CN108331325A - Builder's jack constructing device and method - Google Patents

Builder's jack constructing device and method Download PDF

Info

Publication number
CN108331325A
CN108331325A CN201810132878.9A CN201810132878A CN108331325A CN 108331325 A CN108331325 A CN 108331325A CN 201810132878 A CN201810132878 A CN 201810132878A CN 108331325 A CN108331325 A CN 108331325A
Authority
CN
China
Prior art keywords
shaped steel
main body
rod
concrete main
scaffold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810132878.9A
Other languages
Chinese (zh)
Inventor
施群凯
丁丽祯
惠小军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201810132878.9A priority Critical patent/CN108331325A/en
Publication of CN108331325A publication Critical patent/CN108331325A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/18Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by cantilevers or other provisions mounted in openings in the building, e.g. window openings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/007Devices and methods for erecting scaffolds, e.g. automatic scaffold erectors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/046Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of builder's jack constructing devices, scaffold includes upright bar and cross bar, upright bar is fixedly connected with composition frame body with cross bar, the constructing device includes concrete main body, shaped steel and pull rod, one end of pull rod is connected with the top of concrete main body, the other end is connected with one end of shaped steel, the other end of shaped steel is fixed with steel plate, steel plate is mutually fixed with the lower part of concrete main body by bolt, shaped steel in locating rod is fixed in horizontally disposed and shaped steel upper water plane, with upright bar mutually fix by locating rod.The invention also discloses a kind of construction method of suspending scaffold.It is simpler reliable that the invention enables the constructions of builder's jack, and the stressing conditions of shaped steel are substantially improved in the case where reducing the length of shaped steel, improve the load bearing effect of shaped steel;It avoids to stay on concrete main body simultaneously and sets more hole eye, reduce later stage patch work;And it can guarantee that building structure construction is not affected in building, is conducive to lifting construction progress.

Description

Builder's jack constructing device and method
Technical field
The present invention relates to technical field of building construction, and in particular to a kind of builder's jack constructing device and method.
Background technology
In the builder's jack construction of existing building engineering, the method for generally use is:Length is set according to a certain percentage A shaped steel is set, so that one end of shaped steel is anchored in floor on floor using anchoring piece, and keeps shaped steel other end stretching building external, The upper surface of building outer body is stretched out in the shaped steel set up scaffold again.This method needs to bury anchoring piece on floor in advance, operation Cumbersome and shaped steel, which is anchored in floor, to bring inconvenience to construction in building, and needs to stay in Lou Tishang to set more hole eye, especially On exterior wall, hole eye is dealt with improperly and easily causes water leakage through exterior wall, while can also influence the intensity and durability of building structure, peace Full hidden danger is larger.
Invention content
The technical problem to be solved in the present invention is to provide a kind of builder's jack constructing device and methods so that overhanging foot hand The construction of frame is simpler reliable, and the stressing conditions of shaped steel are substantially improved in the case where reducing the length of shaped steel, are improved The load bearing effect of shaped steel;It avoids to stay on concrete main body simultaneously and sets more hole eye, reduce later stage patch work, be not easy to send out Raw water leakage through exterior wall phenomenon, more conducively ensures the intensity and stress equalization of building structure;In addition it can guarantee building structure in building Construction is not affected, and is conducive to lifting construction progress.
In order to solve the above technical problem, the present invention provides technical solution it is as follows:
A kind of builder's jack constructing device, the scaffold include upright bar and cross bar, and the upright bar is fixedly connected with structure with cross bar At frame body, which includes concrete main body, shaped steel and pull rod, one end of the pull rod and the top phase of concrete main body Connection, the other end is connected with one end of shaped steel, and the other end of shaped steel is fixed with steel plate, under the steel plate and concrete main body Portion is mutually fixed by bolt, and the shaped steel is fixed with locating rod in the upper water plane in the horizontally disposed and described shaped steel, described Locating rod is mutually fixed with upright bar.
The diameter of the locating rod is not less than 22mm, and length is not less than 15cm.
The upper outside of the concrete main body is embedded with draw ring, is fixed with hook on the shaped steel, and the one of the pull rod End hook is hung on the draw ring, and the other end is hooked on the hook.
The pull rod is retractable structure, and the retractable structure includes flower basket bolt, head rod and the second connection Bar, one end of the flower basket bolt are connected with the head end of head rod, the tail end of head rod and concrete main body Top is connected, and the head end of the other end of flower basket bolt and the second connecting rod is connected, the tail end and shaped steel phase of the second connecting rod Connection.
A kind of construction method of suspending scaffold, includes the following steps:
1) locating rod is welded in the upper surface of shaped steel, and in one end welding steel of shaped steel;
2)Steel plate is mutually fixed with the lower part of concrete main body by bolt, and shaped steel is made to keep horizontally disposed;
3)One end of pull rod is connected with the top of concrete main body, the other end is connected with the one end of shaped steel far from steel plate;
4)Locating rod is mutually fixed with the upright bar of scaffold, then cross bar is mutually fixed to the frame body for forming scaffold with upright bar.
The step 1)Middle locating rod and shaped steel are perpendicular.
The step 3)The upper outside of middle concrete main body is embedded with draw ring, and hook, pull rod are fixed on the shaped steel One end be hooked on the draw ring, the other end is hooked on the hook.
The concrete main body buries the strength grade of concrete at draw ring and is not less than C25.
The step 1)The upper surface of Shaped Steel is at least welded with two locating rods being mutually parallel.
The invention has the advantages that:The invention avoids grouted parts so that and the length of shaped steel greatly reduces, and Cooperation is substantially improved the stressing conditions of shaped steel, is improved the load bearing effect of shaped steel with the setting of pull rod;It is avoided simultaneously mixed It is stayed in solidifying soil main body and sets more hole eye, reduced later stage patch work, be not susceptible to water leakage through exterior wall phenomenon, be also conducive to ensure to build The intensity and stress equalization of building structure so that building structure more consolidates durable;In addition it can guarantee building structure construction in building It is not affected, is conducive to lifting construction progress.
Description of the drawings
Fig. 1 is the structural schematic diagram of the present invention;
In figure:1, concrete main body, 2, draw ring, 3, pull rod, 31, flower basket bolt, 32, head rod, the 33, second connecting rod, 4, shaped steel, 5, locating rod, 6, hook, 7, steel plate, 8, bolt, 9, nut, 10, gusset.
Specific implementation mode
The invention will be further described in the following with reference to the drawings and specific embodiments, so that those skilled in the art can be with It more fully understands the present invention and can be practiced, but illustrated embodiment is not as a limitation of the invention.
As shown in Figure 1, a kind of builder's jack constructing device, scaffold includes upright bar and cross bar, and upright bar and cross bar are fixed Frame body is connected and composed, which includes concrete main body 1, shaped steel 4 and pull rod 3, one end of pull rod 3 and concrete main body 1 Top be connected, the other end is connected with one end of shaped steel 4, and the other end of shaped steel 4 is fixed with steel plate 7, steel plate 7 and concrete The lower part of main body 1 is fixed by 8 phase of bolt, and shaped steel 4 is in be fixed with locating rod 5 in horizontally disposed and shaped steel 4 upper water plane, Locating rod 5 is mutually fixed with upright bar.
Wherein, there are four the threaded holes being symmetric, four bolts 8 to pass through threaded hole until running through for setting on steel plate 7 Concrete body 1 is locked after the fixation of shaped steel 4 and concrete main body 1, bolt 8 pass through concrete main body 1 by nut 9 to realize Tightly.
Further, the junction of steel plate 7 and shaped steel 4 is provided with gusset 10, and one end of gusset 10 is mutually welded with steel plate 7, The other end is mutually welded with shaped steel 4, to enhance bonding strength.
Further, the diameter of locating rod 5 is not less than 22mm, and length is not less than 15cm, to ensure bonding strength and positioning Effect.
Further, the upper outside of concrete main body 1 is embedded with draw ring 2, and hook 6 is fixed on shaped steel 4, pull rod 3 One end is hooked on draw ring 2, and the other end is hooked on hook 6.
Wherein, pull rod 3 is retractable structure, ensures tension effects, retractable structure with the entire length of adjusting yoke 3 Including flower basket bolt 31, head rod 32 and the second connecting rod 33, the head of one end and head rod 32 of flower basket bolt 31 End is connected, and the tail end of head rod 32 is connected with the draw ring 2 on the top of concrete main body 1, flower basket bolt 31 it is another End is connected with the head end of the second connecting rod 33, and the tail end of the second connecting rod 33 is connected with the hook 6 on shaped steel 4.Pass through flower The adjusting of basket bolt 31 may make head rod 32 and 33 opposite flower basket bolt 31 of the second connecting rod to stretch out or shrink, to adjust The entire length of whole pull rod 3, tension of the effective adjusting yoke 3 to shaped steel 4.
A kind of construction method of suspending scaffold, includes the following steps:
1) in the upper surface vertical welding locating rod 5 of shaped steel 4, and in one end welding steel 7 of shaped steel 4;
Further, the upper surface of shaped steel 4 is welded with two locating rods being mutually parallel 5, and the spacing of two locating rods 5 is equal to foot The width of hand cradle, to play preferable positioning action to scaffold;It should be understood that the quantity of locating rod 5 also can be according to reality Situation is increased, to better ensure that the stable degree of the locating effect and follow-up scaffold building of locating rod 5;Locating rod 5 can Using steel pipe or reinforcing bar.
2)Steel plate 7 mutually to be fixed with the lower outside of concrete main body 1 by bolt 8,8 tail end of bolt is locked by nut 9, And shaped steel 4 is made to keep horizontally disposed;
3)One end of pull rod 3 is connected with the top of concrete main body 1, the other end is connected with the one end of shaped steel 4 far from steel plate 7 It connects;
Specifically:The fixed hook 6 on the embedded draw ring 2 of the upper outside of concrete main body 1, shaped steel 4, one end of pull rod 3 hook On draw ring 2, the other end is hooked on hook 6;
Wherein, concrete main body 1 bury the strength grade of concrete at draw ring 2 be not less than C25, with ensure draw ring 2 bear compared with It will not be got loose when big pulling force.
4)Locating rod 5 is mutually fixed with the upright bar of scaffold, then cross bar is mutually fixed to the frame body for forming scaffold with upright bar.
The specification type of its Shaped Steel 4, pull rod 3, bolt 8,2 rings of drawing etc. can set up scaffold according to the top of shaped steel 4 Height and the size etc. of bearing load are calculated.
The builder's jack constructing device and construction method of the present embodiment so that the construction of builder's jack is simpler can It leans on, avoids and shaped steel 4 is fixed using anchorage style, avoid grouted part so that the length of shaped steel 4 greatly reduces, and coordinates With the setting of pull rod 3, the stressing conditions of shaped steel are substantially improved, the deformation of shaped steel 4 can be more effectively reduced, improve shaped steel 4 Load bearing effect, and shaped steel dosage is saved, improve working security;It avoids to stay on concrete main body 1 simultaneously and sets more hole Eye, reduces later stage patch work, is not susceptible to water leakage through exterior wall phenomenon, is also conducive to ensure that the intensity of building structure and stress are equal Weighing apparatus property so that building structure more consolidates durable;In addition building structure construction is not yet in the case of no grouted part, in building It is vulnerable to influence, is conducive to lifting construction progress;Simple in structure, formed steel construction and cantilever span are unified, are convenient for batch machining.
Embodiment described above is only to absolutely prove preferred embodiment that is of the invention and being lifted, protection model of the invention It encloses without being limited thereto.Those skilled in the art on the basis of the present invention made by equivalent substitute or transformation, in the present invention Protection domain within.Protection scope of the present invention is subject to claims.

Claims (9)

1. a kind of builder's jack constructing device, the scaffold includes upright bar and cross bar, and the upright bar is fixedly connected with cross bar Constitute frame body, characterized in that the constructing device includes concrete main body, shaped steel and pull rod, one end of the pull rod and concrete The top of main body is connected, and the other end is connected with one end of shaped steel, and the other end of shaped steel is fixed with steel plate, the steel plate and mixed The lower part of solidifying soil main body is mutually fixed by bolt, and the shaped steel is fixed in the upper water plane in the horizontally disposed and described shaped steel Locating rod, the locating rod are mutually fixed with upright bar.
2. builder's jack constructing device as described in claim 1, characterized in that the diameter of the locating rod is not less than 22mm, length are not less than 15cm.
3. builder's jack constructing device as described in claim 1, characterized in that the upper outside of the concrete main body is buried Equipped with draw ring, hook is fixed on the shaped steel, one end of the pull rod is hooked on the draw ring, and the other end is hooked on described On hook.
4. builder's jack constructing device as described in claim 1, characterized in that the pull rod is retractable structure, described Retractable structure includes flower basket bolt, head rod and the second connecting rod, one end of the flower basket bolt and head rod Head end be connected, the tail end of head rod is connected with the top of concrete main body, the other end of flower basket bolt and second The head end of connecting rod is connected, and the tail end of the second connecting rod is connected with shaped steel.
5. a kind of construction method of suspending scaffold, characterized in that include the following steps:
1) locating rod is welded in the upper surface of shaped steel, and in one end welding steel of shaped steel;
2)Steel plate is mutually fixed with the lower part of concrete main body by bolt, and shaped steel is made to keep horizontally disposed;
3)One end of pull rod is connected with the top of concrete main body, the other end is connected with the one end of shaped steel far from steel plate;
4)Locating rod is mutually fixed with the upright bar of scaffold, then cross bar is mutually fixed to the frame body for forming scaffold with upright bar.
6. construction method of suspending scaffold as claimed in claim 5, characterized in that the step 1)Middle locating rod and shaped steel phase Vertically.
7. construction method of suspending scaffold as claimed in claim 5, characterized in that the step 3)Middle concrete main body it is upper It is embedded with draw ring on the outside of portion, hook is fixed on the shaped steel, one end of pull rod is hooked on the draw ring, and the other end is hooked on On the hook.
8. construction method of suspending scaffold as claimed in claim 7, characterized in that the concrete main body is buried at draw ring Strength grade of concrete is not less than C25.
9. construction method of suspending scaffold as claimed in claim 5, characterized in that the step 1)The upper surface of Shaped Steel is extremely It is welded with two locating rods being mutually parallel less.
CN201810132878.9A 2018-02-08 2018-02-08 Builder's jack constructing device and method Pending CN108331325A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810132878.9A CN108331325A (en) 2018-02-08 2018-02-08 Builder's jack constructing device and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810132878.9A CN108331325A (en) 2018-02-08 2018-02-08 Builder's jack constructing device and method

Publications (1)

Publication Number Publication Date
CN108331325A true CN108331325A (en) 2018-07-27

Family

ID=62927386

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810132878.9A Pending CN108331325A (en) 2018-02-08 2018-02-08 Builder's jack constructing device and method

Country Status (1)

Country Link
CN (1) CN108331325A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110397042A (en) * 2019-07-13 2019-11-01 济邦建设集团有限公司 A kind of support system of deep basal pit
CN113322972A (en) * 2021-05-21 2021-08-31 广东省建筑工程集团有限公司 Support structure for reducing length-to-thickness ratio of lattice column of deep foundation pit and construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3850306B2 (en) * 2002-02-14 2006-11-29 株式会社国元商会 Scaffolding plate support device for veranda handrail
CN201546435U (en) * 2009-11-11 2010-08-11 龙信建设集团有限公司 Bolted stayed cantilever scaffold
CN202209044U (en) * 2011-08-15 2012-05-02 江苏南通二建集团有限公司 Turnbuckle draw bar type overhanging scaffold
CN203961238U (en) * 2014-07-22 2014-11-26 四川省第十五建筑有限公司 Bolt anchor slab adjustable tool formula builder's jack
CN105926925A (en) * 2016-06-21 2016-09-07 中天建设集团有限公司天津分公司 Joist steel cantilever beam of suspended scaffold and construction method thereof
CN106930531A (en) * 2017-05-03 2017-07-07 中建二局第二建筑工程有限公司华东分公司 A kind of pull-up manomelia is encorbelmented the construction method of heavy frame
CN206562753U (en) * 2017-01-25 2017-10-17 周成军 Adjustable steel wire rope builder's jack constructing device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3850306B2 (en) * 2002-02-14 2006-11-29 株式会社国元商会 Scaffolding plate support device for veranda handrail
CN201546435U (en) * 2009-11-11 2010-08-11 龙信建设集团有限公司 Bolted stayed cantilever scaffold
CN202209044U (en) * 2011-08-15 2012-05-02 江苏南通二建集团有限公司 Turnbuckle draw bar type overhanging scaffold
CN203961238U (en) * 2014-07-22 2014-11-26 四川省第十五建筑有限公司 Bolt anchor slab adjustable tool formula builder's jack
CN105926925A (en) * 2016-06-21 2016-09-07 中天建设集团有限公司天津分公司 Joist steel cantilever beam of suspended scaffold and construction method thereof
CN206562753U (en) * 2017-01-25 2017-10-17 周成军 Adjustable steel wire rope builder's jack constructing device
CN106930531A (en) * 2017-05-03 2017-07-07 中建二局第二建筑工程有限公司华东分公司 A kind of pull-up manomelia is encorbelmented the construction method of heavy frame

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110397042A (en) * 2019-07-13 2019-11-01 济邦建设集团有限公司 A kind of support system of deep basal pit
CN113322972A (en) * 2021-05-21 2021-08-31 广东省建筑工程集团有限公司 Support structure for reducing length-to-thickness ratio of lattice column of deep foundation pit and construction method

Similar Documents

Publication Publication Date Title
CN102661054B (en) Lateral reinforcing structure in whole lifting of plane steel truss and whole lifting method
CN208293567U (en) A kind of detachable hangs muscle system for borehole filling pile cage of reinforcement
CN102864795A (en) Light steel factory post foundation suitable for sedimentation of filled-in ground and construction method
CN104389419A (en) Cantilevered formwork platform installation structure and construction method
CN108331325A (en) Builder's jack constructing device and method
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN204266133U (en) A kind of pier stud reinforcing cage whole lifting structure
CN203654708U (en) Side slope scaffold unloading device
CN103866692A (en) Novel assembling method for bent cap bearing frame
CN205329738U (en) Novel umbelliform ground bearing capacity detecting device
CN205663175U (en) Adjustable reinforcing pull rod formula scaffold frame of encorbelmenting
CN202809636U (en) Light steel plant column foundation adapted to filling subgrade settlement
CN206034887U (en) I -steel cantilever beam of suspension type scaffold frame
CN202766974U (en) Bent cap bearing frame without full framing
CN204876620U (en) Peripheral hardware concrete frame reinforced structure
CN109138272A (en) A kind of Super High rod iron group is connected and fixed device and method
CN205677156U (en) Hang mould special utility supporting steel bar
CN209261322U (en) A kind of indirect dry cooling tower X-type rod structure
CN205205847U (en) Frame construction of stake cushion cap
CN208934257U (en) A kind of Super High rod iron group is connected and fixed device
CN209523450U (en) A kind of adjustable exterior wall builder's jack drawknot structure
CN204385762U (en) A kind of Rock Bolt Foundation structure
CN203531413U (en) Auxiliary structure hoisting whole steel structure wire frame
CN210002829U (en) shear wall ligature installation operation platform
CN202658874U (en) Flexible wall connecting piece device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180727