CN108487072A - 一种上跨营业线铁路现浇框架桥快速施工方法 - Google Patents
一种上跨营业线铁路现浇框架桥快速施工方法 Download PDFInfo
- Publication number
- CN108487072A CN108487072A CN201810315591.XA CN201810315591A CN108487072A CN 108487072 A CN108487072 A CN 108487072A CN 201810315591 A CN201810315591 A CN 201810315591A CN 108487072 A CN108487072 A CN 108487072A
- Authority
- CN
- China
- Prior art keywords
- cover board
- construction
- business line
- frame bridge
- line railway
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Abstract
本发明涉及一种上跨营业线铁路现浇框架桥快速施工方法,包括以下步骤:在营业线铁路两侧施工桩基;在桩基顶部施工钢筋混凝土系梁;在系梁顶部施工侧墙;在侧墙顶部吊装预制盖板并使盖板形成简支梁,所述预制盖板的顶部及端头均预留接茬钢筋,将盖板的端头预留接茬钢筋与侧墙钢筋焊接在一起;以盖板作为底模施工顶板,在盖板顶部绑扎顶板钢筋,并将盖板的顶部预留接茬钢筋与顶板钢筋焊接成一体,然后浇筑混凝土形成整体的顶板结构。本发明可以解决上跨营业线框架桥施工时安全风险高、施工投入大、请点施工时间长、施工周期长、影响既有线路运营等问题。
Description
技术领域
本发明涉及一种上跨营业线铁路现浇框架桥快速施工方法,特别适用于上跨营业线铁路框架桥现浇施工。
背景技术
在既有营业线铁路上跨新建框架桥时,为保证框架桥的整体性,一般将框架桥底板及顶板设计成框架现浇结构,然而,在实际施工时采用此设计施工方法存在以下诸多缺陷:
(1)在既有营业线铁路下方开挖底板基坑时,需提前施工D型便梁,对既有线进行加固,并需紧贴既有线施工桩基,安全风险高,需请点施工,施工周期长,对既有线运营影响较大;
(2)在既有营业线铁路下方顶推底板时,施工场地受限,不具备顶推作业,底板只能采取现浇施工工艺,安全风险大,施工周期长;
(3)框架桥顶板采用现浇结构能很好保证框架桥的整体性,然而根据传统设计施工工艺施工顶板时,需搭设钢管门式支架及大跨度顶板模板体系,安全风险高,投入大,请点时间长,施工周期长;
(4)由于既有线接触网为高压线路,搭设钢管门式支架及顶板模板时需请点施工(施工前,向调度部门申请开始施工),且需施工静电板,施工周期长、措施费用投入大;
(5)框架桥施工所搭设的支架模板体系,在后期顶板施工完成需再次拆除,需再次请点施工,投入巨大的人力和财力,且安全风险高,施工周期长。
经申请人检索发现,在现有公开技术中,尚未查询到上跨既有线现浇框架桥的施工方法。
发明内容
本发明要解决技术问题是:提供一种上跨营业线铁路现浇框架桥快速施工方法,可以解决上跨营业线框架桥施工时安全风险高、施工投入大、请点施工时间长、施工周期长、影响既有线路运营等问题。
为了解决上述技术问题,本发明提出的技术方案是:一种上跨营业线铁路现浇框架桥快速施工方法,包括以下步骤:
第一步、在营业线铁路两侧施工桩基;桩基作为跨架桥的下部基础既能将上部荷载传递至持力层,又能抵抗既有线路的侧方压力。
第二步、在营业线铁路每一侧的桩基顶部施工钢筋混凝土系梁,系梁将侧墙荷载传递至桩基。
第三步、在系梁顶部施工侧墙。
第四步、在侧墙顶部吊装预制盖板并使盖板形成简支梁,所述预制盖板的顶部及端头均预留接茬钢筋,将盖板的端头预留接茬钢筋与侧墙钢筋焊接在一起。预制盖板可在侧墙施工的同时按照设计进行生产。
第五步、以盖板作为底模施工顶板,在盖板顶部绑扎顶板钢筋,并将盖板的顶部预留接茬钢筋与顶板钢筋焊接成一体,然后浇筑混凝土形成整体的顶板结构。
本发明对现有技术作了两处主要改进:1)将传统的底板下穿营业线框架结构优化为桩基+系梁的结构形式,取消了底板下穿作业,降低了安全风险,提高了施工效率。2)将传统的框架桥顶板支架法现浇工艺优化为采用预制钢筋混凝土盖板吊装作为顶板底模,作为框架桥的永久结构,然后再在预制盖板上进行框架顶板现浇施工,取消顶板支架法现浇作业,避免了传统框架桥模板拆卸工作及支架的搭设。另外,本发明采用预制盖板作为模板,避免了传统方法静电板的施工,安全系数高。本发明经过上述改进,请点施工时间比传统方法减小70%,施工周期短、效率高、投入小。
附图说明
下面结合附图对本发明作进一步说明。
图1是框架桥的结构示意图。
图2是盖板的安装示意图。
附图标记:桩基1,系梁2,侧墙3,顶板4,预制盖板5,钢轨6,道床7,接触网8,接触网立柱9。
具体实施方式
实施例
如图1和图2所示,本实施例中框架桥横跨在营业线铁路上,接触网8和接触网立柱9从框架桥下方穿过。本实施例的上跨营业线铁路现浇框架桥快速施工方法,包括以下步骤:
第一步、在营业线铁路两侧施工桩基1即在道床7两侧施工桩基1,钢轨6铺设在道床7上。桩基1施工时采用跳孔施工,按照桩基施工原则,相邻桩基1不能同时开挖,桩基1开挖采用人工挖孔桩,开挖过程中,做好护壁及有限空间通风。
在施工桩基1前,需完善既有线防护措施,包括注浆、埋设沉降观测点、防护排架搭设、桩基施工等。在营业线铁路两侧施工桩基前,对影响施工的既有线构筑物进行拆除或迁移,然后根据设计位置做好基坑开挖等既有线防护排架搭设及既有构筑物的拆除工作。
本实施例中,桩基1采用方桩,方桩作为跨架桥的下部基础即能将上部荷载传递至持力层,又能抵抗既有线路的侧方压力。
第二步、在营业线铁路每一侧的桩基1顶部施工钢筋混凝土系梁2。桩基施工完成后,在桩基1之间开槽、立模,并安装钢筋施工系梁2。
第三步、在系梁2顶部施工侧墙3。系梁2施工完成后顶面进行凿毛处理,绑扎钢筋,采用翻模施工侧墙3。
第四步、在侧墙3顶部吊装预制盖板5并使盖板5形成简支梁,所述预制盖板5的顶部及端头均预留接茬钢筋,将盖板5的端头预留接茬钢筋与侧墙钢筋焊接在一起。
第五步、以盖板5作为底模施工顶板4,在盖板5顶部进行凿毛,绑扎顶板钢筋,并将盖板5的顶部预留接茬钢筋与顶板钢筋焊接成一体,然后浇筑混凝土形成整体的顶板结构。盖板吊装根据其重量及距离选择合适的履带吊,盖板吊装后需处理好盖板之间的间隙,采用泡沫胶进行封堵。在顶板施工完成后施工框架桥保护层、防水及栏杆。
本实施例的施工方法对于上跨营业线铁路现浇框架桥施工具有很好的推广效果,避免了传统框架桥底板下穿营业线施工时架设D型便梁加固线路及底板顶推作业施工;避免了传统框架桥顶板跨营业线铁路支架模板搭设拆除作业;避免了静电板安装等请点作业施工等,具有施工安全风险小,投入低,请点作业频率低、时间短,对营业线运营影响小,施工作业速度快的特点,使其在保证结构及运营安全的前提下,大大提高了作业效率、降低了安全风险、缩短了施工周期、减少了营业线运营影响,克服了营业线施工等级高、安全风险高,请点作业施工频率高、时间长,施工周期长,施工措施费用投入大等诸多难题。
本发明不局限于上述实施例所述的具体技术方案,除上述实施例外,本发明还可以有其他实施方式。对于本领域的技术人员来说,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等形成的技术方案,均应包含在本发明的保护范围之内。
Claims (9)
1.一种上跨营业线铁路现浇框架桥快速施工方法,包括以下步骤:
第一步、在营业线铁路两侧施工桩基;
第二步、在营业线铁路每一侧的桩基顶部施工钢筋混凝土系梁;
第三步、在系梁顶部施工侧墙;
第四步、在侧墙顶部吊装预制盖板并使盖板形成简支梁,所述预制盖板的顶部及端头均预留接茬钢筋,将盖板的端头预留接茬钢筋与侧墙钢筋焊接在一起;
第五步、以盖板作为底模施工顶板,在盖板顶部绑扎顶板钢筋,并将盖板的顶部预留接茬钢筋与顶板钢筋焊接成一体,然后浇筑混凝土形成整体的顶板结构。
2.根据权利要求1所述的上跨营业线铁路现浇框架桥快速施工方法,其特征在于:第一步中,人工挖孔桩进行桩基开挖,并保证相邻桩基不能同时开挖。
3.根据权利要求1所述的上跨营业线铁路现浇框架桥快速施工方法,其特征在于:第二步中,在桩基之间开槽、立模,并安装钢筋施工系梁。
4.根据权利要求1所述的上跨营业线铁路现浇框架桥快速施工方法,其特征在于:第三步中,系梁顶面进行凿毛处理,并绑扎钢筋,采用翻模施工侧墙。
5.根据权利要求1所述的上跨营业线铁路现浇框架桥快速施工方法,其特征在于:第四步中,盖板之间的间隙,采用泡沫胶进行封堵。
6.根据权利要求1所述的上跨营业线铁路现浇框架桥快速施工方法,其特征在于:所述盖板为钢筋混凝土板。
7.根据权利要求1所述的上跨营业线铁路现浇框架桥快速施工方法,其特征在于:在营业线铁路两侧施工桩基前,对影响施工的既有线构筑物进行拆除或迁移。
8.根据权利要求1所述的上跨营业线铁路现浇框架桥快速施工方法,其特征在于:在顶板施工完成后施工框架桥保护层、防水及栏杆。
9.根据权利要求1所述的上跨营业线铁路现浇框架桥快速施工方法,其特征在于:所述桩基为方桩。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810315591.XA CN108487072B (zh) | 2018-04-10 | 2018-04-10 | 一种上跨营业线铁路现浇框架桥快速施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810315591.XA CN108487072B (zh) | 2018-04-10 | 2018-04-10 | 一种上跨营业线铁路现浇框架桥快速施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108487072A true CN108487072A (zh) | 2018-09-04 |
CN108487072B CN108487072B (zh) | 2019-07-19 |
Family
ID=63315363
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810315591.XA Active CN108487072B (zh) | 2018-04-10 | 2018-04-10 | 一种上跨营业线铁路现浇框架桥快速施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108487072B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114277695A (zh) * | 2022-01-24 | 2022-04-05 | 中铁上海工程局集团有限公司 | 一种临近营业线钢混凝土组合梁施工方法 |
CN114808663A (zh) * | 2022-04-06 | 2022-07-29 | 北京市市政二建设工程有限责任公司 | 一种桥梁加宽结构及其施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101845793A (zh) * | 2009-12-23 | 2010-09-29 | 中铁大桥局集团第一工程有限公司 | 小角度斜交跨越公路或铁路线路的多跨门式框架墩现浇梁的施工方法 |
CN105064216A (zh) * | 2015-07-29 | 2015-11-18 | 中铁六局集团天津铁路建设有限公司 | 一种顶进超长框架桥时防止既有线路出现横移的方法 |
CN106120853A (zh) * | 2016-06-30 | 2016-11-16 | 中铁第四勘察设计院集团有限公司 | 一种框架桥的逆序施工方法 |
JP2017053196A (ja) * | 2015-09-11 | 2017-03-16 | 清水建設株式会社 | 水平反力調整装置および方法 |
KR101743509B1 (ko) * | 2016-12-26 | 2017-06-07 | 주식회사 더빔 | 내진성능이 강화된 일시적 힌지구조를 가지도록 제작된 라멘교 및 그 시공방법 |
CN107675628A (zh) * | 2017-10-12 | 2018-02-09 | 中铁六局集团有限公司 | 城市道路框架桥上穿运营地铁下穿运营铁路顶进施工方法 |
-
2018
- 2018-04-10 CN CN201810315591.XA patent/CN108487072B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101845793A (zh) * | 2009-12-23 | 2010-09-29 | 中铁大桥局集团第一工程有限公司 | 小角度斜交跨越公路或铁路线路的多跨门式框架墩现浇梁的施工方法 |
CN105064216A (zh) * | 2015-07-29 | 2015-11-18 | 中铁六局集团天津铁路建设有限公司 | 一种顶进超长框架桥时防止既有线路出现横移的方法 |
JP2017053196A (ja) * | 2015-09-11 | 2017-03-16 | 清水建設株式会社 | 水平反力調整装置および方法 |
CN106120853A (zh) * | 2016-06-30 | 2016-11-16 | 中铁第四勘察设计院集团有限公司 | 一种框架桥的逆序施工方法 |
KR101743509B1 (ko) * | 2016-12-26 | 2017-06-07 | 주식회사 더빔 | 내진성능이 강화된 일시적 힌지구조를 가지도록 제작된 라멘교 및 그 시공방법 |
CN107675628A (zh) * | 2017-10-12 | 2018-02-09 | 中铁六局集团有限公司 | 城市道路框架桥上穿运营地铁下穿运营铁路顶进施工方法 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114277695A (zh) * | 2022-01-24 | 2022-04-05 | 中铁上海工程局集团有限公司 | 一种临近营业线钢混凝土组合梁施工方法 |
CN114808663A (zh) * | 2022-04-06 | 2022-07-29 | 北京市市政二建设工程有限责任公司 | 一种桥梁加宽结构及其施工方法 |
CN114808663B (zh) * | 2022-04-06 | 2024-02-02 | 北京市市政二建设工程有限责任公司 | 一种桥梁加宽结构及其施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN108487072B (zh) | 2019-07-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101838968B (zh) | 跨越既有铁路运营线的双线桥施工工艺 | |
CN103243652B (zh) | 一种大跨度非落地式现浇梁膺架及其施工方法 | |
CN105002931B (zh) | 一种大尺寸下穿通道双向预制节段拼装构筑方法 | |
CN111945891B (zh) | 一种环桁架高空原位散拼施工方法 | |
CN107059667A (zh) | 门形装配式钢筋混凝土箱型涵洞及其施工方法 | |
CN102352590A (zh) | 采用桩板式挡墙进行高填方路基拼接的方法 | |
CN108867310A (zh) | 先张法预应力混凝土矮肋t梁桥及其施工方法 | |
CN106894347B (zh) | 一种基于现浇整体化层调坡的拼接桥及桥梁改扩建方法 | |
CN105350526B (zh) | 钢平台的搭设方法 | |
CN105735139A (zh) | 用于立交桥现浇箱梁施工的支撑系统及箱梁的施工方法 | |
CN102286924A (zh) | 一种工序倒置的桥梁施工方法 | |
CN110306559A (zh) | 一种地铁出入口支护桩的施工方法 | |
CN108487072B (zh) | 一种上跨营业线铁路现浇框架桥快速施工方法 | |
CN106320192B (zh) | 一种用于大跨径混凝土连续梁桥的梁段置换加固方法 | |
CN206495233U (zh) | 门形装配式钢筋混凝土箱型涵洞 | |
CN109594581B (zh) | 跨河段管道结构及其安装方法 | |
JP4559370B2 (ja) | 橋梁側方からのエレクションガータによる桁架設工法 | |
CN108589568B (zh) | 一种狭小空间内上跨营业线棚洞t型梁快速施工方法 | |
CN110106915A (zh) | 一种免支撑逆作地下工程施工方法及地下工程建筑结构 | |
CN108277750A (zh) | 高填方深厚软基桩承式大断面多孔现浇箱涵施工方法 | |
CN106592598A (zh) | 同层双榀大直径钢管支撑及其组成的深基坑组合内支撑 | |
CN108755701A (zh) | 深基坑的支撑结构的施工方法 | |
CN205501840U (zh) | 用于立交桥现浇箱梁施工的支撑系统 | |
CN204151662U (zh) | 一种一跨跨越河谷的临时栈桥 | |
CN114562129A (zh) | 一种履带吊上地下室顶板三位一体加固方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |