CN108914776A - A kind of construction hanging basket built for municipal works and room - Google Patents
A kind of construction hanging basket built for municipal works and room Download PDFInfo
- Publication number
- CN108914776A CN108914776A CN201810710470.5A CN201810710470A CN108914776A CN 108914776 A CN108914776 A CN 108914776A CN 201810710470 A CN201810710470 A CN 201810710470A CN 108914776 A CN108914776 A CN 108914776A
- Authority
- CN
- China
- Prior art keywords
- gauge
- snap
- hanging basket
- municipal works
- construction hanging
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/10—Cantilevered erection
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/28—Mobile scaffolds; Scaffolds with mobile platforms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/28—Mobile scaffolds; Scaffolds with mobile platforms
- E04G3/34—Mobile scaffolds; Scaffolds with mobile platforms characterised by supporting structures provided on the roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/28—Mobile scaffolds; Scaffolds with mobile platforms
- E04G2003/283—Mobile scaffolds; Scaffolds with mobile platforms mobile horizontally
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a kind of construction hanging baskets built for municipal works and room, its key points of the technical solution are that including main couple, crossbeam on main couple is set, moving track on beam face is set, it further include two side forms, the length of the side form is greater than the length that supporting beam carries out once-paving, the top side detachable of the side form is fixedly connected with snap-gauge, the snap-gauge is in inverted L-shaped and can be affixed with the upper surface of supporting beam, the upper surface of the snap-gauge is installed with lifting assembly, the upper surface of support beam is equipped with close to snap-gauge setting and snap-gauge is driven to carry out mobile driving assembly.The present invention solves mobile not convenient enough the technical problem of Hanging Basket side form.
Description
Technical field
The present invention relates to municipal administrations and supporting beam construction field, more specifically, it is related to one kind for municipal works and room
The construction hanging basket built.
Background technique
Cradle construction is also construction hanging basket, is the one of prestressed concrete continuous beam, T steel structure and cantilever beam section construction
Item capital equipment, it can be whole forward along track.Cradle construction is available:Cradle in truss type, trigonometric expression Hanging Basket, prismatic Hanging Basket and
The techniques such as stayed-cable hanging basket.It is most widely used in supporting beam construction.
In the prior art, the application publication number that can refer to is the patent document of CN107747281A, and one kind being used for city's political and ideological work
The construction hanging basket that journey and room are built, its key points of the technical solution are that:Pacifying including main couple, the crossbeam being arranged on main couple, setting
Moving track on dress face is provided with placing groove on main couple bottom surface, several accommodating grooves is evenly distributed on placing groove internal groove side wall,
It is provided with several oil cylinders on main truss top of support, rotation seat, the company of rotation on rotation seat are fixedly connected on the end of cylinder piston rod
It is connected to the first idler wheel, is provided with motor on rotation seat, when needing mobile main couple, control cylinder piston rod elongation, so that the
One idler wheel is moved towards moving track side.When the first idler wheel and moving track offset, oil cylinder pushing main couple is upward
It is mobile.Control motor is opened and the first idler wheel is driven to be rotated later.At the same time, the first idler wheel drives main couple to carry out
It is mobile.The construction hanging basket moving process being arranged in this way is more convenient, quick, and improves making for the construction hanging basket to a certain extent
Use efficiency.
The documents drive main couple to move up by oil cylinder, before then driving main couple to carry out by the first idler wheel
Move, which can eaily realize the movement of main couple, but Hanging Basket side form movement in order to prevent its topple,
It needs multiple fixation and needs to disassemble these fixing pieces when moving, movement is still not convenient enough.
Summary of the invention
In view of the deficiencies of the prior art, the present invention intends to provide a kind of to apply for what municipal works and room were built
Work Hanging Basket is stuck in the snap-gauge of supporting beam two sides by being equipped at the top of side form, and passes through lifting assembly and driving assembly band
Dynamic snap-gauge is moved and is gone up and down, and the mounting process of side form is reduced, so that side form be made eaily to move, and reduces side
The risk of mould installation.
To achieve the above object, the present invention provides following technical solutions:A kind of construction built for municipal works and room
Hanging Basket further includes two side forms, institute including main couple, the crossbeam being arranged on main couple, the moving track being arranged on beam face
The length for stating side form is greater than the length that supporting beam carries out once-paving, and the top side detachable of the side form is fixedly connected with snap-gauge,
The snap-gauge is in inverted L-shaped and can be affixed with the upper surface of supporting beam, and the upper surface of the snap-gauge is installed with lifting assembly, described
Upper surface of support beam is equipped with close to snap-gauge setting and snap-gauge is driven to carry out mobile driving assembly.
It by the way that snap-gauge is arranged at the top of side form is needing that side form is driven to be moved by using above-mentioned technical proposal
Or when lifting, drives snap-gauge to be moved by lifting assembly and driving assembly, can very easily realize the advance of side form,
And the upper surface of supporting beam is stuck in by snap-gauge to prevent side form from run-off the straight or toppling when mobile, it is moved by side form
It moves corresponding position and then is fixed with simple fixed mechanism, after mobile complete, by snap-gauge and side form
It dismantles to carry out pouring for concrete.
The present invention is further arranged to:There are two the moving track is total and set on the top two sides of supporting beam, the shifting
Multiple support rods being placed in upper surface of support beam are bolted on the outside of dynamic rail road, multiple support rods correspond to the position of snap-gauge
The place of setting is installed with the bar of the axis direction setting along side form, and the bar is square, bends downward simultaneously inside the snap-gauge
It can be affixed with the inside side walls of bar.
By using above-mentioned technical proposal, by the way that support rod is arranged in the outside of moving track, and by support rod
Outside connection baffle blocks snap-gauge, prevents side form from moving outward in the process of moving.
The present invention is further arranged to:It is hinged with what multiple pairs of the two were fixed between the snap-gauge and the top of side form
Fastening bolt and the fastening nut being threaded in fastening bolt.
By using above-mentioned technical proposal, snap-gauge and side form are fixed by fastening nut and fastening bolt, in side
Mould unscrews fastening nut snap-gauge is turned to outside after being moved to corresponding position, to realize between two side forms
Concrete pours.
The present invention is further arranged to:The lifting assembly include the first hydraulic cylinder that is connected on beam face of bottom bolts and
Link block on first hydraulic cylinder piston rod, the top of the link block are rotatably connected to multiple rotating rollers.
By using above-mentioned technical proposal, risen by the flexible drive snap-gauge of multiple first hydraulic cylinder piston rods,
When moving to snap-gauge, the lower part of snap-gauge can be slided in rotating roller, to eaily realize the movement of snap-gauge.
The present invention is further arranged to:The driving component includes the pedestal being bolted on bar and is installed in pedestal
On second hydraulic cylinder, the piston rod of the second hydraulic cylinder can be affixed with the side wall of snap-gauge.
By using above-mentioned technical proposal, second hydraulic cylinder is fixed on bar by pedestal, and passes through its piston rod
It upholds and snap-gauge is driven to be moved, after mobile a distance, pedestal is retightened a position to carry out next time
Snap-gauge movement.
The present invention is further arranged to:The main couple is diamond shape frame, and the lower part two sides of the main couple are equipped with left-hand thread
Wheel, the inverse buckling wheel rolling are connected on moving track.
It is more stable using diamond shape frame as main couple by using above-mentioned technical proposal, by inverse buckling wheel in moving track
The upper rotation rotated to realize main couple, inverse buckling wheel can be stuck on moving track to guarantee that main couple will not topple.
The present invention is further arranged to:The bolt fixed to the two is connected between the inverse buckling wheel and main couple.
By using above-mentioned technical proposal, inverse buckling wheel and main couple are fixed by bolt, installation and removal are compared
It is more convenient.
The present invention is further arranged to:The crossbeam is set to the top outer of two main couples, and two main couples are equal
It is connect with transom bolt.
By using above-mentioned technical proposal, two main couples and crossbeam are fixed by bolt, the installation of crossbeam and
It is convenient for disassembly.
The present invention is further arranged to:Middle door frame, two sides above and below the middle door frame are inserted between two main couples
It is equipped with angle steel with the angle of main couple, the two sides of the angle steel are bolted with the welding of middle door frame and main couple respectively.
It by using above-mentioned technical proposal, is fixed by angle steel centering door frame and main couple, middle door frame will not occur
Shake, and in capable of eaily realizing door frame disassembly and installation.
The present invention is further arranged to:It further include the bed die between two side forms, the bed die includes two levels
The cross bar of setting and both ends are respectively welded multiple connecting rods on two cross bars of connection, outside cross bar and crossbeam, inboard rail with
It is connected by steel wire between middle door frame.
By using above-mentioned technical proposal, consolidated respectively by two sides of the steel wire on crossbeam and middle door frame to bed die
It is fixed, it is more convenient when pulling the wirerope of crossbeam to be opened bed die in this way.
In conclusion the present invention has the advantages that compared with the prior art:The present invention passes through at the top of side form
It drives snap-gauge to be moved and gone up and down equipped with the snap-gauge for being stuck in supporting beam two sides, and by lifting assembly and driving assembly, reduces
The mounting process of side form, so that side form be made eaily to move.
Detailed description of the invention
Fig. 1 is overall structure figure in embodiment;
Fig. 2 is the structural schematic diagram of main couple and bed die in embodiment saliency;
Fig. 3 is the structural schematic diagram of embodiment saliency driving assembly;
Fig. 4 is the partial schematic sectional view of embodiment saliency side form structure;
Fig. 5 is lifting assembly structural schematic diagram in embodiment.
In figure:1, moving track;11, sole piece;12, support rod;13, bar;2, main couple;21, inverse buckling wheel;22, strut;
23, bolt;3, crossbeam;4, middle door frame;41, angle steel;5, side form;51, outer nose girder;52, snap-gauge;53, fastening bolt;531, it fastens
Nut;54, lifting assembly;541, first hydraulic cylinder;542, link block;543, rotating roller;544, attachment base;55, driving assembly;
551, pedestal;5511, connection sheet;552, second hydraulic cylinder;553, push plate;6, bed die;61, cross bar;62, connecting rod;63, steel wire
Rope;7, beam column is supported.
Specific embodiment
The present invention is described in further detail below in conjunction with the accompanying drawings.The wherein identical appended drawing reference of identical components
It indicates.It should be noted that word "front", "rear" used in the following description, "left", "right", "up" and "down" refer to it is attached
Direction in figure, word " bottom surface " and " top surface ", "inner" and "outside" are referred respectively to towards or away from geometric center of specific component
Direction.
Embodiment:A kind of construction hanging basket built for municipal works and room, as shown in Figure 1, including moving track 1, main truss
Frame 2, crossbeam 3, middle door frame 4, side form 5 and bed die 6.There are two and set on the top two sides of support beam column 7 altogether for moving track 1, move
Dynamic rail road 1 passes through multiple sole pieces 11 of bottom, is fixed on support beam column 7, moving track 1 is horizontally disposed.
As shown in Fig. 2, main couple 2 altogether there are two and be diamond shape frame, be equipped between two endpoints of main couple 2 strut 22 from
And main couple 2 is made to form two triangles, to guarantee the stability of main couple 2, two main couples 2 are vertically arranged and difference position
In the surface of two moving tracks 1, the two sides of the bottom of main couple 2 are equipped with the inverse buckling wheel 21 being vertically arranged, inverse buckling wheel 21 and master
It is connected between the bottom of truss 2 by bolt 23, inverse buckling wheel 21 and main couple 2 is fixed by bolt 23 in this way, installed
It is more convenient with dismantling.Inverse buckling wheel 21 is vertically arranged and rolls and is connected on moving track 1, the wheel of inverse buckling wheel 21 and shifting
The inner sidewall in dynamic rail road 1 is affixed to block the top of moving track 1, and in this way when main couple 2 is mobile, inverse buckling wheel 21 can be stuck in
To prevent main couple 2 from shifting on moving track 1.
Crossbeam 3 is horizontally disposed and is set to the outside at 2 top of main couple, and crossbeam 3 passes through bolt and two 2 phases of main couple
Even, two main couples 2 and crossbeam 3 are fixed by bolt in this way, the installation and removal of crossbeam 3 are more convenient.
There are two middle door frame 4 is total and vertically set on the two sides of strut 22, middle door frame 4 is in frame-type and is set in strut 22
Portion, two middle 4 sustained height of door frame settings, the two sides up and down of middle door frame 4 are equipped with an angle of 90 degrees steel 41, the two sides difference of angle steel 41
It is affixed in the side wall of middle door frame 4 and strut 22,41 side of angle steel is welded and fixed with middle door frame 4, and the other side and main couple 2 pass through spiral shell
Bolt is fixed.It being fixed by 41 centering door frame 4 of angle steel and main couple 2, the meeting centering door frame 4 of angle steel 41 plays the role of limit,
Middle door frame 4 will not shake, and in capable of eaily realizing door frame 4 disassembly and installation.
Bed die 6 includes two cross bars 61 and multiple connecting rods 62.Two cross bars 61 are arranged in parallel and are set to middle door
The underface of frame 4 and crossbeam 3, multiple connecting rods 62 be parallel to each other and be vertically arranged with cross bar 61, the two of each connecting rod 62
End is fixedly connected with two cross bars 61.It is carried out respectively by two sides of the steel wire on crossbeam 3 and middle door frame 4 to bed die 6 in this way
It is fixed, operate bed die 6 when being opened in the wirerope 63 of pulling crossbeam 3 so more convenient.
As shown in Figure 3 and Figure 4, there are two and set on the top two sides of support beam column 7 altogether for side form 5, support the lower part of beam column 7
Two sides are fixed, and there are two horizontally disposed outer nose girders 51, and two side forms 5, which are vertically arranged, to be threaded through respectively on two outer nose girders 51, side
Mould 5 is L-shaped and is staggeredly formed by fixedly connecting by more coupling beams, and the top of side form 5 is concordant with the support top of beam column 7, each side
The top of mould 5 is installed with the snap-gauge 52 for being located at 7 top of support beam column, and the cross section of snap-gauge 52 is in inverted L-shaped, the lower part of snap-gauge 52
Handover has fastening bolt 53 and fastening nut 531 between the top of side form 5, and fastening nut 531 is threaded in fastening bolt
On 53, when fastening nut 531 is tightened, snap-gauge 52 is fixed to each other with side form 5, can be by snap-gauge when fastening nut 531 is unscrewed
52 turn to the outside of side form 5, to not influence pouring for subsequent concrete.
The outside of 1 lower section sole piece 11 of moving track is installed with multiple horizontally disposed support rods 12, and support rod 12 is due to moving
Dynamic rail road 1 is mutually perpendicular to, and the outside of support rod 12 is installed with the bar 13 arranged in parallel with moving track 1, bar 13
Cross section is rectangle and the underface for being set to snap-gauge 52, and the inside of snap-gauge 52 is turned over downwards and is affixed with the inner sidewall of bar 13,
Bar 13 can play the role of limit to side form 5 to snap-gauge 52 when side form 5 is mobile in this way, prevent side form 5 in movement
When topple and cause danger.
As shown in Figure 4 and Figure 5, lifting assembly 54 is equipped between the outside of bar 13 and snap-gauge 52, lifting assembly 54 is shared
Multiple underfaces for being uniformly set to snap-gauge 52, lifting assembly 54 include first hydraulic cylinder 541, link block 542 and rotating roller 543.
First hydraulic cylinder 541 is vertically arranged and its bottom is installed with attachment base 544, between attachment base 544 and the top for supporting beam column 7
It is bolted, link block 542 is horizontally disposed and is fixedly connected with the piston rod of first hydraulic cylinder 541, in link block 542
Portion open up it is fluted, rotating roller 543 share it is multiple and be set to groove in, the both ends of rotating roller 543 are rotatably connected on link block
In 542, risen in this way by the flexible drive snap-gauge 52 of multiple 541 piston rods of first hydraulic cylinder, is carried out to snap-gauge 52
When mobile, the lower part of snap-gauge 52 can be slided in multiple rotating rollers 543, the more laborsaving convenience of the movement of side form 5, when needing to build
When next section of supporting beam, the bolt lemon on attachment base 544 is gone out, first hydraulic cylinder 541 is bolted on next section of branch
It supports on beam, it is more convenient.
Bar 13 is installed with driving assembly 55 far from one end that support beam column 7 builds end, and driving assembly 55 includes pedestal 551
With second hydraulic cylinder 552.Pedestal 551 is vertically arranged and its underpart protrudes horizontally up connection sheet 5511, connection sheet 5511 and bar
It is bolted between 13, second hydraulic cylinder 552 is horizontally disposed with and is installed with the push plate being vertically arranged on its piston rod
553, the side wall of the side wall and snap-gauge 52 of push plate 553 is affixed, the piston rod of such second hydraulic cylinder 552 uphold drive snap-gauge 52 into
Bolt on pedestal 551 is unloaded and is fixed on again another position after the mobile a distance of snap-gauge 52 by row movement,
It promotes layer by layer in this way, side form 5 is pushed to move at next position for needing to build, the length of snap-gauge 52 is greater than what needs were built
The side of the length of one section of supporting beam, such snap-gauge 52 is connected in the supporting beam constructed, reduces the generation of accident.
It drives snap-gauge 52 to be moved by setting lifting assembly 54 and driving assembly 55, can very easily realize side form
5 advance, and the upper surface of supporting beam is stuck in by snap-gauge 52 to prevent side form 5 from run-off the straight or inclining when mobile
It covers, side form 5 is being moved to corresponding position and then is being fixed with simple fixed mechanism, in mobile completion
Afterwards, snap-gauge 52 and side form 5 are dismantled to carry out pouring for concrete.
The above is only a preferred embodiment of the present invention, protection scope of the present invention is not limited merely to above-mentioned implementation
Example, all technical solutions belonged under thinking of the present invention all belong to the scope of protection of the present invention.It should be pointed out that for the art
Those of ordinary skill for, several improvements and modifications without departing from the principles of the present invention, these improvements and modifications
It should be regarded as protection scope of the present invention.
Claims (10)
1. a kind of construction hanging basket built for municipal works and room, including main couple (2), the crossbeam being arranged on main couple (2)
(3), the moving track (1) on beam face is set, it is characterised in that:It further include two side forms (5), the length of the side form (5)
Greater than the length that supporting beam (7) carry out once-paving, the top side detachable of the side form (5) is fixedly connected with snap-gauge (52), institute
Snap-gauge (52) are stated in inverted L-shaped and can be affixed with the upper surface of supporting beam (7), the upper surface of the snap-gauge (52) is installed with lifting
Component (54), supporting beam (7) upper surface are equipped with close to snap-gauge (52) setting and snap-gauge (52) are driven to carry out mobile drive
Dynamic component (55).
2. a kind of construction hanging basket built for municipal works and room according to claim 1, it is characterised in that:The movement
Multiple placements have been bolted there are two track (1) is total and on the outside of the top two sides of supporting beam, the moving track (1)
Support rod (12) in upper surface of support beam is installed with along side form at the position of multiple support rods (12) corresponding snap-gauge (52)
(5) bar (13) of axis direction setting, the bar (13) are square, and snap-gauge (52) inside bends downward and can
It is affixed with the inside side walls of bar (13).
3. a kind of construction hanging basket built for municipal works and room according to claim 1, it is characterised in that:The snap-gauge
(52) fastening bolt (53) and be threaded in fastening that multiple pairs of the two are fixed are hinged between the top of side form (5)
Fastening nut (531) on bolt (53).
4. a kind of construction hanging basket built for municipal works and room according to claim 1, it is characterised in that:The lifting
Component (54) include the first hydraulic cylinder (541) that bottom bolts are connected on beam face and be set to first hydraulic cylinder (541) piston rod
On link block (542), the top of the link block (542) is rotatably connected to multiple rotating rollers (543).
5. a kind of construction hanging basket built for municipal works and room according to claim 1, it is characterised in that:The driving
Component (55) includes the pedestal (551) being bolted on bar (13) and the second hydraulic cylinder being installed on pedestal (551)
(552), the piston rod of the second hydraulic cylinder (552) can be affixed with the side wall of snap-gauge (52).
6. a kind of construction hanging basket built for municipal works and room according to claim 1, it is characterised in that:The main truss
Frame (2) is diamond shape frame, and the lower part two sides of the main couple (2) are equipped with inverse buckling wheel (21), and the inverse buckling wheel (21) rolls connection
On moving track (1).
7. a kind of construction hanging basket built for municipal works and room according to claim 6, it is characterised in that:The left-hand thread
The bolt (23) fixed to the two is connected between wheel (21) and main couple (2).
8. a kind of construction hanging basket built for municipal works and room according to claim 1, it is characterised in that:The crossbeam
(3) it is set to the top outer of two main couples (2), two main couples (2) are bolted with crossbeam (3).
9. a kind of construction hanging basket built for municipal works and room according to claim 1, it is characterised in that:Described in two
It is inserted between main couple (2) middle door frame (4), the angle of two sides and main couple (2) is equipped with angle to the middle door frame (4) up and down
Steel (41), the two sides of the angle steel (41) are bolted with middle door frame (4) welding and main couple (2) respectively.
10. a kind of construction hanging basket built for municipal works and room according to claim 9, it is characterised in that:Further include
Bed die (6) between two side forms (5), the bed die (6) include that two horizontally disposed cross bars (61) and both ends are distinguished
The multiple connecting rods (62) being welded to connect on two cross bars (61), outside cross bar (61) and crossbeam (3), inboard rail (61) are in
It is connected by steel wire between door frame (4).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810710470.5A CN108914776B (en) | 2018-07-02 | 2018-07-02 | A basket is hung in construction for municipal works and room are built |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810710470.5A CN108914776B (en) | 2018-07-02 | 2018-07-02 | A basket is hung in construction for municipal works and room are built |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108914776A true CN108914776A (en) | 2018-11-30 |
CN108914776B CN108914776B (en) | 2020-06-23 |
Family
ID=64423746
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810710470.5A Active CN108914776B (en) | 2018-07-02 | 2018-07-02 | A basket is hung in construction for municipal works and room are built |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108914776B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109610323A (en) * | 2018-12-07 | 2019-04-12 | 江西集银科技有限公司 | A kind of bridge cantilever construction Hanging Basket equipment suspension system |
CN111576248A (en) * | 2020-05-29 | 2020-08-25 | 中铁七局集团有限公司 | Dismantling method for cantilever cast-in-situ beam hanging basket system |
CN111646362A (en) * | 2020-06-01 | 2020-09-11 | 吕友飞 | Be applied to bridge construction's quick hoist mechanism |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09125318A (en) * | 1995-10-30 | 1997-05-13 | Ohbayashi Corp | Construction device of bridge girder |
CN201280693Y (en) * | 2008-10-22 | 2009-07-29 | 中铁大桥局集团第一工程有限公司 | Totally enclosed hanging basket |
CN103437302A (en) * | 2013-08-21 | 2013-12-11 | 中交二公局第一工程有限公司 | Hanging basket construction method for suspension pouring section of single cable plane cable-stayed bridge |
CN204080651U (en) * | 2014-10-29 | 2015-01-07 | 中铁建大桥工程局集团第五工程有限公司 | A kind of Diamond-Shape Form Traveler main couple walking system for road and bridge construction |
CN204753406U (en) * | 2015-06-17 | 2015-11-11 | 安徽奥发建筑制品有限公司 | Basket is hung with double track from anchor formula rhombus to passenger dedicated line construction |
CN206279460U (en) * | 2016-12-09 | 2017-06-27 | 中铁建大桥工程局集团第二工程有限公司 | A kind of running gear for Construction of continuous beam Hanging Basket |
-
2018
- 2018-07-02 CN CN201810710470.5A patent/CN108914776B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09125318A (en) * | 1995-10-30 | 1997-05-13 | Ohbayashi Corp | Construction device of bridge girder |
CN201280693Y (en) * | 2008-10-22 | 2009-07-29 | 中铁大桥局集团第一工程有限公司 | Totally enclosed hanging basket |
CN103437302A (en) * | 2013-08-21 | 2013-12-11 | 中交二公局第一工程有限公司 | Hanging basket construction method for suspension pouring section of single cable plane cable-stayed bridge |
CN204080651U (en) * | 2014-10-29 | 2015-01-07 | 中铁建大桥工程局集团第五工程有限公司 | A kind of Diamond-Shape Form Traveler main couple walking system for road and bridge construction |
CN204753406U (en) * | 2015-06-17 | 2015-11-11 | 安徽奥发建筑制品有限公司 | Basket is hung with double track from anchor formula rhombus to passenger dedicated line construction |
CN206279460U (en) * | 2016-12-09 | 2017-06-27 | 中铁建大桥工程局集团第二工程有限公司 | A kind of running gear for Construction of continuous beam Hanging Basket |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109610323A (en) * | 2018-12-07 | 2019-04-12 | 江西集银科技有限公司 | A kind of bridge cantilever construction Hanging Basket equipment suspension system |
CN111576248A (en) * | 2020-05-29 | 2020-08-25 | 中铁七局集团有限公司 | Dismantling method for cantilever cast-in-situ beam hanging basket system |
CN111646362A (en) * | 2020-06-01 | 2020-09-11 | 吕友飞 | Be applied to bridge construction's quick hoist mechanism |
Also Published As
Publication number | Publication date |
---|---|
CN108914776B (en) | 2020-06-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102367651B (en) | U-shaped concrete beam bridge girder erection machine | |
CN108914776A (en) | A kind of construction hanging basket built for municipal works and room | |
CN104631335A (en) | Novel large-tonnage bridge girder erection machine and construction method thereof | |
CN101082280A (en) | Single-track railway tunnel lining trolley | |
CN101249927A (en) | Mounting and dismounting method for gantry crane | |
CN208151870U (en) | A kind of supporting bracket of bridge construction | |
CN206801592U (en) | Hydraulic lining trolley for cut-and-cover tunnel concreting | |
CN105946104B (en) | A kind of die station tipper | |
CN107448215A (en) | A kind of Tunnel Second Lining A fonts chassis width tunable arrangement | |
LU501348B1 (en) | METHOD FOR CONSTRUCTING LARGE-SPAN THIN-WALLED CONCRETE SOUND BARRIER WITH POURING TROLLEY | |
CN110629793A (en) | Rapid supporting die frame for pipe gallery and construction method thereof | |
CN215252400U (en) | Self-supporting synchronous hanger system for corrugated steel web construction | |
CN109702396A (en) | Box-type room top frame bottom frame welding production line | |
CN105332718A (en) | Trolley for construction of large-span multi-section tunnel | |
CN211547809U (en) | Pipe gallery is with supporting die carrier fast | |
CN218708558U (en) | Device for hoisting reinforcement cage in cantilever casting segment construction | |
CN209760294U (en) | Narrow corridor formwork supporting trolley with clear width smaller than 1.8M in corridor | |
CN208844612U (en) | A kind of stalk vaulted type open trench tunnel main body construction mobile formwork | |
CN204418034U (en) | Novel large-tonnage Bridge Erector | |
CN212867563U (en) | Tunnel super-large section two-lining trolley capable of being widened for multiple times | |
CN113152309A (en) | Self-supporting synchronous hanging bracket system for corrugated steel web construction and construction method | |
CN211874002U (en) | LED stage | |
CN209584868U (en) | A kind of sunpender underneath type Bridge Erector box beam | |
CN210767825U (en) | Turnover formwork construction system | |
CN207297033U (en) | A kind of Tunnel Second Lining A fonts trolley width tunable arrangement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |