CN108333049B - Test model and test method for loading and then excavating deep underground chamber - Google Patents

Test model and test method for loading and then excavating deep underground chamber Download PDF

Info

Publication number
CN108333049B
CN108333049B CN201810426302.3A CN201810426302A CN108333049B CN 108333049 B CN108333049 B CN 108333049B CN 201810426302 A CN201810426302 A CN 201810426302A CN 108333049 B CN108333049 B CN 108333049B
Authority
CN
China
Prior art keywords
chamber
rigid bearing
surrounding rock
loading
support mechanism
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810426302.3A
Other languages
Chinese (zh)
Other versions
CN108333049A (en
Inventor
高富强
黄强
杨修飞
刘利兵
贾尚星
杨波
何怡
刘翠然
李聪玲
刘欢欢
刘鹏
史百齐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luoyang Institute of Science and Technology
Original Assignee
Luoyang Institute of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luoyang Institute of Science and Technology filed Critical Luoyang Institute of Science and Technology
Priority to CN201810426302.3A priority Critical patent/CN108333049B/en
Publication of CN108333049A publication Critical patent/CN108333049A/en
Application granted granted Critical
Publication of CN108333049B publication Critical patent/CN108333049B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N3/00Investigating strength properties of solid materials by application of mechanical stress
    • G01N3/08Investigating strength properties of solid materials by application of mechanical stress by applying steady tensile or compressive forces
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N33/00Investigating or analysing materials by specific methods not covered by groups G01N1/00 - G01N31/00
    • G01N33/24Earth materials

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Immunology (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Pathology (AREA)
  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Remote Sensing (AREA)
  • Food Science & Technology (AREA)
  • Medicinal Chemistry (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

The invention relates to the field of underground rock mass construction tests, in particular to a test model and a test method for loading and then excavating a deep buried chamber. The model comprises a surrounding rock simulation block, a chamber simulation cavity penetrating through the surrounding rock simulation block and a temporary support mechanism arranged in the chamber simulation cavity, wherein the temporary support mechanism comprises a rigid bearing pipe corresponding to the chamber simulation cavity in shape, a paraffin layer, an electric heating wire for melting the paraffin layer to simulate the excavation and unloading of the chamber and a plurality of paraffin removal holes for guiding melted paraffin into the inner cavity of the rigid bearing pipe are arranged on the outer wall of the rigid bearing pipe. The invention can solve the defect that the excavation and stress loading sequence of the chamber cannot be reflected correctly in the prior art, so that an experimental model can reflect the cracking area and range of the surrounding rock of the real chamber, and further provide accurate reference for the excavation construction of the actual chamber.

Description

Test model and test method for loading and then excavating deep underground chamber
Technical Field
The invention relates to the field of underground rock mass construction tests, in particular to a test model and a test method for loading and then excavating a deep buried chamber.
Background
With the rapid development of traffic engineering and mining engineering, a large amount of chamber space needs to be built in mountain areas and underground by construction units. However, due to the complex environment of underground engineering, the excavation of the chamber is extremely easy to cause the deterioration of surrounding rocks, the phenomena of loosening, cracking, falling rocks and the like of the surrounding rocks, and the large-scale collapse can occur when serious, thereby endangering the construction and the use of the underground engineering. The method of model test is a feasible method for predicting the fracture form and range of surrounding rock by simulating chamber excavation.
When the underground chamber is excavated, peripheral stress is gradually unloaded, surrounding rocks generate radial or annular fracture areas, and the size and the shape of the fracture areas determine the strength and the mode of underground chamber support. Many scholars try to obtain the damage range of the surrounding rock of the chamber through a model test mode, and due to the limitation of test conditions, the method mostly adopts a mode of firstly punching holes and then loading, but has the defect that the excavation sequence and the stress loading sequence of the chamber cannot be reflected correctly, and the experimental model cannot reflect the cracking area and the range of the surrounding rock of the real chamber, so that accurate reference cannot be provided for actual construction.
Disclosure of Invention
The invention aims to provide a test model and a test method for loading and then excavating a deep-buried chamber, which are used for solving the defect that the excavation and stress loading sequence of the chamber cannot be accurately reflected in the prior art, so that the test model can reflect the cracking area and range of surrounding rock of a real chamber, and further provide accurate reference for the actual chamber excavation construction.
In order to solve the technical problems, the invention adopts the following technical scheme: the utility model provides a test model of excavation after loading earlier of deep underground chamber, includes the surrounding rock analog block, runs through the chamber analog chamber of seting up in the surrounding rock analog block and set up the temporary support mechanism in the chamber analog chamber, temporary support mechanism includes the rigidity carrier tube corresponding with chamber analog chamber shape, is equipped with the paraffin layer on the outer wall of rigidity carrier tube, is used for melting the heating wire in order to simulate chamber excavation uninstallation with the paraffin layer and is used for leading into a plurality of wax removal holes in the rigidity carrier tube inner chamber with the paraffin after melting.
Preferably, the heating wire is spirally wound on the outer wall of the rigid bearing tube, two ends of the heating wire are respectively arranged outside the surrounding rock simulation block, and a power supply and a switch for controlling the energization of the heating wire are connected between the two ends of the heating wire.
Preferably, the number of the heating wires is multiple, and the two ends of any one heating wire are provided with marks corresponding to the distribution positions of the heating wires on the rigid bearing tube.
Preferably, the rigid carrier tube is made of a non-conductive polyethylene hard plastic material.
Preferably, the surrounding rock simulation block is cuboid, and the chamber simulation cavities are distributed along the length or width direction of the surrounding rock simulation block.
Preferably, the chamber simulation cavity and the surrounding rock simulation block are integrally formed in a layered ramming mode through the temporary support mechanism.
A test method for loading and then excavating a deep buried chamber comprises the following steps:
1) Prefabricating a rigid bearing pipe according to the shape of a test to-be-excavated chamber, arranging a plurality of wax removing holes on the pipe wall of the rigid bearing pipe at intervals, arranging an electric heating wire on the outer wall of the rigid bearing pipe in a spiral coiling mode, and finally uniformly pouring a paraffin layer on the outer wall of the rigid bearing pipe to obtain the temporary support mechanism;
2) Respectively weighing sand, cement and water according to the mass ratio of 8-12:2.5:1, uniformly stirring the sand and the cement, adding water, and uniformly stirring again to prepare a mixture;
3) Firstly horizontally placing a mold with an open top, taking part of the mixture prepared in the step 2) to be backfilled to the bottom of the mold in a layering manner and tamping, then placing the temporary support mechanism prepared in the step 1) in the mold and on the tamping layer, placing the end part of the heating wire on the temporary support mechanism outside the mold, taking the rest part of the mixture prepared in the step 2), backfilling the mixture in the grinding tool in a layering manner and tamping, finally packaging the mold in a plastic package manner, and after a curing period of 26-30 days, demolding and sampling to prepare the test model of the deep buried chamber after loading;
4) Installing the test model of the deep-buried chamber which is loaded and then excavated in the step 3) on special three-way loading equipment, and uniformly externally loading six faces of the test model of the deep-buried chamber which is loaded and then excavated through a pressure head of the special three-way loading equipment until the specified load is reached, and stopping external loading and stabilizing the load;
5) Sequentially electrifying and heating electric heating wires arranged on the rigid bearing pipes according to the excavation sequence of the laboratory, so that paraffin layers on the rigid bearing pipes are melted in sections and flow into the rigid supporting pipes through the paraffin removal holes, and unloading of the temporary support mechanism on the inner wall of the simulation chamber of the laboratory is realized through melting of the paraffin layers so as to simulate the excavation process of the laboratory;
6) And taking down the test model which is firstly loaded and then excavated in the deep-buried chamber from the special three-way loading equipment, drawing out the temporary support mechanism from the chamber simulation cavity, breaking the surrounding rock simulation block, and recording the damage area and the damage range of the surrounding rock simulation block.
Advantageous effects
The method utilizes the characteristic of quick melting of paraffin after being electrified and heated to realize the excavation of the model chamber under the condition of three-dimensional stress, and has the advantages of high construction speed, high safety, convenient and quick operation and the like; during the test, the test model can be loaded in three directions simultaneously, and the load applied in the three directions can be independently adjusted, so that the test research of the damage of the chamber surrounding rock under different surrounding rock stress conditions is realized.
Drawings
FIG. 1 is a schematic diagram of three loading forces of a surrounding rock simulation block in the test process;
FIG. 2 is a schematic view of the structure of a temporary support mechanism portion of the present invention;
the marks in the figure: 1. surrounding rock simulation block 2, temporary support mechanism 201, heating wire 202, power supply 203, switch 204, wax removing hole 205, paraffin layer 206, rigid bearing tube 3, chamber simulation cavity.
Detailed Description
As shown in fig. 1 and 2, the test model of the deep buried chamber of the present invention comprises a surrounding rock simulation block 1, a chamber simulation cavity 207 penetrating through the surrounding rock simulation block 1, and a temporary support mechanism 2 arranged in the chamber simulation cavity 207.
The surrounding rock simulation block 1 is rectangular, the chamber simulation cavities 207 are distributed along the length or width direction of the surrounding rock simulation block 1, the surrounding rock simulation block 1 is made by ramming a mixture of sand, cement and water which are uniformly mixed, the mass ratio of the sand to the cement to the water is 8-12:2.5:1, and when the strength of a simulated rock body is high, the sand occupation ratio takes a small value, and otherwise takes a large value.
The temporary support mechanism 2 comprises a rigid bearing pipe 206 corresponding to the shape of a chamber simulation cavity 207, wherein a paraffin layer 205, an electric heating wire 201 for melting the paraffin layer 205 to simulate chamber excavation unloading and a plurality of paraffin removal holes 204 for guiding melted paraffin into the inner cavity of the rigid bearing pipe 206 are arranged on the outer wall of the rigid bearing pipe 206. The chamber simulation cavity 207 is integrally formed with the surrounding rock simulation block 1 in a layered ramming mode through the temporary support mechanism 2, so that supporting force is loaded on the inner wall of the chamber simulation cavity 207 through the temporary support mechanism 2, a paraffin layer 205 in the temporary support mechanism 2 is uniformly covered on the outer surface of the rigid bearing pipe 206 in a pouring mode, the paraffin layer 205 is melted through electrifying and heating of the electric heating wire 201, and the melted paraffin flows into the rigid bearing pipe 206 along with the paraffin removal hole 204 to achieve unloading of the supporting force of the temporary support mechanism 2 on the inner wall of the chamber, so that the effect of simulating the chamber excavation process is achieved.
The rigid carrier tube 206 in this embodiment is made of a non-conductive polyethylene hard plastic material. The number of the heating wires 201 is multiple, the plurality of heating wires 201 are respectively spirally wound on the outer wall of the rigid bearing tube 206, two ends of any one heating wire 201 are respectively arranged outside the surrounding rock simulation block 1 in the form of enameled wires, and a power supply 202 and a switch 203 for controlling the energization of the heating wires 201 are connected between the two ends of the heating wires 201. The two ends of any one heating wire 201 are provided with marks corresponding to the distribution positions of the heating wire 201 on the rigid bearing tube 206, in actual operation, the marks can be set to be red, orange, green, blue, purple and other colors according to the distribution positions of the plurality of resistance wires on the rigid bearing tube 206, and numbers such as 1, 2, 3, 4, 5 and the like can also be produced.
The invention discloses a test method for loading and then excavating a deep buried chamber, which comprises the following steps:
1) Firstly, prefabricating a rigid bearing pipe 206 according to the shape of a chamber to be excavated in a test, and arranging a plurality of wax discharging holes 204 on the pipe wall of the rigid bearing pipe 206 in a row and column mode, wherein the wax discharging holes 204 can be arranged in a conical shape, and the small end faces the center of the rigid bearing pipe 206 so as to perform proper guiding action on the melted paraffin layer 205 entering the rigid bearing pipe 206; then, arranging the heating wires 201 on the outer wall of the rigid bearing tube 206 in a spiral coiling mode, ensuring that each smashing heating wire 201 is not contacted with each other, and leading out the two ends of each heating wire 201 in an insulated mode of an enameled wire; finally, uniformly pouring a paraffin layer 205 on the outer wall of the rigid bearing tube 206 to obtain the temporary support mechanism 2;
2) Respectively weighing sand, cement and water according to the mass ratio of 8-12:2.5:1, uniformly stirring the sand and the cement by a stirrer, adding water into the sand and the cement, and stirring again to support the mixture for standby;
3) The mold with the open top is placed horizontally. The mould in this embodiment adopts the 45 steel sheets of high strength to pass through the bolt concatenation to support, and the mould includes bottom plate, preceding curb plate, posterior lateral plate, left side board and right side board, is equipped with turn-ups and bolt hole respectively in bottom plate, preceding curb plate, posterior lateral plate, left side board and the hookup location that right side board corresponds. In the splicing process, the bottom plate is placed on the horizontal ground, the left side plate is installed, and the connecting bolt between the side plate and the bottom plate is screwed; then, respectively installing front and rear side plates, and screwing connecting bolts between the front and rear side plates and the left side plate and the bottom plate; finally, the right side plate is installed and firmly connected with the front and rear side plates and the bottom plate.
After the splicing of the mould is completed, firstly, part of the mixture prepared in the step 2) is backfilled to the bottom of the mould in a layering way and is compacted, and the backfill amount is approximately equal to half of the height of the mould; then placing the temporary support mechanism 2 prepared in the step 1) in a mould and on a ramming layer, placing the end part of the heating wire 201 on the temporary support mechanism 2 outside the mould to avoid sealing the two ends of the heating wire 201 and in the surrounding rock simulation block 1, taking the rest part of the mixture prepared in the step 2), backfilling the mixture into a grinding tool in layers and ramming, finally packaging the mould in a plastic package mode, and after a curing period of 26-30 days, demoulding and sampling to prepare a test model of deep-buried chamber which is firstly loaded and then excavated;
4) Installing the test model of the deep-buried chamber which is loaded and then excavated in the step 3) on special three-way loading equipment, and uniformly externally loading six faces of the test model of the deep-buried chamber which is loaded and then excavated through a pressure head of the special three-way loading equipment until the specified load is reached, and stopping external loading and stabilizing the load;
5) And sequentially electrifying and heating the electric heating wires arranged on the rigid bearing pipe 206 according to the excavation sequence of the laboratory, so that the paraffin layer 205 on the rigid bearing pipe 206 is melted in sections and flows into the rigid supporting pipe through the paraffin discharging holes 204, and the temporary support mechanism 2 is used for unloading the inner wall of the laboratory simulation cavity 207 through the melting of the paraffin layer 205 so as to simulate the excavation process of the laboratory.
6) And after the chamber excavation simulation process is finished, the test model of the deep-buried chamber which is loaded firstly and excavated later is taken down from the special three-way loading equipment, the temporary support mechanism 2 is slowly excavated from the chamber simulation cavity 207, and finally the surrounding rock simulation block 1 is broken and cleaned through receipts and brushes, so that a reference basis is provided for support in the deep-buried chamber construction by recording the damage area and range of the surrounding rock simulation block 1.

Claims (4)

1. The utility model provides a test model of excavation after deep underground chamber loads earlier which characterized in that: the device comprises a surrounding rock simulation block (1), a chamber simulation cavity (3) penetrating through the surrounding rock simulation block (1) and a temporary support mechanism (2) arranged in the chamber simulation cavity (3), wherein the temporary support mechanism (2) comprises a rigid bearing pipe (206) corresponding to the chamber simulation cavity (3), a paraffin layer (205) is arranged on the outer wall of the rigid bearing pipe (206), an electric heating wire (201) for melting the paraffin layer (205) to simulate chamber excavation and unloading, and a plurality of paraffin discharging holes (204) for guiding melted paraffin into the inner cavity of the rigid bearing pipe (206);
the rigid bearing tube (206) is made of non-conductive polyethylene hard plastic material;
the chamber simulation cavity (3) and the surrounding rock simulation block (1) are integrally formed in a layered ramming mode through the temporary support mechanism (2);
the test method for carrying out the loading-before-excavation test of the deep-buried chamber by the test model for carrying out the loading-before-excavation test of the deep-buried chamber comprises the following steps:
1) Firstly prefabricating a rigid bearing pipe (206) according to the shape of a chamber to be excavated in a test, arranging a plurality of wax removing holes (204) on the pipe wall of the rigid bearing pipe (206) at intervals, arranging an electric heating wire (201) on the outer wall of the rigid bearing pipe (206) in a spiral coiling mode, and finally uniformly pouring a paraffin layer (205) on the outer wall of the rigid bearing pipe (206) to obtain the temporary support mechanism (2);
2) Respectively weighing sand, cement and water according to the mass ratio of 8-12:2.5:1, uniformly stirring the sand and the cement, adding water, and uniformly stirring again to prepare a mixture;
3) Firstly horizontally placing a mold with an open top, taking part of the mixture prepared in the step 2) to be backfilled to the bottom of the mold in a layering manner, tamping, then placing the temporary support mechanism (2) prepared in the step 1) in the mold and on the tamping layer, placing the end part of the heating wire (201) on the temporary support mechanism (2) outside the mold, taking the rest part of the mixture prepared in the step 2), backfilling the mixture in the grinding tool in a layering manner, tamping, finally packaging the mold in a plastic package manner, and after a curing period of 26-30 days, demolding and sampling to prepare the test model of deep-buried chamber which is firstly loaded and then excavated;
4) Installing the test model of the deep-buried chamber which is loaded and then excavated in the step 3) on special three-way loading equipment, and uniformly externally loading six faces of the test model of the deep-buried chamber which is loaded and then excavated through a pressure head of the special three-way loading equipment until the specified load is reached, and stopping external loading and stabilizing the load;
5) Sequentially electrifying and heating electric heating wires arranged on the rigid bearing pipe (206) according to the experimental chamber excavation sequence, so that the paraffin layer (205) on the rigid bearing pipe (206) is melted in sections and flows into the rigid bearing pipe (206) through the paraffin discharging holes (204), and unloading of the temporary support mechanism (2) on the inner wall of the chamber simulation cavity (3) is realized through melting of the paraffin layer (205) so as to simulate the chamber excavation process;
6) Taking down the test model of the deep-buried chamber which is firstly loaded and then excavated from the special three-way loading equipment, drawing out the temporary support mechanism (2) from the chamber simulation cavity (3), breaking the surrounding rock simulation block (1) and recording the damage area and range of the surrounding rock simulation block (1).
2. A test model for loading and then excavating a deep underground chamber according to claim 1, wherein: the electric heating wire (201) is spirally wound on the outer wall of the rigid bearing tube (206), two ends of the electric heating wire (201) are respectively arranged outside the surrounding rock simulation block (1), and a power supply (202) and a switch (203) for controlling the electric heating wire (201) to be electrified are connected between the two ends of the electric heating wire (201).
3. A test model for loading and then excavating a deep underground chamber according to claim 2, wherein: the number of the heating wires (201) is multiple, and marks corresponding to the distribution positions of the heating wires (201) on the rigid bearing tube (206) are arranged at two ends of any one heating wire (201).
4. A test model for loading and then excavating a deep underground chamber according to claim 1, wherein: the surrounding rock simulation block (1) is cuboid, and the chamber simulation cavities (3) are distributed along the length or width direction of the surrounding rock simulation block (1).
CN201810426302.3A 2018-05-07 2018-05-07 Test model and test method for loading and then excavating deep underground chamber Active CN108333049B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810426302.3A CN108333049B (en) 2018-05-07 2018-05-07 Test model and test method for loading and then excavating deep underground chamber

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810426302.3A CN108333049B (en) 2018-05-07 2018-05-07 Test model and test method for loading and then excavating deep underground chamber

Publications (2)

Publication Number Publication Date
CN108333049A CN108333049A (en) 2018-07-27
CN108333049B true CN108333049B (en) 2024-01-26

Family

ID=62934942

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810426302.3A Active CN108333049B (en) 2018-05-07 2018-05-07 Test model and test method for loading and then excavating deep underground chamber

Country Status (1)

Country Link
CN (1) CN108333049B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109269907B (en) * 2018-11-09 2020-11-06 中南大学 Rock mass internal excavation unloading simulation experiment device and application method thereof
CN110275008B (en) * 2019-06-11 2021-03-26 同济大学 Non-contact tunnel excavation physical model capable of simulating rainfall and test method
CN114047078B (en) * 2021-10-18 2022-10-11 中南大学 Dynamic excavation unloading test device and test method under true three-dimensional stress state

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0138446A1 (en) * 1983-10-17 1985-04-24 Inco Limited Ground support coating
JPH05107166A (en) * 1991-10-18 1993-04-27 Ngk Insulators Ltd Method for evaluating and testing strength of ceramic parts for insert
CN103278360A (en) * 2013-05-17 2013-09-04 山东科技大学 Reserved chamber simulating test piece manufacturing die assembly and method used for manufacturing test piece
JP2013245546A (en) * 2012-05-30 2013-12-09 Hitachi Zosen Corp Tunnel excavation method
CN103616287A (en) * 2013-11-28 2014-03-05 湖南大学 Laboratory model testing device for tunnel excavation
CN203656527U (en) * 2014-01-07 2014-06-18 洛阳理工学院 Steel arch strain meter fixing device
CN103915030A (en) * 2014-04-24 2014-07-09 湖南大学 Underground engineering tunneling model test device with expanding and contracting function
CN104614242A (en) * 2015-02-01 2015-05-13 东华理工大学 Excavation and surrounding rock stress and strain monitoring model testing device for rock-soil chamber under complicated conditions, and method thereof
CN205805579U (en) * 2016-05-26 2016-12-14 西安科技大学 Coal mine inclined shaft dark cave section excavation supporting constructing structure
CN206114438U (en) * 2016-10-21 2017-04-19 辽宁工程技术大学 Tailings dam model test case based on freeze -thaw cycle effect
CN106771058A (en) * 2016-12-01 2017-05-31 中国矿业大学 A kind of experimental technique of the comprehensive tunneling process in simulation tunnel
CN106996903A (en) * 2017-05-09 2017-08-01 洛阳理工学院 A kind of experimental rig and method for being used to simulate buried Tunnel Rockburst
CN107807051A (en) * 2017-11-23 2018-03-16 中南大学 Simulate the experimental rig and test method of Blasting Excavation off-load under three-dimensional loading environment
CN208239202U (en) * 2018-05-07 2018-12-14 洛阳理工学院 A kind of buried chamber first loads the test model excavated afterwards

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008112631A1 (en) * 2007-03-09 2008-09-18 The Board Of Regents Of The University Of Oklahoma Test cell for applying a shear stress to a test specimen

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0138446A1 (en) * 1983-10-17 1985-04-24 Inco Limited Ground support coating
JPH05107166A (en) * 1991-10-18 1993-04-27 Ngk Insulators Ltd Method for evaluating and testing strength of ceramic parts for insert
JP2013245546A (en) * 2012-05-30 2013-12-09 Hitachi Zosen Corp Tunnel excavation method
CN103278360A (en) * 2013-05-17 2013-09-04 山东科技大学 Reserved chamber simulating test piece manufacturing die assembly and method used for manufacturing test piece
CN103616287A (en) * 2013-11-28 2014-03-05 湖南大学 Laboratory model testing device for tunnel excavation
CN203656527U (en) * 2014-01-07 2014-06-18 洛阳理工学院 Steel arch strain meter fixing device
CN103915030A (en) * 2014-04-24 2014-07-09 湖南大学 Underground engineering tunneling model test device with expanding and contracting function
CN104614242A (en) * 2015-02-01 2015-05-13 东华理工大学 Excavation and surrounding rock stress and strain monitoring model testing device for rock-soil chamber under complicated conditions, and method thereof
CN205805579U (en) * 2016-05-26 2016-12-14 西安科技大学 Coal mine inclined shaft dark cave section excavation supporting constructing structure
CN206114438U (en) * 2016-10-21 2017-04-19 辽宁工程技术大学 Tailings dam model test case based on freeze -thaw cycle effect
CN106771058A (en) * 2016-12-01 2017-05-31 中国矿业大学 A kind of experimental technique of the comprehensive tunneling process in simulation tunnel
CN106996903A (en) * 2017-05-09 2017-08-01 洛阳理工学院 A kind of experimental rig and method for being used to simulate buried Tunnel Rockburst
CN107807051A (en) * 2017-11-23 2018-03-16 中南大学 Simulate the experimental rig and test method of Blasting Excavation off-load under three-dimensional loading environment
CN208239202U (en) * 2018-05-07 2018-12-14 洛阳理工学院 A kind of buried chamber first loads the test model excavated afterwards

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
Mechanism for Controlling Floor Heave of Mining Roadways Using Reinforcing Roof and Sidewalls in Underground Coal Mine;Gangye Guo;《sustainability》;1-15 *
岩爆物理模拟试验研究现状及思考;周辉 等;《岩石力学与工程学报》;第34卷(第5期);915-923 *
露天煤矿爆破震动的模型试验及数值计算;高富强 等;《煤矿安全》;第48卷(第1期);55-58 *

Also Published As

Publication number Publication date
CN108333049A (en) 2018-07-27

Similar Documents

Publication Publication Date Title
CN108333049B (en) Test model and test method for loading and then excavating deep underground chamber
CN105673049B (en) Empty horizontal tunnel model test device and method after a kind of simulation lining wall
CN108709977B (en) Indoor model test device and method for influencing existing subway tunnel by ground overload
US20220234460A1 (en) Precast block for housing and routing electrical power cables, an electric vehicle charging station using the block and a manufacturing method
CN103616287A (en) Laboratory model testing device for tunnel excavation
CN204044148U (en) A kind of centrifugal model test tunnel construction simulation device
CN108643247A (en) Soft clay area rectangle foundation pit bottom soil body reinforced model testing device and test method
CN108535126A (en) A kind of test model and test method of simulation deep tunnel Blasting Excavation
CN114894514B (en) Test system and test method for arch tunnel active support bearing structure model
CN111660409A (en) Large-span tunnel lining model prefabricating device and method in geomechanical model test
CN208902713U (en) Ground preloading influences the indoor model test device of existing subway tunnel
CN205422740U (en) Horizontal tunnel model test device in cavity behind simulation lining wall
CN208239202U (en) A kind of buried chamber first loads the test model excavated afterwards
CN108896736A (en) A kind of vertical physical model and test method for wearing Landslide Hazards of oil-gas pipeline
CN208239223U (en) A kind of test model for simulating deep tunnel Blasting Excavation
CN104634932A (en) Step-by-step controllable unloading test device
CN113640136B (en) Shield segment contraction scale model experimental device and experimental method
CN113848122B (en) Hydraulic tunnel surrounding rock and lining structure simulation test method considering external water pressure
CN214539016U (en) Tunnel full-section excavation simulation system
CN115453086A (en) Preparation method of geological model for simulating pile to penetrate karst caves with different filling states
CN113155626A (en) Tunnel full-section excavation simulation system and method
CN212904265U (en) Self-balancing double-loading mode geomechanical model test device
CN117969292B (en) Tunnel full-scale model test device and construction method thereof
CN113551968B (en) Preparation method of pipe jacking structure and surrounding rock soil body model forming device
CN218674460U (en) Spherical concrete impermeability test piece and test mold and impermeability detection device thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant