CN108625594A - 一种超大转换梁分层分次浇筑施工方法 - Google Patents
一种超大转换梁分层分次浇筑施工方法 Download PDFInfo
- Publication number
- CN108625594A CN108625594A CN201810563326.3A CN201810563326A CN108625594A CN 108625594 A CN108625594 A CN 108625594A CN 201810563326 A CN201810563326 A CN 201810563326A CN 108625594 A CN108625594 A CN 108625594A
- Authority
- CN
- China
- Prior art keywords
- conversion beam
- divergence
- super large
- top layer
- conversion
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
本发明公开了一种超大转换梁分层分次浇筑施工方法,首先按照施工工艺要求浇筑底层转换梁,浇筑时,在底层转换梁的表面位置留设水平施工缝,并在水平施工缝上增设构造钢筋,同时在水平施工缝表面增设条状凹槽,待底层转换梁的混凝土强度达到80%以上时,在水平施工缝上浇筑顶层转换梁,待混凝土充分凝固后,这样便可是底层转换梁和顶层转换梁牢固地结合在一起,形成一个整体的超大转换梁。本发明能够运用普通钢管脚手架作为超大截面转换梁的支撑体系进行施工,且能够保证转换梁整体浇筑质量。
Description
技术领域
本发明涉及一种超大转换梁分层分次浇筑施工方法,属于建筑施工技术领域。
背景技术
随着经济的发展和施工工艺水平的提高,越来越多现代高层建筑在底层需要超大空间作为商场、大堂等,上层作为办公室、酒店等小空间需求的设计,带有转换层设计的高层建筑很好的解决了这一问题。但转换梁多数为超大截面尺寸,一次性浇筑混凝土对其下方模板支撑体系要求非常严格。往往使用普通钢管扣件式脚手架搭设会非常密,并且需要从基础一直回顶至转换层,导致工人操作难度非常大,且由于线荷载普遍会很大,危险系数非常高,容易对下层楼板产生结构破坏,用其他支撑方式造价又会大幅增加。因此,对传统超大转换梁施工方法的改进已迫在眉睫。
发明内容
本发明的目的在于,提供一种工艺简单、施工方便、能够能够提高施工工效的超大转换梁分层分次浇筑施工方法,该方法能够运用普通钢管脚手架作为超大截面转换梁的支撑体系进行施工,且能够保证转换梁整体浇筑质量。
本发明的技术方案:一种超大转换梁分层分次浇筑施工方法,首先按照施工工艺要求浇筑底层转换梁,浇筑时,在底层转换梁的表面位置留设水平施工缝,并在水平施工缝上增设构造钢筋,同时在水平施工缝表面增设条状凹槽,待底层转换梁的混凝土强度达到80%以上时,在水平施工缝上浇筑顶层转换梁,待混凝土充分凝固后,这样便可是底层转换梁和顶层转换梁牢固地结合在一起,形成一个整体的超大转换梁。
上述方法中,浇筑顶层转换梁的混凝土前,需要将水平施工缝表面凿毛并洒水养护。
由于采用上述技术方案,本发明的优点在于:本发明能够运用普通钢管脚手架作为超大截面转换梁的支撑体系进行施工,且能够保证转换梁整体浇筑质量。
附图说明
图1是本发明的结构示意图;
图2是底层转换梁的结构示意图。
附图标记说明:1-构造钢筋;2-条状凹槽;3-底层转换梁;4-顶层转换梁。
具体实施方式
为了使本发明的目的、技术方案和优点更加清楚,下面结合附图和实施例对本发明作进一步的详细说明。
本发明的实施例:参见图1及图2,本发明的一种超大转换梁分层分次浇筑施工方法,首先按照施工工艺要求浇筑底层转换梁3,浇筑时,在底层转换梁3的表面位置留设水平施工缝,并在水平施工缝上增设构造钢筋1,同时在水平施工缝表面增设条状凹槽2,待底层转换梁3的混凝土强度达到80%以上时,在水平施工缝上浇筑顶层转换梁4,浇筑顶层转换梁4的混凝土前,需要将水平施工缝表面凿毛并洒水养护,待混凝土充分凝固后,这样便可是底层转换梁3和顶层转换梁4牢固地结合在一起,形成一个整体的超大转换梁。
本发明不仅施工安全可靠,节约成本,而且能够运用普通钢管脚手架作为超大截面转换梁的支撑体系进行施工,对转换梁混凝土整体浇筑质量也有很好的保证。
Claims (2)
1.一种超大转换梁分层分次浇筑施工方法,其特征在于:首先按照施工工艺要求浇筑底层转换梁(3),浇筑时,在底层转换梁(3)的表面位置留设水平施工缝,并在水平施工缝上增设构造钢筋(1),同时在水平施工缝表面增设条状凹槽(2),待底层转换梁(3)的混凝土强度达到80%以上时,在水平施工缝上浇筑顶层转换梁(4),待混凝土充分凝固后,这样便可是底层转换梁(3)和顶层转换梁(4)牢固地结合在一起,形成一个整体的超大转换梁。
2.根据权利要求1所述的超大转换梁分层分次浇筑施工方法,其特征在于:浇筑顶层转换梁(4)的混凝土前,需要将水平施工缝表面凿毛并洒水养护。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810563326.3A CN108625594A (zh) | 2018-06-04 | 2018-06-04 | 一种超大转换梁分层分次浇筑施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810563326.3A CN108625594A (zh) | 2018-06-04 | 2018-06-04 | 一种超大转换梁分层分次浇筑施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108625594A true CN108625594A (zh) | 2018-10-09 |
Family
ID=63691330
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810563326.3A Pending CN108625594A (zh) | 2018-06-04 | 2018-06-04 | 一种超大转换梁分层分次浇筑施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108625594A (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20100050552A1 (en) * | 2007-04-02 | 2010-03-04 | Cfs Concrete Forming Systems Inc. | Methods and apparatus for providing linings on concrete structures |
CN102995613A (zh) * | 2012-12-17 | 2013-03-27 | 中国水电顾问集团贵阳勘测设计研究院 | 水电站厂房墙体与板梁分期浇筑的连接方法及结构 |
CN103628575A (zh) * | 2013-09-30 | 2014-03-12 | 中建三局建设工程股份有限公司 | 大高差变截面混凝土结构施工缝及其施工方法 |
CN104060703A (zh) * | 2014-06-19 | 2014-09-24 | 浙江勤业建工集团有限公司 | 高层建筑结构转换层中对水平施工缝的处置方法 |
CN107090918A (zh) * | 2017-06-16 | 2017-08-25 | 中国二十二冶集团有限公司 | 砼施工缝接茬施工方法 |
-
2018
- 2018-06-04 CN CN201810563326.3A patent/CN108625594A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20100050552A1 (en) * | 2007-04-02 | 2010-03-04 | Cfs Concrete Forming Systems Inc. | Methods and apparatus for providing linings on concrete structures |
CN102995613A (zh) * | 2012-12-17 | 2013-03-27 | 中国水电顾问集团贵阳勘测设计研究院 | 水电站厂房墙体与板梁分期浇筑的连接方法及结构 |
CN103628575A (zh) * | 2013-09-30 | 2014-03-12 | 中建三局建设工程股份有限公司 | 大高差变截面混凝土结构施工缝及其施工方法 |
CN104060703A (zh) * | 2014-06-19 | 2014-09-24 | 浙江勤业建工集团有限公司 | 高层建筑结构转换层中对水平施工缝的处置方法 |
CN107090918A (zh) * | 2017-06-16 | 2017-08-25 | 中国二十二冶集团有限公司 | 砼施工缝接茬施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204386002U (zh) | 一种装配式楼盖体系 | |
CN209443766U (zh) | 建筑用的浇灌模型 | |
CN105421632B (zh) | 捷约楼盖系统及其施工方法 | |
CN203247831U (zh) | 屋面穹顶圆弧结构模块 | |
CN101487293A (zh) | 梁柱节点不同强度等级混凝土浇筑方法 | |
CN101560803A (zh) | 一种钢筋混凝土桁架转换层结构施工方法 | |
CN109812620A (zh) | 一次性浇筑大口径钢管混凝土包封方法 | |
CN109372262A (zh) | 一种地下室模板支撑结构及施工方法 | |
CN206438529U (zh) | 梁板式筏型基础模板支撑结构 | |
CN108894483A (zh) | 一种悬挑结构支撑系统及其施工方法 | |
CN108086674A (zh) | 一种屋面板吊模及屋面板的施工方法 | |
CN213953189U (zh) | 一种保证预制水箱下锥壳表面平整的支撑装置 | |
CN203034799U (zh) | 塔吊标准节支承高空支模钢平台结构 | |
CN108625594A (zh) | 一种超大转换梁分层分次浇筑施工方法 | |
CN106930308A (zh) | 管桩与承台连接结构 | |
CN109537738A (zh) | 钢结构建筑现浇混凝土空腹楼盖自支承吊架支模工艺 | |
CN205153504U (zh) | 可拆卸式悬挑架体底座 | |
CN210658679U (zh) | 一种装配式柱梁连接结构 | |
CN207959532U (zh) | 一种墙板与连梁连接的结构 | |
CN106760189B (zh) | 高层建筑结构转换梁施工方法 | |
CN207749817U (zh) | 一种悬挑脚手架安装系统 | |
CN202850486U (zh) | 铝木结合梁受力模板体系 | |
CN206359993U (zh) | 用于主变防火墙的托柱结构 | |
CN207160358U (zh) | 一种新型桁架式组合楼板 | |
CN205955244U (zh) | 一种样板间外立面展示防护棚 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181009 |