CN113482013A - Manual hole digging construction method for cast-in-place pile - Google Patents

Manual hole digging construction method for cast-in-place pile Download PDF

Info

Publication number
CN113482013A
CN113482013A CN202110785081.0A CN202110785081A CN113482013A CN 113482013 A CN113482013 A CN 113482013A CN 202110785081 A CN202110785081 A CN 202110785081A CN 113482013 A CN113482013 A CN 113482013A
Authority
CN
China
Prior art keywords
hole
cast
core
place pile
rock mass
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110785081.0A
Other languages
Chinese (zh)
Inventor
党朋
范丹丹
侯娟
冯秀明
范羽航
高欣驰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Corp Engineering Bureau 15 Co Ltd
Original Assignee
Sinohydro Corp Engineering Bureau 15 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Corp Engineering Bureau 15 Co Ltd filed Critical Sinohydro Corp Engineering Bureau 15 Co Ltd
Priority to CN202110785081.0A priority Critical patent/CN113482013A/en
Publication of CN113482013A publication Critical patent/CN113482013A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Earth Drilling (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A construction method for manually digging a hole in a cast-in-place pile adopts mechanical or manual cleaning and leveling of a field around an orifice of a cast-in-place pile hole; excavating the hole opening part of the cast-in-place pile hole to a rock surface, and then pouring concrete with a certain height along the periphery of the hole opening; drilling a core around a bored concrete pile hole; excavating a central rock mass; after the central rock mass is lifted out, cleaning the hole wall and the residual rock mass at the hole bottom, and finishing the excavation of the cost layer; and (5) excavating the next layer until the designed depth is reached, and finishing the whole hole excavating construction of the cast-in-place pile hole. The invention has the advantages of simple process, low cost, strong adaptability and high construction efficiency.

Description

Manual hole digging construction method for cast-in-place pile
Technical Field
The invention belongs to the technical field of hydraulic engineering, and particularly relates to a manual hole digging construction method for a cast-in-place pile.
Background
Generally, rock foundation cast-in-place piles adopt percussion drilling to dig holes, but some cast-in-place piles are far away in design position, such as on a hillside, limited by terrain conditions, and difficult to reach construction parts by percussion drilling equipment, and some cast-in-place piles are less in design engineering quantity, and construction units are unwilling to invest large-scale equipment; and in addition, some rock foundation cast-in-place piles can be excavated by manual blasting, but the blasting procedure is complicated, and blasting materials are controlled and cannot be carried out. The method is unconditional to the failure of expansion construction of impact drilling equipment and manual blasting hole digging.
Disclosure of Invention
The invention aims to overcome the defects of the existing cast-in-place pile construction method and provide the cast-in-place pile manual hole digging construction method which is simple in process, low in cost, strong in adaptability and high in construction efficiency.
The technical scheme for solving the technical problems is as follows: a construction method for manually digging a hole in a cast-in-place pile comprises the following steps:
s1, leveling a field
Mechanically or manually cleaning and flattening the field around the hole opening of the cast-in-place pile;
s2. concrete fore shaft
Excavating the hole opening part of the cast-in-place pile hole to a rock surface, and then pouring concrete with a certain height along the periphery of the hole opening;
s3, drilling and taking the rock core around the dug pile
Sequentially drilling core cores around a bored pile hole by using a water mill drilling machine, designing a boundary line to be externally placed for 5cm to drill, wherein the drilling depth is 65-75 cm each time, the diameter of the core is 15cm, the core is outwards inclined by 3 degrees or 4 degrees during drilling, the first peripheral hole is drilled to the required depth, then the drill is lifted and stopped, then the core is manually pried off, the core is lifted out of the hole by using a special clamp, the core is loaded into an iron bucket to be lifted and transported outwards, and after the first core is taken out, all the core cores around are sequentially drilled and transported outwards by a circulating drilling process;
s4. excavating central rock mass
After all the rock cores at the periphery are drilled and transported outside, the central rock mass is broken manually by adopting a steel wedge and an iron pry, then the central rock mass is bound by adopting a special steel wire rope, and finally the central rock mass is lifted out of the hole by lifting equipment;
s5, manually cleaning
After the central rock mass is lifted out, cleaning the residual rock mass on the hole wall and the hole bottom until the requirement of the design excavation size is met, and finishing excavation of the stratum;
and S6, performing next layer excavation, and sequentially repeating the steps S3-S5 to complete the next layer excavation until the designed depth is reached, so as to complete the whole hole excavation construction of the cast-in-place pile hole.
As a preferable technical scheme, in the step S2, the height of the concrete is 30-50 cm, and the thickness of the concrete is 15-25 cm.
The invention has the following beneficial effects:
(1) the invention adopts conventional equipment, has simple process, can avoid the problems of incapability of in-place percussion drilling and environmental pollution caused by construction wall-fixing slurry of the percussion drilling, can also avoid the use problem of blasting hole-digging initiating explosive materials, and only needs to be configured with a small power supply on site;
(2) the invention has strong adaptability, is suitable for the hole digging requirement of the rock foundation cast-in-place pile under various topographic and geological conditions, can be adopted by the cast-in-place pile with the diameter of more than 0.8m, and can be excavated by layers and blocks; the hole digging depth can reach more than 40m, and the hole digging depth exceeds 10m, and air needs to be supplied into the hole;
(3) the method has the advantages of less investment and higher construction efficiency, generally, a group of three people can dig holes of two cast-in-place piles at the same time, and one layer of two cast-in-place piles with the diameter of 1.2m can be dug every shift, namely the depth is 65-75 cm;
(4) the invention has good hole digging effect and lower cost, because the periphery digging control is carried out by adopting the water mill drilling machine, the digging forming section is more standard and regular, the over digging amount is small, the digging cost of the filling pile with the diameter of 1.2m is 800 yuan, which is obviously lower than the construction cost of the impact drill and the construction cost of other manual hole digging piles.
Drawings
FIG. 1 is a schematic flow diagram of the present invention.
Detailed Description
The present invention will be described in further detail below with reference to the drawings and examples, but the present invention is not limited to the embodiments described below.
In fig. 1, the method for constructing a bored concrete pile by manual hole excavation according to this embodiment includes the following steps:
s1, leveling a field
Mechanically or manually cleaning and flattening the field around the hole opening of the cast-in-place pile;
s2. concrete fore shaft
Excavating the hole opening part of the cast-in-place pile hole to a rock surface, and then pouring concrete with a certain height along the periphery of the hole opening, wherein the height of the concrete is 45cm, and the thickness of the concrete is 20 cm;
s3, drilling and taking the rock core around the dug pile
Sequentially drilling core cores around a bored pile hole by using a water mill drilling machine, setting a boundary line to be externally placed by 5cm for pulling out a drill, wherein the drilling depth is 65-75 cm each time, the diameter of the core is 15cm, the core is outwards inclined by 3 degrees during drilling, the drill is lifted and stopped after the first peripheral hole is drilled to the required depth, then the core is manually pried off, the core is lifted out of the hole by using a special clamp, the core is loaded into an iron bucket for lifting and outward transportation, and after the first core is taken out, all the core cores around are sequentially drilled and transported by a circular drilling process;
s4. excavating central rock mass
After all the rock cores at the periphery are drilled and transported outside, the central rock mass is broken manually by adopting a steel wedge and an iron pry, then the central rock mass is bound by adopting a special steel wire rope, and finally the central rock mass is lifted out of the hole by lifting equipment;
s5, manually cleaning
After the central rock mass is lifted out, cleaning the residual rock mass on the hole wall and the hole bottom until the requirement of the design excavation size is met, and finishing excavation of the stratum;
and S6, performing next layer excavation, and sequentially repeating the steps S3-S5 to complete the next layer excavation until the designed depth is reached, so as to complete the whole hole excavation construction of the cast-in-place pile hole.
The method of the invention is adopted to excavate the bored concrete pile hole with the diameter of 1.1m, the excavation amount is reduced by 0.4 square per linear meter, and the concrete is correspondingly reduced by 0.4 square.

Claims (2)

1. A construction method for manually digging a hole in a cast-in-place pile is characterized by comprising the following steps:
s1, leveling a field
Mechanically or manually cleaning and flattening the field around the hole opening of the cast-in-place pile;
s2. concrete fore shaft
Excavating the hole opening part of the cast-in-place pile hole to a rock surface, and then pouring concrete with a certain height along the periphery of the hole opening;
s3, drilling a rock core around a bored concrete pile hole
Sequentially drilling core cores around a bored pile hole by using a water mill drilling machine, designing a boundary line to be externally placed for 5cm to drill, wherein the drilling depth is 65-75 cm each time, the diameter of the core is 15cm, the core is outwards inclined by 3 degrees or 4 degrees during drilling, the first peripheral hole is drilled to the required depth, then the drill is lifted and stopped, then the core is manually pried off, the core is lifted out of the hole by using a special clamp, the core is loaded into an iron bucket to be lifted and transported outwards, and after the first core is taken out, all the core cores around are sequentially drilled and transported outwards by a circulating drilling process;
s4. excavating central rock mass
After all the rock cores at the periphery are drilled and transported outside, the central rock mass is broken manually by adopting a steel wedge and an iron pry, then the central rock mass is bound by adopting a special steel wire rope, and finally the central rock mass is lifted out of the hole by lifting equipment;
s5, manually cleaning
After the central rock mass is lifted out, cleaning the residual rock mass on the hole wall and the hole bottom until the requirement of the design excavation size is met, and finishing excavation of the stratum;
s6, performing next-layer excavation
And (5) sequentially repeating the steps S3-S5 to finish the next layer of excavation until the excavation reaches the designed depth, and finishing the whole hole excavation construction of the cast-in-place pile hole.
2. The manual hole digging construction method for the cast-in-place pile according to claim 1, characterized in that: in the step S2, the height of the concrete is 30-50 cm, and the thickness of the concrete is 15-25 cm.
CN202110785081.0A 2021-07-12 2021-07-12 Manual hole digging construction method for cast-in-place pile Pending CN113482013A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110785081.0A CN113482013A (en) 2021-07-12 2021-07-12 Manual hole digging construction method for cast-in-place pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110785081.0A CN113482013A (en) 2021-07-12 2021-07-12 Manual hole digging construction method for cast-in-place pile

Publications (1)

Publication Number Publication Date
CN113482013A true CN113482013A (en) 2021-10-08

Family

ID=77938731

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110785081.0A Pending CN113482013A (en) 2021-07-12 2021-07-12 Manual hole digging construction method for cast-in-place pile

Country Status (1)

Country Link
CN (1) CN113482013A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010106543A (en) * 2008-10-30 2010-05-13 Railway Technical Res Inst Construction method for cast-in-place pile
CN107059847A (en) * 2017-06-20 2017-08-18 中国华西企业有限公司 A kind of competent bed water mill bores pouring pile hole structure and its construction from the bottom of one's heart
CN108589740A (en) * 2018-03-28 2018-09-28 江苏省交通工程集团有限公司 The water mill of artificial digging pile bores construction method
CN108625385A (en) * 2018-06-25 2018-10-09 成都市市政工程(集团)有限责任公司 Mountain area rocky stratum bridge pile foundation water mill drilling construction method
CN109469051A (en) * 2018-10-25 2019-03-15 江苏南通三建集团股份有限公司 The construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010106543A (en) * 2008-10-30 2010-05-13 Railway Technical Res Inst Construction method for cast-in-place pile
CN107059847A (en) * 2017-06-20 2017-08-18 中国华西企业有限公司 A kind of competent bed water mill bores pouring pile hole structure and its construction from the bottom of one's heart
CN108589740A (en) * 2018-03-28 2018-09-28 江苏省交通工程集团有限公司 The water mill of artificial digging pile bores construction method
CN108625385A (en) * 2018-06-25 2018-10-09 成都市市政工程(集团)有限责任公司 Mountain area rocky stratum bridge pile foundation water mill drilling construction method
CN109469051A (en) * 2018-10-25 2019-03-15 江苏南通三建集团股份有限公司 The construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area

Similar Documents

Publication Publication Date Title
JP7177554B2 (en) Wall subsidence construction method
CN104947690B (en) Grooving construction method for embedding underground continuous wall into rock
CN104612179B (en) Through the construction method of the diaphram wall of super thick silty sand ground
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN105442532A (en) Construction method for pile-head-expanded bored pile
CN106812149A (en) A kind of construction method of pile foundation
CN112030956A (en) Karst stratum bored pile construction method
CN113186903A (en) Combined pile structure and construction method for treating insufficient bearing capacity of deep foundation pit construction pile by adopting combined pile structure
CN104480929B (en) A kind of pile wall interaction construction method that interlocking pile is applied to permanent outer wall of basement
CN112761076A (en) Lock catch steel pipe pile cofferdam applied to water level change condition and construction method
CN113431045B (en) Construction method for rotary drilling pore-forming karst leaking stoppage
CN114482099A (en) Steel sheet pile cofferdam construction method
CN112627199A (en) Construction method for foundation pit support of cyclone well
CN104264679A (en) Construction method of tower transmission iron tower foundation large-diameter underwater cast-in-place piles
CN106638611A (en) Micro steel pipe pile-anchor combined support construction method
CN113482013A (en) Manual hole digging construction method for cast-in-place pile
CN211773974U (en) Building inclination correcting and sinking accelerating device
CN109653193B (en) Reverse construction method for underground continuous wall
CN112144516A (en) Construction method of concrete pile
CN112252312A (en) Construction method for enhancing integral stress performance of PHC pipe pile
CN114855778B (en) Pile replacing construction method under complex geological condition of hillside slope
JP7466044B1 (en) Installation method of underpinning piles and inspection anchor piles
CN214423184U (en) Be applied to hasp steel-pipe pile cofferdam under water level variation condition
CN110185028B (en) Construction method of stratum triaxial mixing pile with high local strength
CN213508492U (en) Construction structure for large-diameter manual hole digging to penetrate through weak stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211008

RJ01 Rejection of invention patent application after publication