CN210263138U - Prefabricated piping lane installation car - Google Patents

Prefabricated piping lane installation car Download PDF

Info

Publication number
CN210263138U
CN210263138U CN201921120004.8U CN201921120004U CN210263138U CN 210263138 U CN210263138 U CN 210263138U CN 201921120004 U CN201921120004 U CN 201921120004U CN 210263138 U CN210263138 U CN 210263138U
Authority
CN
China
Prior art keywords
installation
piping lane
prefabricated
vehicle
pipe gallery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921120004.8U
Other languages
Chinese (zh)
Inventor
朱立雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Application granted granted Critical
Publication of CN210263138U publication Critical patent/CN210263138U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a prefabricated pipe gallery installation vehicle, which comprises an installation vehicle and a transport trolley, wherein the installation vehicle moves along an installation track, and the installation track is arranged in a prefabricated pipe gallery after installation; set up the transportation track along the central line of laying the piping lane, set up the travelling bogie on the transportation track, the prefabricated piping lane that the travelling bogie will treat the installation transports installation work position, and the front end of installing vehicle is equipped with the arm, and the installing vehicle holds the prefabricated piping lane of treating the installation through the arm. The utility model discloses utilize the travelling bogie will treat the prefabricated piping lane of installation and carry installation work position, utilize the installation vehicle of setting in the prefabricated piping lane of having installed completion to accomplish butt joint and installation, can reduce the use of crane in the installation of prefabricated piping lane to and the arrangement degree of difficulty in peripheral place, improve the installation effectiveness, reduce installation cost.

Description

Prefabricated piping lane installation car
Technical Field
The utility model relates to a prefabricated piping lane erection equipment specifically is a prefabricated piping lane installation car.
Background
At present, the state vigorously develops the comprehensive pipe gallery and the assembly type building, and the prefabricated pipe gallery is suitable for transportation, and has good appearance size, good appearance and good waterproof effect.
The utility tunnel generally adopts large-scale hoisting equipment to hoist, and the peripheral place of piping lane requires highly, need follow the piping lane construction progress, handles peripheral hoist and mount place, makes installation effectiveness low, installation cost high.
SUMMERY OF THE UTILITY MODEL
The to-be-solved technical problem of the utility model is to provide a prefabricated piping lane installation car can reduce the use of crane in the prefabricated piping lane installation to and the arrangement degree of difficulty in peripheral place, improve the installation effectiveness, reduce installation cost.
In order to solve the technical problem, the utility model adopts the following technical scheme:
a prefabricated pipe gallery installation vehicle comprises an installation vehicle and a transport trolley, wherein the installation vehicle moves along an installation rail, and the installation rail is arranged in an installed prefabricated pipe gallery; set up the transportation track along the central line of laying the piping lane, set up the travelling bogie on the transportation track, the prefabricated piping lane that the travelling bogie will treat the installation transports installation work position, and the front end of installing vehicle is equipped with the arm, and the installing vehicle holds the prefabricated piping lane of treating the installation through the arm.
Through setting up installation vehicle, travelling bogie, utilize the travelling bogie will treat the prefabricated piping lane of installation and carry installation work position, utilize the installation vehicle of setting in the prefabricated piping lane of having installed completion to accomplish butt joint and installation.
Adopt above-mentioned technical scheme the utility model discloses, compare with prior art, its outstanding characteristics are:
(1) the installation car moves in the prefabricated piping lane of installation, can not cause damage or destruction to peripheral place in the installation.
(2) The travelling bogie moves along the laid travelling rail, and the travelling rail and the pipeline line for laying the pipe gallery are superposed, so that the peripheral field cannot be damaged or destroyed.
(3) The installation is convenient fast, and the travelling bogie will treat that the installation piping lane carries installation work position, and the installation vehicle stretches out the arm, risees the arm, will treat that the installation piping lane is lifted off from the travelling bogie, and the height of adjustment arm reaches the position about, makes and treats that the installation piping lane will treat that the installation piping lane installation is fixed after accomplishing the butt joint with the initial piping lane of installing and accomplish the installation promptly, compares the crane hoist and mount and has reduced the butt joint installation time, has improved the installation effectiveness, has reduced installation cost.
The further preferred scheme is as follows:
the top surface of the mechanical arm is provided with a rubber soft contact surface. Through setting up the soft contact surface of rubber, can make the installation vehicle accept when treating the prefabricated piping lane of installation, prevent to cause the damage to the prefabricated piping lane of installation.
Drawings
Fig. 1 is a side view of an installation vehicle, an installation rail, a transport trolley and a transport rail according to an embodiment of the present invention;
FIG. 2 is a schematic view of a piping lane installation process;
description of reference numerals: 1-a transportation track; 2-transporting the trolley; 3-a prefabricated pipe gallery to be installed; 4-cantilever beam supporting; 5-lifting support; 6-hydraulic jack; 7-rubber soft contact surface; 8, mounting a vehicle; 9-driving device and counterweight; 10-mounting a rail; 11-installing the completed prefabricated pipe gallery.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and examples.
Referring to fig. 1, a prefabricated pipe gallery installation vehicle is composed of an installation vehicle 8, a transport trolley 2 and a track; the mounting vehicle 8 moves along a mounting rail 10, and the mounting rail 10 is arranged in the mounted prefabricated pipe gallery 11; set up transportation track 1 along the central line of laying the piping lane, set up travelling bogie 2 on the transportation track 1, prefabricated piping lane 3 that travelling bogie 2 will treat the installation transports installation work position, and the front end of installing vehicle 8 is equipped with the arm, and installing vehicle 8 holds the prefabricated piping lane 3 of treating the installation through the arm.
The mechanical arm 3 described in this embodiment is composed of a cantilever beam support 4, a lifting support 5 and a hydraulic jack 6, the cantilever beam support 4 is fixed with an installation vehicle 8, the lifting support 5 is installed on the upper portion of the cantilever beam support 4 through the hydraulic jack 6, and the hydraulic jack 6 drives the lifting support 5 to lift or descend.
The top surface of arm is lifting support 5's top surface promptly and is equipped with soft contact surface of rubber 7, and soft contact surface of rubber 7 can make installation vehicle 8 accept when waiting the prefabricated piping lane 3 of installation, prevents to treat that prefabricated piping lane 3 of installation from causing the damage.
The transport trolley 2 conveys the prefabricated pipe gallery 3 to be installed to an installation working position, and the installation vehicle 8 arranged in the installed prefabricated pipe gallery 11 is used for completing butt joint and installation.
Referring to fig. 2, specifically, the method for installing the pipe gallery by using the prefabricated pipe gallery installation vehicle comprises the following steps:
(1) installing an initial pipe gallery of the first section;
(2) laying an installation rail 10 in the installed pipe gallery, and arranging an installation vehicle 8 on the installation rail 10; the mounting vehicle 8 is provided with a driving device and a balance weight 9 and can move forwards or backwards automatically;
(3) a transportation track 1 is arranged along the central line of the laying pipe gallery, and a transportation trolley 2 is arranged on the transportation track 1; the transport trolley 2 of the pipe gallery is provided with a driving device and can automatically advance or retreat;
(4) loading (hoisting) a prefabricated pipe gallery 3 to be installed onto a transport trolley 2, and conveying the prefabricated pipe gallery 3 to be installed to the front end of an installed initial pipe gallery by the transport trolley 2 along a transport rail 1;
(5) the mounting vehicle 8 moves forwards, the cantilever beam support 4 is inserted into the prefabricated pipe gallery 3 to be mounted, the hydraulic jack 6 is started, the lifting support 5 is lifted, the prefabricated pipe gallery 3 to be mounted is jacked, the prefabricated pipe gallery 3 to be mounted is dismounted from the transport trolley 2, the height of the hydraulic jack 6 is adjusted, the prefabricated pipe gallery 3 to be mounted and the prefabricated pipe gallery 11 which is mounted are butted, the prefabricated pipe gallery 3 to be mounted is fixed, and one section of pipe gallery is mounted;
(6) continuously laying an extended installation track 10 in the section of the installed and fixed pipe gallery to enable the installation vehicle 8 to enter the installed and fixed pipe gallery;
(7) and (5) transporting the next section of the prefabricated pipe gallery 3 to be installed by the transport trolley 2, repeating the step (4) -the step (5), and continuing to install until the pipe gallery is installed.
The above description is only a preferred and practical embodiment of the present invention, and not intended to limit the scope of the present invention, and all structural equivalents made by using the contents of the specification and drawings are included in the scope of the present invention.

Claims (2)

1. The utility model provides a prefabricated piping lane installation car, includes installation car, travelling bogie, its characterized in that: the mounting vehicle moves along a mounting rail, and the mounting rail is arranged in the mounted prefabricated pipe gallery; set up the transportation track along the central line of laying the piping lane, set up the travelling bogie on the transportation track, the prefabricated piping lane that the travelling bogie will treat the installation transports installation work position, and the front end of installing vehicle is equipped with the arm, and the installing vehicle holds the prefabricated piping lane of treating the installation through the arm.
2. The prefabricated pipe gallery installation vehicle of claim 1, wherein: the top surface of the mechanical arm is provided with a rubber soft contact surface.
CN201921120004.8U 2018-07-28 2019-07-17 Prefabricated piping lane installation car Active CN210263138U (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2018212085818 2018-07-28
CN201821208581 2018-07-28

Publications (1)

Publication Number Publication Date
CN210263138U true CN210263138U (en) 2020-04-07

Family

ID=70012913

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921120004.8U Active CN210263138U (en) 2018-07-28 2019-07-17 Prefabricated piping lane installation car

Country Status (1)

Country Link
CN (1) CN210263138U (en)

Similar Documents

Publication Publication Date Title
CN104762882A (en) Bridge segment lifting device and method
CN111038940A (en) Rail mounted is used for hoist and mount traction system of transportation
CN210510510U (en) Fine adjustment aligning device for axes of pipeline thermal pipeline
CN202220327U (en) Moving pulley of side web plate of full space support cast-in-place box beam
CN109112963B (en) Bridge hoisting equipment
CN210263138U (en) Prefabricated piping lane installation car
CN110206065A (en) Prefabricated method piping lane installation vehicle and its install piping lane
JP4508073B2 (en) Method and system for transporting and loading heavy objects
CN113818478B (en) Overweight prefabricated pipe gallery installation system and construction method thereof
JP5292019B2 (en) Pile construction device and cast-in-place concrete pile construction method
JP2008303657A (en) Girder installation apparatus and girder installation carriage
CN110904861A (en) Cable-stayed bridge girder erection crane and construction method thereof
JP3884689B2 (en) Mobile trolley for erection of members and bridge member erection method using the same
CN112357821B (en) PCCP spiral welding and water pressure inspection automatic assembly line and application method thereof
CN209974209U (en) BOP shifting and transporting device
CN204551280U (en) Bridge subsection hanging apparatus
CN204982676U (en) Conveyer is assembled on steel purlin girder segment section ground
CN109083013B (en) Bridge hoisting method
JP2006028734A (en) Launching erection method for bridge girder, using traveling staging
CN113022745A (en) Horizontal transportation tool for steam turbine condenser and application method thereof
CN213169974U (en) Horizontal transportation and translation tool for large equipment in factory building
CN219214997U (en) Flat-plate transport vehicle for installing reaction kettle
JPS63210304A (en) Method and apparatus for constructing bridge
CN114060064B (en) Defective highway tunnel numerical control steel belt reinforcing trolley
CN215439345U (en) Transportation device for pressure steel pipes under complex terrain conditions

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant