CN108717623A - A kind of assembled architecture tracks of device, method and system based on BIM - Google Patents
A kind of assembled architecture tracks of device, method and system based on BIM Download PDFInfo
- Publication number
- CN108717623A CN108717623A CN201810480856.1A CN201810480856A CN108717623A CN 108717623 A CN108717623 A CN 108717623A CN 201810480856 A CN201810480856 A CN 201810480856A CN 108717623 A CN108717623 A CN 108717623A
- Authority
- CN
- China
- Prior art keywords
- bim
- prefabricated components
- real
- assembled architecture
- time
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title abstract description 20
- 238000009434 installation Methods 0.000 claims abstract description 25
- 238000004519 manufacturing process Methods 0.000 claims abstract description 19
- 238000007726 management method Methods 0.000 abstract description 27
- 238000005516 engineering process Methods 0.000 abstract description 6
- 238000002834 transmittance Methods 0.000 abstract description 5
- 239000003086 colorant Substances 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 235000013399 edible fruits Nutrition 0.000 description 2
- 230000002035 prolonged effect Effects 0.000 description 2
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06K—GRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
- G06K17/00—Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
- G06K17/0022—Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- Economics (AREA)
- General Business, Economics & Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Data Mining & Analysis (AREA)
- General Engineering & Computer Science (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention relates to assembled architecture technical fields, disclose a kind of assembled architecture tracks of device, method and system based on BIM, which includes:Prefabricated components, two-dimension code label and real-time inductor, the two-dimension code label and the real-time inductor are fixed on the prefabricated components, the real-time inductor is used to obtain the real time status information of the prefabricated components, and the real time status information is uploaded to tracing management platform;Based on Quick Response Code and BIM technology, it being capable of real-time collecting the development of projects situation, investment situation, monitor production status, travel position and the installation condition of prefabricated components, the real-time status of component can be illustrated on model, if inevitably mistake occurs for engineering project, policymaker can obtain information in time by platform, convenient for improving efficiency to next step decision, cost is reduced, loss of the information in transmittance process is reduced.
Description
Technical field
The present invention relates to assembled architecture technical fields more particularly to a kind of assembled architecture based on BIM to track dress
It sets, method and system.
Background technology
Currently, assembled architecture develop at home it is like a raging fire.It is given birth in pre-fabricated factory specifically, assembled architecture refers to
Production is completed, and by logistics transportation to scene, finally completes the overall process of assembly.But existing assembled architecture management method is difficult
To realize full-range real-time tracing.
Invention content
It is a primary object of the present invention to propose a kind of assembled architecture tracks of device, method and system based on BIM,
Based on Quick Response Code and BIM technology, can real-time collecting the development of projects situation, investment situation, monitor the production shape of prefabricated components
The real-time status of state, travel position and installation condition, component can be illustrated on model, if engineering project generation can not be kept away
When the mistake exempted from, policymaker can obtain information in time by platform, convenient for improving efficiency to next step decision, reduce cost,
Reduce loss of the information in transmittance process.
To achieve the above object, a kind of assembled architecture tracks of device based on BIM provided by the invention, including:It is prefabricated
Component, two-dimension code label and real-time inductor, the two-dimension code label and the real-time inductor are fixed on the prefabricated components
On, the real-time inductor is used to obtain the real time status information of the prefabricated components, and the real time status information is uploaded
To tracing management platform.
Optionally, further include plastic card sets, the two-dimension code label is set in the plastic card sets, the plastic clip
One end of set is connected on the prefabricated components, and the other end of the plastic card sets freely hangs.
Optionally, it is stored with transit information on the two-dimension code label.
Optionally, the transit information includes:Transportation route, storage position, transfer position and the purpose of prefabricated components
Ground.
Optionally, the real time status information includes:It does not install, installing, installation is complete and late instalment.
As another aspect of the present invention, a kind of assembled architecture tracking based on BIM provided, including:
BIM models are established, prefabricated components are generated by BIM models;
Generation and the one-to-one two-dimension code label of the prefabricated components, the two-dimension code label are fixed on described pre-
On component processed;It is stored with transit information on the two-dimension code label;
Traffic unit is transported according to the transit information, and transit information is uploaded to tracing management platform;
Prefabricated components are assembled after arriving at, and incude prefabricated components by the real-time inductor on prefabricated components
Real time status information, and the real time status information is uploaded to tracing management platform.
Optionally, the tracing management stage+module is on mobile terminals.
Optionally, the real time status information includes:It does not install, installing, installation is complete and late instalment.
As another aspect of the invention, a kind of assembled architecture tracking system based on BIM provided, including:Decision
Cockpit, BIM model online browses module, BIM model components load-on module, production management module, transportation management module and peace
Fill management module, wherein the decision cockpit, BIM model online browse modules and BIM model component load-on modules are used for
BIM models are established, and generate prefabricated components;The production management module is for producing the prefabricated components;The transportation management
Module is for transporting the prefabricated components;The installation management module is for installing the prefabricated components.
Optionally, further include:Manufacturing schedule view interface, production cost view interface, transport progress view interface, fortune
Defeated cost view interface, installation progress view interface and installation cost view interface.
A kind of assembled architecture tracks of device, method and system based on BIM proposed by the present invention, the tracks of device packet
It includes:Prefabricated components, two-dimension code label and real-time inductor, the two-dimension code label and the real-time inductor are fixed on described
On prefabricated components, the real-time inductor is used to obtain the real time status informations of the prefabricated components, and by the real-time status
Information is uploaded to tracing management platform;It, being capable of real-time collecting the development of projects situation, investment feelings based on Quick Response Code and BIM technology
Condition monitors the production status, travel position and installation condition of prefabricated components, and the real-time status of component can be illustrated on model,
If inevitably mistake occurs for engineering project, policymaker can obtain information in time by platform, convenient for next
It walks decision and improves efficiency, reduce cost, reduce loss of the information in transmittance process.
Description of the drawings
Fig. 1 is a kind of assembled architecture tracks of device structural schematic diagram based on BIM that the embodiment of the present invention one provides;
Fig. 2 is the two-dimension code label fixed structure chart that the embodiment of the present invention one provides;
Fig. 3 is a kind of assembled architecture tracking flow chart based on BIM provided by Embodiment 2 of the present invention;
Fig. 4 is a kind of demonstrative structure for assembled architecture tracking system based on BIM that the embodiment of the present invention three provides
Block diagram.
Wherein, the reference numeral of Fig. 2 is:1- prefabricated components, 2- plastic card sets, 3- two-dimension code labels.
The embodiments will be further described with reference to the accompanying drawings for the realization, the function and the advantages of the object of the present invention.
Specific implementation mode
It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to limit this hair
It is bright.
In subsequent description, using for indicating that the suffix of such as " module ", " component " or " unit " of element is only
Be conducive to the explanation of the present invention, itself there is no specific meanings.Therefore, " module " can mixedly make with " component "
With.
Embodiment one
As shown in Figure 1, in the present embodiment, a kind of assembled architecture tracks of device based on BIM, including:Prefabricated structure
Part, two-dimension code label and real-time inductor, the two-dimension code label and the real-time inductor are fixed on the prefabricated components
On, the real-time inductor is used to obtain the real time status information of the prefabricated components, and the real time status information is uploaded
To tracing management platform.
In the present embodiment, be based on Quick Response Code and BIM technology, can real-time collecting the development of projects situation, investment situation,
Production status, travel position and the installation condition of prefabricated components are monitored, the real-time status of component can be illustrated on model, such as
When inevitably mistake occurs for fruit engineering project, policymaker can obtain information in time by platform, convenient for determining in next step
Plan improves efficiency, reduces cost, reduces loss of the information in transmittance process.
As shown in Fig. 2, in the present embodiment, a kind of assembled architecture tracks of device based on BIM further includes plastic clip
Set, the two-dimension code label are set in the plastic card sets, and one end of the plastic card sets is connected to the prefabricated components
On, the other end of the plastic card sets freely hangs, and plastic card sets ensure that the integrality and safety of two-dimension code label information
Property.
In the present embodiment, it is stored with transit information on the two-dimension code label.
In the present embodiment, the transit information includes:The transportation routes of prefabricated components, storage position, transfer position and
Destination.
In the present embodiment, the real time status information includes:It does not install, installing, installation is complete and installation is prolonged
Accidentally;And indicate status information in different colors on tracing management platform, such as:It is blue not install color, is being installed as
Green, it is grey that installation is complete, and late instalment is red.
Embodiment two
As shown in figure 3, in the present embodiment, a kind of assembled architecture tracking based on BIM, including:
S10, BIM models are established, prefabricated components is generated by BIM models;
S20, generation and the one-to-one two-dimension code label of the prefabricated components, institute is fixed on by the two-dimension code label
It states on prefabricated components;It is stored with transit information on the two-dimension code label;
S30, traffic unit are transported according to the transit information, and transit information is uploaded to tracing management platform;
S40, prefabricated components are assembled after arriving at, and are incuded by the real-time inductor on prefabricated components prefabricated
The real time status information of component, and the real time status information is uploaded to tracing management platform.
In the present embodiment, be based on Quick Response Code and BIM technology, can real-time collecting the development of projects situation, investment situation,
Production status, travel position and the installation condition of prefabricated components are monitored, the real-time status of component can be illustrated on model, such as
When inevitably mistake occurs for fruit engineering project, policymaker can obtain information in time by platform, convenient for determining in next step
Plan improves efficiency, reduces cost, reduces loss of the information in transmittance process.
In the present embodiment, the tracing management platform APP is mounted on the mobile terminals such as mobile phone, tablet;APP's obtains
Take mode that can be downloaded with corresponding Quick Response Code below scan tracing management platform;Corresponding function item is clicked in mobile phone terminal
Afterwards, data real-time delivery is realized to tracking system, and the administrative staff of tracking system just can be appreciated that the progresses in real time feelings of project
Condition can be that owner, component production unit, traffic unit and site operation unit progress permission are set after administrative staff log in
It sets, different assembled management units, into corresponding administration interface, to reach the management work to prefabricated member.
In the present embodiment, the real time status information includes:It does not install, installing, installation is complete and installation is prolonged
Accidentally;And indicate status information in different colors on tracing management platform, such as:It is blue not install color, is being installed as
Green, it is grey that installation is complete, and late instalment is red.
Embodiment three
As shown in figure 4, in the present embodiment, a kind of assembled architecture tracking system based on BIM, including:Decision drives
Cabin, BIM model online browses module, BIM model components load-on module, production management module, transportation management module and installing pipe
Manage module, wherein the decision cockpit, BIM model online browse modules and BIM model component load-on modules are for establishing
BIM models, and generate prefabricated components;The production management module is for producing the prefabricated components;The transportation management module
For transporting the prefabricated components;The installation management module is for installing the prefabricated components.
In the present embodiment, further include:Manufacturing schedule view interface, production cost view interface, transport schedule view circle
Face, transportation cost view interface, installation progress view interface and installation cost view interface;Pass through above-mentioned view interface, tracking
The administrative staff of system just can be appreciated that the progresses in real time situation of project.
It should be noted that herein, the terms "include", "comprise" or its any other variant are intended to non-
It is exclusive to include, so that process, method, article or device including a series of elements include not only those elements,
But also include other elements that are not explicitly listed, or further include for this process, method, article or device institute
Intrinsic element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that
There is also other identical elements in process, method, article or device including the element.
The embodiments of the present invention are for illustration only, can not represent the quality of embodiment.
Through the above description of the embodiments, those skilled in the art can be understood that above-described embodiment
Method can add the mode of required general hardware platform to realize by software, naturally it is also possible to by hardware, but many situations
It is lower the former be more preferably embodiment.Based on this understanding, technical scheme of the present invention is substantially in other words to the prior art
The part to contribute can be expressed in the form of software products, which is stored in a storage and is situated between
In matter (such as ROM/RAM, magnetic disc, CD), including some instructions are used so that a station terminal equipment (can be mobile phone, calculate
Machine, server, air conditioner or network equipment etc.) execute method described in each embodiment of the present invention.
It these are only the preferred embodiment of the present invention, be not intended to limit the scope of the invention, it is every to utilize this hair
Equivalent structure or equivalent flow shift made by bright specification and accompanying drawing content, it is relevant to be applied directly or indirectly in other
Technical field is included within the scope of the present invention.
Claims (10)
1. a kind of assembled architecture tracks of device based on BIM, which is characterized in that including:Prefabricated components, two-dimension code label and reality
When inductor, the two-dimension code label and the real-time inductor be fixed on the prefabricated components, and the real-time inductor is used
In the real time status information of the acquisition prefabricated components, and the real time status information is uploaded to tracing management platform.
2. a kind of assembled architecture tracks of device based on BIM according to claim 1, which is characterized in that further include modeling
Expect that cutting ferrule, the two-dimension code label are set in the plastic card sets, one end of the plastic card sets is connected to the prefabricated structure
On part, the other end of the plastic card sets freely hangs.
3. a kind of assembled architecture tracks of device based on BIM according to claim 1, which is characterized in that the two dimension
It is stored with transit information on code label.
4. a kind of assembled architecture tracks of device based on BIM according to claim 3, which is characterized in that the transport
Information includes:Transportation route, storage position, transfer position and the destination of prefabricated components.
5. a kind of assembled architecture tracks of device based on BIM according to claim 1, which is characterized in that described real-time
Status information includes:It does not install, installing, installation is complete and late instalment.
6. a kind of assembled architecture tracking based on BIM, which is characterized in that including:
BIM models are established, prefabricated components are generated by BIM models;
Generation and the one-to-one two-dimension code label of the prefabricated components, the prefabricated components are fixed on by the two-dimension code label
On;It is stored with transit information on the two-dimension code label;
Traffic unit is transported according to the transit information, and transit information is uploaded to tracing management platform;
Prefabricated components are assembled after arriving at, and incude the real-time of prefabricated components by the real-time inductor on prefabricated components
Status information, and the real time status information is uploaded to tracing management platform.
7. a kind of assembled architecture tracking based on BIM according to claim 6, which is characterized in that the tracking
Management platform is installed on mobile terminals.
8. a kind of assembled architecture tracking based on BIM according to claim 6, which is characterized in that described real-time
Status information includes:It does not install, installing, installation is complete and late instalment.
9. a kind of assembled architecture tracking system based on BIM, which is characterized in that including:Decision cockpit, BIM models are online
Browsing module, BIM model components load-on module, production management module, transportation management module and installation management module, wherein institute
Decision cockpit, BIM model online browse modules and BIM model component load-on modules are stated for establishing BIM models, and is generated pre-
Component processed;The production management module is for producing the prefabricated components;The transportation management module is described prefabricated for transporting
Component;The installation management module is for installing the prefabricated components.
10. a kind of assembled architecture tracking system based on BIM according to claim 1, which is characterized in that further include:
Manufacturing schedule view interface, production cost view interface, transport progress view interface, transportation cost view interface, installation progress
View interface and installation cost view interface.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810480856.1A CN108717623A (en) | 2018-05-18 | 2018-05-18 | A kind of assembled architecture tracks of device, method and system based on BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810480856.1A CN108717623A (en) | 2018-05-18 | 2018-05-18 | A kind of assembled architecture tracks of device, method and system based on BIM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108717623A true CN108717623A (en) | 2018-10-30 |
Family
ID=63899959
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810480856.1A Pending CN108717623A (en) | 2018-05-18 | 2018-05-18 | A kind of assembled architecture tracks of device, method and system based on BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108717623A (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109460928A (en) * | 2018-11-14 | 2019-03-12 | 南通四建集团有限公司 | The prefabricated warehouse logistics control method of BIM electromechanical pipeline and device |
CN109636408A (en) * | 2018-11-02 | 2019-04-16 | 成都四平软件有限公司 | Build things system |
CN109784693A (en) * | 2018-12-29 | 2019-05-21 | 陕西铁路工程职业技术学院 | A kind of Three-Dimensional Dynamic production management system for prefabricated components field |
CN110457801A (en) * | 2019-07-30 | 2019-11-15 | 上海建工集团股份有限公司 | The monitoring method and system of assembled project component |
CN112613818A (en) * | 2020-12-24 | 2021-04-06 | 深圳大学 | Tracking method, device, equipment and storage medium of prefabricated part |
CN112950165A (en) * | 2021-03-10 | 2021-06-11 | 上海浩悟智能科技有限公司 | Pipeline digital production system based on BIM |
CN113489963A (en) * | 2021-07-08 | 2021-10-08 | 宁波宝贝第一母婴用品有限公司 | Method and device for guiding installation of cart |
CN113538661A (en) * | 2021-07-06 | 2021-10-22 | 万翼科技有限公司 | Information display method based on building model and related device |
CN114692271A (en) * | 2022-03-22 | 2022-07-01 | 中国建筑第二工程局有限公司 | BIM-based material progress display method |
CN114881392A (en) * | 2022-03-10 | 2022-08-09 | 中国建筑第二工程局有限公司 | Management method and system of assembled component |
WO2022257100A1 (en) * | 2021-06-09 | 2022-12-15 | 青岛理工大学 | Intelligent assembled building whole construction process simulation method based on bim and two-dimensional code |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105654318A (en) * | 2016-01-13 | 2016-06-08 | 上海振华重工(集团)股份有限公司 | Production internet of things management method |
CN105844336A (en) * | 2016-03-15 | 2016-08-10 | 杭州睿兴栋宇工程咨询有限公司 | BIM-based property management system and method |
CN106407570A (en) * | 2016-09-22 | 2017-02-15 | 南京航空航天大学 | An airplane assembling process online simulating optimization system |
CN106600239A (en) * | 2016-12-28 | 2017-04-26 | 中建科技有限公司 | Assembly type building construction full process data cooperation management system based on BIM |
CN208283963U (en) * | 2018-05-18 | 2018-12-25 | 深圳大学 | A kind of assembled architecture tracking device based on BIM |
-
2018
- 2018-05-18 CN CN201810480856.1A patent/CN108717623A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105654318A (en) * | 2016-01-13 | 2016-06-08 | 上海振华重工(集团)股份有限公司 | Production internet of things management method |
CN105844336A (en) * | 2016-03-15 | 2016-08-10 | 杭州睿兴栋宇工程咨询有限公司 | BIM-based property management system and method |
CN106407570A (en) * | 2016-09-22 | 2017-02-15 | 南京航空航天大学 | An airplane assembling process online simulating optimization system |
CN106600239A (en) * | 2016-12-28 | 2017-04-26 | 中建科技有限公司 | Assembly type building construction full process data cooperation management system based on BIM |
CN208283963U (en) * | 2018-05-18 | 2018-12-25 | 深圳大学 | A kind of assembled architecture tracking device based on BIM |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109636408A (en) * | 2018-11-02 | 2019-04-16 | 成都四平软件有限公司 | Build things system |
CN109460928A (en) * | 2018-11-14 | 2019-03-12 | 南通四建集团有限公司 | The prefabricated warehouse logistics control method of BIM electromechanical pipeline and device |
CN109784693A (en) * | 2018-12-29 | 2019-05-21 | 陕西铁路工程职业技术学院 | A kind of Three-Dimensional Dynamic production management system for prefabricated components field |
CN109784693B (en) * | 2018-12-29 | 2023-09-19 | 陕西铁路工程职业技术学院 | Three-dimensional dynamic production management system for prefabricated part field |
CN110457801A (en) * | 2019-07-30 | 2019-11-15 | 上海建工集团股份有限公司 | The monitoring method and system of assembled project component |
CN112613818A (en) * | 2020-12-24 | 2021-04-06 | 深圳大学 | Tracking method, device, equipment and storage medium of prefabricated part |
CN112950165A (en) * | 2021-03-10 | 2021-06-11 | 上海浩悟智能科技有限公司 | Pipeline digital production system based on BIM |
WO2022257100A1 (en) * | 2021-06-09 | 2022-12-15 | 青岛理工大学 | Intelligent assembled building whole construction process simulation method based on bim and two-dimensional code |
CN113538661A (en) * | 2021-07-06 | 2021-10-22 | 万翼科技有限公司 | Information display method based on building model and related device |
CN113489963A (en) * | 2021-07-08 | 2021-10-08 | 宁波宝贝第一母婴用品有限公司 | Method and device for guiding installation of cart |
CN113489963B (en) * | 2021-07-08 | 2024-02-23 | 宁波宝贝第一母婴用品有限公司 | Cart installation guiding method and device |
CN114881392A (en) * | 2022-03-10 | 2022-08-09 | 中国建筑第二工程局有限公司 | Management method and system of assembled component |
CN114692271A (en) * | 2022-03-22 | 2022-07-01 | 中国建筑第二工程局有限公司 | BIM-based material progress display method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108717623A (en) | A kind of assembled architecture tracks of device, method and system based on BIM | |
CN109978409B (en) | Multi-engineering enterprise-level intelligent construction site block chain management method | |
Ivanov et al. | Digital supply chain, smart operations and industry 4.0 | |
Porter et al. | How smart, connected products are transforming competition | |
KR101059061B1 (en) | Facility Integration System and Method for Smart Grid | |
CN105303306A (en) | Electric power material dispatching platform system | |
CN103544458A (en) | Two-dimensional code, RFID (radio frequency identification) and GPS (global positioning system) trinity based electrical product positioning system and positioning method thereof | |
CN103345165A (en) | Intelligent transportation hardware online simulation system of miniature intelligent vehicle group | |
CN109754190A (en) | Production management-control method, device, MES and storage medium based on MES | |
CN107454945A (en) | The navigation system of unmanned plane | |
CN104301862A (en) | Internet of Things information platform | |
Ivankova et al. | Internet of Things (IoT) in logistics | |
CN103241269A (en) | Comprehensive dispatching and control system of modern trams | |
CN106845809A (en) | A kind of engineering course line work dispatching method, system and device, dispatching system | |
CN107172047A (en) | The virtual augmented reality 3D interactive systems of factory and its implementation | |
CN110930111A (en) | APP (application) for unified management of physical assets and mobile operation | |
CN113888140A (en) | Mine auxiliary transportation intelligent management platform based on RFID technology | |
CN209785053U (en) | Visual management and control platform for material sampling inspection link | |
CN208283963U (en) | A kind of assembled architecture tracking device based on BIM | |
Feng et al. | An intelligent logistics management model in prefabricated construction | |
TW201824166A (en) | Service assembly system of software-defined drive cloud computing network component being worn by a client end for operation and establishing respective oriented input and output port interfaces and links | |
CN105631631A (en) | Novel logistics vehicle transportation way intelligent monitoring and management system | |
Cheung et al. | Digital Manufacturing Systems | |
CN111880462A (en) | Intelligent management and control platform for 'intelligent plus' distribution network without power outage | |
CN209296332U (en) | A kind of dry run device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |