CN104180658B - A kind of installation method of sintering machine dust pelletizing system - Google Patents

A kind of installation method of sintering machine dust pelletizing system Download PDF

Info

Publication number
CN104180658B
CN104180658B CN201410389647.8A CN201410389647A CN104180658B CN 104180658 B CN104180658 B CN 104180658B CN 201410389647 A CN201410389647 A CN 201410389647A CN 104180658 B CN104180658 B CN 104180658B
Authority
CN
China
Prior art keywords
type electric
car
factory building
absolute altitude
cleaning shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410389647.8A
Other languages
Chinese (zh)
Other versions
CN104180658A (en
Inventor
王彩东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Tianjin Corp Ltd
Original Assignee
Tianjin MCC20 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin MCC20 Construction Co Ltd filed Critical Tianjin MCC20 Construction Co Ltd
Priority to CN201410389647.8A priority Critical patent/CN104180658B/en
Publication of CN104180658A publication Critical patent/CN104180658A/en
Application granted granted Critical
Publication of CN104180658B publication Critical patent/CN104180658B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)

Abstract

The invention discloses a kind of installation method of sintering machine dust pelletizing system, the method comprises, and " on the Cement Concrete beam of factory building absolute altitude a, surveying setting-out is to determine cleaning shaft center line locus and absolute altitude b, the steel platform that upper surface is absolute altitude a is set up in factory building head side, lay and be used for planer-type electric hang car and extend to the temporary track of steel platform and make planer-type electric hang car, lay and be used for bracket type electric motor car and the temporary track extended to outside factory building, each group joint of handling pipe laying support and cleaning shaft, the Cement Concrete beam of factory building absolute altitude c is installed each little lattice funnel, complete the laying and welding of walking on stage cleaning shaft inside, repack planer-type electric hang car into bracket type electric motor car, handling also installs each flue-dust retainer " etc. step.Advantage of the present invention is: the many defects overcoming prior art, shorten installation period, reduce mounting cost; Ensure that higher installation quality, make installation process have reliable security.

Description

A kind of installation method of sintering machine dust pelletizing system
Technical field
The present invention relates to a kind of installation method of sintering machine, in particular, the present invention relates to a kind of installation method of sintering machine dust pelletizing system.
Background technology
Generally, sintering machine is mounted in multi storied factory building, and installs by order from bottom to top.In the whole process of installing sintering machine, the operation of most critical is the installation of dust pelletizing system.
Fig. 1, Fig. 2 respectively illustrate the situation of sintering machine dust pelletizing system component units, this component units comprises and is positioned at sintering machine factory building and the flue-dust retainer 4 being arranged on little lattice funnel 2 on upper strata Cement Concrete beam 6, being arranged on the cleaning shaft 3 on middle level Cement Concrete beam 6 and being arranged on below described cleaning shaft 3 by support of pipelines 5, and the conventional installation methods of this component units comprises the following steps:
(1) surveying setting-out on the Cement Concrete beam 6 of factory building absolute altitude a, determines center line locus and the center line absolute altitude b of cleaning shaft 3;
(2) set up steel platform in factory building head 1 side, the upper surface absolute altitude a of described steel platform is the lower surface absolute altitude of interim slideway (being generally H profile steel);
(3) make a temporary trolley being suitable for interim slideway, and the power that a hoist engine slides as dilatory temporary trolley on described interim slideway is installed in factory building tail side;
(4) temporary trolley is moved to steel platform, with 25t crane, the component units of dust pelletizing system is placed on temporary trolley sequentially, drag temporary trolley to corresponding installation site with hoist engine;
(5) with temporary trolley, little lattice funnel 2 is transported to relevant position, then promoted with driving a vehicle in jack or factory building, and be temporarily fixed at the height that can not affect cleaning shaft 3 and transport with temporary support;
(6) transport to relevant position with the group joint of temporary trolley by composition cleaning shaft 3 and brought up to more than the setting height(from bottom) of support of pipelines 5 with jack, then, support of pipelines 5 under first this group being saved installs, then is fixed on mounted support of pipelines 5 by this group joint;
(7) step (5) and step (6) is repeated, until each group joint of each little lattice funnel 2, support of pipelines 5 and composition cleaning shaft 3 installs;
(8) with wooden handcart the flue-dust retainer 4 be arranged on below cleaning shaft 3 is transported to the certain position outside factory building, the relevant position below described cleaning shaft 3 is dragged it to again with tractor, then moved to erectility with 4 jacks and be pulled to vertically upward and connected with described cleaning shaft 3, welding in place;
(9) after described flue-dust retainer 4 installs, cut and peel off the arc of itself and cleaning shaft 3 joining part, and this block arc is transported after pipe interior is cut into small pieces;
(10) laying and welding of walking on stage cleaning shaft 3 inside is completed.
In the installation method of above-mentioned prior art:
The installation of each group joint of described cleaning shaft 3 needs time of 3 days, and all group joint installation in position needs 1 first quarter moon to time of 2 months.
The installation of described flue-dust retainer 4 each need time of 1 day, whole flue-dust retainer 4 installation in position needs the time of 20-30.
After each flue-dust retainer 4 installs, itself and described cleaning shaft 3 connecting position cut and peel off arc must be cut into small pieces from the inside of described cleaning shaft 3 again after just can transport, substantially become the waste product waste material that can not again utilize.
If install relatively large cleaning shaft 3, often need 25T crane about more than 30 machine-team, artificial work day 400-600, auxiliary material expense about 10,000 yuan, total installed cost (TIC) about 200,000 yuan, and the installation of flue-dust retainer 4 also needs 25T crane more than 20 machine-team, artificial work day 200-300, auxiliary material expense about 5000 yuan, total installed cost (TIC) about 100,000 yuan, two expenses amount to about 300,000 yuan.
The installation of described support of pipelines 5, can only relevant position be transported at each group joint of described cleaning shaft 3 and just can carry out after proper height of slinging with jack, and due to limited space, be difficult to use its alignment error of instrument testing after mounting again, be difficult to ensure installation quality.
The unsettled lifting of described cleaning shaft 3 and the installation of described support of pipelines and flue-dust retainer 4, all operate with multiple jack, and unavoidable effort is time-consuming; The installation of described support of pipelines 5 is then under unsettled cleaning shaft 3, there is inevitable potential safety hazard.
In sum, really there is many deficiencies in the conventional installation methods of described sintering machine dust pelletizing system:
(1) set-up time is long; (2) mounting cost is high; (3) installation quality not easily ensures; (4) hidden danger is installed more.
Summary of the invention
Object of the present invention is exactly the defect overcoming prior art, and provides a kind of for this reason and shorten the set-up time, reduces mounting cost, ensure installation quality and have the installation method of the sintering machine dust pelletizing system of security.
The installation method of sintering machine dust pelletizing system of the present invention, comprises the following steps:
(1) surveying setting-out on the Cement Concrete beam of factory building absolute altitude a, determines locus and the center line absolute altitude b of cleaning shaft center line;
(2) set up in factory building head side the steel platform that its upper surface is absolute altitude a;
(3) lay on the Cement Concrete beam of factory building absolute altitude a two be for planer-type electric hang car and highly h, length extends to the temporary track of aforementioned steel platform;
(4) make planer-type electric hang car and be placed on the temporary track of upper surface absolute altitude a+h, then checking its bearing capacity;
(5) on the Cement Concrete beam of factory building absolute altitude 0, two are laid for bracket type electric motor car and highly for h, length extend to the temporary track of factory building certain distance outward;
(6) with 25t truck crane, the component units of dust pelletizing system is placed on steel platform sequentially, then uses planer-type electric hang car by its handling to corresponding installation site;
(7) to use planer-type electric hang car that support of pipelines handling is completed installation to relevant position, each group of handling formation cleaning shaft saves and ensures that the surrounding of centerline direction in its counterpart process all possesses enough adjustment surpluses again, then it to be installed to successively on support of pipelines and to complete butt welding, centerline deviation after allowing it to install is ± 5mm, and absolute altitude deviation is ± 2mm;
(8) on the left of factory building or right side use truck crane to be winched to the Cement Concrete beam of factory building absolute altitude c by little lattice funnel, re-use factory building driving and each little lattice funnel be lifted into the relevant position of the cleaning shaft top Cement Concrete beam having completed butt welding successively and fixed;
(9) repack planer-type electric hang car into bracket type electric motor car and be placed on the temporary track of upper surface absolute altitude 0+h;
(10) the inside laying of walking on stage of described cleaning shaft and welding is completed and the position of each installation flue-dust retainer is cut and peeled off the arc being equivalent to mouth-shaped and size on described flue-dust retainer bottom described cleaning shaft, then this arc bracket type electric motor car is transported to outside factory building, gives over to rear use;
(11) flue-dust retainer vertically to be hung in bracket type electric motor car with 25t truck crane and with described bracket type electric motor car, each flue-dust retainer be transported to immediately below described cleaning shaft installation site successively, first coordinate jack to be risen to 100-200mm place apart from described cleaning shaft bottom surface with hoist engine, then finely tuned in place and spot welding with jack and fix.
In aforementioned installation method, described planer-type electric hang car comprises two vehicle frames, the upper end of two described vehicle frames is provided with car beam, described car beam is provided with slideway, described slideway is provided with and hangs with two cat heads of its formation sliding motion pair, the bottom of two described vehicle frames is respectively arranged with two by motor-driven driving wheel.
In aforementioned installation method, described bracket type electric motor car comprises two vehicle frames, the bottom of two described vehicle frames is provided with four frames be made up of two longitudinal bottom girders and two horizontal bottom girders, the upper end of two described vehicle frames arranges two symmetrical short car beams respectively, and the corner place of described four frames is separately installed with by motor-driven driving wheel.
In order to save labor and materials, described bracket type electric motor car is converted by the planer-type electric hang car after using, and its method of modifying is:
(1) weld two longitudinal bottom girders and two horizontal bottom girders in the vehicle frame bottom of described planer-type electric hang car, make it formation four frame;
(2) remove cat head to hang, and the car beam of described vehicle frame upper end is together cut away together with slideway, then vehicle frame made two symmetries and perpendicular to the rectangle frame of bottom four frame along direction of travel;
(3) two symmetrical short car beams are set respectively on the rectangle frame described in two.
So far, described bracket type electric motor car repacking is complete.
Compared with prior art, its beneficial effect is in the present invention:
(1) installation period of described cleaning shaft can greatly be shortened: 3-4 group joints just can be installed for one day, 5-7 days just can whole installation in position, thus more than the 30 day duration of saving.
(2) installation period of described flue-dust retainer can greatly be shortened: within one day, just 6-8 flue-dust retainers can be installed, 3-4 days just can whole installation in position, thus save more than 20 day duration.
(3) greatly mounting cost can be reduced: even if install large-scale cleaning shaft, total installation fee also only needs 50,000 yuan, only accounts for 1/4 of original expense, and the total installed cost (TIC) of flue-dust retainer also only needs 30,000 yuan, also 1/3, two expenses of not enough original expense amount to and only need 80,000 yuan.
(4) higher installation quality can be ensured: just by unified for all supports of pipelines installation in place before described cleaning shaft is installed, be convenient to instrument detect, the handling of each group joint of cleaning shaft subsequently and counterpart is made to connect relatively easy, thus the installation quality met design requirement.
(5) can be salvaged: can complete cutting peeling off with the arc of described flue-dust retainer connecting position bottom described cleaning shaft, make surplus material obtain the chance of recycling.
(6) security can be ensured: in the unsettled lifting of cleaning shaft and the installation process of described support of pipelines and flue-dust retainer, described planer-type electric hang car and enabling of bracket type electric motor car make the workload of manual operation jack greatly reduce, and the fine setting of the Main Function of jack before to be material installed in place, thus decrease labour's operation, ensure that the personal security in installation process.
Accompanying drawing explanation
Fig. 1 is the structural representation of sintering machine dust pelletizing system.
Fig. 2 is the side view of Fig. 1.
Fig. 3 is the structural representation of planer-type electric hang car.
Fig. 4 is the side view of Fig. 3.
Fig. 5 is the structural representation of bracket type electric motor car.
Fig. 6, Fig. 7 are side view and the top view of Fig. 5 respectively.
Detailed description of the invention
In order to make technical scheme of the present invention more easily be understood, below in conjunction with drawings and Examples, it is described in detail.
The installation method of sintering machine dust pelletizing system of the present invention, adopts homemade planer-type electric hang car and bracket type electric motor car to carry out.
With reference to Fig. 3, Fig. 4, described planer-type electric hang car, comprises two vehicle frames 11 made with angle steel, H profile steel or steel plate; The upper end of two described vehicle frames 11 is provided with car beam 12, described car beam 12 is made up of the steel plate and the I-steel be welded between two steel plates being laid on described vehicle frame 11 upper end width both sides respectively, two sides of described I-steel footing form two slideways respectively, and it is secondary that the slideway described in two and two cat heads be installed on it hang 13 formation sliding motions; The both sides, bottom of two described vehicle frames 11 are separately installed with the driving wheel 14 driven by motor 15.
With reference to Fig. 5, Fig. 6, Fig. 7, described bracket type electric motor car, comprise the upper end of two vehicle frames, 11, two described vehicle frames 11 made with angle steel, H profile steel or steel plate and be respectively arranged with two symmetrical short car beams 16, described short car beam 16 is made up of the H profile steel being welded on described vehicle frame 11 upper end; The bottom of two described vehicle frames 11 is respectively arranged with two the longitudinal bottom girders 17 and two horizontal bottom girders 18 that are parallel to each other, longitudinal bottom girder 17 described in two and the horizontal bottom girder 18 described in two form four frames, and the corner place of described four frames is separately installed with the driving wheel 14 driven by motor 15.
With reference to Fig. 1, Fig. 2, the installation method of sintering machine dust pelletizing system of the present invention, comprises the following steps:
(1) surveying setting-out on the Cement Concrete beam 6 of factory building absolute altitude a, determines center line locus and the center line absolute altitude b of cleaning shaft 3;
(2) set up steel platform in factory building head 1 side, and make the upper surface of described steel platform be absolute altitude a;
(3) according to the locus of described cleaning shaft 3 center line and the size in absolute altitude b and space, described cleaning shaft 3 place, the Cement Concrete beam 6 of factory building absolute altitude a is laid two for planer-type electric hang car and be highly the temporary track of h, and make this temporary track extend to aforesaid steel platform;
(4) according to the upper surface absolute altitude a+h of the width between two temporary tracks, temporary track and the size of installing space, make planer-type electric hang car and check the bearing capacity of described planer-type electric hang car, ensureing to use it for when the different cleaning shaft 3 of caliber is installed and can be applicable to;
(5) according to the size of flue-dust retainer 4 installing space, the Cement Concrete beam 6 of factory building absolute altitude 0 is laid two for bracket type electric motor car and be highly h temporary track, and make this temporary track extend to factory building certain distance outward;
(6) with 25t truck crane, the component units of described dust pelletizing system 3 is placed on described steel platform sequentially, then described planer-type electric hang car is started to steel platform along its temporary track, and the component units of dust pelletizing system 3 described in handling is to corresponding installation site;
(7) with described planer-type electric hang car, support of pipelines 5 handling that is used for installing cleaning shaft 3 is completed installation to relevant position, re-use each group joint that the handling of planer-type electric hang car forms cleaning shaft 3, and ensure that each group joint surrounding of its centerline direction in counterpart process has enough adjustment surpluses, then each group joint to be installed on described support of pipelines 5 successively by direction from inside to outside and to complete butt welding, centerline deviation after allowing it to install is ± 5mm, and absolute altitude deviation is ± 2mm;
(8) on the left of factory building or right side use truck crane to be winched to by little lattice funnel 2 the Cement Concrete beam 6 of factory building absolute altitude c, then use factory building driving each little lattice funnel 2 is lifted into the relevant position of the cleaning shaft 3 top Cement Concrete beam 6 having completed butt welding successively and fixed;
(9) the planer-type electric hang car of having finished the work is transform as bracket type electric motor car, and on the temporary track of the upper surface absolute altitude 0+h laid in placing it in step (5);
(10) walk on stage in the laid inside of described cleaning shaft 3 and complete welding, then complete walk on stage lay and welding cleaning shaft 3 bottom the position of each installation flue-dust retainer 4 cut and peel off its size, arc that described flue-dust retainer 4 that shape is equivalent to connect with it is suitable for reading, and the arc hoist engine peeled off is hung handling to be transported to outside factory building to the bracket type electric motor car be positioned at below it, is persisted in later engineering and uses;
(11) bracket type electric motor car is started to outside factory building, with 25t truck crane, described flue-dust retainer 4 is vertically hung in bracket type electric motor car, and each flue-dust retainer 4 is transported to immediately below the installation site of each group of described cleaning shaft 3 joint by bracket type electric motor car described in using successively, first coordinate jack to be risen to 100-200mm place apart from described cleaning shaft 3 bottom surface with hoist engine, then finely tuned in place and spot welding with jack and fix.
With reference to Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, by the method that described planer-type electric hang car is adapted as bracket type electric motor car be:
(1) weld two longitudinal bottom girders 17 and two horizontal bottom girders 18 in vehicle frame 11 bottom of described planer-type electric hang car, make it formation four frame;
(2) remove described cat head and hang 13, and the car beam 12 of described vehicle frame 11 upper end is together cut away together with slideway, more described vehicle frame 11 made two symmetries and perpendicular to the rectangle frame of bottom four frame along its direction of travel;
(3) two symmetrical short car beams 16 are set respectively on the rectangle frame described in two.
Adopt the inventive method to install sintering machine dust pelletizing system, its advantage is:
(1) installation of described little lattice funnel 2 does not affect the installation in advance of sintering machine support, and after little lattice funnel 2 installs, the bellows of sintering machine system and the installation of the equipment such as head, tail can be in full swing.
(2) along with the installation in position successively of each group joint in described cleaning shaft 3, the part that the temporary track can removing absolute altitude a+h does not successively re-use, and the fractional orbital after dismounting is placed in absolute altitude 0 place below described cleaning shaft 3, until each group joint of described cleaning shaft 3 all installs, the temporary track also corresponding formation of absolute altitude 0+h.
(3) after described cleaning shaft 3 installs, planer-type electric hang car can be adapted as bracket type electric motor car, for installing the flue-dust retainer 4 bottom described cleaning shaft 3, and the arc being positioned at the cutting removing of described flue-dust retainer 4 position suitable for reading bottom described cleaning shaft 3 is transported to outside factory building.
(4) compared with the installation method of sintering machine dust pelletizing system routine, this invention simplifies the work progress installing dust pelletizing system, make original crossings on different level and the operation interfered with each other changes into nowadays parallel expansion and non-interfering operation, both the installation in position time can be saved, make transport, counterpart, the operations such as installation in succession complete in the short time on a mobile platform, in turn save a large amount of manpowers and construction cost, thus effectively solve the installation period using routine techniques to bring, the variety of problems of mounting cost and the aspect such as installation quality and installation safety, there is good practicality.
Above with reference to drawings and Examples, schematically describe technical scheme of the present invention, this description is not restricted.Those skilled in the art will be understood that in actual applications, and in the present invention, the shape of each parts or set-up mode some all may occur change, and other staff also may make similar Design under its enlightenment.Special needs to be pointed out is: installation method of the present invention can also be used in installing of other various device systems, as long as it possesses features such as " are arranged in multi storied factory building, installation procedure space multistory intersects also restriction mutually ".Therefore, only otherwise depart from design aim of the present invention, all apparent changes or similar Design, be all included within protection scope of the present invention.

Claims (6)

1. an installation method for sintering machine dust pelletizing system, is characterized in that, the method comprises the following steps:
(1) surveying setting-out on the Cement Concrete beam of factory building absolute altitude a, determines locus and the center line absolute altitude b of cleaning shaft center line;
(2) set up in factory building head side the steel platform that its upper surface is absolute altitude a;
(3) lay on the Cement Concrete beam of factory building absolute altitude a two be for planer-type electric hang car and highly h, length extends to the temporary track of aforementioned steel platform;
(4) make planer-type electric hang car and be placed on the temporary track of upper surface absolute altitude a+h, then checking its bearing capacity;
(5) on the Cement Concrete beam of factory building absolute altitude 0, two are laid for bracket type electric motor car and highly for h, length extend to the temporary track of factory building certain distance outward;
(6) with 25t truck crane, the component units of dust pelletizing system is placed on steel platform sequentially, then uses planer-type electric hang car by its handling to corresponding installation site;
(7) to use planer-type electric hang car that support of pipelines handling is completed installation to relevant position, each group of handling formation cleaning shaft saves and ensures that the surrounding of centerline direction in its counterpart process all possesses enough adjustment surpluses again, then it to be installed to successively on support of pipelines and to complete butt welding, centerline deviation after allowing it to install is ± 5mm, and absolute altitude deviation is ± 2mm;
(8) on the left of factory building or right side use truck crane to be winched to the Cement Concrete beam of factory building absolute altitude c by little lattice funnel, re-use factory building driving and each little lattice funnel be lifted into the relevant position of the cleaning shaft top Cement Concrete beam having completed butt welding successively and fixed;
(9) repack planer-type electric hang car into bracket type electric motor car and be placed on the temporary track of upper surface absolute altitude 0+h;
(10) the inside laying of walking on stage of described cleaning shaft and welding is completed and the position of each installation flue-dust retainer is cut and peeled off the arc being equivalent to mouth-shaped and size on described flue-dust retainer bottom described cleaning shaft, then this arc bracket type electric motor car is transported to outside factory building, gives over to rear use;
(11) flue-dust retainer vertically to be hung in bracket type electric motor car with 25t truck crane and with described bracket type electric motor car, each flue-dust retainer be transported to immediately below described cleaning shaft installation site successively, first coordinate jack to be risen to 100-200mm place apart from described cleaning shaft bottom surface with hoist engine, then finely tuned in place and spot welding with jack and fix.
2. the installation method of sintering machine dust pelletizing system according to claim 1, it is characterized in that, described planer-type electric hang car comprises two vehicle frames, the upper end of two described vehicle frames is provided with car beam, described car beam is provided with slideway, described slideway is provided with and hangs with two cat heads of its formation sliding motion pair, the bottom of two described vehicle frames is respectively arranged with two by motor-driven driving wheel.
3. the installation method of sintering machine dust pelletizing system according to claim 1, it is characterized in that, described bracket type electric motor car comprises two vehicle frames, the bottom of two described vehicle frames is provided with four frames be made up of two longitudinal bottom girders and two horizontal bottom girders, the upper end of two described vehicle frames is symmetrically arranged with two short car beams respectively, and the corner place of described four frames is separately installed with by motor-driven driving wheel.
4. the installation method of sintering machine dust pelletizing system according to claim 2, is characterized in that, described slideway is made up of two sides of I-steel footing.
5. the installation method of the sintering machine dust pelletizing system according to Claims 2 or 3, is characterized in that, described vehicle frame makes with angle steel, H profile steel or steel plate.
6. the installation method of sintering machine dust pelletizing system according to claim 1, is characterized in that, described bracket type electric motor car is converted by the planer-type electric hang car after using, and its method of modifying is:
(1) weld two longitudinal bottom girders and two horizontal bottom girders in the vehicle frame bottom of described planer-type electric hang car, make it formation four frame;
(2) remove cat head to hang, and the car beam of described vehicle frame upper end is together cut away together with slideway, then vehicle frame made two symmetries and perpendicular to the rectangle frame of bottom four frame along direction of travel;
(3) two symmetrical short car beams are set respectively on the rectangle frame described in two.
CN201410389647.8A 2014-08-08 2014-08-08 A kind of installation method of sintering machine dust pelletizing system Active CN104180658B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410389647.8A CN104180658B (en) 2014-08-08 2014-08-08 A kind of installation method of sintering machine dust pelletizing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410389647.8A CN104180658B (en) 2014-08-08 2014-08-08 A kind of installation method of sintering machine dust pelletizing system

Publications (2)

Publication Number Publication Date
CN104180658A CN104180658A (en) 2014-12-03
CN104180658B true CN104180658B (en) 2015-12-30

Family

ID=51961874

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410389647.8A Active CN104180658B (en) 2014-08-08 2014-08-08 A kind of installation method of sintering machine dust pelletizing system

Country Status (1)

Country Link
CN (1) CN104180658B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108571894A (en) * 2017-03-07 2018-09-25 中国二十冶集团有限公司 It is sintered the installation method of owner's exhaust duct

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104896937B (en) * 2015-06-17 2017-01-04 中冶宝钢技术服务有限公司 A kind of method changing sintering machine wind box chute and bellows beam
CN104973517B (en) * 2015-06-26 2017-03-08 中冶天工集团天津有限公司 A kind of electronic gantry platform that installs for sintering machine head device and its using method
CN110127520B (en) * 2019-05-10 2021-01-01 上海二十冶建设有限公司 Method for installing small-lattice funnel and dust-settling pipe of large sintering machine
CN110542312B (en) * 2019-07-19 2021-07-27 五冶集团上海有限公司 Method for mounting lower ash bucket of environment-friendly sintering machine

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07286216A (en) * 1994-04-19 1995-10-31 Nippon Steel Corp Sintering method by waste gas circulation and waste gas circulation equipment
CN1458435A (en) * 2002-05-15 2003-11-26 上海自来水给水设备工程公司 Mounting and construction equipment for large span large bore river crossing bridge pipe and its construction method
CN201301323Y (en) * 2008-11-28 2009-09-02 中冶京诚工程技术有限公司 A turnover-type top dust removal cover
CN101725154A (en) * 2009-11-16 2010-06-09 天津二十冶建设有限公司 Method and device for installing and regulating light equipment and steel structure
CN102146492A (en) * 2011-05-24 2011-08-10 天津二十冶建设有限公司 Method for installing converter body equipment and tooling platform
CN202924624U (en) * 2012-10-22 2013-05-08 北京首钢建设集团有限公司 Large-diameter pipeline lifting device of roof of steel-making plant

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07286216A (en) * 1994-04-19 1995-10-31 Nippon Steel Corp Sintering method by waste gas circulation and waste gas circulation equipment
CN1458435A (en) * 2002-05-15 2003-11-26 上海自来水给水设备工程公司 Mounting and construction equipment for large span large bore river crossing bridge pipe and its construction method
CN201301323Y (en) * 2008-11-28 2009-09-02 中冶京诚工程技术有限公司 A turnover-type top dust removal cover
CN101725154A (en) * 2009-11-16 2010-06-09 天津二十冶建设有限公司 Method and device for installing and regulating light equipment and steel structure
CN102146492A (en) * 2011-05-24 2011-08-10 天津二十冶建设有限公司 Method for installing converter body equipment and tooling platform
CN202924624U (en) * 2012-10-22 2013-05-08 北京首钢建设集团有限公司 Large-diameter pipeline lifting device of roof of steel-making plant

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108571894A (en) * 2017-03-07 2018-09-25 中国二十冶集团有限公司 It is sintered the installation method of owner's exhaust duct

Also Published As

Publication number Publication date
CN104180658A (en) 2014-12-03

Similar Documents

Publication Publication Date Title
CN104180658B (en) A kind of installation method of sintering machine dust pelletizing system
CN109505613A (en) Originating method in the hole of earth pressure balanced shield, EPBS in small space
CN109573851B (en) Arc-shaped roof internode steel truss hanging and installing integrated device and butt-joint hanging method
CN103821376A (en) Single-layer reticulated shell structure high-altitude inclined rail accumulated slide moving construction method
CN208379596U (en) Foundation pit supporting construction
CN104195948A (en) Bridge hanging pipeline pushing installation and construction method
CN105773004B (en) Flexible equipment for manufacturing steel structure bridge and disassembling and assembling method thereof
CN104670418B (en) Assembly process of helideck of offshore platform
CN108952768A (en) A kind of stage apparatus of Shield tunnel secondary grouting
CN204386608U (en) A kind of tunnel invert construction tool
CN204608611U (en) Be applicable to the movable die block table system of large-sized concrete prefabricated units
CN109706856B (en) Box culvert assembling method and device, processor and memory
CN107060831A (en) One kind is used for tunnel groove constructing device
CN208203298U (en) A kind of big punching block of rail type side wall
CN109487646A (en) Shield section and platform section running track traveling process become automatically across method
CN106192761A (en) A kind of method disassembling mobile formwork in bridge tunnel narrow short transition time section
CN102808632B (en) Full-circle type formwork trolley assembly and construction method thereof
CN107642089B (en) Narrow space concrete pouring method
CN113123800B (en) Construction method of starting base of large-diameter shield tunnel steel structure
CN210509222U (en) Circular device with steel strip lining tunnel
CN108217448A (en) A kind of integrated bridge floor device for hoisting for composite beam construction
CN210530883U (en) Construction system for horizontal splicing, vertical rotation and combination of circular strip steel lining tunnel
CN208778011U (en) Concrete- liner tunnel side wall steel formwork trolley
CN205702936U (en) The flexible equipment that steel structure bridge manufactures
CN206985538U (en) A kind of extraordinary overhead traveling crane for rigid landfill yard

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP03 Change of name, title or address

Address after: 300301 Dongli District, flawless Street Jintang Highway Bridge No. ten

Patentee after: MCC TIANGONG GROUP TIANJIN CO., LTD.

Address before: 300301 Dongli District, Tianjin Street

Patentee before: Tianjin MCC20 Construction Co., Ltd.