CN108301529A - A kind of construction method of building heat preservation wall - Google Patents

A kind of construction method of building heat preservation wall Download PDF

Info

Publication number
CN108301529A
CN108301529A CN201810086547.6A CN201810086547A CN108301529A CN 108301529 A CN108301529 A CN 108301529A CN 201810086547 A CN201810086547 A CN 201810086547A CN 108301529 A CN108301529 A CN 108301529A
Authority
CN
China
Prior art keywords
thermal insulation
insulation board
wall
installation
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810086547.6A
Other languages
Chinese (zh)
Other versions
CN108301529B (en
Inventor
栾清扬
谢冬冬
韦甦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University of Technology ZJUT
Original Assignee
Zhejiang University of Technology ZJUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University of Technology ZJUT filed Critical Zhejiang University of Technology ZJUT
Priority to CN201810086547.6A priority Critical patent/CN108301529B/en
Publication of CN108301529A publication Critical patent/CN108301529A/en
Application granted granted Critical
Publication of CN108301529B publication Critical patent/CN108301529B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • E04B1/762Exterior insulation of exterior walls
    • E04B1/7625Details of the adhesive connection of the insulation to the wall
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • E04B1/762Exterior insulation of exterior walls
    • E04B1/7629Details of the mechanical connection of the insulation to the wall
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • E04B1/78Heat insulating elements
    • E04B1/80Heat insulating elements slab-shaped
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/166Landings, receiving platforms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Electromagnetism (AREA)
  • Acoustics & Sound (AREA)
  • Mechanical Engineering (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Finishing Walls (AREA)
  • Building Environments (AREA)

Abstract

The invention discloses a kind of construction methods of building heat preservation wall, include the following steps:Base cleaning;Surveying setting-out;The lifting of operation platform;The installation of plank is fixed;Detection.Short construction period of the present invention, construction is simple, constructing operation is safer, wall can be effectively prevent hollowing warping phenomenon occur simultaneously, effectively extend the service life of wall, and the sound-insulating effect of the wall is more preferable, effectively enhance the functional characteristic of building heat preservation wall, all kinds of planks used in construction can be carried out by classification division by the design of plank mounting table in the present invention, plank mounting table is fixedly connected with operation platform again, with high-altitude is lifted into together with operation platform, it not only can taking in order to construction personnel, shorten construction period, and construction safety performance can be improved again.

Description

A kind of construction method of building heat preservation wall
Technical field
The present invention relates to a kind of construction methods of building heat preservation wall.
Background technology
Insulated wall necessarily plays the role of insulation as its name suggests, and indoor temperature is maintained to stablize, and refers to and uses centainly Fixed form(Bonding, mechanical anchor, stickup+mechanical anchor, spraying, cast etc.), thermal coefficient is relatively low(That is thermal insulation separation thermal effect Fruit is preferable)Heat-insulating material be fixed as one with building masonry wall, increase the evenly heat resistance value of wall, to reach heat preservation or it is heat-insulated A kind of engineering way of effect.
Exterior-wall heat insulation is by polymer mortar, fiberglass gridding cloth, flame retardant type molded polystyrene foams plate(EPS)Or Extruded sheet(XPS)Equal Material claddings form, and scene bonds construction.
Existing insulated wall in the construction process, is in high-altitude construction operation, but typically just simple in existing construction The lug boss that plank is placed on to operation platform, there are some potential safety problems, plank is easy from falling from high altitude, nor It takes to plank convenient for construction personnel.Existing heat insulation wall structure heat insulation effect is good simultaneously, but soundproof effect is general, the later stage Wall is also susceptible to phenomena such as hollowing warpage in use, influences the actual use of wall.
Invention content
Present invention aims at a kind of construction method of building heat preservation wall is provided for deficiency of the prior art Technical solution, short construction period, construction is simple, constructing operation is safer, while wall can be effectively prevent hollowing occur and stuck up Qu Xianxiang effectively extends the service life of wall, and the sound-insulating effect of the wall is more preferable, effectively enhances building heat preservation The functional characteristic of wall.
A kind of construction method of building heat preservation wall, it is characterised in that include the following steps:
Step 1: base cleaning:
Step 1.1 clears up base course wall surface, knocks out hollowing, and levelling metope clears up sundries, it is ensured that base course wall surface It is dry, clean, then review measurement is carried out to the outer profile size of wall, drawing Deepen Design is carried out, determines line setting, and Installation block number, area and the specification of thermal insulation board, sound panel, decorative panel are determined according to wall size;
Thermal insulation board used in construction, sound panel, decorative panel are transported to job location by step 1.2, and according to different sizes It is fitly stacked on the ground with type;
Step 2: surveying setting-out:
Snap the line setting-out is carried out to surface of wall, horizontal control lines and degree control line is set, has reset the level of each floor Control line and mounting plane line;
Step 3: the lifting of operation platform:
Step 3.1 is first in operation platform upper mounting plate material mounting table, by the fixed plate and operation platform of plank mounting table bottom Be fixedly connected, installation bolt passes through the mounting hole at fixed plate both ends to be connected and fixed with operation platform, to by plank mounting table and Operation platform connects, and plank mounting table adjusts the distance between placing frame and operation platform after installation is complete, and pulling manually pulls Handle pulls handle and drives placing frame to be slided on slide bar by sliding block, changes the position of placing frame so that placing frame is moved to At appropriate position, convenient for taking to plank when construction;
Step 3.2 then carries out the placement of thermal insulation board, sound panel and decorative panel, will be met according to the installation requirements at position to be onstructed Thermal insulation board, sound panel, the decorative panel of installation dimension are placed in the placing frame on plank mounting table, by different types of heat preservation Plate, sound panel, decorative panel are placed in different placing frames, while by various sizes of thermal insulation board, sound panel or decorative panel It is placed in different placing frames, realizes that the classification of plank divides, be convenient for subsequent construction operation;
Step 3.3 again fixes the both ends of operation platform and hanging apparatus installation, and carries out safety detection, after detection is qualified, Construction personnel stands on operation platform, and operation platform is lifted at the metope to be onstructed in high vacancy by hanging apparatus, is applied Worker person again carries out wall the installation of plank;
Step 4: the installation of plank is fixed:
The installation of step 4.1 thermal insulation board:
Step 4.1.1 determines the installation site of thermal insulation board according to design drawing first, is consolidated in the installed position of thermal insulation board The installation for determining part installs the first fixing piece at the bottom edge both ends of thermal insulation board, and is with the horizontal direction on every piece of thermal insulation board bottom edge Datum line, it is ensured that the bottom surface of the first support baseboard is aligned with datum line, and then the position according to the connecting hole on fixed side panel is true Determine the position of installation hole, then remove the first fixing piece and drill, then by the bottom surface of the first support baseboard and datum line weight It closes, is then fixedly connected with the first fixing piece with surface of wall by hook screw;
Step 4.1.2 then uniform coated polymer mortars on the bonding interface layer of thermal insulation board, while reserving thermal insulation board bottom Then thermal insulation board is pasted surface of wall by the position at side both ends, and the surrounding of thermal insulation board is tapped using rubber hammer, and adjustment is protected The verticality and levelness of warm plate, while ensuring that the bottom both ends of thermal insulation board snap onto in the first card slot of the first fixing piece, then Thermal insulation board is flattened, ensures its flatness and adhesion firmness;
Step 4.1.3 installs the second fixing piece at the top surface both ends of thermal insulation board again, it is ensured that the second fixing piece and the first fixing piece pair Claim setting, while the top of thermal insulation board snaps onto in the second card slot of the second fixing piece, then uses hook screw by second Support bottom plate is fixedly connected with the top surface of thermal insulation board;
First piece of thermal insulation board of step 4.1.4 after installation is complete, on the installation foundation of first piece of thermal insulation board press by second piece of thermal insulation board Installed according to the installation steps of first piece of thermal insulation board, while being fitted closely between adjacent two pieces of thermal insulation boards, adjacent thermal insulation board it Between gap be less than 2mm, until complete integral wall laying;
The installation of step 4.2 sound panel:
One layer of sound panel is installed in the outside of thermal insulation board layer, sound panel is covered on thermal insulation board, first by the top margin of sound panel two End is fixedly connected by hook screw with the second snap-gauge on the second fixing piece respectively, then the bottom edge both ends of sound panel are led to respectively Hook screw is crossed to be fixedly connected with the first snap-gauge on the first fixing piece;
The installation of step 4.3 grid cloth:
First in the cracking resistance mucilage layer of one layer of 15mm~25mm thickness of the external coating of sound panel layer, then on cracking resistance mucilage layer upper berth If layer of glass fiber grid cloth, and be fixedly connected with glass fiber reticular cloth with cracking resistance mucilage layer with expansion anchor, then in fiberglass mesh Brush the cracking resistance mucilage layer of one layer of 10mm~12mm thickness in the outer surface of cloth;
The installation of step 4.4 decorative panel:
After grid cloth installs, in the outer surface sticking decorative board of outermost cracking resistance mucilage layer, in the bonding interface of decorative panel Uniform coated polymer mortar on layer, then pastes cracking resistance rubber cement layer surface, and flatten compacting, insulation and decoration by decorative panel After plate pastes 72h, its surface is cleared up, the cleaning in adjacent decoration plate stitch gap is kept, foam is then inserted in gap Sealing material;
Step 5: detection:
After the construction for completing entire insulated wall, final detection process is carried out to construction wall.
Further, in step 5, entire heat-preserving wall is detected using random sampling, per 50m2It spot-check a bit, And it makes a record, evaluates quality, to further being detected around the undesirable test point of quality, increase test point Number subsequently carries out maintenance consolidation to undesirable wall again.
Further, in step 4, in the construction process, when the thermal insulation board, sound panel or decorative panel of placing frame front end make When being finished, pusher cylinder is elapsed thermal insulation board, sound panel or the decorative panel in placing frame toward placing frame front end by scraping wings, directly The front end of placing frame is moved to thermal insulation board, sound panel or decorative panel, consequently facilitating construction personnel's takes.
The present invention is by adopting the above-described technical solution, have the advantages that:
All kinds of planks used in construction can be carried out by the design of plank mounting table by classification division in the present invention, then by plate Material mounting table is fixedly connected with operation platform, and high-altitude is lifted into together with operation platform, compared with the existing technology in plank is straight Connect the design being deposited on operation platform, not only can taking in order to construction personnel, shorten construction period, and can carry again High construction safety performance, plank is fallen from high-altitude when construction personnel being avoided to extract plank, causes some potential safety problems, The placing frame on plank mounting table can carry out certain according to the installation site between plank mounting table and operation platform again simultaneously Position adjustment so that placing frame is farthest close to operation platform, consequently facilitating taking for plank, reasonable in design, It is easy to use, and during construction in later period, when the plank of placing frame front end has used, pusher cylinder can by scraping wings The plank forward impelling of back end of frame will be placed so that the plank of rear end is moved to placing frame front end, convenient for taking for construction personnel It takes, global design more hommization, effectively improves safe operation performance, design is more ingenious reasonable.
The present invention is be combined with each other by thermal insulation board, sound panel, grid cloth and decorative panel, realizes structural thermal insulation, sound insulation With the integration of decoration again so that the function of building heat preservation wall is more preferable, effectively prevent wall warpage hollowing phenomenon occur, while can The heat-insulating property of wall is improved, and the design of the first fixing piece can play the role of thermal insulation board to support clip, pass through polymerization Object mortar and the first fixing piece realize being connected and fixed between thermal insulation board and wall, are positioned convenient for the installation of thermal insulation board, avoid protecting The dislocation of warm plate is moved, and construction is simple, structure is safe and reliable, and the first fixing piece is arranged on four round angles of thermal insulation board, It is possible to prevente effectively from the warpage of thermal insulation board, then can be in order to sound panel and guarantor by the design of the second fixing piece and the first fixing piece Location and installation between warm plate, while being combined with polymer mortar, effectively ensure the connection knot between thermal insulation board and sound panel Structure intensity, overall construction design is reasonable, while effectivelying prevent the cracking phenomenon of surface of wall by the laying of grid cloth again, Finally increase the aesthetics of wall by decorative panel again.
The configuration of the present invention is simple, short construction period, construction is simple, constructing operation is safer, while can effectively prevent wall There is hollowing warping phenomenon in body, effectively extends the service life of wall, and the sound-insulating effect of the wall is more preferable, effectively increases The strong functional characteristic of building heat preservation wall.
Description of the drawings
The invention will be further described below in conjunction with the accompanying drawings:
Fig. 1 is the structural schematic diagram of plank mounting table in the present invention;
Fig. 2 is the mounting structure schematic diagram that handle and sliding block are pulled in the present invention;
Fig. 3 is the mounting structure schematic diagram between thermal insulation board, sound panel and the first fixing piece, the second fixing piece in the present invention;
Fig. 4 is the structural schematic diagram of the second fixing piece in the present invention;
Fig. 5 is the structural schematic diagram of the first fixing piece in the present invention;
Fig. 6 is the flowage structure block diagram of the present invention.
In figure:1- plank mounting tables;2- fixed plates;3- mounting holes;4- placing frames;5- pulls handle;6- sliding blocks;7- is slided Bar;8- pusher cylinders;9- scraping wings;10- thermal insulation boards;11- sound panels;The first fixing pieces of 12-;The first support baseboards of 13-;14- Fixed side panel;15- connecting holes;16- hook screws;The first card slots of 17-;The second fixing pieces of 18-;The second card slots of 19-;20- second Support baseboard;The first snap-gauges of 21-;The second snap-gauges of 22-.
Specific implementation mode
As shown in Figures 1 to 6, it is a kind of construction method of building heat preservation wall of the present invention, includes the following steps:
Step 1: base cleaning:
Step 1.1 clears up base course wall surface, knocks out hollowing, and levelling metope clears up sundries, it is ensured that base course wall surface It is dry, clean, then review measurement is carried out to the outer profile size of wall, drawing Deepen Design is carried out, determines line setting, and Installation block number, area and the specification of thermal insulation board 10, sound panel 11, decorative panel are determined according to wall size;
Thermal insulation board used in construction 10, sound panel 11, decorative panel are transported to job location by step 1.2, and according to difference Size and type are fitly stacked on the ground;
Step 2: surveying setting-out:
Snap the line setting-out is carried out to surface of wall, horizontal control lines and degree control line is set, has reset the level of each floor Control line and mounting plane line;
Step 3: the lifting of operation platform:
Step 3.1 is flat with construction by the fixed plate 2 of 1 bottom of plank mounting table first in operation platform upper mounting plate material mounting table 1 Platform is fixedly connected, and installation bolt passes through the mounting hole 3 at 2 both ends of fixed plate to be connected and fixed with operation platform, to place plank Platform 1 is connect with operation platform, and plank mounting table 1 adjusts the distance between placing frame 4 and operation platform, manually after installation is complete Pulling pulls handle 5, pulls handle 5 and drives placing frame 4 to be slided on slide bar 7 by sliding block 6, changes the position of placing frame 4, make It obtains placing frame 4 to be moved at appropriate position, convenient for taking to plank when construction;
Step 3.2 then carries out the placement of thermal insulation board 10, sound panel 11 and decorative panel, will according to the installation requirements at position to be onstructed Meet in the placing frame 4 that the thermal insulation board 10, sound panel 11, decorative panel of installation dimension are placed on plank mounting table 1, by inhomogeneity Thermal insulation board 10, sound panel 11, the decorative panel of type are placed in different placing frames 4, at the same by various sizes of thermal insulation board 10, every Soundboard 11 or decorative panel are also disposed in different placing frames 4, are realized that the classification of plank divides, are convenient for subsequent construction operation;
Step 3.3 again fixes the both ends of operation platform and hanging apparatus installation, and carries out safety detection, after detection is qualified, Construction personnel stands on operation platform, and operation platform is lifted at the metope to be onstructed in high vacancy by hanging apparatus, is applied Worker person again carries out wall the installation of plank;
Step 4: the installation of plank is fixed:
The installation of step 4.1 thermal insulation board 10:
Step 4.1.1 determines the installation site of thermal insulation board 10 according to design drawing first, thermal insulation board 10 installed position into The installation of row fixing piece installs the first fixing piece 12 at the bottom edge both ends of thermal insulation board 10, and with every piece of 10 bottom edge of thermal insulation board Line on the basis of horizontal direction, it is ensured that the bottom surface of the first support baseboard 13 is aligned with datum line, then according on fixed side panel 14 Then the position of the location determination installation hole of connecting hole 15 removes the first fixing piece 12 and drills, then support bottom by first The bottom surface of plate 13 is overlapped with datum line, is then fixedly connected with the first fixing piece 12 with surface of wall by hook screw 16;
Step 4.1.2 then uniform coated polymer mortars on the bonding interface layer of thermal insulation board 10, while reserving thermal insulation board Then thermal insulation board 10 is pasted surface of wall, and taps the four of thermal insulation board 10 using rubber hammer by the position on 10 bottom edges both ends In week, the verticality and levelness of thermal insulation board 10 are adjusted, while ensuring that the bottom both ends of thermal insulation board 10 snap onto the first fixing piece 12 The first card slot 17 in, then thermal insulation board 10 is flattened, ensures its flatness and adhesion firmness;
Step 4.1.3 installs the second fixing piece 18 at the top surface both ends of thermal insulation board 10 again, it is ensured that the second fixing piece 18 and first is solid Determine part 12 to be symmetrical arranged, while the top of thermal insulation board 10 snaps onto in the second card slot 19 of the second fixing piece 18, then uses hook Second support baseboard 20 is fixedly connected by head screw 16 with the top surface of thermal insulation board 10;
First piece of thermal insulation board 10 of step 4.1.4 is after installation is complete, installation base of second piece of thermal insulation board 10 in first piece of thermal insulation board 10 It on plinth, is installed, while being fitted closely between adjacent two pieces of thermal insulation boards 10, phase according to the installation steps of first piece of thermal insulation board 10 Gap between adjacent thermal insulation board 10 is less than 2mm, until the laying of integral wall is completed, between adjacent two pieces of thermal insulation boards 10 When gap is more than 2mm, using thermal insulation board, 10 fill up gap;
Step 4.1.5 in the construction process, when the thermal insulation board 10 of 4 front end of placing frame, sound panel 11 or decorative panel have used, is pushed away Expect that cylinder 8 is elapsed thermal insulation board 10, sound panel 11 or the decorative panel in placing frame 4 toward 4 front end of placing frame by scraping wings 9, directly The front end of placing frame 4 is moved to thermal insulation board 10, sound panel 11 or decorative panel, consequently facilitating construction personnel's takes;
The installation of step 4.2 sound panel 11:
One layer of sound panel 11 is installed in 10 layers of outside of thermal insulation board, sound panel 11 is covered on thermal insulation board 10, first by sound panel 11 top margin both ends are fixedly connected by hook screw 16 with the second snap-gauge 22 on the second fixing piece 18 respectively, then by sound panel 11 bottom edge both ends are fixedly connected by hook screw 16 with the first snap-gauge 21 on the first fixing piece 12 respectively;
The installation of step 4.3 grid cloth:
First in the cracking resistance mucilage layer of one layer of 15mm~25mm thickness of external coating of 11 layers of sound panel, then on cracking resistance mucilage layer It is laid with layer of glass fiber grid cloth, and is fixedly connected with glass fiber reticular cloth with cracking resistance mucilage layer with expansion anchor, then in glass fiber net Brush the cracking resistance mucilage layer of one layer of 10mm~12mm thickness in the outer surface of lattice cloth;
The installation of step 4.4 decorative panel:
After grid cloth installs, in the outer surface sticking decorative board of outermost cracking resistance mucilage layer, in the bonding interface of decorative panel Uniform coated polymer mortar on layer, then pastes cracking resistance rubber cement layer surface, and flatten compacting, insulation and decoration by decorative panel After plate pastes 72h, its surface is cleared up, the cleaning in adjacent decoration plate stitch gap is kept, foam is then inserted in gap Sealing material;
Step 5: detection:
After the construction for completing entire insulated wall, final detection process is carried out to construction wall, using random sampling to entirely keeping the temperature Wall is detected, and is spot-check a bit per 50m2, and make a record, is evaluated quality, to quality undesirable test point week It encloses and is further detected, increase test point number, maintenance consolidation subsequently is carried out to undesirable wall again.
All kinds of planks used in construction can be carried out by classification division by the design of plank mounting table 1 in the present invention, Plank mounting table 1 is fixedly connected with operation platform again, high-altitude is lifted into together with operation platform, it is middle compared with the existing technology to incite somebody to action Plank is directly deposited in the design on operation platform, not only can taking in order to construction personnel, shorten construction period, Er Qieyou Construction safety performance can be improved, plank is fallen from high-altitude when construction personnel being avoided to extract plank, causes certain peace Full hidden danger, while the placing frame 4 on plank mounting table 1 again can be according to the installation position between plank mounting table 1 and operation platform It sets and carries out certain position adjustment so that placing frame 4 is farthest close to operation platform, consequently facilitating plank is taken, knot Structure reasonable design, it is easy to use, and during construction in later period, when the plank of 4 front end of placing frame has used, pusher cylinder 8 can be by the plank forward impelling of 4 rear end of placing frame by scraping wings 9 so that and the plank of rear end is moved to 4 front end of placing frame, Convenient for taking for construction personnel, global design more hommization effectively improves safe operation performance, designs more ingenious conjunction Reason.
The present invention is be combined with each other by thermal insulation board 10, sound panel 11, grid cloth and decorative panel, realize structural thermal insulation, The integration of sound insulation and decoration so that the function of building heat preservation wall is more preferable, effectively prevent wall warpage hollowing phenomenon occur, simultaneously The heat-insulating property of wall can be improved again, and the design of the first fixing piece 12 can play the role of thermal insulation board 10 to support clip, Being connected and fixed between thermal insulation board 10 and wall is realized by polymer mortar and the first fixing piece 12, is convenient for the peace of thermal insulation board 10 Position is set, the dislocation of thermal insulation board 10 is avoided to move, construction is simple, structure is safe and reliable, and the setting of the first fixing piece 12 is existed On four round angles of thermal insulation board 10, it is possible to prevente effectively from the warpage of thermal insulation board 10, then pass through the second fixing piece 18 and the first fixing piece 12 design can be in order to the location and installation between sound panel 11 and thermal insulation board 10, while being combined with polymer mortar, effectively Ensure the connection structure intensity between thermal insulation board 10 and sound panel 11, overall construction design is reasonable, while passing through grid cloth again It is laid with, effectively prevent the cracking phenomenon of surface of wall, finally increase the aesthetics of wall by decorative panel again.
The configuration of the present invention is simple, short construction period, construction is simple, constructing operation is safer, while can effectively prevent wall There is hollowing warping phenomenon in body, effectively extends the service life of wall, and the sound-insulating effect of the wall is more preferable, effectively increases The strong functional characteristic of building heat preservation wall.
It these are only specific embodiments of the present invention, but the technical characteristic of the present invention is not limited thereto.It is any with this hair Based on bright, for the technique effect for realizing essentially identical, made ground simple change, equivalent replacement or modification etc. are all covered Among protection scope of the present invention.

Claims (3)

1. a kind of construction method of building heat preservation wall, it is characterised in that include the following steps:
Step 1: base cleaning:
Step 1.1 clears up base course wall surface, knocks out hollowing, and levelling metope clears up sundries, it is ensured that base course wall surface It is dry, clean, then review measurement is carried out to the outer profile size of wall, drawing Deepen Design is carried out, determines line setting, and Installation block number, area and the specification of thermal insulation board, sound panel, decorative panel are determined according to wall size;
Thermal insulation board used in construction, sound panel, decorative panel are transported to job location by step 1.2, and according to different sizes It is fitly stacked on the ground with type;
Step 2: surveying setting-out:
Snap the line setting-out is carried out to surface of wall, horizontal control lines and degree control line is set, has reset the level of each floor Control line and mounting plane line;
Step 3: the lifting of operation platform:
Step 3.1 is first in operation platform upper mounting plate material mounting table, by the fixed plate and operation platform of plank mounting table bottom Be fixedly connected, installation bolt passes through the mounting hole at fixed plate both ends to be connected and fixed with operation platform, to by plank mounting table and Operation platform connects, and plank mounting table adjusts the distance between placing frame and operation platform after installation is complete, and pulling manually pulls Handle pulls handle and drives placing frame to be slided on slide bar by sliding block, changes the position of placing frame so that placing frame is moved to At appropriate position, convenient for taking to plank when construction;
Step 3.2 then carries out the placement of thermal insulation board, sound panel and decorative panel, will be met according to the installation requirements at position to be onstructed Thermal insulation board, sound panel, the decorative panel of installation dimension are placed in the placing frame on plank mounting table, by different types of heat preservation Plate, sound panel, decorative panel are placed in different placing frames, while by various sizes of thermal insulation board, sound panel or decorative panel It is placed in different placing frames, realizes that the classification of plank divides, be convenient for subsequent construction operation;
Step 3.3 again fixes the both ends of operation platform and hanging apparatus installation, and carries out safety detection, after detection is qualified, Construction personnel stands on operation platform, and operation platform is lifted at the metope to be onstructed in high vacancy by hanging apparatus, is applied Worker person again carries out wall the installation of plank;
Step 4: the installation of plank is fixed:
The installation of step 4.1 thermal insulation board:
Step 4.1.1 determines the installation site of thermal insulation board according to design drawing first, is consolidated in the installed position of thermal insulation board The installation for determining part installs the first fixing piece at the bottom edge both ends of thermal insulation board, and is with the horizontal direction on every piece of thermal insulation board bottom edge Datum line, it is ensured that the bottom surface of the first support baseboard is aligned with datum line, and then the position according to the connecting hole on fixed side panel is true Determine the position of installation hole, then remove the first fixing piece and drill, then by the bottom surface of the first support baseboard and datum line weight It closes, is then fixedly connected with the first fixing piece with surface of wall by hook screw;
Step 4.1.2 then uniform coated polymer mortars on the bonding interface layer of thermal insulation board, while reserving thermal insulation board bottom Then thermal insulation board is pasted surface of wall by the position at side both ends, and the surrounding of thermal insulation board is tapped using rubber hammer, and adjustment is protected The verticality and levelness of warm plate, while ensuring that the bottom both ends of thermal insulation board snap onto in the first card slot of the first fixing piece, then Thermal insulation board is flattened, ensures its flatness and adhesion firmness;
Step 4.1.3 installs the second fixing piece at the top surface both ends of thermal insulation board again, it is ensured that the second fixing piece and the first fixing piece pair Claim setting, while the top of thermal insulation board snaps onto in the second card slot of the second fixing piece, then uses hook screw by second Support bottom plate is fixedly connected with the top surface of thermal insulation board;
First piece of thermal insulation board of step 4.1.4 after installation is complete, on the installation foundation of first piece of thermal insulation board press by second piece of thermal insulation board Installed according to the installation steps of first piece of thermal insulation board, while being fitted closely between adjacent two pieces of thermal insulation boards, adjacent thermal insulation board it Between gap be less than 2mm, until complete integral wall laying;
The installation of step 4.2 sound panel:
One layer of sound panel is installed in the outside of thermal insulation board layer, sound panel is covered on thermal insulation board, first by the top margin of sound panel two End is fixedly connected by hook screw with the second snap-gauge on the second fixing piece respectively, then the bottom edge both ends of sound panel are led to respectively Hook screw is crossed to be fixedly connected with the first snap-gauge on the first fixing piece;
The installation of step 4.3 grid cloth:
First in the cracking resistance mucilage layer of one layer of 15mm~25mm thickness of the external coating of sound panel layer, then on cracking resistance mucilage layer upper berth If layer of glass fiber grid cloth, and be fixedly connected with glass fiber reticular cloth with cracking resistance mucilage layer with expansion anchor, then in fiberglass mesh Brush the cracking resistance mucilage layer of one layer of 10mm~12mm thickness in the outer surface of cloth;
The installation of step 4.4 decorative panel:
After grid cloth installs, in the outer surface sticking decorative board of outermost cracking resistance mucilage layer, in the bonding interface of decorative panel Uniform coated polymer mortar on layer, then pastes cracking resistance rubber cement layer surface, and flatten compacting, insulation and decoration by decorative panel After plate pastes 72h, its surface is cleared up, the cleaning in adjacent decoration plate stitch gap is kept, foam is then inserted in gap Sealing material;
Step 5: detection:
After the construction for completing entire insulated wall, final detection process is carried out to construction wall.
2. a kind of construction method of building heat preservation wall according to claim 1, it is characterised in that:In the step 5, Entire heat-preserving wall is detected using random sampling, per 50m2Selective examination a bit, and makes a record, and evaluates quality, confrontation It measures and is further detected around undesirable test point, increase test point number, subsequently again to undesirable Wall carries out maintenance consolidation.
3. a kind of construction method of building heat preservation wall according to claim 1, it is characterised in that:In the step 4, In the construction process, when the thermal insulation board of placing frame front end, sound panel or decorative panel have used, pusher cylinder will by scraping wings Thermal insulation board, sound panel or decorative panel in placing frame are elapsed toward placing frame front end, until thermal insulation board, sound panel or decorative panel movement To the front end of placing frame, consequently facilitating construction personnel's takes.
CN201810086547.6A 2018-01-30 2018-01-30 A kind of construction method of building heat preservation wall Active CN108301529B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810086547.6A CN108301529B (en) 2018-01-30 2018-01-30 A kind of construction method of building heat preservation wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810086547.6A CN108301529B (en) 2018-01-30 2018-01-30 A kind of construction method of building heat preservation wall

Publications (2)

Publication Number Publication Date
CN108301529A true CN108301529A (en) 2018-07-20
CN108301529B CN108301529B (en) 2019-11-08

Family

ID=62866689

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810086547.6A Active CN108301529B (en) 2018-01-30 2018-01-30 A kind of construction method of building heat preservation wall

Country Status (1)

Country Link
CN (1) CN108301529B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109487915A (en) * 2018-12-07 2019-03-19 河南省第建设集团第七建筑工程有限公司 A kind of outer wall heat insulation layer construction process
CN109989591A (en) * 2019-04-25 2019-07-09 李秀娟 A kind of prefabricated residential house construction wall assembling device
CN110924570A (en) * 2019-12-13 2020-03-27 中铁二局集团有限公司 Construction method of light foamed ceramic wall
CN111321903A (en) * 2020-03-06 2020-06-23 郑州七彩装饰工程有限公司 External wall heat insulation engineering equipment and method thereof
CN112392165A (en) * 2020-11-11 2021-02-23 宁波市北仑大矸建筑工程有限公司 Building heat-insulation outer wall structure and construction method thereof
CN115030460A (en) * 2022-07-04 2022-09-09 中建八局第一建设有限公司 Construction device and method for external wall heat-insulation and decoration integrated plate

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2888001Y (en) * 2006-04-24 2007-04-11 张礼信 Assembling thermal-insulating wall board
CN1948654A (en) * 2006-11-02 2007-04-18 邹家祥 Manufacturing method of heat insulating wall board and construction method of its wall body
WO2008129174A1 (en) * 2007-03-15 2008-10-30 Arpegy Panel for correcting acoustic properties and ceiling equipped with such a panel
CN203113679U (en) * 2013-03-06 2013-08-07 刘兴兵 Decoration heat insulation board system
CN107476471A (en) * 2017-08-15 2017-12-15 浙江科达新型建材有限公司 One kind assembling combined type external wall system and its construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2888001Y (en) * 2006-04-24 2007-04-11 张礼信 Assembling thermal-insulating wall board
CN1948654A (en) * 2006-11-02 2007-04-18 邹家祥 Manufacturing method of heat insulating wall board and construction method of its wall body
WO2008129174A1 (en) * 2007-03-15 2008-10-30 Arpegy Panel for correcting acoustic properties and ceiling equipped with such a panel
CN203113679U (en) * 2013-03-06 2013-08-07 刘兴兵 Decoration heat insulation board system
CN107476471A (en) * 2017-08-15 2017-12-15 浙江科达新型建材有限公司 One kind assembling combined type external wall system and its construction method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109487915A (en) * 2018-12-07 2019-03-19 河南省第建设集团第七建筑工程有限公司 A kind of outer wall heat insulation layer construction process
CN109487915B (en) * 2018-12-07 2020-08-11 河南省第一建设集团第七建筑工程有限公司 Construction process of outer wall heat insulation layer
CN109989591A (en) * 2019-04-25 2019-07-09 李秀娟 A kind of prefabricated residential house construction wall assembling device
CN110924570A (en) * 2019-12-13 2020-03-27 中铁二局集团有限公司 Construction method of light foamed ceramic wall
CN111321903A (en) * 2020-03-06 2020-06-23 郑州七彩装饰工程有限公司 External wall heat insulation engineering equipment and method thereof
CN112392165A (en) * 2020-11-11 2021-02-23 宁波市北仑大矸建筑工程有限公司 Building heat-insulation outer wall structure and construction method thereof
CN115030460A (en) * 2022-07-04 2022-09-09 中建八局第一建设有限公司 Construction device and method for external wall heat-insulation and decoration integrated plate
CN115030460B (en) * 2022-07-04 2023-06-16 中建八局第一建设有限公司 Construction device and method for external wall heat-insulation and decoration integrated plate

Also Published As

Publication number Publication date
CN108301529B (en) 2019-11-08

Similar Documents

Publication Publication Date Title
CN108301529B (en) A kind of construction method of building heat preservation wall
CN104790595B (en) Pitched roof adjustable tile system construction method
CN206346443U (en) A kind of new adjustable floor heating paving structure
CN104047406A (en) Construction process for ultra-thin stone-facing heat-preserving decorative plate
CN103835505B (en) Compound heat-insulation board of outer wall constructional method
CN103046714A (en) Construction method for double-sided inorganic composite phenolic aldehyde fire-proof heat-insulating decorating integration plates
CN104499614B (en) Wall heat-preservation integration point hanging system and mounting method thereof
CN102011437B (en) Fireproof outer wall heat-insulating system and manufacturing method thereof
CN102877622A (en) Mounting structure of outer wall decorative plate
CN208650487U (en) A kind of ground tile paving mortar levelling tool
CN202882126U (en) Thermal insulation and decoration integrated fireproof composite insulation wall body structure
CN102277936A (en) Grade A fireproof light thermal insulating decorative integrated plate and production process thereof
CN214941477U (en) Heat preservation and sound insulation system for floating floor
CN215368500U (en) Flame-retardant anti-cracking extruded polystyrene foam heat-insulation terrace
CN104179265A (en) Inorganic fireproof heat preservation structure and construction method thereof
CN110424625A (en) One kind exempting from formwork complex heat-preservation sound insulationg board and heat insulating and sound insulating floor method of construction
CN102635213A (en) Polyurethane aluminum alloy composite board
CN215670776U (en) Gap bridge structure of floor tiles and wood floors
CN115961765A (en) Tiling device of fire prevention heat preservation mortar
CN205776838U (en) A kind of wire netting rock cotton board
CN209369086U (en) A kind of heat preserving exterior wall for building
CN113882538A (en) Rock panel indoor heat insulation layer construction method
CN201517255U (en) Integral cement composite heat-insulating external wall
CN202577832U (en) Polyurethane aluminum alloy composite board
CN202248387U (en) Lightgage steel joist gypsum plate vetrified tile decorative wall body

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20180720

Assignee: Hangzhou Zuolian Advertising Co.,Ltd.

Assignor: JIANG University OF TECHNOLOGY

Contract record no.: X2022330000922

Denomination of invention: A construction method of building thermal insulation wall

Granted publication date: 20191108

License type: Common License

Record date: 20221229

EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20180720

Assignee: Hangzhou Lianshi Decoration Engineering Co.,Ltd.

Assignor: JIANG University OF TECHNOLOGY

Contract record no.: X2023980033129

Denomination of invention: A Construction Method of Building Thermal Insulation Wall

Granted publication date: 20191108

License type: Common License

Record date: 20230306

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20180720

Assignee: Deqing Yuanhao Building Materials Co.,Ltd.

Assignor: JIANG University OF TECHNOLOGY

Contract record no.: X2023980040860

Denomination of invention: A construction method for building insulation walls

Granted publication date: 20191108

License type: Common License

Record date: 20230831

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20180720

Assignee: Zhejiang Tianzao Environmental Protection Technology Co.,Ltd.

Assignor: JIANG University OF TECHNOLOGY

Contract record no.: X2023980047334

Denomination of invention: A construction method for building insulation walls

Granted publication date: 20191108

License type: Common License

Record date: 20231116

Application publication date: 20180720

Assignee: Lishui Qianyuan Building Materials Technology Co.,Ltd.

Assignor: JIANG University OF TECHNOLOGY

Contract record no.: X2023980047331

Denomination of invention: A construction method for building insulation walls

Granted publication date: 20191108

License type: Common License

Record date: 20231116

Application publication date: 20180720

Assignee: Taizhou Nanyang building materials Co.,Ltd.

Assignor: JIANG University OF TECHNOLOGY

Contract record no.: X2023980047326

Denomination of invention: A construction method for building insulation walls

Granted publication date: 20191108

License type: Common License

Record date: 20231116

EE01 Entry into force of recordation of patent licensing contract