CN108952768A CN201810999049.0A CN201810999049A CN108952768A CN 108952768 A CN108952768 A CN 108952768A CN 201810999049 A CN201810999049 A CN 201810999049A CN 108952768 A CN108952768 A CN 108952768A
Authority
CN
China
Prior art keywords
slip casting
paralell
secondary grouting
shield tunnel
wheel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810999049.0A
Other languages
Chinese (zh)
Inventor
李应川
刘长林
曹耀东
王宁
李木秋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN201810999049.0A priority Critical patent/CN108952768A/en
Publication of CN108952768A publication Critical patent/CN108952768A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms
    • E21D9/122Working or loading platforms

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to a kind of stage apparatus of Shield tunnel secondary grouting, belong to water conservancy and hydropower civil engineering technical field, including slip casting paralell, bottom traveling wheel, lateral support wheel, skirting board, coating steel pipe railing, water butt, ladder, the bottom rear end sides of slip casting paralell install a bottom traveling wheel respectively, ladder is fixedly installed on the bracket and slip casting paralell of one of bottom traveling wheel, water butt is mounted on the bottom of slip casting paralell, the lower front of slip casting paralell is equipped with the lateral support wheel being obliquely installed, slip casting paralell top rear is equipped with coating steel pipe railing and skirting board, skirting board is located at the lower part of coating steel pipe railing.The present invention improves the utilization of small space in hole, reduces the security risk of operation in hole;Reduce interference of other operations to secondary grouting operation in hole, improve construction efficiency, accelerate shield-tunneling construction progress, saves a large amount of duration;Reduce artificial, material investment, saves cost.

Description

A kind of stage apparatus of Shield tunnel secondary grouting
Technical field
The invention belongs to water conservancy and hydropower civil engineering technical fields, specifically, being related to a kind of Shield tunnel secondary grouting Stage apparatus.
Background technique
When Shield tunnel tunneling construction, the mobile assembled matter for generating faulting of slab ends and influencing section of jurisdiction occurs for section of jurisdiction position in order to prevent Amount, needs to synchronize slip casting (cement mortar).Because synchronous grouting is lacked along with the indispensable quality such as large-scale cavity It falls into, causes section of jurisdiction to generate load, increase tunnel security risk.In order to guarantee the whole stress of section of jurisdiction, need to section of jurisdiction It is timely carried out after wall secondary grouting (cement slurry), the cavity after the wall of section of jurisdiction is filled up.When carrying out secondary grouting construction, need to match The parking space of the construction materials such as equipment and water tank, waterglass, bagged cement such as standby blender, double-fluid grouting machine, in this way Space shared by a set of secondary grouting system is relatively large, and mating trailer is not provided with corresponding secondary grouting system after shield machine System, and narrow space in Shield tunnel, secondary grouting construction can only carry out on pedestrian passage.Often applied in progress secondary grouting Working hour, personnel's passage in hole will be unfavorable for the safety management of operation in hole, and easily cause channel by very big interference And its pollution of surrounding devices, destroy civilized construction image clean and tidy in hole.
Therefore, it is necessary to which a secondary grouting platform is arranged in mating trailer tail portion after shield machine, make secondary grouting operation It is separated with exit passageway in hole, meets the safety construction requirement in hole.
Summary of the invention
In order to solve the problems, such as background technique, the present invention provides a kind of convenience, practical Shield tunnel are secondary The stage apparatus of slip casting separates secondary grouting operation with exit passageway in hole, reduces to other works carried out in Shield tunnel The interference of industry, guarantees the clean and tidy of operating environment, and energy save the cost generates preferable social and economic benefit.
To achieve the above object, the present invention is achieved through the following technical solutions:
The stage apparatus of the Shield tunnel secondary grouting include slip casting paralell 1, bottom traveling wheel 2, lateral support wheel 3, Coating steel pipe railing 5, water butt 6, ladder 7, the bottom rear end sides of the slip casting paralell 1 are separately installed with a bottom Traveling wheel 2 is fixedly installed with ladder 7 on the bracket and slip casting paralell 1 of one of bottom traveling wheel 2, and water butt 6 is mounted on The bottom of slip casting paralell 1, the lower front of slip casting paralell 1 are equipped with the lateral support wheel 3 being obliquely installed, and slip casting is flat 1 top rear of rack is equipped with coating steel pipe railing 5.
Further, the lower part of the coating steel pipe railing 5 is provided with skirting board 4, and it is flat that skirting board 4 is also secured to slip casting On rack 1.
Preferably, H profile steel welding production of the slip casting paralell 1 using HW150 × 150mm.
Preferably, two bottom traveling wheels 2 are triangularly arranged with a lateral support wheel 3, and tilting moment is 0。
Preferably, the bottom traveling wheel 2 is the concave steel wheel that diameter is 350mm.
Preferably, the lateral support wheel 3 is the rigid plastics wheel that diameter is 150mm.
Beneficial effects of the present invention:
Use of the invention improves the utilization of small space in hole, reduces the security risk of operation in hole;Reduce in hole Interference of other operations to secondary grouting operation, improves construction efficiency, accelerates shield-tunneling construction progress, saves a large amount of work Phase;Eliminate the later period construct exclusively for secondary grouting and the operation platform set up, reduce artificial, material investment, saved at This.
Detailed description of the invention
Fig. 1 is main view of the invention;
Fig. 2 is left view of the invention;
Fig. 3 is the schematic diagram of slip casting paralell of the present invention.
In figure, 1- slip casting paralell, the bottom 2- traveling wheel, 3- lateral support wheel, 4- skirting board, 5- coating steel pipe railing, 6- water butt, 7- ladder.
Specific embodiment
Below in conjunction with the embodiment of the present invention and attached drawing, technical solution in the embodiment of the present invention carries out clear, complete Ground description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Based on this Embodiment in invention, every other reality obtained by those of ordinary skill in the art without making creative efforts Example is applied, shall fall within the protection scope of the present invention.
As shown in Figure 1-3, the stage apparatus of the Shield tunnel secondary grouting includes slip casting paralell 1, bottom walking 2, lateral support wheel 3, skirting board 4, coating steel pipe railing 5, water butt 6, ladder 7 are taken turns, behind the bottom of the slip casting paralell 1 End two sides are separately installed with a bottom traveling wheel 2, fix on the bracket and slip casting paralell 1 of one of bottom traveling wheel 2 Ladder 7 is installed, water butt 6 is mounted on the bottom of slip casting paralell 1, and the diameter of water butt 6 is 600mm, and being equipped with water butt 6 has Effect avoids the in disorder phenomenon of work surface pipeline.The lower front of slip casting paralell 1 is equipped with the lateral branch being obliquely installed Support wheel 3, two bottom traveling wheels 2 are triangularly arranged with a lateral support wheel 3, and tilting moment is 0, is greatly improved The safety of operating environment.1 top rear of slip casting paralell is equipped with coating steel pipe railing 5 and skirting board 4, and skirting board 4 In the lower part of coating steel pipe railing 5, during slip casting, place can be kicked by the cement slurry of 4 sole of skirting board.
The slip casting paralell 1 uses the H profile steel welding production of HW150 × 150mm.
The bottom traveling wheel 2 is the concave steel wheel that diameter is 350mm.
The lateral support wheel 3 is the rigid plastics wheel that diameter is 150mm.
Installation method of the invention is as follows:
1) production of slip casting paralell 1 processing: slip casting paralell 1 uses the H profile steel welding production of HW150 × 150mm, first to each group Cutting stock is carried out at component, then the welding of each H profile steel component is integral, finally checkered steel plate is welded on paralell 1.
2) bottom traveling wheel 2 is processed: the concave that the bottom traveling wheel 2 on secondary grouting paralell 1 is 350mm using diameter The steel plate of steel wheel, the H profile steel of HW150 × 150mm and 20mm thickness makes, and 20mm thick steel plate is cut into having a size of 180mm × 390mm Rectangle (4), H profile steel Cutting Length 520mm(2 part), recombinant weld integral (2).
3) lateral support wheel 3 is processed: the rigid plastics wheel and 20mm thick steel plate that lateral support wheel 3 is 150mm using diameter Production, it is respectively 390mm × 100mm that 20mm thick steel plate, which is cut into size, and each one, the rectangle of 230mm × 100mm, and bottom The upper bottom 120mm of 230mm, the right-angled trapezium of high 80mm one, recombinant welding are integral.
4) each component of machine-shaping is transported to the tail portion of mating trailer after shield machine using battery truck in hole, uses trailer Sunpender combination chain block on the tailstock of tail portion is lifted, installation site as needed, temporarily by 1 spot welding of slip casting paralell It is temporarily fixed in the tail portion of trailer, then carries out the two bottom traveling wheels 2 and a lateral support wheel 3 of 1 bottom of slip casting paralell Welding unclamp again tailstock after bottom traveling wheel 2 and lateral support wheel 3 are welded according to track and section of jurisdiction intrados position Sunpender and chain block, finally install 1 bottom of slip casting paralell water butt 6 and welding 1 upper height of slip casting paralell be The coating steel pipe railing 5 of 1.2m high and the small ladder 7 of tail portion.
The working principle of the invention:
Orbit Matching in two bottom traveling wheels 2 and tunnel, lateral support wheel 3 is contacted with the side wall of tunnel, with two bottoms Traveling wheel 2 forms triangle load-carrying members, guarantees the stability of entire stage apparatus, to also ensure that slip casting paralell 1 guarantees In the state of relative level, at work, staff can carry out secondary grouting work on slip casting paralell 1.
It is usually small in subway tunnel and the lesser tunnel of some sections, the more spaces of shield inboard installation.Secondary grouting is usual Using single fluid grouting machine or double-fluid grouting machine, while secondary grouting need to usually carry out mixing, i.e. secondary grouting inside shield machine Equipment, material need biggish slip casting space to realize, generate contradiction with the small space of shield machine.For this purpose, the present invention is main It connect to form individual slip casting trolley with shield machine by rear mating carriage track, it is mobile simultaneously during shield machine driving Realize that secondary grouting follows up in time.
Use of the invention improves the utilization of small space in hole, reduces the security risk of operation in hole;Reduce Interference of other operations to secondary grouting operation, improves construction efficiency in hole, accelerates shield-tunneling construction progress, saves a large amount of Duration;Eliminate the later period construct exclusively for secondary grouting and the operation platform set up, reduce artificial, material investment, save Cost.
The invention enables secondary grouting working spaces and exit passageway in hole to separate, and makes full use of narrow in Shield tunnel Space reduces interference of other operations in hole to secondary grouting operation;Operation in a safe and reliable hole is provided simultaneously Environment ensure that the safety construction image in Shield tunnel;Mating trailer after shield machine can be followed to go ahead together, no The reuse that mating carriage track, sleeper are removed after influence shield machine.
Finally, it is stated that the above examples are only used to illustrate the technical scheme of the present invention and are not limiting, although by upper It states preferred embodiment the present invention is described in detail, however, those skilled in the art should understand that, can be in form Various changes are made to it in upper and details, without departing from claims of the present invention limited range.

Claims (7)

1. a kind of stage apparatus of Shield tunnel secondary grouting, it is characterised in that: the platform of the Shield tunnel secondary grouting Device include slip casting paralell (1), bottom traveling wheel (2), lateral support wheel (3), coating steel pipe railing (5), water butt (6), Ladder (7), the bottom rear end sides of the slip casting paralell (1) are separately installed with a bottom traveling wheel (2), one of them It is fixedly installed with ladder (7) on the bracket and slip casting paralell (1) of bottom traveling wheel (2), water butt (6) is mounted on slip casting platform The bottom of frame (1), the lower front of slip casting paralell (1) are equipped with the lateral support wheel (3) being obliquely installed, slip casting platform Frame (1) top rear is equipped with coating steel pipe railing (5).
2. a kind of stage apparatus of Shield tunnel secondary grouting according to claim 1, it is characterised in that: described is zinc-plated The lower part of steel pipe railing (5) is provided with skirting board (4), and skirting board (4) is also secured on slip casting paralell (1).
3. a kind of stage apparatus of Shield tunnel secondary grouting according to claim 1, it is characterised in that: the slip casting Paralell (1) uses the H profile steel welding production of HW150 × 150mm.
4. a kind of stage apparatus of Shield tunnel secondary grouting according to claim 1, it is characterised in that: two bottom lines It walks wheel (2) to be triangularly arranged with a lateral support wheel (3), and tilting moment is 0.
5. a kind of stage apparatus of Shield tunnel secondary grouting according to claim 1 or 4, it is characterised in that: described Bottom traveling wheel (2) is the concave steel wheel that diameter is 350mm.
6. a kind of stage apparatus of Shield tunnel secondary grouting according to claim 1 or 4, it is characterised in that: described Lateral support wheel (3) is the rigid plastics wheel that diameter is 150mm.
7. a kind of stage apparatus of Shield tunnel secondary grouting according to claim 1 or 2, it is characterised in that: described The height of coating steel pipe railing (5) is 1.2m.
CN201810999049.0A 2018-08-30 2018-08-30 A kind of stage apparatus of Shield tunnel secondary grouting Pending CN108952768A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810999049.0A CN108952768A (en) 2018-08-30 2018-08-30 A kind of stage apparatus of Shield tunnel secondary grouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810999049.0A CN108952768A (en) 2018-08-30 2018-08-30 A kind of stage apparatus of Shield tunnel secondary grouting

Publications (1)

Publication Number Publication Date
CN108952768A true CN108952768A (en) 2018-12-07

Family

ID=64473660

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810999049.0A Pending CN108952768A (en) 2018-08-30 2018-08-30 A kind of stage apparatus of Shield tunnel secondary grouting

Country Status (1)

Country Link
CN (1) CN108952768A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110030003A (en) * 2019-04-03 2019-07-19 中船第九设计研究院工程有限公司 A kind of the anti-collapse excavating device and its technique of tunnel construction
CN110566233A (en) * 2019-09-20 2019-12-13 成龙建设集团有限公司 method for duct piece wall post-grouting in shield tunnel construction of full-section hard rock stratum
CN113585811A (en) * 2021-08-19 2021-11-02 中铁十四局集团大盾构工程有限公司 Assembled movable crawling ladder for large-diameter shield tunnel

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11173072A (en) * 1997-12-11 1999-06-29 Ohbayashi Corp Chemical grouting method and chemical grouting equipment
CN101864969A (en) * 2010-03-19 2010-10-20 中铁十四局集团有限公司 Segment caulking and hand hole blocking trolley for large-diameter shield tunnel
CN204877488U (en) * 2015-07-09 2015-12-16 中铁十二局集团有限公司 A bracket device that can walk that is used for tunnel no. 2 lining side wall operations
CN205477636U (en) * 2016-02-25 2016-08-17 天津智导科技有限公司 Underground railway track moving platform
CN205591817U (en) * 2016-05-06 2016-09-21 中国铁建电气化局集团第二工程有限公司 Railway tunnel lateral wall construction tower wagon
CN207470205U (en) * 2017-11-22 2018-06-08 中国水利水电第八工程局有限公司 A kind of tunnel concrete maintenance repairing trolley

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11173072A (en) * 1997-12-11 1999-06-29 Ohbayashi Corp Chemical grouting method and chemical grouting equipment
CN101864969A (en) * 2010-03-19 2010-10-20 中铁十四局集团有限公司 Segment caulking and hand hole blocking trolley for large-diameter shield tunnel
CN204877488U (en) * 2015-07-09 2015-12-16 中铁十二局集团有限公司 A bracket device that can walk that is used for tunnel no. 2 lining side wall operations
CN205477636U (en) * 2016-02-25 2016-08-17 天津智导科技有限公司 Underground railway track moving platform
CN205591817U (en) * 2016-05-06 2016-09-21 中国铁建电气化局集团第二工程有限公司 Railway tunnel lateral wall construction tower wagon
CN207470205U (en) * 2017-11-22 2018-06-08 中国水利水电第八工程局有限公司 A kind of tunnel concrete maintenance repairing trolley

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110030003A (en) * 2019-04-03 2019-07-19 中船第九设计研究院工程有限公司 A kind of the anti-collapse excavating device and its technique of tunnel construction
CN110030003B (en) * 2019-04-03 2021-05-07 中船第九设计研究院工程有限公司 Anti-collapse excavation device for tunnel construction and process thereof
CN110566233A (en) * 2019-09-20 2019-12-13 成龙建设集团有限公司 method for duct piece wall post-grouting in shield tunnel construction of full-section hard rock stratum
CN113585811A (en) * 2021-08-19 2021-11-02 中铁十四局集团大盾构工程有限公司 Assembled movable crawling ladder for large-diameter shield tunnel

Similar Documents

Publication Publication Date Title
CN201246169Y (en) Tunnel development synchronous lining formwork trolley
CN102345461B (en) Subsequent project and shield driving parallel construction method for long-distance railway tunnel
CN109538238A (en) A kind of tunnel arch prefabricated pipe section constructing device and control method
CN108952768A (en) A kind of stage apparatus of Shield tunnel secondary grouting
CN103032073B (en) Urban subway mudstone stratum connected aisle and shield tunneling parallel construction method
CN104564102B (en) A kind of tunnel lining concrete grouting device
CN100482891C (en) Method for building railway bridge and simple support T beam bridge
CN103277110A (en) Construction method of overlapped shield tunnel
CN105952482A (en) Self-propelled tunnel invert lining trolley
CN101831888B (en) 1200 tonner water conservancy aqueduct transportation and erection equipment
CN203685216U (en) Composite grouting system for shield passing-through section
CN102061926A (en) TBM tunneling and secondary lining synchronous construction method at mucking of continuous belt conveyor and trolley
CN202659247U (en) Back templates and combined steel die for tunnel inverted arch construction
CN104018426A (en) Steel truss installation method
CN104180658B (en) A kind of installation method of sintering machine dust pelletizing system
CN203499697U (en) Trolley used for concrete construction of various cross sections through mining method
CN204662270U (en) A kind of case girder transferring system
CN105736012A (en) Concrete grouting device for tunnel lining
CN208184749U (en) A kind of shield well side wall haunch every template node structure
CN207538841U (en) A kind of hydraulic tunnel inverted arch cambered surface slip form construction device
CN207131969U (en) The rail-mounted concrete pump pipe carrier of solid concrete roabed cast-in-place construction in subway tunnel
CN204267046U (en) A kind of tunnel lining concrete grouting device
CN105927247A (en) Large section full-automatic mechanical numeric control bogie and construction method thereof
CN208718683U (en) A kind of stage apparatus of Shield tunnel secondary grouting
CN206816265U (en) A kind of air channel arch combined retaining structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181207