CN108505644B - CL composite concrete shear wall construction method - Google Patents

CL composite concrete shear wall construction method Download PDF

Info

Publication number
CN108505644B
CN108505644B CN201810256046.8A CN201810256046A CN108505644B CN 108505644 B CN108505644 B CN 108505644B CN 201810256046 A CN201810256046 A CN 201810256046A CN 108505644 B CN108505644 B CN 108505644B
Authority
CN
China
Prior art keywords
concrete
wall
plate
self
sealing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201810256046.8A
Other languages
Chinese (zh)
Other versions
CN108505644A (en
Inventor
宋梦
潘俊波
高良艳
付国鑫
刘保林
陈思烨
刘允才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huanghe Science and Technology College
Original Assignee
Huanghe Science and Technology College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huanghe Science and Technology College filed Critical Huanghe Science and Technology College
Priority to CN201810256046.8A priority Critical patent/CN108505644B/en
Publication of CN108505644A publication Critical patent/CN108505644A/en
Application granted granted Critical
Publication of CN108505644B publication Critical patent/CN108505644B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B62LAND VEHICLES FOR TRAVELLING OTHERWISE THAN ON RAILS
    • B62BHAND-PROPELLED VEHICLES, e.g. HAND CARTS OR PERAMBULATORS; SLEDGES
    • B62B3/00Hand carts having more than one axis carrying transport wheels; Steering devices therefor; Equipment therefor
    • B62B3/10Hand carts having more than one axis carrying transport wheels; Steering devices therefor; Equipment therefor characterised by supports specially adapted to objects of definite shape
    • B62B3/108Hand carts having more than one axis carrying transport wheels; Steering devices therefor; Equipment therefor characterised by supports specially adapted to objects of definite shape the objects being plates, doors, panels, or the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/08Forms, which are completely dismantled after setting of the concrete and re-built for next pouring
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/06Solidifying concrete, e.g. by application of vacuum before hardening

Abstract

The CL composite concrete shear wall construction method comprises the following steps: (1) lifting the CL net rack plate; (2) placing the CL net rack plate on a temporary field adjacent to a construction site; (3) a plurality of positioning and adjusting components are uniformly arranged on two side surfaces of the CL net rack plate; (4) the CL net rack plates provided with the positioning and adjusting assemblies are conveyed to a wall construction site by using a trolley, and are sequentially hoisted into CL net rack plate installation control lines by using a tower crane and are butted; (5) installing a wall formwork; (6) pouring self-sealing concrete downwards from the top of the wall formwork; (7) removing the wall formwork; (8) maintaining the wall body; (9) and (5) checking and accepting the wall quality. The invention is suitable for the construction of composite concrete shear walls with different thicknesses, ensures the levelness of the upper end edge of the wall body template of the inner wall of the wall body, improves the construction quality, and avoids the defects of external thermal insulation of the outer wall and insufficient durability of the internal thermal insulation of the outer wall; realizing the modernization of the building industry and the factory production of building products.

Description

CL composite concrete shear wall construction method
Technical Field
The invention belongs to the technical field of building construction, and particularly relates to a CL composite concrete shear wall construction method.
Background
The CL building system is a brand-new composite concrete shear wall building system, and a core component of the CL composite concrete shear wall is a wall body which integrates stress and heat preservation and is formed by pouring concrete on two sides of a CL net frame plate (a net frame which is formed by clamping EPS heat preservation plates in two layers of steel bar welding nets in a deviated middle way and then fixing the two layers of steel bar welding nets by using split bolts). The system has the following characteristics: replacing clay bricks; the defects of external thermal insulation of the outer wall and insufficient durability of the internal thermal insulation of the outer wall are solved; the thickness of the wall body is reduced, and the use area is enlarged by 5-8 percent; realizing the modernization of the building industry and the factory production of building parts.
In the construction process of the existing cast-in-place reinforced concrete shear wall, the CL net rack plate also needs to be carried, the existing carrying process completely depends on manual work, the labor intensity is high, the efficiency is low, and because the two sides of the CL net rack are both provided with steel wire meshes, workers are easy to touch the steel wire meshes to be injured in the carrying process; and because the design size of the outer protective layer of the wall body can not be accurately controlled, the problems that the building quality is influenced by rib leakage, fracture, bulging and the like of the wall body after the template is removed can be caused, so that the quality of the cast-in-place reinforced concrete wall body is seriously influenced, and the problems are not well solved.
Disclosure of Invention
The invention aims to overcome the defects in the prior art and provides the CL composite concrete shear wall construction method which is low in labor intensity, safe to carry, high in construction efficiency, capable of ensuring the wall casting thickness and adjusting the wall casting thickness, easy to adjust the template height and good in construction quality.
In order to solve the technical problems, the invention adopts the following technical scheme: the construction method of the CL composite concrete shear wall comprises the following steps,
(1) lifting the CL net rack plate: the CL rack plate is a nonstandard block, the CL composite shear wall is decomposed according to the arrangement condition of the CL composite shear wall in the construction drawing and according to a node detail drawing in the construction drawing and a related technical specification and a construction joint reservation condition, the specification, the size, the peripheral node characteristics, the number and the position of the CL rack plate are expressed in detail, and the CL rack plate is communicated with a professional manufacturer in advance through an order form to produce and supply a goods plan; (ii) a
(2) Placing the purchased CL net rack plate in a temporary field adjacent to a construction site;
(3) uniformly arranging a plurality of positioning and adjusting components on two side surfaces of the CL net rack plate in the leveled construction site; meanwhile, ejecting a wall form in-place control line and a CL grid plate installation control line on a construction site;
(4) the CL net rack plates provided with the positioning and adjusting assemblies are conveyed to a wall construction site by using a trolley, the CL net rack plates are sequentially hoisted into CL net rack plate installation control lines by using a tower crane and are butted, and the CL net rack plates are temporarily positioned by building temporary protective frames by using steel pipes;
(5) respectively installing wall formworks on the inner side and the outer side of the CL net frame plate according to the formwork in-place control line; an operation platform is erected above the wall formwork by adopting a scaffold, the operation platform consists of a platform plate, a guardrail and a ladder, the temporary protective frame is gradually removed in the process of installing the wall formwork, so that the positioning adjusting components arranged on the inner side and the outer side of the CL net frame plate are respectively contacted with the wall formwork, and a wall penetrating bolt and a plastic sleeve are arranged at a preset position;
(6) pouring self-sealing concrete into the cavity between the CL net frame plate and the wall formwork at the inner side and the cavity between the CL net frame plate and the wall formwork at the outer side from the top of the wall formwork;
(7) removing the wall formwork;
(8) maintaining the wall body;
(9) and (5) checking and accepting the wall quality.
The CL rack plate comprises a polystyrene board with a rectangular structure, an inner steel wire mesh and an outer steel wire mesh are respectively arranged on the inner side and the outer side of the polystyrene board and are connected through oblique inserted steel bars penetrating through the polystyrene board, a convex rib is arranged on one side edge of the polystyrene board in the vertical direction, and a sealing positioning groove is formed in the other side edge of the polystyrene board in the vertical direction; the cross sections of the convex edge strips and the sealing positioning grooves are the same in shape and size;
the positioning and adjusting component in the step (3) comprises an inner concrete block and an outer concrete block, the outer side of the inner concrete block is in contact with the inner side face of the polyphenyl plate, the inner side of the outer concrete block is in contact with the outer side face of the polyphenyl plate, the positioning sleeve penetrates through the polyphenyl plate along the inner horizontal direction and the outer horizontal direction, the inner end portion of the positioning sleeve is embedded in the inner concrete block, the outer end portion of the positioning sleeve is embedded in the outer concrete block, the portion, in contact with the inner concrete block, of an inner steel wire mesh is embedded in the inner concrete block, the portion, in contact with the outer concrete block, of the outer steel wire mesh is embedded in the outer concrete block, the outer end portion of the inner adjusting rod extends into and is in threaded connection with the inner port of the positioning sleeve, the inner end portion of the outer adjusting rod extends into and is in threaded connection with the outer port of the positioning sleeve, an inner limiting plate is fixedly arranged at the inner end of the inner adjusting rod; the outer concrete block is in a circular truncated cone-shaped structure with thick inside and thin outside, and the inner concrete block is in a circular truncated cone-shaped structure with thick outside and thin inside;
the specific manufacturing and installation process for setting the positioning and adjusting assembly in the step (3) is as follows: firstly, horizontally placing a CL net rack plate in a field, enabling the inner side of a polyphenyl plate to face upwards, uniformly forming a plurality of through holes in the polyphenyl plate, enabling a positioning sleeve to penetrate through the through holes, enabling the length of the positioning sleeve to be slightly larger than the distance between an inner steel wire mesh and an outer steel wire mesh, enabling the lower end of the positioning sleeve to be in contact with the ground, coaxially sleeving a mould which is in a circular truncated cone shape and is provided with two through ends, outside the positioning sleeve, enabling the edge of the upper end of the mould to be flush with the positioning sleeve, enabling the edge of the lower end of the mould to be in contact with the polyphenyl plate, forming a through seam for penetrating through the steel wire mesh on the mould, adding concrete into the mould, tamping, scraping off redundant concrete, leveling the top surface of; inserting positioning sleeves into other through holes on the polystyrene board in sequence according to the operation process and manufacturing an inner concrete block; after the inner concrete blocks are completely manufactured, watering and curing the inner concrete blocks, turning up the polystyrene board after at least two days, and manufacturing the outer concrete module according to the manufacturing process of the inner concrete module; after the outer concrete module is watered and maintained, the outer end part of the inner adjusting rod extends into and is in threaded connection with the inner port of the positioning sleeve, and the inner end part of the outer adjusting rod extends into and is in threaded connection with the outer port of the positioning sleeve.
The cart in the step (4) comprises a bottom plate, universal wheels with locking mechanisms are arranged on the bottom surface of the bottom plate, a vertical frame is fixedly arranged on the rear side of the upper surface of the bottom plate, the front side of the vertical frame is arranged in a manner that the front side is low in front and high in back, handrails are arranged on the left side and the right side of the middle part of the rear side of the vertical frame, a support frame is arranged on the upper part of the rear side of the vertical frame, a small hydraulic station is arranged on the support frame, a pushing oil cylinder is fixedly arranged at the top of the small hydraulic station along the front-back horizontal direction, a hooking oil cylinder is fixedly arranged at the front end of a piston rod of the pushing oil cylinder along the vertical direction, a positioning nail is arranged at the lower end of the piston rod of the hooking oil cylinder, the pushing oil cylinder and the hooking oil cylinder are both connected with the small hydraulic station;
the process that the cart in the step (4) conveys the CL net rack plate provided with the positioning and adjusting assembly to a wall construction site comprises the following steps: placing a plurality of CL net frame plates on a bottom plate side by side, enabling a CL net frame plate on the last side to lean against a vertical frame in an inclined mode, enabling other CL net frame plates to lean against adjacent CL net frame plates on the back side in sequence, operating an operation panel, pushing a piston rod of an oil cylinder to extend forwards to a position right above the CL net frame plate on the foremost side to stop, enabling a piston rod of a hook oil cylinder to extend downwards, positioning and pinning the piston rod inside the upper end face of a polystyrene board, and enabling a worker to hold an armrest to push a cart to convey the CL net frame plates to a wall construction site; two annular steel wire ropes are connected to a lifting hook of the tower crane, a piston rod of a pushing oil cylinder is controlled to extend firstly, the upper part of a CL net frame plate at the foremost side is pushed to move forwards to a vertical state through a hooking oil cylinder and a positioning nail, one annular steel wire rope is hung on two inner concrete blocks or outer concrete blocks at the same height at the front side of the CL net frame plate, a worker holds the CL net frame plate in the vertical state firstly, then the piston rod of the hooking oil cylinder is controlled to retract upwards, a positioning needle is separated from the polystyrene plate, the piston rod of the pushing oil cylinder is controlled to move backwards to the upper side of the next polystyrene plate, the piston rod of the hooking oil cylinder extends downwards, the positioning nail is fixed into the polystyrene plate, then the other annular steel wire rope is hung on the two outer concrete blocks or inner concrete blocks at the rear side of the CL net frame plate, the outer concrete blocks and the inner concrete blocks hung by the two annular steel wire, hoisting the CL rack plate to the specified position of the CL rack plate installation control line; sequentially hoisting all CL net rack plates on the cart in place according to the process; in the tower crane operation process, the other cart is provided with the CL net frame plate and pushed to a construction site, the two carts transport the CL net frame plate in turn, and the tower crane does not stop hoisting the CL net frame plate in place; in the CL rack board hoist and mount in-place process, make between two adjacent polyphenyl boards reach the sealed effect of location through protruding ribbing and the cooperation of sealed positioning groove, use overlap joint net piece and iron wire simultaneously and connect two adjacent interior steel wire nets that link up and two adjacent outer steel wire nets that link up as an organic whole.
Before the wall body formwork is installed in the step (5), a release agent is coated on the inner wall of the wall body formwork, the inner limiting plate and the outer limiting plate are rotated in advance according to the thickness of the wall body, the inner adjusting rod moves inwards while rotating in the positioning sleeve, the outer adjusting rod moves outwards while rotating in the positioning sleeve until the distance between the inner limiting plate and the outer limiting plate is equal to the thickness of the wall body, and then the wall body formwork on the inner side is in contact with the inner limiting plate and the wall body formwork on the outer side is in contact with the outer limiting plate.
The concrete process of pouring the self-sealing concrete in the step (6) is as follows: when the hanging hopper for self-sealing concrete is used for pouring, the distance between a discharge hole at the bottom of the hanging hopper and an inlet at the top of the wall body template is as small as possible, a series of cylinders or chutes can be added as necessary to avoid segregation, the height difference of the self-sealing concrete grout surface at the inner side and the outer side of the polystyrene board can be observed in time in the pouring process, and the size of the self-sealing concrete grout surface at the outer side higher than that at the inner side is controlled within 400 mm;
when the self-sealing concrete is pumped, a funnel or a baffle is arranged at the upper opening of the wall body template after the self-sealing concrete falls from the opening of the delivery pipe, so that the concrete enters a mold at a slow speed, the height difference h of the liquid level of the self-sealing concrete generated by different resistance and flow rates of the self-sealing concrete at any section in the wall body template at two sides of the polystyrene board is not more than 400 mm, namely the size of the self-sealing concrete slurry level at the outer side higher than the self-sealing concrete slurry level at the inner side is controlled within 400 mm; in the process of pouring the self-sealing concrete, a specially-assigned person is arranged to observe the liquid level height of the concrete of each section, the liquid level height can be measured through flashlight irradiation and inserted rod during observation, and when the liquid level height difference of the self-sealing concrete at a certain section is close to 400 mm, the self-sealing concrete is poured at the point immediately.
In order to control the flow rate of self-sealing concrete on the inner side and the outer side of the CL net frame plate, a steel pipe for a scaffold is vertically inserted into the thicker side to control the section in the pouring process of the self-sealing concrete, a hook is welded on the steel pipe so as to be conveniently drawn out, and the inner limiting plate and the outer limiting plate play a role of limiting the polystyrene board to keep a vertical state when the polystyrene board is subjected to the pressure of the self-sealing concrete; the mold-entering temperature of the self-sealing concrete is controlled to be 5-35 ℃, and the self-sealing concrete pouring point is arranged at the intersection part of the cross-shaped, T-shaped or L-shaped wall body so as to facilitate the uniform flow of the self-sealing concrete; the same pouring point is preferably used for the push type continuous pouring, and when the pouring points are switched, the next layer of self-sealing concrete is poured before the initial setting of the self-sealing concrete of the front layer.
In the step (6), in order to achieve the purpose of smooth surface when the self-sealing concrete is poured, auxiliary vibration is carried out outside the wall formwork, and a leather hammer, a small flat vibrator or a vibrating rod vibrates from bottom to top along with the pouring of the self-sealing concrete in an auxiliary vibration mode; when the hidden column with a complex steel bar structure or the middle part of the composite shear wall is poured, a small vibrating rod is adopted for proper inserting and tamping, and the obliquely inserted steel bars of the CL net rack plate cannot be touched during inserting and tamping.
When the wall body formwork is in place in the step (5), mortar is paved on the lower part of the wall body formwork or mortar joints are hooked after the wall body formwork is in place, so that mortar return on the lower part of the wall body formwork is prevented;
the wall template frame of the door and window opening is fixedly provided with steel plate corner protectors by wood screws, and the overall rigidity of the door and window frame is ensured and the corners are prevented from deforming and leaking slurry by adopting thickened frames and increased diagonal supports;
sealing the splicing seams of all the wall formworks by adopting a sponge sealing strip pressing measure; auxiliary measures of sticking plastic adhesive tapes or applying sealant can be adopted at local parts as necessary, so that the leakage of cement mortar is practically avoided.
Air vents are reserved at internal corners or other dead corners of the opening, the self-sealing concrete is observed in time during pouring, and the self-sealing concrete is plugged immediately after being filled. To prevent mortar loss.
The concrete process of maintaining the wall body in the step (8) is as follows: because the concrete in the poured CL wall is thin in section and is only 60 mm thick at the outdoor side, in order to prevent the occurrence of drying shrinkage cracks, a plastic film is covered, a curing agent is coated or watering is covered for curing immediately after the wall formwork is removed, and the curing time is not less than 14 d;
when the horizontal length of the concrete layer on the outdoor side of the CL wall body in the same plane exceeds 26m, a vertical separation seam for guiding a shrinkage crack is reserved, the vertical separation seam is arranged at the connecting part of the lower window wall and the partition wall, the main section of the vertical separation seam is a triangle with the outer width and the inner width, the depth is 10-30 mm, and the width is 10-30 mm; after concrete pouring and final setting, the vertical separation joints are cut by a toothless saw or other tools and are blocked by polyurethane or other elastic building joint filling glue for the outer wall; or before concrete pouring, vertically placing a rubber or other flexible elastic material separating strip directly on the inner wall of the wall formwork on the outer side, wherein the separating strip is replaced by a water stop;
after the wall form is removed, the bolt holes are also required to be plugged, the plugged bolt holes are firstly filled with heat insulation materials with the same thickness as the polystyrene board, then dry and hard mortar or fine aggregate concrete is used for filling the two ends of the holes, and the outer surface is coated with a water-based organic silicon waterproof coating, wherein the diameter of the waterproof coating is not less than 3 times of the diameter of the holes;
after the CL wall is constructed, the outer wall surface is subjected to waterproof and anticorrosion treatment, and the treatment method comprises the following steps:
(1) removing dust, oil stains and soft impurities on the wall surface, removing flowing ash, and filling holes and gaps; when the vertical flatness of the wall surface does not meet the requirement, a layer of leveling ash bottom is smeared, and then a protective coating is coated;
(2) the weight ratio of 1: TN-922 Tynen glue 1 and 32.5 cement are placed in a container to be uniformly stirred, the mixture is kept stand for five minutes, after bubbles are removed and the mixture is uniformly stirred, the mixture is coated on a structure base surface which is cleaned completely by a brush method, the brush is coated for one time and then coated for the next time after being dried, and the coating is carried out for three times; the brushing direction is along the vertical direction for up-and-down brushing, so that the brush leakage is prevented; or spraying the mucilage onto the cleaned structure base surface by a spraying method, filtering by a 100-mesh screen during spraying, and diluting the prepared mucilage within 2 hours by adding a proper amount of Tynen mucilage if the mucilage is thickened; after the coating or spraying is finished for three times, TN-921 Tynen glue, 32.5 cement and fine sand are used according to the weight ratio of 1: 1.5: 2, stirring uniformly, standing for 5 minutes, stirring into pasty mortar, throwing and coating on the surface layer by using a napping method, and plastering or pasting a ceramic tile facing within 48 hours after air drying for 4 hours; and 0.3 kg of the tylene rubber 921 and 0.5 kg of the tylene rubber 922 are used for each square meter of wall surface.
By adopting the technical scheme, the invention adopts the mode that at least two trolleys transport and install the CL net rack plate of the positioning and adjusting assembly, and the tower crane does not stop hoisting operation, thereby not only reducing the labor intensity of workers, but also improving the construction efficiency. The small hydraulic station is arranged on the rear side of the top of the vertical frame on the rear side of the cart, and the positioning needle is pricked at the top of the polystyrene board on the last side through the coordinated operation of the pushing oil cylinder and the hooking oil cylinder, so that the position of the polystyrene board can be limited, the stability of the CL net rack board is ensured in the transportation process of the cart, and the CL net rack board is prevented from falling off the cart. In addition, the coordinated operation of the pushing oil cylinder and the hooking oil cylinder can push the CL net rack plate forwards to a vertical state when the tower crane hoists the CL net rack plate, so that the labor intensity of workers can be fully reduced, and the annular steel wire rope can be conveniently hooked. The limiting block plays a role in limiting the backward slipping when the plurality of CL net rack plates are placed on the bottom plate. Because the small hydraulic station and the pushing oil cylinder are both arranged at the top of the rear side of the cart, when the CL net rack plate is not placed on the bottom plate, in order to keep the stability of the cart, a balancing weight is specially arranged at the front side of the lower surface of the bottom plate.
According to the invention, the CL net rack plate is additionally provided with the positioning and adjusting assembly near the construction site, and the positioning and adjusting assembly is used for limiting the positions of the CL net rack plate in the wall formwork at the inner side and the wall formwork at the outer side, so that the phenomena of rib leakage, cracking and bulging caused by the bending of the CL net rack plate due to pressure difference generated at two sides of the CL net rack plate during concrete pouring are avoided. Interior concrete piece and outer concrete piece pass through the position sleeve and are connected as an organic wholely with the polyphenyl board respectively, and inside the concrete piece including the steel wire net is pre-buried in the part, and the steel wire net is pre-buried outside inside the concrete piece partially, also makes interior steel wire net, polyphenyl board and outer steel wire net fixed connection as an organic whole like this, fully strengthens CL rack board's intensity. The inner adjusting rod and the outer adjusting rod are in threaded connection in the positioning sleeve, the length can be adjusted along the axis direction, so that the CL net rack plate is suitable for walls with different thicknesses, and the application range of the CL net rack plate is widened.
According to the invention, two adjacent polystyrene boards are in plug fit with each other through the convex ribs and the convex-concave parts between the sealing and positioning grooves, and the two adjacent and connected inner steel wire meshes and the two adjacent and connected outer steel wire meshes are connected into a whole through the lapping net sheets and the iron wires, so that the connection strength between the CL net frame plates is improved, the stability is enhanced during pouring, and the heat insulation effect of the poured wall body is fully enhanced.
In conclusion, the invention has scientific principle, low labor intensity of workers, high construction efficiency, good heat preservation effect, more energy saving and environmental protection, is suitable for the construction of CL walls with different thicknesses, improves the construction quality, and avoids the defects of external heat preservation of external walls and insufficient durability of internal heat preservation of external walls; realizing the modernization of the building industry and the factory production of building products.
Drawings
Fig. 1 is a schematic structural view of the cart in transporting CL net rack boards;
fig. 2 is a schematic view of a CL net rack plate disposed inside a wall form;
fig. 3 is a schematic view of the connection between two adjacent CL net rack plates.
Detailed Description
The construction method of the CL composite concrete shear wall comprises the following steps,
(1) lifting the CL net rack plate: the CL rack plate is a nonstandard block, the CL composite shear wall is decomposed according to the arrangement condition of the CL composite shear wall in the construction drawing and according to a node detail drawing in the construction drawing and a related technical specification and a construction joint reservation condition, the specification, the size, the peripheral node characteristics, the number and the position of the CL rack plate are expressed in detail, and the CL rack plate is communicated with a professional manufacturer in advance through an order form to produce and supply a goods plan; (ii) a
(2) Placing the purchased CL net rack plate in a temporary field adjacent to a construction site;
(3) uniformly arranging a plurality of positioning and adjusting components on two side surfaces of the CL net rack plate in the leveled construction site; meanwhile, ejecting a wall form in-place control line and a CL grid plate installation control line on a construction site;
(4) the CL net rack plates provided with the positioning and adjusting assemblies are conveyed to a wall construction site by using a trolley, the CL net rack plates are sequentially hoisted into CL net rack plate installation control lines by using a tower crane and are butted, and the CL net rack plates are temporarily positioned by building temporary protective frames by using steel pipes;
(5) respectively installing wall formworks on the inner side and the outer side of the CL net frame plate according to a formwork in-place control line, erecting an operation platform above the wall formworks by adopting a scaffold, wherein the operation platform consists of a platform plate, a guardrail and a ladder stand;
(6) pouring self-sealing concrete into the cavity between the CL net frame plate 9 and the wall formwork 8 on the inner side and the cavity between the CL net frame plate 9 and the wall formwork 8 on the outer side from the top of the wall formwork 8;
(7) removing the wall formwork 8;
(8) maintaining the wall body;
(9) and (5) checking and accepting the wall quality.
As shown in fig. 2, the CL mesh frame plate 9 includes a polystyrene board 10 having a rectangular structure, an inner steel wire mesh 11 and an outer steel wire mesh 12 are respectively disposed on the inner side and the outer side of the polystyrene board 10, the inner steel wire mesh 11 and the outer steel wire mesh 12 are connected by an oblique steel bar 13 penetrating through the polystyrene board 10, a convex rib 14 is disposed on one side of the polystyrene board 10 along the vertical direction, and a sealing and positioning groove 15 is disposed on the other side of the polystyrene board 10 along the vertical direction; the cross sections of the convex ribs 14 and the sealing and positioning grooves 15 are the same in shape and size;
the positioning and adjusting assembly in the step (3) comprises an inner concrete block 16, an outer concrete block 17, a positioning sleeve 18, an inner adjusting rod 19 and an outer adjusting rod 20, wherein the outer side of the inner concrete block 16 is contacted with the inner side surface of the polystyrene board 10, the inner side of the outer concrete block 17 is contacted with the outer side surface of the polystyrene board 10, the positioning sleeve 18 penetrates through the polystyrene board 10 along the inner and outer horizontal directions, the inner end part of the positioning sleeve 18 is embedded in the inner concrete block 16, the outer end part of the positioning sleeve 18 is embedded in the outer concrete block 17, the part of the inner steel wire mesh 11, which is contacted with the inner concrete block 16, is embedded in the inner concrete block 16, the part of the outer steel wire mesh 12, which is contacted with the outer concrete block 17, is embedded in the outer concrete block 17, the outer end part of the inner adjusting rod 19 extends into and is in the inner port of the positioning sleeve 18 in a threaded manner, the inner end part of the outer adjusting, an inner limiting plate 21 is fixedly arranged at the inner end of the inner adjusting rod 19, and an outer limiting plate 22 is fixedly arranged at the outer end of the outer adjusting rod 20;
the specific manufacturing and installation process for setting the positioning and adjusting assembly in the step (3) is as follows: firstly, horizontally placing a CL net rack plate 9 in a field, enabling the inner side of a polyphenyl plate 10 to face upwards, uniformly forming a plurality of through holes in the polyphenyl plate 10, enabling a positioning sleeve 18 to penetrate through the through holes, enabling the length of the positioning sleeve 18 to be slightly larger than the distance between an inner steel wire mesh 11 and an outer steel wire mesh 12, enabling the lower end of the positioning sleeve 18 to be in contact with the ground, coaxially sleeving a mould which is in a circular truncated cone shape and is provided with two through ends outside the positioning sleeve 18, enabling the edge of the upper end of the mould to be flush with the positioning sleeve 18, enabling the edge of the lower end of the mould to be in contact with the polyphenyl plate 10, forming through seams for penetrating the steel wire mesh on the mould, adding concrete into the mould and tamping, scraping off redundant concrete, leveling the top surface of the concrete in the; inserting positioning sleeves 18 into other through holes on the polystyrene board 10 in sequence according to the operation process and manufacturing an inner concrete block 16; after the inner concrete block 16 is completely manufactured, watering and curing the inner concrete block 16, turning up the polystyrene board 10 at least two days later, and manufacturing the outer concrete module according to the manufacturing process of the inner concrete module; after the outer concrete 17 module is watered and cured, the outer end part of the inner adjusting rod 19 extends into and is in threaded connection with the inner port of the positioning sleeve 18, and the inner end part of the outer adjusting rod 20 extends into and is in threaded connection with the outer port of the positioning sleeve 18. The outer concrete block 17 is in a circular truncated cone structure with a thick inner part and a thin outer part, and the inner concrete block 16 is in a circular truncated cone structure with a thick outer part and a thin inner part, so that the demoulding of the mould is convenient.
As shown in fig. 1, the cart in step (4) includes a bottom plate 23, universal wheels 24 having a locking mechanism are provided on the bottom surface of the bottom plate 23, a vertical frame 25 is fixedly provided on the rear side of the upper surface of the bottom plate 23, the front side of the vertical frame 25 is inclined from front to back, handrails 26 are provided on the left and right sides of the rear middle portion of the vertical frame 25, a support frame 27 is provided on the upper portion of the rear side of the vertical frame 25, a small hydraulic station 28 is provided on the support frame 27, a push cylinder 29 is fixedly provided on the top of the small hydraulic station 28 along the front-back horizontal direction, a hook cylinder 30 is fixedly provided on the front end of the piston rod of the push cylinder 29 along the vertical direction, a positioning pin 31 is provided on the lower end of the piston rod of the hook cylinder 30, the push cylinder 29 and the hook cylinder 30 are both connected to the small hydraulic station 28 through a high pressure oil pipe, an operation panel 32 of the small hydraulic station 28, a balancing weight 34 is arranged on the front side of the lower surface of the bottom plate 23;
the process of conveying the CL net rack plate 9 provided with the positioning and adjusting assembly to the wall construction site by the cart in the step (4) comprises the following steps: placing a plurality of CL net frame plates 9 on a bottom plate 23 side by side, enabling one CL net frame plate 9 on the last side to lean against a vertical frame 25 in an inclined mode, enabling other CL net frame plates 9 to lean against adjacent CL net frame plates 9 on the rear side in sequence, operating an operation panel 32, pushing a piston rod of an oil cylinder 29 to extend forwards to the position right above the foremost CL net frame plate 9 to stop, enabling a piston rod of a hook oil cylinder 30 to extend downwards, enabling a positioning nail 31 to be pricked into the upper end face of a polystyrene board 10, and enabling a worker to hold an armrest 26 to push a cart to convey the CL net frame plates 9 to a wall construction site; two annular steel wire ropes are connected to a lifting hook of the tower crane, a piston rod of a pushing cylinder 29 is controlled to extend firstly, the upper part of a CL net frame plate 9 at the forefront side is pushed to move forwards to a vertical state through a hooking cylinder 30 and a positioning nail 31, one annular steel wire rope is hung on two inner concrete blocks 16 or outer concrete blocks 17 at the same height at the front side of the CL net frame plate 9, a worker holds the CL net frame plate 9 at the vertical state firstly, then the piston rod of the hooking cylinder 30 is controlled to retract upwards, a positioning needle is separated from a polyphenyl plate 10, the piston rod of the pushing cylinder 29 is controlled to move backwards to the upper part of the next polyphenyl plate 10, the piston rod of the hooking cylinder 30 extends downwards, the positioning nail 31 is pricked into the polyphenyl plate 10, then the other annular steel wire rope is hung on two outer concrete blocks 17 or inner concrete blocks 16 at the rear side of the CL net frame plate 9, the outer concrete blocks 17 and the inner concrete blocks 16 hung by the two annular steel wire ropes, finally, starting the tower crane, and hoisting the CL net frame plate 9 to the designated position of the CL net frame plate 9 for installing the control line; sequentially hoisting all CL net rack plates 9 on the cart in place according to the process; in the tower crane operation process, the other cart is provided with the CL net frame plate 9 and pushed to a construction site, the two carts transport the CL net frame plate 9 in turn, and the tower crane does not stop hoisting the CL net frame plate 9 in place; in the process of hoisting the CL rack plate 9 in place, the two adjacent polystyrene boards 10 are matched with the sealing and positioning groove 15 through the convex ribs 14 to achieve the effect of positioning and sealing, and meanwhile, the two adjacent and connected inner steel wire nets 11 and the two adjacent and connected outer steel wire nets 12 are connected into a whole by using the lapping net piece 35 and the iron wires, as shown in fig. 3.
In the step (5), before the wall formwork 8 is installed, a release agent is coated on the inner wall of the wall formwork 8, the inner limiting plate 21 and the outer limiting plate 22 are rotated in advance according to the thickness of the wall, the inner adjusting rod 19 rotates in the positioning sleeve 18 and moves inwards, the outer adjusting rod 20 rotates in the positioning sleeve 18 and moves outwards until the distance between the inner limiting plate 21 and the outer limiting plate 22 is equal to the thickness of the wall and stops, after the wall formwork 8 is installed, the inner wall formwork 8 is in contact with the inner limiting plate 21, and the outer wall formwork 8 is in contact with the outer limiting plate 22.
The concrete process of pouring the self-sealing concrete in the step (6) is as follows: when the hanging hopper for the self-sealing concrete is used for pouring, the distance between a discharge hole at the bottom of the hanging hopper and an inlet at the top of the wall body template 8 is as small as possible, a series of cylinders or chutes can be added as necessary to avoid segregation, the height difference of the self-sealing concrete grout surface at the inner side and the outer side of the polystyrene board 10 is observed in time in the pouring process, and the size of the self-sealing concrete grout surface at the outer side higher than that at the inner side is controlled within 400 mm;
when the self-sealing concrete is pumped, a funnel or a baffle is arranged at the upper opening of the wall formwork 8 after the self-sealing concrete falls from the opening of the delivery pipe, so that the concrete enters the formwork at a slow speed, the height difference h of the liquid level of the self-sealing concrete generated by different resistances and flow rates of the self-sealing concrete at two sides of the polystyrene board 10 at any section in the wall formwork 8 is not more than 400 mm, namely the size of the self-sealing concrete slurry level at the outer side higher than that at the inner side is controlled within 400 mm; in the process of pouring the self-sealing concrete, a specially-assigned person is arranged to observe the liquid level height of the concrete of each section, the liquid level height can be measured through flashlight irradiation and inserted rod during observation, and when the liquid level height difference of the self-sealing concrete at a certain section is close to 400 mm, the self-sealing concrete is poured at the point immediately.
In order to control the flow rate of the self-sealing concrete on the inner side and the outer side of the CL net frame plate 9, in the pouring process of the self-sealing concrete, a steel pipe for a scaffold is vertically inserted into the thicker side to control the section, a hook is welded on the steel pipe so as to be convenient to draw out, and the inner limiting plate 21 and the outer limiting plate 22 play a role of limiting the polystyrene board 10 to keep a vertical state when the polystyrene board is stressed by the self-sealing concrete; the mold-entering temperature of the self-sealing concrete is controlled to be 5-35 ℃, and the self-sealing concrete pouring point is arranged at the intersection part of the cross-shaped, T-shaped or L-shaped wall body so as to facilitate the uniform flow of the self-sealing concrete; the same pouring point is preferably used for the push type continuous pouring, and when the pouring points are switched, the next layer of self-sealing concrete is poured before the initial setting of the self-sealing concrete of the front layer.
In order to achieve the purpose of smooth surface when the self-sealing concrete is poured in the step (6), the wall formwork 8 is vibrated in an auxiliary mode in which a leather hammer, a small flat vibrator or a vibrating rod vibrates from bottom to top along with the pouring of the self-sealing concrete; when the hidden column with a complex steel bar structure or the middle part of the composite shear wall is poured, a small vibrating rod is adopted for proper inserting and tamping, and the inclined inserted steel bars 13 of the CL net rack plate 9 cannot be touched during inserting and tamping.
When the wall formwork 8 is in place in the step (5), mortar is paved on the lower part of the wall formwork 8 or mortar joints are hooked after the wall formwork is in place, so that mortar return on the lower part of the wall formwork 8 is prevented;
fixing and additionally arranging steel plate corner protectors on the wall body template 8 frame of the door and window opening by using wood screws, and adopting thickened frames and increased diagonal supports to ensure the integral rigidity of the door and window frame and prevent the corners from deforming and leaking slurry;
sealing the splicing seams of all the wall formworks 8 by adopting a sponge sealing strip pressing measure; auxiliary measures of sticking plastic adhesive tapes or applying sealant can be adopted at local parts as necessary, so that the leakage of cement mortar is practically avoided.
Air vents are reserved at internal corners or other dead corners of the opening, the self-sealing concrete is observed in time during pouring, and the self-sealing concrete is plugged immediately after being filled. To prevent mortar loss.
The concrete process of maintaining the wall body in the step (8) is as follows: because the concrete in the poured CL wall is thin in section and is only 60 mm thick outside the room, in order to prevent the occurrence of drying shrinkage cracks, a plastic film is covered, a curing agent is coated or watered immediately after the wall formwork 8 is removed for curing, and the curing time is not less than 14 d;
when the horizontal length of the concrete layer on the outdoor side of the CL wall body in the same plane exceeds 26m, a vertical separation seam for guiding a shrinkage crack is reserved, the vertical separation seam is arranged at the connecting part of the lower window wall and the partition wall, the main section of the vertical separation seam is a triangle with the outer width and the inner width, the depth is 10-30 mm, and the width is 10-30 mm; after concrete pouring and final setting, the vertical separation joints are cut by a toothless saw or other tools and are blocked by polyurethane or other elastic building joint filling glue for the outer wall; or before concrete pouring, vertically placing a rubber or other flexible elastic material separating strip directly on the inner wall of the wall formwork 8 on the outer side, wherein the separating strip is replaced by a water stop;
after the wall template 8 is removed, the bolt holes are also required to be plugged, the heat insulation materials with the same thickness as the polystyrene board 10 are filled in the plugged bolt holes, then the dry and hard mortar or fine aggregate concrete is used for filling the two ends of the holes, and the outer surface is coated with a water-based organic silicon waterproof coating, wherein the diameter of the waterproof coating is not less than 3 times of the diameter of the holes;
after the CL wall is constructed, the outer wall surface is subjected to waterproof and anticorrosion treatment, and the treatment method comprises the following steps:
(1) removing dust, oil stains and soft impurities on the wall surface, removing flowing ash, and filling holes and gaps; when the vertical flatness of the wall surface does not meet the requirement, a layer of leveling ash bottom is smeared, and then a protective coating is coated;
(2) the weight ratio of 1: TN-922 Tynen glue 1 and 32.5 cement are placed in a container to be uniformly stirred, the mixture is kept stand for five minutes, after bubbles are removed and the mixture is uniformly stirred, the mixture is coated on a structure base surface which is cleaned completely by a brush method, the brush is coated for one time and then coated for the next time after being dried, and the coating is carried out for three times; the brushing direction is along the vertical direction for up-and-down brushing, so that the brush leakage is prevented; or spraying the mucilage onto the cleaned structure base surface by a spraying method, filtering by a 100-mesh screen during spraying, and diluting the prepared mucilage within 2 hours by adding a proper amount of Tynen mucilage if the mucilage is thickened; after the coating or spraying is finished for three times, TN-921 Tynen glue, 32.5 cement and fine sand are used according to the weight ratio of 1: 1.5: 2, stirring uniformly, standing for 5 minutes, stirring into pasty mortar, throwing and coating on the surface layer by using a napping method, and plastering or pasting a ceramic tile facing within 48 hours after air drying for 4 hours; and 0.3 kg of the tylene rubber 921 and 0.5 kg of the tylene rubber 922 are used for each square meter of wall surface.
The present embodiment is not intended to limit the shape, material, structure, etc. of the present invention in any way, and any simple modification, equivalent change and modification made to the above embodiments according to the technical spirit of the present invention are within the scope of the technical solution of the present invention.

Claims (8)

  1. The construction method of the CL composite concrete shear wall comprises the following steps of (1) lifting materials of CL net rack plates: the CL rack plate is a nonstandard block, the CL composite shear wall is decomposed according to the arrangement condition of the CL composite shear wall in the construction drawing and according to a node detail drawing in the construction drawing and a related technical specification and a construction joint reservation condition, the specification, the size, the peripheral node characteristics, the number and the position of the CL rack plate are expressed in detail, and the CL rack plate is communicated with a professional manufacturer in advance through an order form to produce and supply a goods plan; the method is characterized in that:
    (2) placing the purchased CL net rack plate in a temporary field adjacent to a construction site;
    (3) uniformly arranging a plurality of positioning and adjusting components on two side surfaces of the CL net rack plate in the leveled construction site; meanwhile, ejecting a wall form in-place control line and a CL grid plate installation control line on a construction site;
    (4) the CL net rack plates provided with the positioning and adjusting assemblies are conveyed to a wall construction site by using a trolley, the CL net rack plates are sequentially hoisted into CL net rack plate installation control lines by using a tower crane and are butted, and the CL net rack plates are temporarily positioned by building temporary protective frames by using steel pipes;
    (5) respectively installing wall formworks on the inner side and the outer side of the CL net frame plate according to a formwork in-place control line, erecting an operation platform above the wall formworks by adopting a scaffold, wherein the operation platform consists of a platform plate, a guardrail and a ladder stand;
    (6) pouring self-sealing concrete into the cavity between the CL net frame plate and the wall formwork at the inner side and the cavity between the CL net frame plate and the wall formwork at the outer side from the top of the wall formwork;
    (7) removing the wall formwork;
    (8) maintaining the wall body;
    (9) checking and accepting the wall quality;
    the CL rack plate comprises a polystyrene board with a rectangular structure, an inner steel wire mesh and an outer steel wire mesh are respectively arranged on the inner side and the outer side of the polystyrene board and are connected through oblique inserted steel bars penetrating through the polystyrene board, a convex rib is arranged on one side edge of the polystyrene board in the vertical direction, and a sealing positioning groove is formed in the other side edge of the polystyrene board in the vertical direction; the cross sections of the convex edge strips and the sealing positioning grooves are the same in shape and size;
    the positioning and adjusting component in the step (3) comprises an inner concrete block and an outer concrete block, the outer side of the inner concrete block is in contact with the inner side face of the polyphenyl plate, the inner side of the outer concrete block is in contact with the outer side face of the polyphenyl plate, the positioning sleeve penetrates through the polyphenyl plate along the inner horizontal direction and the outer horizontal direction, the inner end portion of the positioning sleeve is embedded in the inner concrete block, the outer end portion of the positioning sleeve is embedded in the outer concrete block, the portion, in contact with the inner concrete block, of an inner steel wire mesh is embedded in the inner concrete block, the portion, in contact with the outer concrete block, of the outer steel wire mesh is embedded in the outer concrete block, the outer end portion of the inner adjusting rod extends into and is in threaded connection with the inner port of the positioning sleeve, the inner end portion of the outer adjusting rod extends into and is in threaded connection with the outer port of the positioning sleeve, an inner limiting plate is fixedly arranged at the inner end of the inner adjusting rod; the outer concrete block is in a circular truncated cone-shaped structure with thick inside and thin outside, and the inner concrete block is in a circular truncated cone-shaped structure with thick outside and thin inside;
    the specific manufacturing and installation process for setting the positioning and adjusting assembly in the step (3) is as follows: firstly, horizontally placing a CL net rack plate in a field, enabling the inner side of a polyphenyl plate to face upwards, uniformly forming a plurality of through holes in the polyphenyl plate, enabling a positioning sleeve to penetrate through the through holes, enabling the length of the positioning sleeve to be slightly larger than the distance between an inner steel wire mesh and an outer steel wire mesh, enabling the lower end of the positioning sleeve to be in contact with the ground, coaxially sleeving a mould which is in a circular truncated cone shape and is provided with two through ends, outside the positioning sleeve, enabling the edge of the upper end of the mould to be flush with the positioning sleeve, enabling the edge of the lower end of the mould to be in contact with the polyphenyl plate, forming a through seam for penetrating through the steel wire mesh on the mould, adding concrete into the mould, tamping, scraping off redundant concrete, leveling the top surface of; inserting positioning sleeves into other through holes on the polystyrene board in sequence according to the operation process and manufacturing an inner concrete block; after the inner concrete blocks are completely manufactured, watering and curing the inner concrete blocks, turning up the polystyrene board after at least two days, and manufacturing the outer concrete module according to the manufacturing process of the inner concrete module; after the outer concrete module is watered and maintained, the outer end part of the inner adjusting rod extends into and is in threaded connection with the inner port of the positioning sleeve, and the inner end part of the outer adjusting rod extends into and is in threaded connection with the outer port of the positioning sleeve.
  2. 2. The CL composite concrete shear wall construction method according to claim 1, characterized in that: the cart in the step (4) comprises a bottom plate, universal wheels with locking mechanisms are arranged on the bottom surface of the bottom plate, a vertical frame is fixedly arranged on the rear side of the upper surface of the bottom plate, the front side of the vertical frame is arranged in a manner that the front side is low in front and high in back, handrails are arranged on the left side and the right side of the middle part of the rear side of the vertical frame, a support frame is arranged on the upper part of the rear side of the vertical frame, a small hydraulic station is arranged on the support frame, a pushing oil cylinder is fixedly arranged at the top of the small hydraulic station along the front-back horizontal direction, a hooking oil cylinder is fixedly arranged at the front end of a piston rod of the pushing oil cylinder along the vertical direction, a positioning nail is arranged at the lower end of the piston rod of the hooking oil cylinder, the pushing oil cylinder and the hooking oil cylinder are both connected with the small hydraulic station;
    the process that the cart in the step (4) conveys the CL net rack plate provided with the positioning and adjusting assembly to a wall construction site comprises the following steps: placing a plurality of CL net frame plates on a bottom plate side by side, enabling a CL net frame plate on the last side to lean against a vertical frame in an inclined mode, enabling other CL net frame plates to lean against adjacent CL net frame plates on the back side in sequence, operating an operation panel, pushing a piston rod of an oil cylinder to extend forwards to a position right above the CL net frame plate on the foremost side to stop, enabling a piston rod of a hook oil cylinder to extend downwards, positioning and pinning the piston rod inside the upper end face of a polystyrene board, and enabling a worker to hold an armrest to push a cart to convey the CL net frame plates to a wall construction site; two annular steel wire ropes are connected to a lifting hook of the tower crane, a piston rod of a pushing oil cylinder is controlled to extend firstly, the upper part of a CL net frame plate at the foremost side is pushed to move forwards to a vertical state through a hooking oil cylinder and a positioning nail, one annular steel wire rope is hung on two inner concrete blocks or outer concrete blocks at the same height at the front side of the CL net frame plate, a worker holds the CL net frame plate in the vertical state firstly, then the piston rod of the hooking oil cylinder is controlled to retract upwards, a positioning needle is separated from the polystyrene plate, the piston rod of the pushing oil cylinder is controlled to move backwards to the upper side of the next polystyrene plate, the piston rod of the hooking oil cylinder extends downwards, the positioning nail is fixed into the polystyrene plate, then the other annular steel wire rope is hung on the two outer concrete blocks or inner concrete blocks at the rear side of the CL net frame plate, the outer concrete blocks and the inner concrete blocks hung by the two annular steel wire, hoisting the CL rack plate to the specified position of the CL rack plate installation control line; sequentially hoisting all CL net rack plates on the cart in place according to the process; in the tower crane operation process, the other cart is provided with the CL net frame plate and pushed to a construction site, the two carts transport the CL net frame plate in turn, and the tower crane does not stop hoisting the CL net frame plate in place; in the CL rack board hoist and mount in-place process, make between two adjacent polyphenyl boards reach the sealed effect of location through protruding ribbing and the cooperation of sealed positioning groove, use overlap joint net piece and iron wire simultaneously and connect two adjacent interior steel wire nets that link up and two adjacent outer steel wire nets that link up as an organic whole.
  3. 3. The CL composite concrete shear wall construction method according to claim 1, characterized in that: before the wall body formwork is installed in the step (5), a release agent is coated on the inner wall of the wall body formwork, the inner limiting plate and the outer limiting plate are rotated in advance according to the thickness of the wall body, the inner adjusting rod moves inwards while rotating in the positioning sleeve, the outer adjusting rod moves outwards while rotating in the positioning sleeve until the distance between the inner limiting plate and the outer limiting plate is equal to the thickness of the wall body, and then the wall body formwork on the inner side is in contact with the inner limiting plate and the wall body formwork on the outer side is in contact with the outer limiting plate.
  4. 4. The CL composite concrete shear wall construction method according to claim 1, characterized in that: the concrete process of pouring the self-sealing concrete in the step (6) is as follows: when the hanging hopper for self-sealing concrete is used for pouring, the distance between a discharge hole at the bottom of the hanging hopper and an inlet at the top of the wall body template is as small as possible, a series of cylinders or chutes can be added as necessary to avoid segregation, the height difference of the self-sealing concrete grout surface at the inner side and the outer side of the polystyrene board can be observed in time in the pouring process, and the size of the self-sealing concrete grout surface at the outer side higher than that at the inner side is controlled within 400 mm;
    when the self-sealing concrete is pumped, a funnel or a baffle is arranged at the upper opening of the wall body template after the self-sealing concrete falls from the opening of the delivery pipe, so that the concrete enters a mold at a slow speed, the height difference h of the liquid level of the self-sealing concrete generated by different resistance and flow rates of the self-sealing concrete at any section in the wall body template at two sides of the polystyrene board is not more than 400 mm, namely the size of the self-sealing concrete slurry level at the outer side higher than the self-sealing concrete slurry level at the inner side is controlled within 400 mm; in the process of pouring the self-sealing concrete, a specially-assigned person is arranged to observe the liquid level height of the concrete of each section, the liquid level height can be measured through flashlight irradiation and inserted rod during observation, and when the liquid level height difference of the self-sealing concrete at a certain section is close to 400 mm, the self-sealing concrete is poured at the point immediately.
  5. 5. The CL composite concrete shear wall construction method according to claim 4, characterized in that: in order to control the flow rate of self-sealing concrete on the inner side and the outer side of the CL net frame plate, a steel pipe for a scaffold is vertically inserted into the thicker side to control the section in the pouring process of the self-sealing concrete, a hook is welded on the steel pipe so as to be conveniently drawn out, and the inner limiting plate and the outer limiting plate play a role of limiting the polystyrene board to keep a vertical state when the polystyrene board is subjected to the pressure of the self-sealing concrete; the mold-entering temperature of the self-sealing concrete is controlled to be 5-35 ℃, and the self-sealing concrete pouring point is arranged at the intersection part of the cross-shaped, T-shaped or L-shaped wall body so as to facilitate the uniform flow of the self-sealing concrete; the same pouring point is preferably used for the push type continuous pouring, and when the pouring points are switched, the next layer of self-sealing concrete is poured before the initial setting of the self-sealing concrete of the front layer.
  6. 6. The CL composite concrete shear wall construction method according to claim 5, characterized in that: in the step (6), in order to achieve the purpose of smooth surface when the self-sealing concrete is poured, auxiliary vibration is carried out outside the wall formwork, and a leather hammer, a small flat vibrator or a vibrating rod vibrates from bottom to top along with the pouring of the self-sealing concrete in an auxiliary vibration mode; when the hidden column with a complex steel bar structure or the middle part of the composite shear wall is poured, a small vibrating rod is adopted for proper inserting and tamping, and the obliquely inserted steel bars of the CL net rack plate cannot be touched during inserting and tamping.
  7. 7. The CL composite concrete shear wall construction method according to claim 6, characterized in that: when the wall body formwork is in place in the step (5), mortar is paved on the lower part of the wall body formwork or mortar joints are hooked after the wall body formwork is in place, so that mortar return on the lower part of the wall body formwork is prevented;
    the wall template frame of the door and window opening is fixedly provided with steel plate corner protectors by wood screws, and the overall rigidity of the door and window frame is ensured and the corners are prevented from deforming and leaking slurry by adopting thickened frames and increased diagonal supports;
    sealing the splicing seams of all the wall formworks by adopting a sponge sealing strip pressing measure; auxiliary measures of sticking plastic adhesive tapes or applying sealant can be adopted at local parts as necessary, so that the leakage of cement mortar is practically avoided; air vents are reserved at internal corners or other dead corners of the opening, the self-sealing concrete is timely observed during pouring, and the self-sealing concrete is immediately plugged after being filled to prevent mortar from losing.
  8. 8. The CL composite concrete shear wall construction method according to claim 1, characterized in that: the concrete process of maintaining the wall body in the step (8) is as follows: because the concrete in the poured CL wall is thin in section and is only 60 mm thick at the outdoor side, in order to prevent the occurrence of drying shrinkage cracks, a plastic film is covered, a curing agent is coated or watering is covered for curing immediately after the wall formwork is removed, and the curing time is not less than 14 d;
    when the horizontal length of the concrete layer on the outdoor side of the CL wall body in the same plane exceeds 26m, a vertical separation seam for guiding a shrinkage crack is reserved, the vertical separation seam is arranged at the connecting part of the lower window wall and the partition wall, the main section of the vertical separation seam is a triangle with the outer width and the inner width, the depth is 10-30 mm, and the width is 10-30 mm; after concrete pouring and final setting, the vertical separation joints are cut by a toothless saw or other tools and are blocked by polyurethane or other elastic building joint filling glue for the outer wall; or before concrete pouring, vertically placing a rubber or other flexible elastic material separating strip directly on the inner wall of the wall formwork on the outer side, wherein the separating strip is replaced by a water stop;
    after the wall form is removed, the bolt holes are also required to be plugged, the plugged bolt holes are firstly filled with heat insulation materials with the same thickness as the polystyrene board, then dry and hard mortar or fine aggregate concrete is used for filling the two ends of the holes, and the outer surface is coated with a water-based organic silicon waterproof coating, wherein the diameter of the waterproof coating is not less than 3 times of the diameter of the holes;
    after the CL wall is constructed, the outer wall surface is subjected to waterproof and anticorrosion treatment, and the treatment method comprises the following steps:
    (1) removing dust, oil stains and soft impurities on the wall surface, removing flowing ash, and filling holes and gaps; when the vertical flatness of the wall surface does not meet the requirement, a layer of leveling ash bottom is smeared, and then a protective coating is coated;
    (2) the weight ratio of 1: TN-922 Tynen glue 1 and 32.5 cement are placed in a container to be uniformly stirred, the mixture is kept stand for five minutes, after bubbles are removed and the mixture is uniformly stirred, the mixture is coated on a structure base surface which is cleaned completely by a brush method, the brush is coated for one time and then coated for the next time after being dried, and the coating is carried out for three times; the brushing direction is along the vertical direction for up-and-down brushing, so that the brush leakage is prevented; or spraying the mucilage onto the cleaned structure base surface by a spraying method, filtering by a 100-mesh screen during spraying, and diluting the prepared mucilage within 2 hours by adding a proper amount of Tynen mucilage if the mucilage is thickened; after the coating or spraying is finished for three times, TN-921 Tynen glue, 32.5 cement and fine sand are used according to the weight ratio of 1: 1.5: 2, stirring uniformly, standing for 5 minutes, stirring into pasty mortar, throwing and coating on the surface layer by using a napping method, and plastering or pasting a ceramic tile facing within 48 hours after air drying for 4 hours; and 0.3 kg of the tylene rubber 921 and 0.5 kg of the tylene rubber 922 are used for each square meter of wall surface.
CN201810256046.8A 2018-03-27 2018-03-27 CL composite concrete shear wall construction method Expired - Fee Related CN108505644B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810256046.8A CN108505644B (en) 2018-03-27 2018-03-27 CL composite concrete shear wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810256046.8A CN108505644B (en) 2018-03-27 2018-03-27 CL composite concrete shear wall construction method

Publications (2)

Publication Number Publication Date
CN108505644A CN108505644A (en) 2018-09-07
CN108505644B true CN108505644B (en) 2019-12-27

Family

ID=63378656

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810256046.8A Expired - Fee Related CN108505644B (en) 2018-03-27 2018-03-27 CL composite concrete shear wall construction method

Country Status (1)

Country Link
CN (1) CN108505644B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258848A (en) * 2019-06-24 2019-09-20 南通大学 A kind of construction method of building energy conservation CL composite shear wall
CN110219378A (en) * 2019-07-22 2019-09-10 中铁建设集团有限公司 A kind of disconnected bridge structure of steel bar template integrated wall heat preservation seam crossing sealing
CN111058552A (en) * 2020-01-08 2020-04-24 北京和筑科技有限公司 Resistance welding steel plate concrete shear wall
CN111502294B (en) * 2020-07-01 2020-09-15 上海建工集团股份有限公司 Automatic installation method of movable precast concrete wallboard
CN112502325A (en) * 2020-12-11 2021-03-16 天长市飞龙金属制品有限公司 Concrete shear wall construction process based on steel grating
CN113006311A (en) * 2021-02-26 2021-06-22 阳翼 Building wall heat preservation and insulation system
CN113502937B (en) * 2021-06-16 2022-04-22 江阴市先锋建筑有限责任公司 Assembled building wall component
CN113585330B (en) * 2021-08-10 2022-07-08 杭州伟业建设集团有限公司 Steel formwork device and anti-tilting method for cast-in-place concrete retaining wall
CN115030510A (en) * 2022-06-28 2022-09-09 中冶天工集团有限公司 Construction method for improving pouring quality of self-compacting concrete of CL board wall
CN114961047A (en) * 2022-07-13 2022-08-30 北京城建北方集团有限公司 Novel construction method of composite concrete shear wall structure

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8632332B2 (en) * 2009-09-10 2014-01-21 Tf Forming Systems, Inc. Vertical concrete form with removable forming panels
CN103469961A (en) * 2013-08-09 2013-12-25 昆山川普自动化科技有限公司 CL grid plate production method
US10006200B2 (en) * 2013-12-17 2018-06-26 Benjamin Baader Insulated concrete panel form and method of making same
CN203701592U (en) * 2014-01-17 2014-07-09 陈荣国 Penetrating-type CL net rack plate formwork supporting assembly
CN204186001U (en) * 2014-10-28 2015-03-04 中冶建工集团有限公司 Shear wall protective layer thickness control device
CN107761975B (en) * 2017-10-24 2019-06-18 中国五冶集团有限公司 A kind of CL integrated plate for heat insulation positioned internal bracket

Also Published As

Publication number Publication date
CN108505644A (en) 2018-09-07

Similar Documents

Publication Publication Date Title
CN108505644B (en) CL composite concrete shear wall construction method
CN108505645B (en) CL composite concrete shear wall cast-in-place construction method
CN107989401B (en) Existing building outer wall reconstruction structure and construction method
CN106150001B (en) A kind of fabricated assembly overall stair construction method
CN112854745A (en) Construction process of assembled building aluminum alloy template
CN112412027A (en) Method for manufacturing large-section special-shaped load-bearing concrete bare concrete member
CN108277908B (en) Energy-saving environment-friendly CL wall engineering construction method
CN102661019B (en) Heat preservation and decoration integrated construction method for outer wall of building
CN110306832B (en) Construction method for integral migration of artistic clear water wall of historical building
CN110552440A (en) safe and environment-friendly construction process for high-strength assembled integral type sandwich heat-insulation shear wall
CN111113628B (en) Construction method for spraying prefabricated T-shaped beam
CN110578338A (en) System capable of moving aluminum alloy template integrally and operation method
CN112502325A (en) Concrete shear wall construction process based on steel grating
CN113944342A (en) Leveling layer hollowing repairing method
CN109296117B (en) Composite hollow inner template light partition wall and construction method
CN111663770A (en) Quick and easy combination and shaping mold for post-cast strip of cast-in-place slab and construction method of quick and easy combination and shaping mold
CN110886488A (en) Intelligent integrated high-rise building machine
CN113914530B (en) Inclined roof fish scale type concrete structure and construction method
CN109707152B (en) Aluminum alloy formwork system and construction method thereof
CN107859337A (en) Steel-structure factory building FPB Light trabses cracking structure constructions
CN209053376U (en) A kind of porous brick external decoration wall cladding system
CN108277894A (en) A kind of plate heat preserving formwork mounting process of concrete shear force wall
CN113565236A (en) Manufacturing process of decorative indoor rammed earth pillar
CN111576681A (en) FS composite heat-preservation construction integrated technology construction process
CN112171853B (en) Stone reverse-beating prefabricated outer wall and production method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Song Meng

Inventor after: Pan Junbo

Inventor after: Gao Liangyan

Inventor after: Fu Guoxin

Inventor after: Liu Baolin

Inventor after: Chen Siye

Inventor after: Liu Yuncai

Inventor before: Song Meng

Inventor before: Liu Yuncai

Inventor before: Ding Xu

Inventor before: Chen Enye

Inventor before: Fu Guoxin

GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191227

Termination date: 20210327