CN108612270A - 装配式建筑的预制楼梯安装方法 - Google Patents
装配式建筑的预制楼梯安装方法 Download PDFInfo
- Publication number
- CN108612270A CN108612270A CN201611137617.3A CN201611137617A CN108612270A CN 108612270 A CN108612270 A CN 108612270A CN 201611137617 A CN201611137617 A CN 201611137617A CN 108612270 A CN108612270 A CN 108612270A
- Authority
- CN
- China
- Prior art keywords
- stair
- place
- control line
- staircase boards
- precast stair
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F11/00—Stairways, ramps, or like structures; Balustrades; Handrails
- E04F11/02—Stairways; Layouts thereof
Abstract
本发明涉及装配式建筑。一种装配式建筑的预制楼梯安装方法,包括:完成本层两个休息平台含梯梁混凝土浇筑、养护,每层吊装两个预制楼梯板,预制楼梯板预埋内螺纹;在休息平台上划出安装位置,并根据休息平台完成面标高,在墙面上划出标高控制线;并复核;起吊:将吊装螺栓与楼梯板预埋的内螺纹连接,起吊楼梯段;就位:按照编号在设计位置就位,先找好楼梯板的平面控制线,再缓缓下降吊装就位;校正:基本就位后再用撬棍微调楼梯板,直到位置正确,搁置平实;校正后再脱钩;连接固定:将平台上的预埋螺杆套入楼梯板前端预留孔后用灌浆料填实;成品保护:楼梯安装后及时将踏步面加以保护。本发明有助提高安装楼梯的质量、降低工程造价、缩短工期。
Description
技术领域
本发明涉及装配式建筑,尤其涉及装配式建筑的预制楼梯。
背景技术
随着城市建设节能减排、可持续发展等环保政策的逐步明朗,装配式钢筋混凝土结构建筑迎来了可以健康发展的新机遇,装配式建筑将成为我国房屋建设的必然趋势。预制楼梯在建筑产业化中占有比较重要的地位,由于楼梯间的尺寸很好统一,使装配整体式楼梯能够率先进行大面积应用。采用预制楼梯施工技术代替传统的现浇楼梯,取得了明显的效果:现场加工制作工业化、机械化安装、效率高、成型质量好、尺寸误差小、施工进度快、不需二次装修、安装简便、安全性好,减少了现场浇筑楼梯施工的噪音、扬尘和漏洒,更环保,明显地降低了施工成本,具有良好的推广应用价值。
发明内容
本发明旨在解决上述缺陷,提供一种装配式建筑的预制楼梯安装方法。本发明有助提高安装楼梯的质量、降低工程造价、缩短工期。
为解决上述问题,一种装配式建筑的预制楼梯安装方法,它包括:
步骤一,完成本层两个休息平台含梯梁混凝土浇筑、养护,结构每上去一层吊装两个预制楼梯板,预制楼梯板预埋内螺纹;
步骤二,在休息平台上划出安装位置,即左右、前后控制线,并根据休息平台完成面标高,在墙面上划出标高控制线;对各控制线进行复核;
步骤三,起吊:将吊装螺栓与楼梯板预埋的内螺纹连接,起吊楼梯段;
步骤四,就位:按照编号在设计位置就位,先找好楼梯板的平面控制线,再缓缓下降吊装就位;
步骤五,校正:基本就位后再用撬棍微调楼梯板,直到位置正确,搁置平实;校正后再脱钩;
步骤六,连接固定:将平台上的预埋螺杆套入楼梯板前端预留孔后用灌浆料填实
步骤七,成品保护:楼梯安装后,及时将踏步面加以保护,避免将踏步棱角损坏。
所述的装配式建筑的预制楼梯安装方法,所述步骤五还包括:安装楼梯时,应特别注意标高正确,下口用砂浆或流动性好的灌浆料填实。
所述的灌浆料浇筑后保养1—3天抗压强度达30—50Mpa以上,且无收缩;
自流性高:可填充全部空隙,满足设备二次灌浆的要求。微膨胀性:保证设备与基础之间紧密接触,二次灌浆后无收缩。耐久性强:经上百次疲劳实验,50次冻融循环实验强度无明显变化。在机油中浸泡30天后强度明显提高。可冬季施工:允许在-10C气温进行室外施工。
本发明基本解决支模、绑扎钢筋、浇混凝土、拆模等,现场工序多,支撑量大,结构施工阶段楼梯很难通行,交房時需要加筋抹灰,部分项目需要贴砖,耗费大量人工,同时产生大量的建筑垃圾,支护桩位移后侵占结构、漏水等安全隐患的发生,节约了工时和人力资源的浪费,使得工期大幅度缩短,现场安装质量、效率大大提高。
具体实施方式
一种装配式建筑的预制楼梯安装方法,它包括:
步骤一,完成本层两个休息平台含梯梁混凝土浇筑、养护,结构每上去一层吊装两个预制楼梯板,预制楼梯板预埋内螺纹;
步骤二,在休息平台上划出安装位置,即左右、前后控制线,并根据休息平台完成面标高,在墙面上划出标高控制线;对各控制线进行复核;
步骤三,起吊:将吊装螺栓与楼梯板预埋的内螺纹连接,起吊楼梯段;
步骤四,就位:按照编号在设计位置就位,先找好楼梯板的平面控制线,再缓缓下降吊装就位;
步骤五,校正:基本就位后再用撬棍微调楼梯板,直到位置正确,搁置平实;校正后再脱钩;
步骤六,连接固定:将平台上的预埋螺杆套入楼梯板前端预留孔后用灌浆料填实
步骤七,成品保护:楼梯安装后,及时将踏步面加以保护,避免将踏步棱角损坏。
所述的装配式建筑的预制楼梯安装方法,所述步骤五还包括:安装楼梯时,应特别注意标高正确,下口用砂浆或流动性好的灌浆料填实。
混凝土预制楼梯较现场浇筑施工的楼梯更容易安装和调整。由于预制混凝土楼梯是在专业工厂制造,然后运送到施工现场安装。制造商将这些混凝土楼梯与霉菌,离开他们内部中空,而是以内外墙体仍然支持。1.易于设计当进行正常的一套具体的楼梯,建筑师必须仔细规划为结石的确切比例,并创建一个数字蓝图他们。如果有任何变化发生,需要移动或改变了楼梯,建筑师必须在一个耗时的过程,许多变化的楼梯。预制楼梯是用一个简单的计算机程序做,这样用户就可以改变大小和创建缺口或空隙的楼梯,甚至创建之前。2.速度工人并不需要设置预制混凝土楼梯复杂的框架,也不需等到天气是正确的,花必要的时间混合和浇筑混凝土。预制楼梯,因为他们的中空特征也比传统的版本更轻。这些因素结合起来,使比传统方法预制楼梯安装快得多。3.稳定由于预制混凝土楼梯被作为一个单独的组件制造,他们有一个稳定的设计,对于不安定移位,不亚于其他混凝土楼梯。如果预制楼梯做转移,他们的团结可以很容易地调整。没有裂缝和差距裂缝和空隙,为所有混凝土楼梯的麻烦。水分会渗入裂缝,陷入冻结与解冻,可以很容易损坏的混凝土,随着时间的推移。这些裂缝中生长,附着传统的混凝土楼梯的螺栓和接缝。混凝土预制楼梯没有这么多裂缝,因为他们的无缝设计。
本工法基本解决支模、绑扎钢筋、浇混凝土、拆模等,现场工序多,支撑量大,结构施工阶段楼梯很难通行,交房時需要加筋抹灰,部分项目需要贴砖,耗费大量人工,同时产生大量的建筑垃圾,支护桩位移后侵占结构、漏水等安全隐患的发生,节约了工时和人力资源的浪费,使得工期大幅度缩短,现场安装质量、效率大大提高。
Claims (3)
1.一种装配式建筑的预制楼梯安装方法,其特征在于,它包括:
步骤一,完成各层两个休息平台施工,包括梯梁混凝土浇筑、养护,每层吊装两个预制楼梯板,预制楼梯板预埋内螺纹;
步骤二,在休息平台上划出安装位置,即左右、前后控制线,并根据休息平台完成面标高,在墙面上划出标高控制线;对各控制线进行复核;
步骤三,起吊:将吊装螺栓与楼梯板预埋的内螺纹连接,起吊楼梯段;
步骤四,就位:按照编号在设计位置就位,先找好楼梯板的平面控制线,再缓缓下降吊装就位;
步骤五,校正:基本就位后再用撬棍微调楼梯板,直到位置正确,搁置平实;校正后再脱钩;
步骤六,连接固定:将平台上的预埋螺杆套入楼梯板前端预留孔后用灌浆料填实
步骤七,成品保护:楼梯安装后,及时将踏步面加以保护,避免将踏步棱角损坏。
2.根据权利要求1所述的装配式建筑的预制楼梯安装方法,其特征在于,所述步骤五还包括:安装楼梯时,应特别注意标高正确,下口用砂浆或流动性好的灌浆料填实。
3.根据权利要求2所述的装配式建筑的预制楼梯安装方法,其特征在于,所述流动性好的灌浆料浇筑后保养1—3天抗压强度达30—50Mpa以上,且无收缩;
自流性高:可填充全部空隙,满足设备二次灌浆的要求;
微膨胀性:保证设备与基础之间紧密接触,二次灌浆后无收缩;
耐久性强:经上百次疲劳实验,50次冻融循环实验强度无明显变化;在机油中浸泡30天后强度明显提高;
可冬季施工:允许在-10C气温进行室外施工。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611137617.3A CN108612270A (zh) | 2016-12-12 | 2016-12-12 | 装配式建筑的预制楼梯安装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611137617.3A CN108612270A (zh) | 2016-12-12 | 2016-12-12 | 装配式建筑的预制楼梯安装方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108612270A true CN108612270A (zh) | 2018-10-02 |
Family
ID=63657522
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611137617.3A Pending CN108612270A (zh) | 2016-12-12 | 2016-12-12 | 装配式建筑的预制楼梯安装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108612270A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111456395A (zh) * | 2020-04-10 | 2020-07-28 | 吴传江 | 一种装配式建筑预制件安装固定施工方法 |
CN115126257A (zh) * | 2022-07-31 | 2022-09-30 | 中冶建工集团有限公司 | 装配式建筑工序全穿插施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102767288A (zh) * | 2012-01-17 | 2012-11-07 | 中国建筑第四工程局有限公司 | 一种钢筋混凝土预制楼梯的安装方法及结构 |
CN204475714U (zh) * | 2015-01-20 | 2015-07-15 | 上海万双建筑技术有限公司 | 一种快装式预制楼梯 |
CN205012578U (zh) * | 2015-10-14 | 2016-02-03 | 长沙远大住宅工业集团有限公司 | 装配式建筑搁置楼梯连接节点 |
CN105544895A (zh) * | 2016-02-15 | 2016-05-04 | 济南汇富住宅工业有限公司 | 一种混凝土预制楼梯 |
-
2016
- 2016-12-12 CN CN201611137617.3A patent/CN108612270A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102767288A (zh) * | 2012-01-17 | 2012-11-07 | 中国建筑第四工程局有限公司 | 一种钢筋混凝土预制楼梯的安装方法及结构 |
CN204475714U (zh) * | 2015-01-20 | 2015-07-15 | 上海万双建筑技术有限公司 | 一种快装式预制楼梯 |
CN205012578U (zh) * | 2015-10-14 | 2016-02-03 | 长沙远大住宅工业集团有限公司 | 装配式建筑搁置楼梯连接节点 |
CN105544895A (zh) * | 2016-02-15 | 2016-05-04 | 济南汇富住宅工业有限公司 | 一种混凝土预制楼梯 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111456395A (zh) * | 2020-04-10 | 2020-07-28 | 吴传江 | 一种装配式建筑预制件安装固定施工方法 |
CN115126257A (zh) * | 2022-07-31 | 2022-09-30 | 中冶建工集团有限公司 | 装配式建筑工序全穿插施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106013811B (zh) | 一种装配式建筑的安装方法 | |
CN106854873A (zh) | 一种预制拼接的沉井式停车库的工程方法及停车库 | |
CN106836238B (zh) | 一种跌级式深基坑竖向肋板换撑的施工方法及其结构 | |
CN105421188B (zh) | 装配式临时道路的施工方法 | |
CN107558626A (zh) | 一种预制装配式墙体结构及采用此结构建造房屋的方法 | |
CN103410317A (zh) | 采用墙体预制构件现场拼装并浇筑的整体墙体施工方法 | |
CN104563384A (zh) | 一种结构保温装饰一体化大型预制外挂墙板及其制作方法 | |
CN105064555A (zh) | 叠合装饰层和保温层的结构墙板及施工方法 | |
CN204826308U (zh) | 一种预制型钢混凝土剪力墙预拼结构装配式建筑 | |
CN206545215U (zh) | 一种预制拼接的沉井式停车库 | |
JP2011247072A (ja) | 据付け基礎及びその施工方法 | |
CN104631513A (zh) | 地下室外墙后浇带封闭施工方法 | |
CN105696744A (zh) | 蒸压加气混凝土整体墙板及其生产工艺 | |
CN105089178A (zh) | 一种预制型钢混凝土剪力墙预拼结构装配式建筑 | |
CN107143076A (zh) | 一种用于降板区域的带侧翻边的预制叠合楼板及其施工方法 | |
CN111828013A (zh) | 地面盾构隧道实验实体模型及其施工方法 | |
CN108612270A (zh) | 装配式建筑的预制楼梯安装方法 | |
CN204418229U (zh) | 地下室外墙后浇带混凝土卡槽 | |
CN116104224A (zh) | 一种外墙保温一体化缝隙拼装构造节点及施工方法 | |
CN106193120A (zh) | 地下室悬挑底板逆作结构及施工方法 | |
CN103334360A (zh) | 桥式预制钢筋混凝土暗梁板耐磨路面体系及其施工方法 | |
CN206158255U (zh) | 预制装配式通信机房结构 | |
JP2011069151A (ja) | コンクリートパネル型枠 | |
CN115387393A (zh) | 后浇带预封闭快捷施工工法 | |
CN108222349A (zh) | 一种半装配式轻钢-泡沫混凝土组合楼板及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181002 |