CN108412153A - A kind of construction method of Non-vibration non-slip lane - Google Patents

A kind of construction method of Non-vibration non-slip lane Download PDF

Info

Publication number
CN108412153A
CN108412153A CN201810100009.8A CN201810100009A CN108412153A CN 108412153 A CN108412153 A CN 108412153A CN 201810100009 A CN201810100009 A CN 201810100009A CN 108412153 A CN108412153 A CN 108412153A
Authority
CN
China
Prior art keywords
slip
construction method
terrace
vibration
special
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810100009.8A
Other languages
Chinese (zh)
Inventor
刘宝堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201810100009.8A priority Critical patent/CN108412153A/en
Publication of CN108412153A publication Critical patent/CN108412153A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Repair (AREA)

Abstract

A kind of construction method of Non-vibration non-slip lane includes mainly base treatment, five steps of priming paint, skid resistant course, face layer and maintenance;Purpose is to solve the problem of that cement track vibrates big, easy dusting and road-ability difference and ship-and-galley tile track, granite track track resistance is small is easy to cause tyre slip.

Description

A kind of construction method of Non-vibration non-slip lane
Technical field
The present invention relates to work China Democratic National Construction Association fields, and in particular to a kind of construction method of Non-vibration non-slip lane.
Background technology
With the development of society, the raising of people's material life, private car ownership is also being significantly increased, and stops to meet Vehicle demand all builds corresponding construction underground parking in big and middle market, cell etc..
But most of track uses cement track, this track not only vibrates big, easy dusting and road-ability is poor, Class is also low;Also have using ship-and-galley tile track, granite track, although improving grade, track resistance is small, is easy to cause wheel Tire, which skids, causes car accident.
Invention content
The present invention provides a kind of construction method of Non-vibration non-slip lane, it is therefore intended that solves to propose in above-mentioned background technology Cement track vibrate big, easy dusting and road-ability difference and ship-and-galley tile track, granite track track resistance are small, hold The problem of easily leading to tyre slip.
To achieve the above object, the present invention provides a kind of construction method of Non-vibration non-slip lane, specifically includes following step Suddenly:
Step 1, base treatment are ground and are cleaned out to base using special grinder, to remove its table The laitance layer in face has without grease, metal pile, building residue etc., to greasy dirt and metal pile by ridge dress watch terrace surface Processing in advance carries out integral grinding polishing to the plain concrete terrace of condensation, removes the terrace surface formed after concreting molding Laitance, and roughness needed for surface to best adhesion of polishing, are then dusted operation, terrace surface to terrace surface floating dust It carries out applying seal coat operation after dedusting, closed concrete surface enhances the cohesive force of coating material and base;
Step 2, priming paint construct by the way of roller coating to Thief zone epoxy primer, it is made to fill closed concrete table Face makes priming paint material permeate base;
Step 3, skid resistant course dominate special glue, and granted full ground after bottom material mix with special glue, formation about 3mm thickness Resistance to compression layer;
Step 4, face layer are applied after mixing fabric with special glue with steamed bun knife or spray gun special after skid resistant course solidification is dry Form the on-slip road of the colored bar shaped of about 3mm thickness;
Step 5, maintenance carry out the i.e. permissible vehicle pass-through of maintenance in two weeks after construction.
Preferably, in step 1, milling is carried out with plane milling disk in advance to the substrate surface of appearance building residue and scrapes processing;It is right When the plain concrete terrace of condensation carries out integral grinding polishing, operation is ground using flattening disc or diamant abrasive disk;Terrace table The dedusting operation of face floating dust is completed using industrial vacuum cleaner operation.
Preferably, in step 2, priming paint roller coating thickness is 1mm.
Preferably, in step 3, the formula of the special glue is hung for the quartz sand of epoxy resin and 70-100 mesh batch matches Add than applying, the ratio of the epoxy resin and quartz sand is 1:3.
Preferably, in step 4, adhesive tape manufacturing is pasted according to design drawing outside the on-slip road.
Specific implementation mode
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to Limit the present invention.
The application principle of the present invention is further described below.
Embodiment one
A kind of construction method of Non-vibration non-slip lane, specifically includes following steps:
Step 1, base treatment are ground and are cleaned out to base using special grinder, to remove its table The laitance layer in face has without grease, metal pile, building residue etc., to greasy dirt and metal pile by ridge dress watch terrace surface Processing in advance carries out integral grinding polishing to the plain concrete terrace of condensation, removes the terrace surface formed after concreting molding Laitance, and roughness needed for surface to best adhesion of polishing, are then dusted operation, terrace surface to terrace surface floating dust It carries out applying seal coat operation after dedusting, closed concrete surface enhances the cohesive force of coating material and base;
Step 2, priming paint construct by the way of roller coating to Thief zone epoxy primer, it is made to fill closed concrete table Face makes priming paint material permeate base;
Step 3, skid resistant course dominate special glue, and granted full ground after bottom material mix with special glue, formation about 3mm thickness Resistance to compression layer;
Step 4, face layer are applied after mixing fabric with special glue with steamed bun knife or spray gun special after skid resistant course solidification is dry Form the on-slip road of the colored bar shaped of about 3mm thickness;
Step 5, maintenance carry out the i.e. permissible vehicle pass-through of maintenance in two weeks after construction.
Wherein, in step 1, milling is carried out with plane milling disk in advance to the substrate surface of appearance building residue and scrapes processing;To solidifying When the plain concrete terrace of knot carries out integral grinding polishing, operation is ground using flattening disc or diamant abrasive disk;Terrace surface The dedusting operation of floating dust is completed using industrial vacuum cleaner operation;In step 2, priming paint roller coating thickness is 1mm;In step 3, The formula of the special glue is hung proportioning painting for the quartz sand of epoxy resin and 70-100 mesh batch and is added, the epoxy resin and quartz sand Ratio be 1:3;In step 4, adhesive tape manufacturing is pasted according to design drawing outside the on-slip road.
A kind of construction technical method of Non-vibration non-slip lane provided by the present invention, efficiently solves speed of application Slowly, the problems such as the easy dusting in track, skidding, and easy construction, it is easily operated, it can speed up the work, shorten the duration of a project, improve Construction quality reduces construction cost.
It should be noted that herein, the terms "include", "comprise" or its any other variant are intended to non-row His property includes, so that the process, method, article or equipment including a series of elements includes not only those elements, and And further include other elements that are not explicitly listed, or further include for this process, method, article or equipment institute it is intrinsic Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including institute State in the process, method, article or equipment of element that there is also other identical elements.
The above is only the specific implementation mode of the present invention, is made skilled artisans appreciate that or realizing this hair It is bright.Various modifications to these embodiments will be apparent to one skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest range caused.

Claims (5)

1. a kind of construction method of Non-vibration non-slip lane, which is characterized in that specifically include following steps:
Step 1, base treatment are ground and are cleaned out to base using special grinder, to remove its surface Laitance layer has without grease, metal pile, building residue etc. by ridge dress watch terrace surface, leading to greasy dirt and metal pile Processing carries out integral grinding polishing to the plain concrete terrace of condensation, removes the terrace surface laitance formed after concreting molding, And roughness needed for surface to best adhesion of polishing, operation, terrace surface dedusting then are dusted to terrace surface floating dust After carry out apply seal coat operation, closed concrete surface, enhance coating material and base cohesive force;
Step 2, priming paint construct by the way of roller coating to Thief zone epoxy primer, so that it is filled closed concrete surface, make Priming paint material permeates base;
Step 3, skid resistant course dominate special glue, and granted full ground after bottom material is mixed with special glue, the resistance to compression of formation about 3mm thickness Layer;
Step 4, face layer are applied to be formed after mixing fabric with special glue after skid resistant course solidification is dry with steamed bun knife or spray gun special The on-slip road of the colored bar shaped of about 3mm thickness;
Step 5, maintenance carry out the i.e. permissible vehicle pass-through of maintenance in two weeks after construction.
2. a kind of construction method of Non-vibration non-slip lane according to claim 1, which is characterized in that in step 1, Milling is carried out with plane milling disk in advance to the substrate surface of appearance building residue and scrapes processing;Integral grinding is carried out to the plain concrete terrace of condensation When polishing, operation is ground using flattening disc or diamant abrasive disk;The dedusting operation of terrace surface floating dust is inhaled using industry The operation of dirt machine is completed.
3. a kind of construction method of Non-vibration non-slip lane according to claim 1, which is characterized in that in step 2, Priming paint roller coating thickness is 1mm.
4. a kind of construction method of Non-vibration non-slip lane according to claim 1, which is characterized in that in step 3, The formula of the special glue is hung proportioning painting for the quartz sand of epoxy resin and 70-100 mesh batch and is added, the epoxy resin and quartz sand Ratio be 1:3.
5. a kind of construction method of Non-vibration non-slip lane according to claim 1, which is characterized in that in step 4, Outside the on-slip road adhesive tape manufacturing is pasted according to design drawing.
CN201810100009.8A 2018-02-01 2018-02-01 A kind of construction method of Non-vibration non-slip lane Pending CN108412153A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810100009.8A CN108412153A (en) 2018-02-01 2018-02-01 A kind of construction method of Non-vibration non-slip lane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810100009.8A CN108412153A (en) 2018-02-01 2018-02-01 A kind of construction method of Non-vibration non-slip lane

Publications (1)

Publication Number Publication Date
CN108412153A true CN108412153A (en) 2018-08-17

Family

ID=63127424

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810100009.8A Pending CN108412153A (en) 2018-02-01 2018-02-01 A kind of construction method of Non-vibration non-slip lane

Country Status (1)

Country Link
CN (1) CN108412153A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056446A (en) * 2018-09-10 2018-12-21 王海 A kind of construction method in shockproof on-slip lane

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100074696A (en) * 2008-12-24 2010-07-02 최문선 Pavement method of a road on the bridge by using modified sulfur binder
CN102251455A (en) * 2011-05-25 2011-11-23 浙江中富建筑集团股份有限公司 Vibration-free anti-slip lane and construction method thereof
CN103790087A (en) * 2012-11-01 2014-05-14 西安联合交通设施工程有限公司 Making method of shockproof non-slip lane system
CN204825548U (en) * 2015-07-22 2015-12-02 云南鑫磊地坪材料科技有限公司 Friction antiskid lane terrace

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100074696A (en) * 2008-12-24 2010-07-02 최문선 Pavement method of a road on the bridge by using modified sulfur binder
CN102251455A (en) * 2011-05-25 2011-11-23 浙江中富建筑集团股份有限公司 Vibration-free anti-slip lane and construction method thereof
CN103790087A (en) * 2012-11-01 2014-05-14 西安联合交通设施工程有限公司 Making method of shockproof non-slip lane system
CN204825548U (en) * 2015-07-22 2015-12-02 云南鑫磊地坪材料科技有限公司 Friction antiskid lane terrace

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056446A (en) * 2018-09-10 2018-12-21 王海 A kind of construction method in shockproof on-slip lane

Similar Documents

Publication Publication Date Title
US6770328B1 (en) Method of making a terrazzo surface from recycled glass
US7614820B2 (en) Non-slick surface-seeded aggregate concrete and method of forming
CN100591878C (en) Integral seamless grinding stone terrace manufacturing technique thereof
CN101591506B (en) Color crystal color-quality floor coating and construction process
CN109826396A (en) A kind of construction method of A grades of fire prevention artistic floors
CN101143986A (en) Terrace paint
CN102493626A (en) Method for manufacturing epoxy colored-stone terrace
CN102251455A (en) Vibration-free anti-slip lane and construction method thereof
CN102744190A (en) Coating method for imitating marble effect
CN100529261C (en) Rolled polymer modified cement-concrete sprayed colour road surface structure, and its construction method
CN106592926A (en) Construction method for epoxy micro-coarse self-leveling floor paint
KR20150052722A (en) Waterborne resin binder for coating flooring, Special mortar for coating flooring, Mixed composition of water-soluble resin binder and exclusive mortar for coating flooring, and method for coating flooring
CN102431246B (en) Skidproof permeable road pad and manufacturing technology thereof
CN102900004A (en) Vibration-free anti-slip lane and construction method thereof
CN103469711B (en) A kind of melting glomerocryst rock non-skip terrace and construction method thereof
CN108412153A (en) A kind of construction method of Non-vibration non-slip lane
AU2008316246B2 (en) Glass veneer on ceramics
KR100780574B1 (en) The method and paved road to protect sliding
US2216250A (en) Stair tread and floor slab surfacing
US20110121484A1 (en) Method of producing a color enhanced surface seeded exposed aggregate concrete
KR101241795B1 (en) Process for paving with non-slip paving material
KR100822588B1 (en) Non-slip mat and its manufacturing and constructuring method
KR100724163B1 (en) Repairing method of bridge or road using waste tire chip
CN202208874U (en) Anti-skid permeable road mat
CN107304632B (en) Stone gum construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180817

RJ01 Rejection of invention patent application after publication