CN108612270A - 装配式建筑的预制楼梯安装方法 - Google Patents

装配式建筑的预制楼梯安装方法 Download PDF

Info

Publication number
CN108612270A
CN108612270A CN201611137617.3A CN201611137617A CN108612270A CN 108612270 A CN108612270 A CN 108612270A CN 201611137617 A CN201611137617 A CN 201611137617A CN 108612270 A CN108612270 A CN 108612270A
Authority
CN
China
Prior art keywords
stair
place
control line
staircase boards
precast stair
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611137617.3A
Other languages
English (en)
Inventor
王名扬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201611137617.3A priority Critical patent/CN108612270A/zh
Publication of CN108612270A publication Critical patent/CN108612270A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/02Stairways; Layouts thereof

Abstract

本发明涉及装配式建筑。一种装配式建筑的预制楼梯安装方法,包括:完成本层两个休息平台含梯梁混凝土浇筑、养护,每层吊装两个预制楼梯板,预制楼梯板预埋内螺纹;在休息平台上划出安装位置,并根据休息平台完成面标高,在墙面上划出标高控制线;并复核;起吊:将吊装螺栓与楼梯板预埋的内螺纹连接,起吊楼梯段;就位:按照编号在设计位置就位,先找好楼梯板的平面控制线,再缓缓下降吊装就位;校正:基本就位后再用撬棍微调楼梯板,直到位置正确,搁置平实;校正后再脱钩;连接固定:将平台上的预埋螺杆套入楼梯板前端预留孔后用灌浆料填实;成品保护:楼梯安装后及时将踏步面加以保护。本发明有助提高安装楼梯的质量、降低工程造价、缩短工期。

Description

装配式建筑的预制楼梯安装方法
技术领域
本发明涉及装配式建筑,尤其涉及装配式建筑的预制楼梯。
背景技术
随着城市建设节能减排、可持续发展等环保政策的逐步明朗,装配式钢筋混凝土结构建筑迎来了可以健康发展的新机遇,装配式建筑将成为我国房屋建设的必然趋势。预制楼梯在建筑产业化中占有比较重要的地位,由于楼梯间的尺寸很好统一,使装配整体式楼梯能够率先进行大面积应用。采用预制楼梯施工技术代替传统的现浇楼梯,取得了明显的效果:现场加工制作工业化、机械化安装、效率高、成型质量好、尺寸误差小、施工进度快、不需二次装修、安装简便、安全性好,减少了现场浇筑楼梯施工的噪音、扬尘和漏洒,更环保,明显地降低了施工成本,具有良好的推广应用价值。
发明内容
本发明旨在解决上述缺陷,提供一种装配式建筑的预制楼梯安装方法。本发明有助提高安装楼梯的质量、降低工程造价、缩短工期。
为解决上述问题,一种装配式建筑的预制楼梯安装方法,它包括:
步骤一,完成本层两个休息平台含梯梁混凝土浇筑、养护,结构每上去一层吊装两个预制楼梯板,预制楼梯板预埋内螺纹;
步骤二,在休息平台上划出安装位置,即左右、前后控制线,并根据休息平台完成面标高,在墙面上划出标高控制线;对各控制线进行复核;
步骤三,起吊:将吊装螺栓与楼梯板预埋的内螺纹连接,起吊楼梯段;
步骤四,就位:按照编号在设计位置就位,先找好楼梯板的平面控制线,再缓缓下降吊装就位;
步骤五,校正:基本就位后再用撬棍微调楼梯板,直到位置正确,搁置平实;校正后再脱钩;
步骤六,连接固定:将平台上的预埋螺杆套入楼梯板前端预留孔后用灌浆料填实
步骤七,成品保护:楼梯安装后,及时将踏步面加以保护,避免将踏步棱角损坏。
所述的装配式建筑的预制楼梯安装方法,所述步骤五还包括:安装楼梯时,应特别注意标高正确,下口用砂浆或流动性好的灌浆料填实。
所述的灌浆料浇筑后保养1—3天抗压强度达30—50Mpa以上,且无收缩;
自流性高:可填充全部空隙,满足设备二次灌浆的要求。微膨胀性:保证设备与基础之间紧密接触,二次灌浆后无收缩。耐久性强:经上百次疲劳实验,50次冻融循环实验强度无明显变化。在机油中浸泡30天后强度明显提高。可冬季施工:允许在-10C气温进行室外施工。
本发明基本解决支模、绑扎钢筋、浇混凝土、拆模等,现场工序多,支撑量大,结构施工阶段楼梯很难通行,交房時需要加筋抹灰,部分项目需要贴砖,耗费大量人工,同时产生大量的建筑垃圾,支护桩位移后侵占结构、漏水等安全隐患的发生,节约了工时和人力资源的浪费,使得工期大幅度缩短,现场安装质量、效率大大提高。
具体实施方式
一种装配式建筑的预制楼梯安装方法,它包括:
步骤一,完成本层两个休息平台含梯梁混凝土浇筑、养护,结构每上去一层吊装两个预制楼梯板,预制楼梯板预埋内螺纹;
步骤二,在休息平台上划出安装位置,即左右、前后控制线,并根据休息平台完成面标高,在墙面上划出标高控制线;对各控制线进行复核;
步骤三,起吊:将吊装螺栓与楼梯板预埋的内螺纹连接,起吊楼梯段;
步骤四,就位:按照编号在设计位置就位,先找好楼梯板的平面控制线,再缓缓下降吊装就位;
步骤五,校正:基本就位后再用撬棍微调楼梯板,直到位置正确,搁置平实;校正后再脱钩;
步骤六,连接固定:将平台上的预埋螺杆套入楼梯板前端预留孔后用灌浆料填实
步骤七,成品保护:楼梯安装后,及时将踏步面加以保护,避免将踏步棱角损坏。
所述的装配式建筑的预制楼梯安装方法,所述步骤五还包括:安装楼梯时,应特别注意标高正确,下口用砂浆或流动性好的灌浆料填实。
混凝土预制楼梯较现场浇筑施工的楼梯更容易安装和调整。由于预制混凝土楼梯是在专业工厂制造,然后运送到施工现场安装。制造商将这些混凝土楼梯与霉菌,离开他们内部中空,而是以内外墙体仍然支持。1.易于设计当进行正常的一套具体的楼梯,建筑师必须仔细规划为结石的确切比例,并创建一个数字蓝图他们。如果有任何变化发生,需要移动或改变了楼梯,建筑师必须在一个耗时的过程,许多变化的楼梯。预制楼梯是用一个简单的计算机程序做,这样用户就可以改变大小和创建缺口或空隙的楼梯,甚至创建之前。2.速度工人并不需要设置预制混凝土楼梯复杂的框架,也不需等到天气是正确的,花必要的时间混合和浇筑混凝土。预制楼梯,因为他们的中空特征也比传统的版本更轻。这些因素结合起来,使比传统方法预制楼梯安装快得多。3.稳定由于预制混凝土楼梯被作为一个单独的组件制造,他们有一个稳定的设计,对于不安定移位,不亚于其他混凝土楼梯。如果预制楼梯做转移,他们的团结可以很容易地调整。没有裂缝和差距裂缝和空隙,为所有混凝土楼梯的麻烦。水分会渗入裂缝,陷入冻结与解冻,可以很容易损坏的混凝土,随着时间的推移。这些裂缝中生长,附着传统的混凝土楼梯的螺栓和接缝。混凝土预制楼梯没有这么多裂缝,因为他们的无缝设计。
本工法基本解决支模、绑扎钢筋、浇混凝土、拆模等,现场工序多,支撑量大,结构施工阶段楼梯很难通行,交房時需要加筋抹灰,部分项目需要贴砖,耗费大量人工,同时产生大量的建筑垃圾,支护桩位移后侵占结构、漏水等安全隐患的发生,节约了工时和人力资源的浪费,使得工期大幅度缩短,现场安装质量、效率大大提高。

Claims (3)

1.一种装配式建筑的预制楼梯安装方法,其特征在于,它包括:
步骤一,完成各层两个休息平台施工,包括梯梁混凝土浇筑、养护,每层吊装两个预制楼梯板,预制楼梯板预埋内螺纹;
步骤二,在休息平台上划出安装位置,即左右、前后控制线,并根据休息平台完成面标高,在墙面上划出标高控制线;对各控制线进行复核;
步骤三,起吊:将吊装螺栓与楼梯板预埋的内螺纹连接,起吊楼梯段;
步骤四,就位:按照编号在设计位置就位,先找好楼梯板的平面控制线,再缓缓下降吊装就位;
步骤五,校正:基本就位后再用撬棍微调楼梯板,直到位置正确,搁置平实;校正后再脱钩;
步骤六,连接固定:将平台上的预埋螺杆套入楼梯板前端预留孔后用灌浆料填实
步骤七,成品保护:楼梯安装后,及时将踏步面加以保护,避免将踏步棱角损坏。
2.根据权利要求1所述的装配式建筑的预制楼梯安装方法,其特征在于,所述步骤五还包括:安装楼梯时,应特别注意标高正确,下口用砂浆或流动性好的灌浆料填实。
3.根据权利要求2所述的装配式建筑的预制楼梯安装方法,其特征在于,所述流动性好的灌浆料浇筑后保养1—3天抗压强度达30—50Mpa以上,且无收缩;
自流性高:可填充全部空隙,满足设备二次灌浆的要求;
微膨胀性:保证设备与基础之间紧密接触,二次灌浆后无收缩;
耐久性强:经上百次疲劳实验,50次冻融循环实验强度无明显变化;在机油中浸泡30天后强度明显提高;
可冬季施工:允许在-10C气温进行室外施工。
CN201611137617.3A 2016-12-12 2016-12-12 装配式建筑的预制楼梯安装方法 Pending CN108612270A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611137617.3A CN108612270A (zh) 2016-12-12 2016-12-12 装配式建筑的预制楼梯安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611137617.3A CN108612270A (zh) 2016-12-12 2016-12-12 装配式建筑的预制楼梯安装方法

Publications (1)

Publication Number Publication Date
CN108612270A true CN108612270A (zh) 2018-10-02

Family

ID=63657522

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611137617.3A Pending CN108612270A (zh) 2016-12-12 2016-12-12 装配式建筑的预制楼梯安装方法

Country Status (1)

Country Link
CN (1) CN108612270A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456395A (zh) * 2020-04-10 2020-07-28 吴传江 一种装配式建筑预制件安装固定施工方法
CN115126257A (zh) * 2022-07-31 2022-09-30 中冶建工集团有限公司 装配式建筑工序全穿插施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102767288A (zh) * 2012-01-17 2012-11-07 中国建筑第四工程局有限公司 一种钢筋混凝土预制楼梯的安装方法及结构
CN204475714U (zh) * 2015-01-20 2015-07-15 上海万双建筑技术有限公司 一种快装式预制楼梯
CN205012578U (zh) * 2015-10-14 2016-02-03 长沙远大住宅工业集团有限公司 装配式建筑搁置楼梯连接节点
CN105544895A (zh) * 2016-02-15 2016-05-04 济南汇富住宅工业有限公司 一种混凝土预制楼梯

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102767288A (zh) * 2012-01-17 2012-11-07 中国建筑第四工程局有限公司 一种钢筋混凝土预制楼梯的安装方法及结构
CN204475714U (zh) * 2015-01-20 2015-07-15 上海万双建筑技术有限公司 一种快装式预制楼梯
CN205012578U (zh) * 2015-10-14 2016-02-03 长沙远大住宅工业集团有限公司 装配式建筑搁置楼梯连接节点
CN105544895A (zh) * 2016-02-15 2016-05-04 济南汇富住宅工业有限公司 一种混凝土预制楼梯

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456395A (zh) * 2020-04-10 2020-07-28 吴传江 一种装配式建筑预制件安装固定施工方法
CN115126257A (zh) * 2022-07-31 2022-09-30 中冶建工集团有限公司 装配式建筑工序全穿插施工方法

Similar Documents

Publication Publication Date Title
CN106013811B (zh) 一种装配式建筑的安装方法
CN106854873A (zh) 一种预制拼接的沉井式停车库的工程方法及停车库
CN106836238B (zh) 一种跌级式深基坑竖向肋板换撑的施工方法及其结构
CN105421188B (zh) 装配式临时道路的施工方法
CN107558626A (zh) 一种预制装配式墙体结构及采用此结构建造房屋的方法
CN103410317A (zh) 采用墙体预制构件现场拼装并浇筑的整体墙体施工方法
CN104563384A (zh) 一种结构保温装饰一体化大型预制外挂墙板及其制作方法
CN105064555A (zh) 叠合装饰层和保温层的结构墙板及施工方法
CN204826308U (zh) 一种预制型钢混凝土剪力墙预拼结构装配式建筑
CN206545215U (zh) 一种预制拼接的沉井式停车库
JP2011247072A (ja) 据付け基礎及びその施工方法
CN104631513A (zh) 地下室外墙后浇带封闭施工方法
CN105696744A (zh) 蒸压加气混凝土整体墙板及其生产工艺
CN105089178A (zh) 一种预制型钢混凝土剪力墙预拼结构装配式建筑
CN107143076A (zh) 一种用于降板区域的带侧翻边的预制叠合楼板及其施工方法
CN111828013A (zh) 地面盾构隧道实验实体模型及其施工方法
CN108612270A (zh) 装配式建筑的预制楼梯安装方法
CN204418229U (zh) 地下室外墙后浇带混凝土卡槽
CN116104224A (zh) 一种外墙保温一体化缝隙拼装构造节点及施工方法
CN106193120A (zh) 地下室悬挑底板逆作结构及施工方法
CN103334360A (zh) 桥式预制钢筋混凝土暗梁板耐磨路面体系及其施工方法
CN206158255U (zh) 预制装配式通信机房结构
JP2011069151A (ja) コンクリートパネル型枠
CN115387393A (zh) 后浇带预封闭快捷施工工法
CN108222349A (zh) 一种半装配式轻钢-泡沫混凝土组合楼板及其施工方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181002