CN201811241363.9A CN201811241363A CN108999570A CN 108999570 A CN108999570 A CN 108999570A CN 201811241363 A CN201811241363 A CN 201811241363A CN 108999570 A CN108999570 A CN 108999570A
Authority
CN
China
Prior art keywords
tunnel
oil cylinder
drilling
cabinet
link block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811241363.9A
Other languages
Chinese (zh)
Other versions
CN108999570B (en
Inventor
岳中文
宋晨哲
王相元
岳小磊
董智文
赵伟
晋铭
赵旭峰
宋晨光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Tian Ju Heavy Industry Co ltd
China University of Mining and Technology Beijing CUMTB
Original Assignee
Shanxi Tian Ju Heavy Industry Co ltd
China University of Mining and Technology Beijing CUMTB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Tian Ju Heavy Industry Co ltd, China University of Mining and Technology Beijing CUMTB filed Critical Shanxi Tian Ju Heavy Industry Co ltd
Priority to CN201811241363.9A priority Critical patent/CN108999570B/en
Publication of CN108999570A publication Critical patent/CN108999570A/en
Application granted granted Critical
Publication of CN108999570B publication Critical patent/CN108999570B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/02Drilling rigs characterised by means for land transport with their own drive, e.g. skid mounting or wheel mounting
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B44/00Automatic control systems specially adapted for drilling operations, i.e. self-operating systems which function to carry out or modify a drilling operation without intervention of a human operator, e.g. computer-controlled drilling systems; Systems specially adapted for monitoring a plurality of drilling variables or conditions
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • E21D9/108Remote control specially adapted for machines for driving tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physics & Mathematics (AREA)
  • Fluid Mechanics (AREA)
  • Mechanical Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

The present invention relates to coal mining technology fields, and in particular to arrives a kind of tunnel drill carriage, the tunnel drill carriage includes suspension apparatus, for being set to the top in tunnel;It suspends cabinet in midair, the lower section of the suspension apparatus is set, and slide or roll with the suspension apparatus and connect;Unit drill boom device is arranged on the suspention cabinet, for implementing tunnel internal drilling operation;And steady machine support device, it is set on the suspention cabinet, the both ends of the steady machine support device are retractable structure, form support for the two sides side wall opposite with the tunnel.Through the above scheme, unit drill boom device is carried by being set to the suspension apparatus at the top of tunnel, and carry out construction operation in tunnel, improve the degree of automation of unit drill boom device operation, it is difficult to solve existing coal mine high inclination-angle roadway construction, and segment face tunnel is given another the right of way difficult problem, and the working efficiency of stone drifting is improved.

Description

Tunnel drill carriage
Technical field
The invention belongs to coal mining technology fields, and in particular to arrive a kind of tunnel drill carriage.
Background technique
Rock roadway in coal mine generally existing gradient in the country's is big at present, rock is hard, wears the features such as layer is more, and especially inclination angle is at 18-20 ° In stone drifting work progress, difficulty is quite big in construction organization and safety management, and speed of application is slow, and digging is caused to connect contradiction It is prominent.Currently, China's heavy grade rock gangway mechanized construction rawness can be used for reference, during heavy grade construction of rock gangway, manually Borehole hole difficulty of constructing increases, and personnel safety is difficult to ensure;The daily climb and fall walking of operating worker, large labor intensity;Material is auxiliary Transport is helped to face larger problem, these are all an important factor for restricting the speedy drivage of heavy grade rock gangway.
Excavation operation in rock roadway in coal mine, main contents include the operations such as drilling, charge explosion, discharge refuse, usual bench drilling Vehicle to evade blowing out falls cash needing to drop back after drilling is completed, after being generally arranged at desk-top drill carriage due to load mechanism and belt There is difficulty of giving another the right of way in the tunnel of segment face, influence operation process, reduce working efficiency in side.
It would therefore be highly desirable to provide a kind of technical solution that can efficiently realize heavy grade construction of rock gangway.
Summary of the invention
It is an object of the invention to solve bore operation low efficiency, labor intensity of workers in high inclination-angle tunnel in the prior art Large and small section of face tunnel is given another the right of way difficult problem, and a kind of tunnel mono-rail hoister drill carriage and its construction method are provided.
One aspect of the present invention provides a kind of tunnel mono-rail hoister drill carriage, comprising:
Suspension apparatus, for being set to the top in tunnel;
It suspends cabinet in midair, the lower section of the suspension apparatus is set, and slide or roll with the suspension apparatus and connect;
Unit drill boom device is arranged on the suspention cabinet, for implementing tunnel internal drilling operation;And
Steady machine support device, is set on the suspention cabinet, the both ends of the steady machine support device are scalable knot Structure forms support for the two sides side wall opposite with the tunnel.
Optionally, the suspention cabinet includes that box-like body and the cabinet being detachably connected with the box-like body are connect Block,
The cabinet link block is provided with the swinging block with cabinet link block horizontal swing connection, the unit drill boom Device is connect with the swinging block;
The steady machine support device and the cabinet link block are hinged.
Optionally, the steady machine support device includes support ontology,
The both ends of the support body length direction are respectively arranged with the second oil cylinder and third oil cylinder, second oil cylinder and The third oil cylinder is respectively used to support the top and bottom in the tunnel.
Optionally, the steady machine support device further includes the first oil cylinder,
First oil cylinder is articulated with the central region of the support ontology, the bottom in the tunnel is used to support, with right The support ontology provides forward support force.
It optionally, further include the 4th oil cylinder being connected between the cabinet link block and the steady machine support device, institute The 4th oil cylinder is stated for driving the relatively described suspention body pivot of the steady machine support device.
It optionally, further include the 5th oil cylinder being connected between first oil cylinder and the third oil cylinder, the described 5th Oil cylinder is used to adjust the angle between first oil cylinder and the third oil cylinder.
Optionally, the unit drill boom device includes up and down adjustment component, drilling machine link block and drilling assembly,
The drilling assembly is set on the drilling machine link block, for implementing tunnel internal drilling operation,
One end of the up and down adjustment component is connect with the drilling machine link block, the other end of the up and down adjustment component with The swinging block is hinged, for adjusting the height of the drilling assembly.
Optionally, the up and down adjustment component includes the 6th oil cylinder and the 7th oil cylinder,
The cabinet link block, the 6th oil cylinder, the drilling machine link block and the 7th oil cylinder are sequentially hinged, and are formed Four-bar mechanism.
Optionally, the drilling assembly includes drilling cramp and drilling machine propeller,
The drilling machine propeller is set on the drilling cramp, and can be mobile relative to the length direction of the drilling cramp, in institute It states on the length direction of drilling cramp, the drilling machine propeller and the drilling cramp are slidably connected;
Sliding rail is provided on the drilling machine link block, the sliding rail is parallel with the glide direction of the drilling cramp, The drilling cramp is slidably arranged on the sliding rail.
Optionally, the quantity of the unit drill boom device and the steady machine support device is two,
Two unit drill boom devices are respectively arranged at the two sides of the suspention cabinet,
Two steady machine support devices are respectively arranged at the two sides of the suspention cabinet.
Tunnel mono-rail hoister drill carriage provided by the invention has the advantages that
(1) present invention combines the advantages of suspension apparatus and unit drill boom device, can effectively adapt to current high inclination-angle lane Road, noise is small in operating process, and failure rate is low, is easy to repair and maintenance, and cheap, climbing capacity is strong, effectively increases driving Working efficiency;
(2) the adoptable controlling remote control system of tunnel mono-rail hoister drill carriage provided by the invention, can effectively reduce Personal injury rate saves human cost;
(3) tunnel mono-rail hoister drill carriage provided by the invention is set to the top in tunnel, back-and-forth motion side in actual operation Just, the compact difficult problem of giving another the right of way in space in effective solution segment face tunnel, and effectively prevent explosion and fall cash injuring by a crashing object The problem of equipment.
Detailed description of the invention
Fig. 1 is the schematic diagram of tunnel mono-rail hoister drill carriage of the invention;
Fig. 2 is the connection relationship diagram of cabinet link block in Fig. 1, steady machine support device and unit drill boom device;
Fig. 3 is the schematic diagram that tunnel mono-rail hoister drill carriage is constructed in high inclination-angle tunnel in Fig. 1.
Description of symbols
At the top of the tunnel 1-, 12- suspends orbit connection device in midair,
2- suspends track in midair,
3- pipe-hanging hook, 31- crane wheel, 32- suspend ear mount in midair,
4- suspention cabinet, the first ear mount of 41-, the second ear mount of 42-,
5- cabinet link block, 51- third ear mount, the 4th ear mount of 52-, 53- articulated shaft, the 5th ear mount of 54-, the 6th ear of 55- Seat,
The steady machine support device of 6-, the 7th ear mount of 61-, the 8th ear mount of 62-, the 4th oil cylinder of 63-, the second oil cylinder of 64-, 65- One support base, the 9th ear mount of 66-, the first oil cylinder of 67-, the tenth ear mount of 68-, the second support base of 69-, the 5th oil cylinder of 610-, 611- 11st ear mount, 612- third oil cylinder, 613- third support base,
7- unit drill boom device, the 6th oil cylinder of 71-, the 7th oil cylinder of 72-, the 12nd ear mount of 73-, the 13rd ear mount of 74-, 75- drilling machine link block, 76- are rotatablely connected axis, 77- sliding rail, 78- drilling cramp, 79- drilling machine propeller, 710- drilling rod.
Specific embodiment
Below in conjunction with attached drawing, detailed description of the preferred embodiments.It should be understood that this place is retouched The specific embodiment stated is merely to illustrate and explain the present invention, and is not intended to restrict the invention.
Overhead trolley is a kind of mobility strong, the speed of service is fast, loading capacity is big, safe and reliable travels on suspended single-track system The auxiliary conveying equipments of system are mainly used for coal mine fully-mechanized mining working installation, withdraw.Overhead trolley generallys use battery and mentions for it The features such as power, small with operational noise of system, failure rate is low, is easy to repair and maintenance, cheap, and climbing capacity is strong, can It realizes the large scale equipments such as whole Transporting hydraulic support, has in current domestic development of auxiliary transport in coal mines operation and play a very important role. Core of the invention thought is to carry out construction operation in tunnel using overhead trolley, to make overhead trolley that can not only use It in transport, while can also be used in construction operation in tunnel, so that the present invention provides a kind of tunnel mono-rail hoister drill carriage, inclined greatly with realizing Efficient stable bore operation in the tunnel of angle.
As shown in figure 3, shown content is the schematic diagram that tunnel mono-rail hoister drill carriage is constructed in high inclination-angle tunnel.It needs to illustrate , the tunnel inclination angle under this specific operation is 18 °, i.e., 1 and horizontal direction angle are 18 ° at the top of tunnel, wherein suspention track 2 erections parallel at the top of tunnel 1.It should be noted that only cannot be interpreted as the description of the specific degree in inclination angle to the present invention Limitation, that is to say, that it is an enforceable application environment that inclination angle, which is 18 ° of tunnel, the inclination angle can also for 10 °, 15 °, 20 °, 25 ° etc..(i.e. inclination angle is 0 °) is may naturally be used in the not tunnel at inclination angle.
- Fig. 2 refering to fig. 1, specifically, the tunnel mono-rail hoister drill carriage that present embodiment provides includes: suspension apparatus 2, suspention Device 2 is set to the top in tunnel;It suspends cabinet 4 in midair, the lower section of the suspension apparatus 2 is set, and sliding with the suspension apparatus 2 Dynamic or rolling connection;Unit drill boom device 7 is arranged on the suspention cabinet 4, for implementing tunnel internal drilling operation;And Steady machine support device 6, is set on the suspention cabinet 4, and the both ends of the steady machine support device 6 are retractable structure, are used Support is formed in the two sides side wall opposite with the tunnel.Steady machine support device 6 can be supported on any sustainable in tunnel On face, the supporting surface can be the top surface in tunnel, bottom surface, side etc., can provide the position of supporting point for other As the supporting surface of steady machine support device, those skilled in the art can be according to the suitable support of actual construction environment selection Face.Through the above scheme, unit drill boom device 7 is carried by being set to the suspention cabinet 4 at the top of tunnel, and apply in tunnel Work industry, improves the degree of automation of 7 operation of unit drill boom device, solves existing coal mine high inclination-angle roadway construction difficulty, And segment face tunnel is given another the right of way difficult problem, and the working efficiency of stone drifting is improved.
Wherein, suspension apparatus concretely track, 2 subsection setup of suspension apparatus, and be set up on 1 at the top of tunnel, it is adjacent Suspension apparatus 2 by suspend in midair orbit connection device 12 connect, suspension apparatus 2 can driving complete a distance after pacify paragraph by paragraph Dress, suspension apparatus 2 is parallel at the top of tunnel 1, while suspension apparatus 2 can be erected at the top of tunnel 1 left or right.
In conjunction with Fig. 1, there are two pipe-hanging hooks 3, pipe-hanging hook 3 to have crane wheel 31 and suspention for setting on suspension apparatus 2 Ear mount 32, pipe-hanging hook 3 on suspention track 2, are arranged by the two crane wheel 31 that can be rolled settings on pipe-hanging hook 3 There is suspention ear mount 32, be used to be connected with suspention cabinet 4, so that pipe-hanging hook 3 be made to drive suspention cabinet 4 one in the process of moving With mobile.Specifically, suspending in midair has the first ear mount 41 and the second ear mount 42 on cabinet 4, the first ear mount 41 and the second ear mount 42 are divided Yong Yu not be hinged with two suspention ear mounts 32, while suspending the locking and work of cabinet 4 in midair for convenience, it can also be in pipe-hanging hook 3 On be provided with locking system (not shown).Further, suspention cabinet 4 includes box-like body and fills for connecting steady machine support The cabinet link block 5 of 6 and unit drill boom device 7 is set, cabinet link block 5 is removably attachable on the box-like body, not It needs that steady machine support device 6 and unit drill boom device 7 can be removed when bore operation by cabinet link block 5.The cabinet The swinging block with the cabinet link block 5 horizontal swing connection, the unit drill boom device and the pendulum are provided on link block 5 Motion block connection;The steady machine support device and the cabinet link block are hinged.Specifically, leading between swinging block and cabinet link block The connection of articulated shaft 53 is crossed, to make unit drill boom device that can realize horizontal swing, this connection type is conducive to full side in tunnel The construction operation of position.
Further, the steady machine support device 6 and the suspention cabinet 4 are hinged, so that the steady machine support device 6 can It is rotated relative to the suspention cabinet 4.Steady machine support device 6 can pack up in non-operation process, in order to suspend cabinet 4 in midair in tunnel Interior walking, is opened in operation process, and steady machine support device 6 is supported on the supporting surface in tunnel in holding state.Such as Fig. 1 Shown, steady machine support device 6 is in collapsed state, as shown in figure 3, steady machine support device 6 is in holding state.
Referring to Fig.2, the steady machine support device includes support ontology and the first oil cylinder 67, the support ontology is along length side To both ends be respectively arranged with the second oil cylinder 64 and third oil cylinder 612, second oil cylinder 64 and the third oil cylinder 612 difference The top and bottom in the tunnel are used to support, first oil cylinder 67 is articulated with the central region of the support ontology, is used for The bottom in the tunnel is supported, to provide forward support force to the support ontology, the first oil cylinder 67 primarily serves auxiliary branch The effect of support can be used for offsetting the rear active force generated in the course of work.If support ontology has enough support forces certainly, or Recoil backward of person during bore operation is smaller, can also be not provided with the first oil cylinder 67.
Wherein, the tunnel mono-rail hoister drill carriage further include be connected to the suspention cabinet 4 and the steady machine support device 6 it Between the 4th oil cylinder 63, the 4th oil cylinder 6 rotates relative to the suspention cabinet 4 for controlling the steady machine support device 6;Tool Body, the 4th oil cylinder 6 is connected on cabinet link block 5.Cabinet link block 5 has third ear mount 51, steady machine support device 6 and the Three ear mounts 51 are hinged, and the 4th oil cylinder 63 stretches out, and rotate counterclockwise steady machine support device 6 (by the visual angle of such as Fig. 2), when turn Move at the top of the second oil cylinder 64 and tunnel 1 it is vertical when the 4th oil cylinder 63 stop, the second oil cylinder 64, third oil cylinder 612 be simultaneously at this time It stretches out, is respectively supported at the top and bottom in tunnel, complete preliminary support.For the ease of quickly adjusting the first oil cylinder 67, also 5th oil cylinder 610 can be set between first oil cylinder 67 and the third oil cylinder 612, and the 5th oil cylinder 610 is used for Control the angle between first oil cylinder 67 and the third oil cylinder 612.After the completion of preliminary support, the 5th oil cylinder 610 stretches out, Rotate counterclockwise the first oil cylinder 67, then the first oil cylinder 67 stretches out.
In order to realize more stable support, the first support base 65 can be set on the second oil cylinder 64, on third oil cylinder 612 Third support base 613 is set, the second support base 69 is set on the first oil cylinder 67, the first support base 65, the second support base 69 with And third oil cylinder 612 can be respectively articulated with the second oil cylinder 64, the first oil cylinder 67 and third oil cylinder 612.
In the above-mentioned scheme about steady machine support device, related articulated connection is settable to be used for hinged ear Seat, specifically as shown in Fig. 2, including the 4th ear mount 52 on cabinet link block 5, the 7th ear mount 61, the 9th ear on support ontology The 66, the 11st ear mount 611 of seat, the tenth ear mount 68 on the first oil cylinder 67.
For unit drill boom device 7, can be implemented using following examples mode, specifically, the unit drill boom dress It sets including up and down adjustment component, drilling machine link block 75 and drilling assembly, the drilling assembly is set to the drilling machine link block On 75, for implementing tunnel internal drilling operation, one end of the up and down adjustment component is connect with the drilling machine link block 75, described The other end of up and down adjustment component and the swinging block are hinged, for adjusting the height of the drilling assembly.
Wherein, the up and down adjustment component includes: the 6th oil cylinder 71 and the 7th oil cylinder 72, the cabinet link block 5, described 6th oil cylinder 71, the drilling machine link block 75 and the 7th oil cylinder 72 are sequentially hinged, and form four-bar mechanism.Pass through control the The flexible achievable four-bar mechanism of six oil cylinders 71 and the 7th oil cylinder 72 is swung up and down.The both ends of 6th oil cylinder 71 are respectively set There are the 5th ear mount 54 and the 12nd ear mount 73, the both ends of the 7th oil cylinder 72 are respectively arranged with the 13rd ear mount 74 and the 6th ear mount 55。
Further, the drilling assembly includes drilling cramp 78 and drilling machine propeller 79, and the drilling machine propeller 79 is set to institute It states on drilling cramp 78, and can be mobile relative to the length direction of the drilling cramp 78, on the length direction of the drilling cramp 78, the brill Machine propeller 79 and the drilling cramp 78 are slidably connected;Sliding rail, the sliding are provided on the drilling machine link block 75 Track is parallel with the glide direction of the drilling cramp 78, and the drilling cramp 78 is slidably arranged on the sliding rail.Drilling cramp 78 can be with It is set as including a plurality of slide bar disposed in parallel, wherein a slide bar and sliding rail 77 cooperate, another slide bar and drilling machine propeller 79 cooperations.Drilling machine propeller 79 has drilling rod 710, and the front end of drilling rod 710 passes through in the pilot hole of 78 front end of drilling cramp, to guarantee The stability of drilling.Drilling cramp 78 can slide back and forth along sliding rail 77 in the present embodiment, to carry out to direction of advance The fine tuning of one far and near distance after adjusting distance, pushes drilling rod 710 to work by the drilling machine propeller 79 being arranged on drilling cramp 78 Make face and carries out operation.
In the present embodiment, the quantity of the 7 unit drill boom device and the steady machine support device 6 is two, and two A unit drill boom device 7 is respectively arranged at the two sides of the suspention cabinet 4, and two steady machine support devices 6 are set respectively It is placed in the two sides of the suspention cabinet 4.
Tunnel mono-rail hoister drill carriage provided in present embodiment use complete machine hydraulic control system for each hydraulic cylinder and Hydraulic actuator provides power resources, uses electrical control gear to power for each electrical component, and controlling remote control is arranged System processed, operation or Unmanned operation so as to far distance control tunnel mono-rail hoister drill carriage, whole operation is in the process with distant Based on control.Present embodiment preferably uses complete machine hydraulic control system, electrical control gear and controlling remote control system knot It closes and uses, to realize the intelligence of operation in tunnel, mechanical automation.Certain those skilled in the art can also use other Mode controls the work of each execution unit on tunnel mono-rail hoister drill carriage.
Further, in conjunction with the description of above-mentioned tunnel mono-rail hoister drill carriage, present embodiment also provides a kind of tunnel mono-rail hoister brill The construction method of vehicle, successively the following steps are included:
S1, the control tunnel mono-rail hoister drill carriage to construction location;
S2, the support steady machine support device are in tunnel, so that the unit drill boom device is fixed in tunnel;
S3, implement operation in tunnel using the unit drill boom device.
Specifically, it specifically includes: after controlling the tunnel mono-rail hoister drill carriage to construction location, and determining in step sl The monorail crane drill carriage and working face distance are enough to complete work, pass through the fixed monorail crane drill carriage of locking system on suspension apparatus.
Specifically include in step s 2: the 4th oil cylinder 63 for being connected to suspention 4 two sides of cabinet, which tightens, makes steady machine support device 6 Support ontology perpendicular to tunnel surface, the second oil cylinder 64 and third oil cylinder 612 elongation being arranged on support ontology make steady machine Support device 6 is arranged, and each support base resists the upper and lower surface in tunnel in the form of plane-plane contact respectively;It is arranged in suspention cabinet Unit drill boom device 7 on 4 two sides link blocks can be rotated centered on articulated shaft 53, and pass through the 6th oil cylinder 71 and the 7th oil The telescopic action of cylinder 72 determines bore position, and the drilling machine propeller 79 being arranged on support arm pedestal can pass through rotation connection Axis 76 rotates, and can slide along sliding rail 77 and be finely adjusted to adjust the distance, and drilling machine can start after determining good position Bore operation.
It specifically includes in step s3: carrying out bore operation using drilling machine propeller 79.
It is described the prefered embodiments of the present invention in detail above in conjunction with attached drawing, still, the present invention is not limited thereto.At this It, can be with various simple variants of the technical solution of the present invention are made in the range of the technology design of invention.Including each particular technique Feature is combined in any suitable manner.In order to avoid unnecessary repetition, the present invention is to various combinations of possible ways No further explanation will be given.But it should also be regarded as the disclosure of the present invention for these simple variants and combination, belongs to the present invention Protection scope.

Claims (10)

1. a kind of tunnel drill carriage characterized by comprising
Suspension apparatus, for being set to the top in tunnel;
It suspends cabinet in midair, the lower section of the suspension apparatus is set, and slide or roll with the suspension apparatus and connect;
Unit drill boom device is arranged on the suspention cabinet, for implementing tunnel internal drilling operation;And
Steady machine support device, is set on the suspention cabinet, and the both ends of the steady machine support device are retractable structure, uses Support is formed in the two sides side wall opposite with the tunnel.
2. tunnel drill carriage according to claim 1, which is characterized in that the suspention cabinet include box-like body and with it is described The cabinet link block that box-like body is detachably connected;
The cabinet link block is provided with swinging block, and the swinging block and cabinet link block horizontal swing connect, the machine Group drill boom device is connect with the swinging block;
The steady machine support device and the box-like body are hinged.
3. tunnel drill carriage according to claim 2, which is characterized in that the steady machine support device includes support ontology;
The both ends of the support body length direction are respectively arranged with the second oil cylinder and third oil cylinder, second oil cylinder and described Third oil cylinder is respectively used to support the top and bottom in the tunnel.
4. tunnel drill carriage according to claim 3, which is characterized in that the steady machine support device further includes the first oil cylinder;
First oil cylinder is articulated with the central region of the support ontology, the bottom in the tunnel is used to support, to described Ontology is supported to provide forward support force.
5. tunnel drill carriage according to claim 4, which is characterized in that further include be connected to the cabinet link block with it is described The 4th oil cylinder between steady machine support device, the 4th oil cylinder is for driving the relatively described suspention case of the steady machine support device Body rotation.
6. tunnel drill carriage according to claim 4, which is characterized in that further include being connected to first oil cylinder and described the The 5th oil cylinder between three oil cylinders, the 5th oil cylinder are used to adjust the folder between first oil cylinder and the third oil cylinder Angle.
7. tunnel drill carriage according to claim 2, which is characterized in that the unit drill boom device includes up and down adjustment group Part, drilling machine link block and drilling assembly;
The drilling assembly is set on the drilling machine link block, for implementing tunnel internal drilling operation;
One end of the up and down adjustment component is connect with the drilling machine link block, the other end of the up and down adjustment component with it is described Swinging block is hinged, for adjusting the height of the drilling assembly.
8. tunnel drill carriage according to claim 7, which is characterized in that the up and down adjustment component includes the 6th oil cylinder and the Seven oil cylinders;
The cabinet link block, the 6th oil cylinder, the drilling machine link block and the 7th oil cylinder are sequentially hinged, and form four and connect Linkage.
9. tunnel drill carriage according to claim 7, which is characterized in that the drilling assembly includes that drilling cramp and drilling machine promote Device;
The drilling machine propeller is set on the drilling cramp, and can be mobile relative to the length direction of the drilling cramp, in the brill On the length direction of frame, the drilling machine propeller and the drilling cramp are slidably connected;
Sliding rail is provided on the drilling machine link block, the sliding rail is parallel with the glide direction of the drilling cramp, described Drilling cramp is slidably arranged on the sliding rail.
10. tunnel drill carriage according to claim 1, which is characterized in that the unit drill boom device and the steady machine support The quantity of device is two;
Two unit drill boom devices are respectively arranged at the two sides of the suspention cabinet;
Two steady machine support devices are respectively arranged at the two sides of the suspention cabinet.
CN201811241363.9A 2018-10-24 2018-10-24 Roadway drill carriage Active CN108999570B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811241363.9A CN108999570B (en) 2018-10-24 2018-10-24 Roadway drill carriage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811241363.9A CN108999570B (en) 2018-10-24 2018-10-24 Roadway drill carriage

Publications (2)

Publication Number Publication Date
CN108999570A true CN108999570A (en) 2018-12-14
CN108999570B CN108999570B (en) 2023-09-19

Family

ID=64590342

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811241363.9A Active CN108999570B (en) 2018-10-24 2018-10-24 Roadway drill carriage

Country Status (1)

Country Link
CN (1) CN108999570B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736861A (en) * 2019-01-16 2019-05-10 中国矿业大学(北京) A kind of monorail crane drill carriage and construction method
CN116816261A (en) * 2023-08-30 2023-09-29 济宁矿业集团有限公司 Underground roadway support drilling machine supporting device and application method thereof
CN117684873A (en) * 2024-02-04 2024-03-12 山东省地质矿产勘查开发局第七地质大队(山东省第七地质矿产勘查院) Fully-mechanized mining face drilling machine drilling stabilizing mechanism

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU463781A2 (en) * 1970-04-13 1975-03-15 Карагандинский научно-исследовательский угольный институт Burov column
DE3827865C1 (en) * 1988-08-17 1989-06-22 Armo Gesellschaft Fuer Bauelemente, Bau- Und Wohnbedarf Mbh, 4350 Recklinghausen, De Roof-bolt drilling apparatus movable on support sections forming running rails
CA2234745A1 (en) * 1997-04-11 1998-10-11 Robert John Kendall Underground mining drill rig
CN102900362A (en) * 2012-10-16 2013-01-30 廊坊景隆重工机械有限公司 Narrow-machine-body full-hydraulic bolt and anchor cable drill carriage for coal mine tunnel
CN202866651U (en) * 2012-10-16 2013-04-10 廊坊景隆重工机械有限公司 Narrow-body full hydraulic anchor bolt anchor cable drill carriage for coal mine tunnel
CN104213831A (en) * 2014-08-16 2014-12-17 中国煤炭科工集团太原研究院有限公司 Anchor rod drill carriage integrating coal mine digging, supporting and transportation parallel fast operation
CN104632241A (en) * 2014-12-28 2015-05-20 李宝 Track crane with excavation function
CN104948109A (en) * 2014-03-30 2015-09-30 写义明 Suspension type omni-directional anchor rod drill carriage
CN204716247U (en) * 2015-01-26 2015-10-21 南京石诚井巷装备有限责任公司 Suspension stone drifting machinery arm device
CN107269226A (en) * 2017-06-01 2017-10-20 凯盛重工有限公司 Monorail crane hydraulic drill rig
CN107524454A (en) * 2017-09-09 2017-12-29 左垒安 Tunnelling supporting robot, matched bracket and method for protecting support
CN108167006A (en) * 2018-01-19 2018-06-15 中国矿业大学(北京) A kind of rock roadway in coal mine brill anchor device and its construction method
CN208907347U (en) * 2018-10-24 2019-05-28 中国矿业大学(北京) Tunnel drill carriage

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU463781A2 (en) * 1970-04-13 1975-03-15 Карагандинский научно-исследовательский угольный институт Burov column
DE3827865C1 (en) * 1988-08-17 1989-06-22 Armo Gesellschaft Fuer Bauelemente, Bau- Und Wohnbedarf Mbh, 4350 Recklinghausen, De Roof-bolt drilling apparatus movable on support sections forming running rails
CA2234745A1 (en) * 1997-04-11 1998-10-11 Robert John Kendall Underground mining drill rig
CN102900362A (en) * 2012-10-16 2013-01-30 廊坊景隆重工机械有限公司 Narrow-machine-body full-hydraulic bolt and anchor cable drill carriage for coal mine tunnel
CN202866651U (en) * 2012-10-16 2013-04-10 廊坊景隆重工机械有限公司 Narrow-body full hydraulic anchor bolt anchor cable drill carriage for coal mine tunnel
CN104948109A (en) * 2014-03-30 2015-09-30 写义明 Suspension type omni-directional anchor rod drill carriage
CN104213831A (en) * 2014-08-16 2014-12-17 中国煤炭科工集团太原研究院有限公司 Anchor rod drill carriage integrating coal mine digging, supporting and transportation parallel fast operation
CN104632241A (en) * 2014-12-28 2015-05-20 李宝 Track crane with excavation function
CN204716247U (en) * 2015-01-26 2015-10-21 南京石诚井巷装备有限责任公司 Suspension stone drifting machinery arm device
CN107269226A (en) * 2017-06-01 2017-10-20 凯盛重工有限公司 Monorail crane hydraulic drill rig
CN107524454A (en) * 2017-09-09 2017-12-29 左垒安 Tunnelling supporting robot, matched bracket and method for protecting support
CN108167006A (en) * 2018-01-19 2018-06-15 中国矿业大学(北京) A kind of rock roadway in coal mine brill anchor device and its construction method
CN208907347U (en) * 2018-10-24 2019-05-28 中国矿业大学(北京) Tunnel drill carriage

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张俊利;: "煤矿岩巷掘进机械配套方案的探讨与实践", 煤炭与化工, no. 11 *
邵晋敏;: "炮采掘进面装运及支护装置设计", 煤矿机械, no. 06 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736861A (en) * 2019-01-16 2019-05-10 中国矿业大学(北京) A kind of monorail crane drill carriage and construction method
CN116816261A (en) * 2023-08-30 2023-09-29 济宁矿业集团有限公司 Underground roadway support drilling machine supporting device and application method thereof
CN116816261B (en) * 2023-08-30 2023-11-07 济宁矿业集团有限公司 Underground roadway support drilling machine supporting device and application method thereof
CN117684873A (en) * 2024-02-04 2024-03-12 山东省地质矿产勘查开发局第七地质大队(山东省第七地质矿产勘查院) Fully-mechanized mining face drilling machine drilling stabilizing mechanism
CN117684873B (en) * 2024-02-04 2024-05-03 山东省地质矿产勘查开发局第七地质大队(山东省第七地质矿产勘查院) Fully-mechanized mining face drilling machine drilling stabilizing mechanism

Also Published As

Publication number Publication date
CN108999570B (en) 2023-09-19

Similar Documents

Publication Publication Date Title
CN101858213B (en) Drilling, loading, transporting and anchoring integrated machine with dual platforms and four arms for coal roadway
CN106837392A (en) Tunnel gantry type multifunctional supporting chassis
CN108999570A (en) Tunnel drill carriage
CN109736798A (en) Dig six arm anchor driving machines of anchoring integral
CN204899935U (en) All -hydraulic entry driving machine of 6 -degree of freedom series -parallel connection formula
CN111663896A (en) Single-track-crane four-arm hydraulic support anchor rod and anchor cable drilling machine for coal mine
CN102278110A (en) Movable two-arm of lifting platform hanging wall anchor rod and anchor cable construction drill carriage
CN210598982U (en) Overturning working platform and tunneling equipment
CN107654246A (en) Tunnel the basket steel arch-shelf fitting machine of three arm three and steel arch frame construction method
CN201794610U (en) Drilling, loading, anchoring, supporting and transporting integrated machine in high outburst mine coal drift
CN105041329A (en) Six-freedom-degree series-parallel full-hydraulic tunneling machine
CN203271588U (en) Wheel type truck-mounted drilling rig
CN110905406B (en) Multifunctional impact type hydraulic drill carriage suitable for rock roadway working face construction
CN202055821U (en) Two-arm top slope anchor rod and anchor rope construction drill wagon with movable lifting platform
CN208907347U (en) Tunnel drill carriage
CN209838449U (en) Monorail crane drill carriage
CN101975077A (en) High-outburst coal mine coal roadway drilling-loading-bolting integrated machine
CN104632265B (en) Hanger rail type temporary support device
CN207739946U (en) A kind of operating mechanism of multi-functional arching drill jumbo
CN102874691A (en) Middle trough hoisting device for coal mine combined mining scraper conveyor
CN204827225U (en) Tunnel tunnelling equipment
CN201696041U (en) Double-platform four-arm drilling, loading, conveying and anchoring integrated machine for coal roadways
CN209800004U (en) Stope face crossheading circulation self-moving anti-impact advance support system
CN207739940U (en) A kind of multifunctional tunnel rock drilling arching all-in-one machine
CN209025604U (en) A kind of high inclination-angle roadway bolt drill carriage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant