CN108797642A - Prefabricated method piping lane installation vehicle and its install piping lane - Google Patents

Prefabricated method piping lane installation vehicle and its install piping lane Download PDF

Info

Publication number
CN108797642A
CN108797642A CN201810849735.XA CN201810849735A CN108797642A CN 108797642 A CN108797642 A CN 108797642A CN 201810849735 A CN201810849735 A CN 201810849735A CN 108797642 A CN108797642 A CN 108797642A
Authority
CN
China
Prior art keywords
piping lane
installation
vehicle
prefabricated
travelling bogie
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810849735.XA
Other languages
Chinese (zh)
Inventor
朱立雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201810849735.XA priority Critical patent/CN108797642A/en
Publication of CN108797642A publication Critical patent/CN108797642A/en
Priority to CN201910644823.0A priority patent/CN110206065A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells

Abstract

The invention discloses a kind of prefabricated method piping lane installation vehicle and its install piping lane, including installation vehicle, travelling bogie, installation vehicle is moved along attachment rail, and attachment rail is arranged in the prefabricated piping lane that installation is complete;Conveying track is set along the center line for being laid with piping lane, travelling bogie is set on conveying track, prefabricated piping lane to be installed is transported to installment work position by travelling bogie, and the front end for installing vehicle is equipped with mechanical arm, and installation vehicle accepts prefabricated piping lane to be installed by mechanical arm;Prefabricated piping lane to be installed is transported to installment work position by its installation method using travelling bogie, and docking and installation are completed using the installation vehicle being arranged in the prefabricated piping lane that installation is complete.Technical scheme of the present invention can reduce the use of crane in the installation process of prefabricated piping lane, and to the arrangement difficulty in periphery place, improve installation effectiveness, reduce installation cost.

Description

Prefabricated method piping lane installation vehicle and its install piping lane
Technical field
The present invention relates to prefabricated piping lane installation method, specifically a kind of prefabricated piping lane installation vehicle and its side for installing piping lane Method.
Background technology
Country greatly develops pipe gallery and assembled architecture at present, and thus prefabricated piping lane comes into being, outside prefabricated piping lane Shape size, perception are good, good water-proof effect.
Pipe gallery is generally lifted using Large-scale Hoisting equipment, higher to piping lane periphery site requirements, needs to follow Piping lane construction speed, processing periphery lift place, make that installation effectiveness is low, installation cost is high.
Invention content
It, can be with the technical problem to be solved in the present invention is to provide a kind of method prefabricated piping lane installation vehicle and its install piping lane The use of crane in prefabricated piping lane installation process is reduced, and to the arrangement difficulty in periphery place, improves installation effectiveness, reduce peace Dress up this.
In order to solve the above technical problems, the present invention adopts the following technical scheme that:
A kind of prefabricated piping lane installation vehicle, including installation vehicle, travelling bogie, the installation vehicle are moved along attachment rail, mounting rail Road is arranged in the prefabricated piping lane that installation is complete;Conveying track is set along the center line for being laid with piping lane, is arranged on conveying track Prefabricated piping lane to be installed is transported to installment work position by travelling bogie, travelling bogie, and the front end for installing vehicle is equipped with mechanical arm, peace Prefabricated piping lane to be installed is accepted in entrucking by mechanical arm.
Vehicle, travelling bogie are installed by setting, prefabricated piping lane to be installed is transported to installment work using travelling bogie Docking and installation are completed in position using the installation vehicle being arranged in the prefabricated piping lane that installation is complete.
Using the present invention of above-mentioned technical proposal, compared with prior art, the feature protruded is:
(1)Installation vehicle moves in mounted prefabricated piping lane, and periphery place will not be damaged or be destroyed in installation process.
(2)Travelling bogie is moved along the conveying track being laid with, and conveying track is overlapped with the pipeline circuit for being laid with piping lane, Periphery place will not be damaged or be destroyed.
(3)Installation process is quick and convenient, and piping lane to be installed is transported to installment work position by travelling bogie, and installation vehicle stretches out machine Tool arm increases mechanical arm, piping lane to be installed is unloaded from travelling bogie, adjusts the height of mechanical arm and the position of left and right, makes Piping lane to be installed installation is fixed after dock with mounted initial piping lane completion and completes installation by piping lane to be installed, compared to hanging Vehicle lifting reduces the abutting joint time, improves installation effectiveness, reduces installation cost.
Further preferred embodiment is:
The top surface of the mechanical arm is equipped with rubber soft-jointing contacting surface.By the way that rubber soft-jointing contacting surface is arranged, installation vehicle can be made to accept When prefabricated piping lane to be installed, prevent from damaging the prefabricated piping lane of installation.
The method of prefabricated piping lane installation vehicle installation piping lane, comprises the steps of:
(1)Install the initial piping lane of first segment;
(2)It is laid with attachment rail in mounted piping lane, installation vehicle is set on attachment rail;
(3)Conveying track is set along the center line for being laid with piping lane, travelling bogie is set on conveying track;
(4)Piping lane to be installed is loaded on travelling bogie, piping lane to be installed is transported to by travelling bogie along conveying track Before mounted initial piping lane;
(5)Vehicle is installed and stretches out mechanical arm, mechanical arm is increased, piping lane to be installed is unloaded from travelling bogie, adjusts mechanical arm Piping lane to be installed is installed after so that piping lane to be installed is docked with mounted initial piping lane completion and is fixed by the position of height and left and right It is good;
(6)The continued access attachment rail in the piping lane that installation fixes makes installation carriage enter in the piping lane that installation fixes;
(7)Repeat step(4)—(5)Continue installment work, until completing piping lane installation.
Description of the drawings
Fig. 1 is the installation vehicle side view of the embodiment of the present invention;
Fig. 2 is the vertical view of Fig. 1;
Fig. 3 is the side view for installing vehicle, attachment rail and travelling bogie, conveying track;
Fig. 4 is the vertical view of Fig. 3;
Reference sign:11, rubber soft-jointing contacting surface;12, mechanical arm;13, vehicle is installed;14, attachment rail;21, installation is complete Prefabricated piping lane;23, the prefabricated piping lane installed;25, prefabricated piping lane to be installed;26, travelling bogie;27, conveying track.
Specific implementation mode
With reference to the accompanying drawings and embodiments, it further illustrates the present invention.
Referring to Fig. 1 to Fig. 4, a kind of prefabricated piping lane installation vehicle is made of installation vehicle 13, travelling bogie 26;The installation Vehicle 13 is moved along attachment rail 14, and attachment rail 14 is arranged in the prefabricated piping lane 21 that installation is complete;Along the center for being laid with piping lane Conveying track 27 is arranged in line, travelling bogie 26 is arranged on conveying track 27, travelling bogie 26 transports prefabricated piping lane 25 to be installed It is sent to installment work position, the front end of installation vehicle 13 is equipped with mechanical arm 12, and installation vehicle 13 is accepted to be installed pre- by mechanical arm 12 Tubulation corridor 25.
Prefabricated piping lane 25 to be installed is transported to installment work position by travelling bogie 26, using being arranged installation is complete Installation vehicle 13 in prefabricated piping lane 21 completes docking and installation.
The top surface of mechanical arm 12 is equipped with rubber soft-jointing contacting surface 11, and rubber soft-jointing contacting surface 11 can be such that installation vehicle 13 accepts to wait pacifying When the prefabricated piping lane 25 of dress, prevent from damaging the prefabricated piping lane of installation.
The method for installing piping lane using prefabricated piping lane installation vehicle, carries out according to the following steps:
(1)Install the initial piping lane of first segment;
(2)It is laid with attachment rail 14 in mounted piping lane, installation vehicle 13 is set on attachment rail 14;
(3)Conveying track 27 is set along the center line for being laid with piping lane, travelling bogie 26 is set on conveying track 27;
(4)Piping lane to be installed is loaded on travelling bogie 26, travelling bogie 26 is defeated by piping lane to be installed along conveying track 27 Before being sent to mounted initial piping lane;
(5)Vehicle 13 is installed and stretches out mechanical arm 12, mechanical arm 12 is increased, piping lane to be installed is unloaded from travelling bogie 26, is adjusted The height of mechanical arm 12 and the position of left and right, by pipe to be installed after making piping lane to be installed be docked with mounted initial piping lane completion Corridor installation fixes;
(6)The continued access attachment rail 14 in the piping lane that installation fixes makes installation carriage enter in the piping lane that installation fixes;
(7)Repeat step(4)—(5)Continue installment work, until completing piping lane installation.
(1)Installation vehicle 13 moves in mounted prefabricated piping lane, will not be damaged to periphery place in installation process Or it destroys.
(2)Travelling bogie 26 is moved along the conveying track 27 of laying, and conveying track 27 is with the pipeline circuit for being laid with piping lane It overlaps, periphery place will not be damaged or be destroyed.
(3)Installation process is quick and convenient, and piping lane to be installed is transported to installment work position by travelling bogie 26, and installation vehicle 13 is stretched Go out mechanical arm 12, increase mechanical arm 12, piping lane to be installed is unloaded from travelling bogie 26, adjusts height and the left side of mechanical arm 12 Piping lane to be installed installation is fixed after so that piping lane to be installed is docked with mounted initial piping lane completion and is completed by right position Installation, reduces the abutting joint time compared to crane lifting, improves installation effectiveness, reduce installation cost.
The foregoing is merely preferably feasible embodiments of the invention, not thereby limit to the interest field of the present invention, It is all to change with equivalent structure made by description of the invention and accompanying drawing content, it is both contained within the interest field of the present invention.

Claims (3)

1. a kind of prefabricated piping lane installs vehicle, including installation vehicle, travelling bogie, it is characterised in that:The installation vehicle is along mounting rail Road moves, and attachment rail is arranged in the prefabricated piping lane that installation is complete;Along the center line for being laid with piping lane, conveying track, fortune are set Travelling bogie is set on defeated track, and prefabricated piping lane to be installed is transported to installment work position, installs the front end of vehicle by travelling bogie Equipped with mechanical arm, installation vehicle accepts prefabricated piping lane to be installed by mechanical arm.
2. prefabricated piping lane according to claim 1 installs vehicle, it is characterised in that:The top surface of the mechanical arm is equipped with rubber Soft contact surface.
3. a kind of method of prefabricated piping lane installation vehicle installation piping lane described in claim 1, which is characterized in that include following step Suddenly:
(1)Install the initial piping lane of first segment;
(2)It is laid with attachment rail in mounted piping lane, installation vehicle is set on attachment rail;
(3)Conveying track is set along the center line for being laid with piping lane, travelling bogie is set on conveying track;
(4)Piping lane to be installed is loaded on travelling bogie, piping lane to be installed is transported to by travelling bogie along conveying track Before mounted initial piping lane;
(5)Vehicle is installed and stretches out mechanical arm, mechanical arm is increased, piping lane to be installed is unloaded from travelling bogie, adjusts mechanical arm Piping lane to be installed is installed after so that piping lane to be installed is docked with mounted initial piping lane completion and is fixed by the position of height and left and right It is good;
(6)The continued access attachment rail in the piping lane that installation fixes makes installation carriage enter in the piping lane that installation fixes;
(7)Repeat step(4)—(5)Continue installment work, until completing piping lane installation.
CN201810849735.XA 2018-07-28 2018-07-28 Prefabricated method piping lane installation vehicle and its install piping lane Withdrawn CN108797642A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201810849735.XA CN108797642A (en) 2018-07-28 2018-07-28 Prefabricated method piping lane installation vehicle and its install piping lane
CN201910644823.0A CN110206065A (en) 2018-07-28 2019-07-17 Prefabricated method piping lane installation vehicle and its install piping lane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810849735.XA CN108797642A (en) 2018-07-28 2018-07-28 Prefabricated method piping lane installation vehicle and its install piping lane

Publications (1)

Publication Number Publication Date
CN108797642A true CN108797642A (en) 2018-11-13

Family

ID=64078549

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201810849735.XA Withdrawn CN108797642A (en) 2018-07-28 2018-07-28 Prefabricated method piping lane installation vehicle and its install piping lane
CN201910644823.0A Pending CN110206065A (en) 2018-07-28 2019-07-17 Prefabricated method piping lane installation vehicle and its install piping lane

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201910644823.0A Pending CN110206065A (en) 2018-07-28 2019-07-17 Prefabricated method piping lane installation vehicle and its install piping lane

Country Status (1)

Country Link
CN (2) CN108797642A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482045A (en) * 2021-07-21 2021-10-08 中交二公局第六工程有限公司 Traction type pipe gallery installation method
CN114855873A (en) * 2022-04-18 2022-08-05 济南城建集团有限公司 Semi-segment type tramcar prefabricating and assembling construction method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638687B (en) * 2016-11-16 2018-12-14 吉林省天祥建筑材料有限公司 A kind of accurate quick-assembling technique of precast assembly pipe gallery
CN107460888B (en) * 2017-09-07 2023-09-08 鞍山三冶建筑工程有限公司 Mounting structure and method for concrete prefabricated pipe gallery

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482045A (en) * 2021-07-21 2021-10-08 中交二公局第六工程有限公司 Traction type pipe gallery installation method
CN114855873A (en) * 2022-04-18 2022-08-05 济南城建集团有限公司 Semi-segment type tramcar prefabricating and assembling construction method

Also Published As

Publication number Publication date
CN110206065A (en) 2019-09-06

Similar Documents

Publication Publication Date Title
CN108797642A (en) Prefabricated method piping lane installation vehicle and its install piping lane
CN105317008B (en) A kind of Integral lifting method of steel truss girder cable-stayed bridge steel truss girder segment
CN107905253A (en) A kind of piping lane segment mounting process
CN106207812B (en) Installation method in rigid gas insulated power route tunnel
JP5852520B2 (en) Material conveying device and material conveying method
CN108190458A (en) A kind of double-layer lifting rotary rolling machine
CN107867550A (en) A kind of automatic turning coil car
CN205574095U (en) Sufficient dual purpose robot of wheel
CN108582445B (en) Segment water culture conveying system and method
CN103742160A (en) Mounting device for upper structure in tunnel
CN107060432A (en) A kind of vehicle-carrying plate modified rear cantilever type two-layer lift-sliding parking systems
CN104180658B (en) A kind of installation method of sintering machine dust pelletizing system
CN109706856B (en) Box culvert assembling method and device, processor and memory
CN109748049A (en) A kind of auxiliary transfer device for rail above and below equipment
CN108382540A (en) Barge disembarkation, launching method
CN210263138U (en) Prefabricated piping lane installation car
CN107724425A (en) The mechanized construction equipment and construction method of a kind of prefabricated pipe gallery
CN112376464A (en) Automatic mounting robot for safety guardrail of highway
JP2007231560A (en) Equipment and method for conveying segment
CN204053312U (en) A kind of steel pipe assembly welding device
CN205046150U (en) Seal elbow auto -change over device of duplex position vacuum refining system
JP4065445B2 (en) Cart for conveying and installing cylindrical blocks
CN210635590U (en) Scrap steel moving device and scrap steel treatment system with same
CN105502144B (en) Marine soft pipe placing lifting frame and implementation method thereof
CN207062906U (en) A kind of pressure steel pipe of hydropower station transport and mounting and adjusting bracket system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20181113

WW01 Invention patent application withdrawn after publication