CN108589740A - The water mill of artificial digging pile bores construction method - Google Patents
The water mill of artificial digging pile bores construction method Download PDFInfo
- Publication number
- CN108589740A CN108589740A CN201810263684.2A CN201810263684A CN108589740A CN 108589740 A CN108589740 A CN 108589740A CN 201810263684 A CN201810263684 A CN 201810263684A CN 108589740 A CN108589740 A CN 108589740A
- Authority
- CN
- China
- Prior art keywords
- pile foundation
- drilling
- water mill
- depth
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
Abstract
The invention belongs to bridge construction technical fields, are related to a kind of water mill brill construction method of the artificial digging pile for bridge pile foundation engineering.This approach includes the following steps:1)After determining pile foundation borehole position and diameter, it is carried out continuously bore operation along the circumferential edges of pile foundation hole with water mill brill, the depth each to drill is determined by drilling pipe length, and each drilling is tangent successively or intersects, and core is transported after drilling;2)Using the broken removal pile foundation hole central part of pneumatic pick, broken rock slag is transported, the borehole operation of one section of depth is completed;3)Step 1 is repeated several times)To step 2), the borehole operation of next section of depth is completed, until reaching the projected depth of pile foundation hole.The method boring procedure operation of the present invention flexibly, easy maintenance, construction safety, pollution it is small, while shaking and noise is small, in the region of unsuitable explosion, construction has prodigious advantage.
Description
Technical field
The invention belongs to bridge construction technical field, it is related to a kind of artificial digging pile for bridge pile foundation engineering
Water mill bores construction method.
Background technology
At present in Bridges in Mountainous Areas pile foundation construction, manually digging hole enters behind rock stratum the side for generally using emulsion explosion
Formula, but there are larger security risks for this method, and when close to resident house, the shock wave that explosion generates is easy to cause house
Harm, it is unfavorable to the personal safety of resident, and it is serious to disturb residents.It is not easy to control for the aperture in hole simultaneously in explosion, it causes
Aperture is excessive, the serious phenomenon of the super side of concrete.
Invention content
That the technical problem to be solved by the invention is to provide a kind of working securities is good, vibrations and noise are small, dust pollution
Small, the construction high artificial digging pile of accurate size water mill bores construction method.
The water mill of the artificial digging pile of the present invention bores construction method:
Hoisting bracket is set on the aperture ground of pile foundation hole and lifting appliance is installed;
1)After determining pile foundation borehole position and diameter, it is carried out continuously bore operation along the circumferential edges of pile foundation hole 1 with water mill brill, often
The depth of a drilling is determined that each drilling is tangent successively or intersects, and core is transported after drilling by drilling pipe length;
2)Using the broken removal pile foundation hole central part of pneumatic pick, broken rock slag is transported, the borehole for completing one section of depth is made
Industry;
3)Step 1 is repeated several times)To step 2), the borehole operation of next section of depth is completed, until the design for reaching pile foundation hole is deep
Degree.
Further, in above-mentioned steps, derrick 2 is set in the well head of pile foundation hole, and lifting appliance 3 is installed, passes through lifting
Equipment handling drilling pipe, core and rock slag.
The drilling pipe length is 50-70cm, a diameter of 15-18cm.Preferred drilling pipe length is 60cm, a diameter of 16cm.
The present invention method boring procedure operation flexibly, easy maintenance, construction safety, pollution it is small, while shake and noise
It is small, there is prodigious advantage in the region construction of unsuitable explosion.
Description of the drawings
Fig. 1 is the Construction State schematic diagram of the method for the present invention;
Fig. 2 is pile foundation hole bottom hole distribution schematic diagram.
Specific implementation mode
The method of the present invention is described further with reference to embodiment.
Embodiment:
The work progress of the embodiment of the present invention(Referring to Fig. 1):
1)After determining pile foundation borehole position and diameter, derrick is set in the well head of pile foundation hole, and lifting appliance is installed, is bored with water mill
Circumferential edges along pile foundation hole are carried out continuously bore operation, and according to the specification of drilling pipe, the depth each to drill is 60cm, a diameter of
16cm, each drilling is tangent successively or intersects(Such as Fig. 2), fortune goes out core by lifting appliance after drilling;
2)Using the broken removal pile foundation hole central part of pneumatic pick, broken rock slag is transported by lifting appliance, completes one section
The borehole operation of depth;
3)Step 1 is repeated several times)To step 2), the borehole operation of next section of depth is completed, until the design for reaching pile foundation hole is deep
Degree.
Above-mentioned work progress is not necessarily to bursting work, will not cause to damage to neighbouring building construction, ensure that construction safety,
Also reduce the influence to environment.
Claims (4)
1. a kind of water mill of artificial digging pile bores construction method, it is characterized in that:
1)After determining pile foundation borehole position and diameter, it is carried out continuously bore operation along the circumferential edges of pile foundation hole with water mill brill, often
The depth of a drilling is determined that each drilling is tangent successively or intersects, and core is transported after drilling by drilling pipe length;
2)Using the broken removal pile foundation hole central part of pneumatic pick, broken rock slag is transported, the borehole for completing one section of depth is made
Industry;
3)Step 1 is repeated several times)To step 2), the borehole operation of next section of depth is completed, until the design for reaching pile foundation hole is deep
Degree.
2. the water mill of artificial digging pile according to claim 1 bores construction method, it is characterized in that:It is set in the well head of pile foundation hole
Derrick is set, and lifting appliance is installed, passes through lifting appliance handling drilling pipe, core and rock slag.
3. the water mill of artificial digging pile according to claim 1 bores construction method, it is characterized in that:The drilling pipe length is
50-70cm, a diameter of 15-18cm.
4. the water mill of artificial digging pile according to claim 3 bores construction method, it is characterized in that:The drilling pipe length is
60cm, a diameter of 16cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810263684.2A CN108589740A (en) | 2018-03-28 | 2018-03-28 | The water mill of artificial digging pile bores construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810263684.2A CN108589740A (en) | 2018-03-28 | 2018-03-28 | The water mill of artificial digging pile bores construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108589740A true CN108589740A (en) | 2018-09-28 |
Family
ID=63624793
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810263684.2A Pending CN108589740A (en) | 2018-03-28 | 2018-03-28 | The water mill of artificial digging pile bores construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108589740A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110513038A (en) * | 2019-08-27 | 2019-11-29 | 中铁六局集团有限公司 | It closes on Business Line rock geology pile foundation water mill and bores construction |
CN113482013A (en) * | 2021-07-12 | 2021-10-08 | 中国水电建设集团十五工程局有限公司 | Manual hole digging construction method for cast-in-place pile |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102071683A (en) * | 2011-02-15 | 2011-05-25 | 中交第四公路工程局有限公司 | Water drill dug pile construction method |
JP2017020327A (en) * | 2015-05-28 | 2017-01-26 | 隆夫 中野 | Cast-in-place pile method |
CN106381868A (en) * | 2016-09-06 | 2017-02-08 | 中交第航务工程局有限公司 | Water abrasive drilling construction method for manual hole digging pile |
-
2018
- 2018-03-28 CN CN201810263684.2A patent/CN108589740A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102071683A (en) * | 2011-02-15 | 2011-05-25 | 中交第四公路工程局有限公司 | Water drill dug pile construction method |
JP2017020327A (en) * | 2015-05-28 | 2017-01-26 | 隆夫 中野 | Cast-in-place pile method |
CN106381868A (en) * | 2016-09-06 | 2017-02-08 | 中交第航务工程局有限公司 | Water abrasive drilling construction method for manual hole digging pile |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110513038A (en) * | 2019-08-27 | 2019-11-29 | 中铁六局集团有限公司 | It closes on Business Line rock geology pile foundation water mill and bores construction |
CN113482013A (en) * | 2021-07-12 | 2021-10-08 | 中国水电建设集团十五工程局有限公司 | Manual hole digging construction method for cast-in-place pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109026039A (en) | Subway tunnel shield tunnels boulder deep hole blasting and pre-processes construction method | |
CN104005415B (en) | The efficient forming construction method thereof of diaphram wall in light weathered granite | |
CN103835648B (en) | One improves rock stratum performance mine shaft rising boring technique by surface grout injection | |
CN106014421B (en) | A kind of limited rock tunnel excavation method of concussion of blasting | |
CN106194193A (en) | The auxiliary excavation method of a kind of group hole, big cross section vertical shaft non-explosion large aperture | |
CN103046931A (en) | Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode | |
CN106545007A (en) | The method of pile in stratum of the bottom for hard rock stratum | |
CN108589740A (en) | The water mill of artificial digging pile bores construction method | |
CN102912791A (en) | Construction method of bored pile | |
CN103277037A (en) | Pipe pile leading-hole construction method under boulder cluster geological condition | |
CN102661688A (en) | Pile foundation control blasting excavation method of integral-plate rocky area | |
CN107091094A (en) | Short inclined shaft pilot shaft excavation method in one kind | |
CN113882801A (en) | Rotary drilling pile foundation construction method for soil and hard rock combined stratum | |
CN105887814A (en) | Rotary excavating rock-embedded pedestal pile construction method | |
CN102409978B (en) | Rotary drilling hole forming method by using multi-stage alloy pilot roller bit in complex stratum cast-in-place pile construction | |
CN103835647A (en) | Method for drilling floating pebble bed | |
CN114278227B (en) | Construction method of lower pile casing of cast-in-place pile | |
CN116181224A (en) | Construction method of multi-layer oversized karst cave rock-socketed pile foundation in complex karst area | |
CN210507418U (en) | Construction structure close to existing line bridge pile foundation | |
CN105401572A (en) | Construction technique for environment-friendly cast-in-situ bored pile provided with wall protecting tube | |
CN110130321A (en) | The processing method of rock in a kind of manual digging pile construction | |
CN108411919A (en) | Pile bottom sediment cleaning method for rotary drilling mechanical hole-forming pile | |
CN212154699U (en) | Prevent balanced atmospheric pressure system of rock burst | |
CN108729461A (en) | For the constructing structure and construction method on aerial leakage stratum in deep hole impervious wall construction | |
CN204344048U (en) | Foreign matter fisher in hole |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |