CN108301529A - A kind of construction method of building heat preservation wall - Google Patents
A kind of construction method of building heat preservation wall Download PDFInfo
- Publication number
- CN108301529A CN108301529A CN201810086547.6A CN201810086547A CN108301529A CN 108301529 A CN108301529 A CN 108301529A CN 201810086547 A CN201810086547 A CN 201810086547A CN 108301529 A CN108301529 A CN 108301529A
- Authority
- CN
- China
- Prior art keywords
- insulation board
- thermal insulation
- wall
- installation
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/74—Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
- E04B1/76—Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
- E04B1/762—Exterior insulation of exterior walls
- E04B1/7625—Details of the adhesive connection of the insulation to the wall
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/74—Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
- E04B1/76—Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
- E04B1/762—Exterior insulation of exterior walls
- E04B1/7629—Details of the mechanical connection of the insulation to the wall
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/74—Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
- E04B1/76—Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
- E04B1/78—Heat insulating elements
- E04B1/80—Heat insulating elements slab-shaped
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/166—Landings, receiving platforms
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Electromagnetism (AREA)
- Acoustics & Sound (AREA)
- Mechanical Engineering (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
- Finishing Walls (AREA)
- Building Environments (AREA)
Abstract
Description
技术领域technical field
本发明涉及一种建筑保温墙的施工方法。The invention relates to a construction method of a building thermal insulation wall.
背景技术Background technique
保温墙,顾名思义,必然起到保温隔热,维持室内温度稳定的作用,指采用一定的固定方式(粘结、机械锚固、粘贴+机械锚固、喷涂、浇注等),把导热系数较低(即保温隔热效果较好)的绝热材料与建筑物墙体固定一体,增加墙体的平均热阻值,从而达到保温或隔热效果的一种工程做法。Insulation wall, as the name suggests, must play the role of thermal insulation and maintain indoor temperature stability. It is an engineering practice that the thermal insulation material with better thermal insulation effect is fixed with the building wall to increase the average thermal resistance of the wall, so as to achieve thermal insulation or thermal insulation effect.
外墙保温是由聚合物砂浆、玻璃纤维网格布、阻燃型模塑聚苯乙烯泡沫板(EPS)或挤塑板(XPS)等材料复合而成,现场粘结施工。External wall insulation is composed of polymer mortar, glass fiber mesh cloth, flame-retardant molded polystyrene foam board (EPS) or extruded polystyrene board (XPS) and other materials, and is bonded on site.
现有的保温墙在施工过程中,处于高空施工作业,但是现有施工中一般只是单纯的将板材放置在施工平台的凸起部,存在一定的安全隐患,板材容易从高空坠落,而且也不便于施工人员对板材的拿取。同时现有的保温墙结构保温效果好,但是隔音效果一般,后期使用中墙体也容易出现空鼓翘曲等现象,影响墙体实际的使用。During the construction of the existing thermal insulation wall, it is in high-altitude construction work, but in the existing construction, the board is generally simply placed on the raised part of the construction platform, which has certain safety hazards, and the board is easy to fall from the height, and it is not easy to It is convenient for construction personnel to take the board. At the same time, the existing thermal insulation wall structure has good thermal insulation effect, but the sound insulation effect is average, and the wall body is also prone to hollowing and warping during later use, which affects the actual use of the wall body.
发明内容Contents of the invention
本发明目的在于针对现有技术所存在的不足而提供一种建筑保温墙的施工方法的技术方案,施工周期短,施工简单,施工操作更安全,同时可以有效防止墙体出现空鼓翘曲现象,有效延长墙体的使用寿命,并且该墙体的隔音保温效果更好,有效增强了建筑保温墙的功能性特征。The purpose of the present invention is to provide a technical solution for the construction method of the building insulation wall in view of the deficiencies in the prior art. The construction period is short, the construction is simple, the construction operation is safer, and at the same time, it can effectively prevent the hollowing and warping of the wall. , effectively prolonging the service life of the wall, and the sound insulation effect of the wall is better, which effectively enhances the functional characteristics of the building insulation wall.
一种建筑保温墙的施工方法,其特征在于包括如下步骤:A construction method for a building insulation wall is characterized in that it comprises the following steps:
步骤一、基层清理:Step 1. Grassroots cleaning:
步骤1.1对基层墙体表面进行清理,敲除空鼓,找平墙面,清理杂物,确保基层墙体表面干燥、干净,再对墙体的外轮廓尺寸进行复核测量,进行图纸深化设计,确定定位放线,并且根据墙体尺寸确定保温板、隔音板、装饰板的安装块数、面积和规格尺寸;Step 1.1 Clean the surface of the base wall, knock out hollows, level the wall, and clean up debris to ensure that the surface of the base wall is dry and clean, then recheck and measure the outer contour of the wall, and carry out detailed design of the drawings to determine Position and set out the wires, and determine the number, area and size of the insulation board, sound insulation board and decorative board according to the wall size;
步骤1.2将施工中所用的保温板、隔音板、装饰板运送到施工地点,并且按照不同尺寸和类型整齐地堆放在地面上;Step 1.2 Transport the insulation boards, sound insulation boards and decorative boards used in the construction to the construction site, and stack them neatly on the ground according to different sizes and types;
步骤二、测量放线:Step 2, measuring and setting out:
对墙体表面进行弹线放样,设定水平控制线和垂直度控制线,再设定好各楼层的水平控制线和安装平面线;Stakeout the wall surface, set the horizontal control line and verticality control line, and then set the horizontal control line and installation plane line of each floor;
步骤三、施工平台的吊装:Step 3. Hoisting of the construction platform:
步骤3.1首先在施工平台上安装板材放置台,将板材放置台底部的固定板与施工平台固定连接,安装螺栓穿过固定板两端的固定孔与施工平台连接固定,从而将板材放置台与施工平台连接,板材放置台安装完成后,调整放置框与施工平台之间的距离,手动拉动手拉环柄,手拉环柄通过滑块带动放置框在滑杆上滑动,改变放置框的位置,使得放置框移动到恰当的位置处,便于施工时对板材的拿取;Step 3.1 First, install the plate placement platform on the construction platform, fix the fixed plate at the bottom of the plate placement platform with the construction platform, and install the bolts through the fixing holes at both ends of the fixed plate to connect with the construction platform, so as to connect the plate placement platform with the construction platform After the installation of the plate placement table is completed, adjust the distance between the placement frame and the construction platform, manually pull the handle of the handle, and the handle of the handle will drive the placement frame to slide on the slider through the slider, changing the position of the placement frame, so that The placing frame is moved to the proper position, which is convenient for taking the board during construction;
步骤3.2接着进行保温板、隔音板和装饰板的放置,根据待施工部位的安装需求将符合安装尺寸的保温板、隔音板、装饰板放置在板材放置台上的放置框内,将不同类型的保温板、隔音板、装饰板放置在不同的放置框内,同时将不同尺寸的保温板、隔音板或装饰板也放置在不同的放置框内,实现板材的归类划分,便于后续的施工作业;Step 3.2 Next, place the thermal insulation board, sound insulation board and decorative board. According to the installation requirements of the site to be constructed, place the thermal insulation board, sound insulation board and decorative board that meet the installation size in the placement frame on the board placement table. Insulation panels, sound insulation panels, and decorative panels are placed in different placement frames. At the same time, insulation panels, sound insulation panels, or decorative panels of different sizes are also placed in different placement frames to realize the classification and division of the panels and facilitate subsequent construction operations. ;
步骤3.3再将施工平台的两端与吊装装置安装固定,并且进行安全检测,检测合格后,施工人员站立在施工平台上,通过吊装装置将施工平台起吊到高空处的待施工墙面处,施工人员再对墙体进行板材的安装;Step 3.3 Install and fix the two ends of the construction platform with the hoisting device, and conduct a safety inspection. After passing the inspection, the construction personnel stand on the construction platform, and lift the construction platform to the high-altitude wall to be constructed by the hoisting device. The personnel then install the panels on the wall;
步骤四、板材的安装固定:Step 4. Install and fix the board:
步骤4.1保温板的安装 :Step 4.1 Installation of insulation board:
步骤4.1.1首先根据设计图纸确定保温板的安装位置,在保温板的安装位置处进行固定件的安装,在保温板的底边两端安装第一固定件,并且以每块保温板底边的水平方向为基准线,确保第一支撑底板的底面与基准线对齐,然后根据固定侧板上的连接孔的位置确定安装孔洞的位置,然后取下第一固定件进行钻孔,再将第一支撑底板的底面与基准线重合,然后通过钩头螺钉将第一固定件与墙体表面固定连接;Step 4.1.1 First determine the installation position of the insulation board according to the design drawings, install the fixing parts at the installation position of the insulation board, install the first fixing parts at both ends of the bottom edge of the insulation board, and use the bottom edge of each insulation board Make sure that the bottom surface of the first support base is aligned with the reference line, and then determine the position of the installation hole according to the position of the connection hole on the fixed side plate, then remove the first fixing piece and drill the hole, and then place the second The bottom surface of a support base plate coincides with the reference line, and then the first fixing member is fixedly connected to the wall surface by hook screws;
步骤4.1.2接着在保温板的粘结界面层上均匀涂覆聚合物砂浆,同时预留出保温板底边两端的位置,然后将保温板粘贴到墙体表面,并且采用橡胶锤敲击保温板的四周,调整保温板的垂直度和水平度,同时确保保温板的底部两端卡入到第一固定件的第一卡槽内,再对保温板进行压平,保证其平整度及粘结牢固度;Step 4.1.2 Then apply polymer mortar evenly on the bonding interface layer of the insulation board, and reserve the positions at both ends of the bottom edge of the insulation board, then paste the insulation board to the wall surface, and use a rubber hammer to hit the insulation Around the board, adjust the verticality and levelness of the insulation board, and at the same time ensure that both ends of the bottom of the insulation board are snapped into the first slot of the first fixing part, and then flatten the insulation board to ensure its flatness and adhesion. firmness;
步骤4.1.3再在保温板的顶面两端安装第二固定件,确保第二固定件与第一固定件对称设置,同时保温板的顶端卡入到第二固定件的第二卡槽内,然后采用钩头螺钉将第二支撑底板与保温板的顶面固定连接;Step 4.1.3 Install the second fixing piece on both ends of the top surface of the insulation board to ensure that the second fixing piece is arranged symmetrically with the first fixing piece, and at the same time, the top of the insulation board snaps into the second slot of the second fixing piece , and then fixedly connect the second support bottom plate with the top surface of the insulation board with hook-head screws;
步骤4.1.4第一块保温板安装完成后,第二块保温板在第一块保温板的安装基础上,按照第一块保温板的安装步骤进行安装,同时相邻两块保温板之间紧密贴合,相邻保温板之间的间隙小于2mm,直至完成整体墙体的铺设;Step 4.1.4 After the installation of the first insulation board is completed, install the second insulation board according to the installation steps of the first insulation board based on the installation of the first insulation board. Close fit, the gap between adjacent insulation boards is less than 2mm, until the whole wall is laid;
步骤4.2隔音板的安装:Step 4.2 Installation of sound insulation panels:
在保温板层的外侧安装一层隔音板,隔音板覆盖在保温板上,首先将隔音板的顶边两端分别通过钩头螺钉与第二固定件上的第二卡板固定连接,再将隔音板的底边两端分别通过钩头螺钉与第一固定件上的第一卡板固定连接;Install a layer of sound insulation board on the outer side of the insulation board layer, and the sound insulation board is covered on the insulation board. Firstly, the two ends of the top edge of the sound insulation board are fixedly connected to the second clamping plate on the second fixing part through hook screws respectively, and then the Both ends of the bottom edge of the sound insulation board are fixedly connected to the first clamping plate on the first fixing member through hook screws respectively;
步骤4.3网格布的安装:Step 4.3 Installation of grid cloth:
首先在隔音板层的表面涂刷一层15mm~25mm厚的抗裂胶浆层,然后在抗裂胶浆层上铺设一层玻纤网格布,并且用膨胀锚栓将玻纤网格布与抗裂胶浆层固定连接,再在玻纤网格布的外表面涂刷一层10mm~12mm厚的抗裂胶浆层;First, paint a layer of 15mm-25mm thick anti-cracking mortar layer on the surface of the sound insulation board layer, then lay a layer of glass fiber mesh cloth on the anti-cracking mortar layer, and use expansion anchor bolts to seal the glass fiber mesh cloth It is fixedly connected with the anti-cracking glue layer, and then a layer of 10mm-12mm thick anti-cracking glue layer is painted on the outer surface of the glass fiber mesh cloth;
步骤4.4装饰板的安装:Step 4.4 Installation of decorative panels:
网格布安装好后,在最外层的抗裂胶浆层的外表面粘贴装饰板,在装饰板的粘结界面层上均匀涂覆聚合物砂浆,然后将装饰板粘贴到抗裂胶浆层表面,并且压平压实,保温装饰板粘贴72h后,对其表面进行清理,保持相邻装饰板缝隙内的清洁,然后在缝隙中填入泡沫密封材料;After the grid cloth is installed, paste the decorative board on the outer surface of the outermost anti-cracking mortar layer, evenly coat the polymer mortar on the adhesive interface layer of the decorative board, and then paste the decorative board on the anti-cracking mortar After 72 hours of pasting the thermal insulation decorative board, clean the surface, keep the gap between adjacent decorative boards clean, and then fill the gap with foam sealing material;
步骤五、检测:Step five, detection:
完成整个保温墙的施工后,对施工墙体进行最终检测处理。After the construction of the entire insulation wall is completed, the final inspection process is carried out on the construction wall.
进一步,在步骤五中,采用随机抽样对整个保温墙体进行检测,每50m2抽查一点,并且做好记录,评定质量,对质量不符合要求的检测点周围进行进一步的检测,增加检测点个数,后续再对不符合要求的墙体进行维护巩固。Further, in step five, random sampling is used to test the entire thermal insulation wall, and a point is randomly checked every 50m 2 , and records are made to evaluate the quality, and further testing is carried out around the testing points whose quality does not meet the requirements, and the number of testing points is increased. The number of walls that do not meet the requirements will be maintained and consolidated later.
进一步,在步骤四中,在施工过程中,当放置框前端的保温板、隔音板或装饰板使用完时,推料气缸通过推料板将放置框内的保温板、隔音板或装饰板往放置框前端推移,直至保温板、隔音板或装饰板移动到放置框的前端部,从而便于施工人员的拿取。Further, in step 4, during the construction process, when the insulation board, sound insulation board or decorative board at the front end of the placement frame is used up, the pushing cylinder pushes the insulation board, sound insulation board or decoration board in the placement frame through the pusher board. The front end of the placing frame moves until the insulation board, the sound insulation board or the decorative board moves to the front end of the placing frame, thereby facilitating construction workers to take it.
本发明由于采用了上述技术方案,具有以下有益效果:The present invention has the following beneficial effects due to the adoption of the above technical solution:
本发明中通过板材放置台的设计可以将施工中用到的各类板材进行归类划分,再将板材放置台与施工平台固定连接,与施工平台一起吊装到高空,相对于现有技术中将板材直接堆放在施工平台上的设计,不仅可以便于施工人员的拿取,缩短施工周期,而且又可以提高施工安全性能,避免施工人员对板材进行抽取时板材从高空掉落,造成一定的安全隐患,同时板材放置台上的放置框又可以根据板材放置台与施工平台之间的安装位置进行一定的位置调整,使得放置框最大程度地靠近施工平台,从而便于板材的拿取,结构设计合理,使用方便,并且在后期施工过程中,当放置框前端的板材使用完时,推料气缸通过推料板可以将放置框后端的板材往前推进,使得后端的板材移动到放置框前端,便于施工人员的拿取,整体设计更加的人性化,有效提高操作安全性能,设计更加的巧妙合理。In the present invention, through the design of the plate placement platform, various types of plates used in construction can be classified and divided, and then the plate placement platform is fixedly connected with the construction platform, and hoisted to the high altitude together with the construction platform. Compared with the prior art, the The design that the plates are directly stacked on the construction platform can not only facilitate the construction personnel to take them, shorten the construction period, but also improve the construction safety performance, and avoid the plates from falling from the height when the construction workers extract the plates, causing certain safety hazards , at the same time, the placement frame on the board placement table can be adjusted to a certain extent according to the installation position between the board placement table and the construction platform, so that the placement frame is as close as possible to the construction platform, so as to facilitate the picking of the board, and the structural design is reasonable. It is easy to use, and in the post-construction process, when the plate at the front end of the frame is used up, the pusher cylinder can push the plate at the rear end of the frame forward through the pusher plate, so that the plate at the rear end moves to the front end of the frame, which is convenient for construction The overall design is more humanized for the handling of personnel, which effectively improves the safety performance of the operation, and the design is more ingenious and reasonable.
本发明通过保温板、隔音板、网格布和装饰板的相互结合,实现了结构保温、隔音和装饰的一体化,使得建筑保温墙的功能更好,有效防止墙体出现翘曲空鼓现象,同时又能提高墙体的保温性能,并且第一固定件的设计可以对保温板起到支撑卡箍作用,通过聚合物砂浆和第一固定件实现保温板与墙体之间的连接固定,便于保温板的安装定位,避免保温板的错位移动,施工简单,结构安全可靠,并且将第一固定件设置在保温板的四周角上,可以有效避免保温板的翘曲,再通过第二固定件和第一固定件的设计可以便于隔音板与保温板之间的定位安装,同时与聚合物砂浆相结合,有效确保保温板与隔音板之间的连接结构强度,整体结构设计合理,同时再通过网格布的铺设,有效防止墙体表面出现开裂现象,最后再通过装饰板增加墙体的美观性。The present invention realizes the integration of structural heat preservation, sound insulation and decoration through the mutual combination of heat preservation board, sound insulation board, grid cloth and decorative board, so that the function of the building heat preservation wall is better, and the phenomenon of warping and hollowing of the wall is effectively prevented , at the same time, it can improve the thermal insulation performance of the wall, and the design of the first fixing part can play a role of supporting the insulation board, and the connection and fixation between the insulation board and the wall can be realized through the polymer mortar and the first fixing part. It is convenient for the installation and positioning of the insulation board, avoiding the dislocation and movement of the insulation board. The design of the part and the first fixing part can facilitate the positioning and installation between the sound insulation board and the insulation board. Through the laying of the grid cloth, the cracking phenomenon on the surface of the wall can be effectively prevented, and finally the aesthetics of the wall can be increased through the decorative board.
本发明结构简单,施工周期短,施工简单,施工操作更安全,同时可以有效防止墙体出现空鼓翘曲现象,有效延长墙体的使用寿命,并且该墙体的隔音保温效果更好,有效增强了建筑保温墙的功能性特征。The invention has the advantages of simple structure, short construction period, simple construction and safer construction operation. At the same time, it can effectively prevent the phenomenon of hollowing and warping of the wall, effectively prolong the service life of the wall, and the sound insulation and heat preservation effect of the wall is better, effectively Enhances the functional characteristics of building insulation walls.
附图说明Description of drawings
下面结合附图对本发明作进一步说明:The present invention will be further described below in conjunction with accompanying drawing:
图1为本发明中板材放置台的结构示意图;Fig. 1 is the structural representation of plate placing platform among the present invention;
图2为本发明中手拉环柄与滑块的安装结构示意图;Fig. 2 is a schematic diagram of the installation structure of the pull ring handle and the slide block in the present invention;
图3为本发明中保温板、隔音板与第一固定件、第二固定件之间的安装结构示意图;Fig. 3 is a schematic diagram of the installation structure between the insulation board, the sound insulation board, the first fixing part and the second fixing part in the present invention;
图4为本发明中第二固定件的结构示意图;Fig. 4 is the structural schematic diagram of the second fixture in the present invention;
图5为本发明中第一固定件的结构示意图;Fig. 5 is a schematic structural view of the first fixing member in the present invention;
图6为本发明的流程结构框图。Fig. 6 is a flow chart of the present invention.
图中:1-板材放置台;2-固定板;3-固定孔;4-放置框;5-手拉环柄;6-滑块;7-滑杆;8-推料气缸;9-推料板;10-保温板;11-隔音板;12-第一固定件;13-第一支撑底板;14-固定侧板;15-连接孔;16-钩头螺钉;17-第一卡槽;18-第二固定件;19-第二卡槽;20-第二支撑底板;21-第一卡板;22-第二卡板。In the figure: 1-plate placement platform; 2-fixing plate; 3-fixing hole; 4-placement frame; 5-handle ring handle; 6-slider; 7-sliding rod; Material plate; 10-insulation board; 11-sound insulation board; 12-the first fixing piece; 13-the first support bottom plate; 14-fixed side plate; 15-connection hole; 16-hook head screw; ; 18-the second fixing piece; 19-the second card slot; 20-the second support base plate; 21-the first card board; 22-the second card board.
具体实施方式Detailed ways
如图1至图6所示,为本发明一种建筑保温墙的施工方法,包括如下步骤:As shown in Fig. 1 to Fig. 6, be the construction method of a kind of building insulation wall of the present invention, comprise the steps:
步骤一、基层清理:Step 1. Grassroots cleaning:
步骤1.1对基层墙体表面进行清理,敲除空鼓,找平墙面,清理杂物,确保基层墙体表面干燥、干净,再对墙体的外轮廓尺寸进行复核测量,进行图纸深化设计,确定定位放线,并且根据墙体尺寸确定保温板10、隔音板11、装饰板的安装块数、面积和规格尺寸;Step 1.1 Clean the surface of the base wall, knock out hollows, level the wall, and clean up debris to ensure that the surface of the base wall is dry and clean, then recheck and measure the outer contour of the wall, and carry out detailed design of the drawings to determine Locate and set out the wires, and determine the number, area and specification of the thermal insulation board 10, the sound insulation board 11, and the decorative board according to the size of the wall;
步骤1.2将施工中所用的保温板10、隔音板11、装饰板运送到施工地点,并且按照不同尺寸和类型整齐地堆放在地面上;Step 1.2 Transport the insulation panels 10, sound insulation panels 11, and decorative panels used in the construction to the construction site, and stack them neatly on the ground according to different sizes and types;
步骤二、测量放线:Step 2, measuring and setting out:
对墙体表面进行弹线放样,设定水平控制线和垂直度控制线,再设定好各楼层的水平控制线和安装平面线;Stakeout the wall surface, set the horizontal control line and verticality control line, and then set the horizontal control line and installation plane line of each floor;
步骤三、施工平台的吊装:Step 3. Hoisting of the construction platform:
步骤3.1首先在施工平台上安装板材放置台1,将板材放置台1底部的固定板2与施工平台固定连接,安装螺栓穿过固定板2两端的固定孔3与施工平台连接固定,从而将板材放置台1与施工平台连接,板材放置台1安装完成后,调整放置框4与施工平台之间的距离,手动拉动手拉环柄5,手拉环柄5通过滑块6带动放置框4在滑杆7上滑动,改变放置框4的位置,使得放置框4移动到恰当的位置处,便于施工时对板材的拿取;Step 3.1 First, install the plate placement platform 1 on the construction platform, fix the fixed plate 2 at the bottom of the plate placement platform 1 with the construction platform, and install the bolts through the fixing holes 3 at both ends of the fixed plate 2 to connect with the construction platform, so as to secure the plate The placement platform 1 is connected with the construction platform. After the plate placement platform 1 is installed, adjust the distance between the placement frame 4 and the construction platform, and manually pull the handle 5 of the handle. The handle 5 drives the placement frame 4 through the slider 6. Slide on the slide bar 7 to change the position of the placing frame 4, so that the placing frame 4 moves to an appropriate position, which is convenient for taking the board during construction;
步骤3.2接着进行保温板10、隔音板11和装饰板的放置,根据待施工部位的安装需求将符合安装尺寸的保温板10、隔音板11、装饰板放置在板材放置台1上的放置框4内,将不同类型的保温板10、隔音板11、装饰板放置在不同的放置框4内,同时将不同尺寸的保温板10、隔音板11或装饰板也放置在不同的放置框4内,实现板材的归类划分,便于后续的施工作业;Step 3.2 Next, place the insulation board 10, the sound insulation board 11 and the decorative board, and place the insulation board 10, the sound insulation board 11, and the decorative board that meet the installation size on the placement frame 4 on the board placement table 1 according to the installation requirements of the site to be constructed Inside, different types of thermal insulation panels 10, sound insulation panels 11, and decorative panels are placed in different placement frames 4, and thermal insulation panels 10, sound insulation panels 11, or decorative panels of different sizes are also placed in different placement frames 4. Realize the classification and division of plates to facilitate subsequent construction operations;
步骤3.3再将施工平台的两端与吊装装置安装固定,并且进行安全检测,检测合格后,施工人员站立在施工平台上,通过吊装装置将施工平台起吊到高空处的待施工墙面处,施工人员再对墙体进行板材的安装;Step 3.3 Install and fix the two ends of the construction platform with the hoisting device, and conduct a safety inspection. After passing the inspection, the construction personnel stand on the construction platform, and lift the construction platform to the high-altitude wall to be constructed by the hoisting device. The personnel then install the panels on the wall;
步骤四、板材的安装固定:Step 4. Install and fix the board:
步骤4.1保温板10的安装 :Step 4.1 Installation of insulation board 10:
步骤4.1.1首先根据设计图纸确定保温板10的安装位置,在保温板10的安装位置处进行固定件的安装,在保温板10的底边两端安装第一固定件12,并且以每块保温板10底边的水平方向为基准线,确保第一支撑底板13的底面与基准线对齐,然后根据固定侧板14上的连接孔15的位置确定安装孔洞的位置,然后取下第一固定件12进行钻孔,再将第一支撑底板13的底面与基准线重合,然后通过钩头螺钉16将第一固定件12与墙体表面固定连接;Step 4.1.1 First determine the installation position of the insulation board 10 according to the design drawings, install the fixing parts at the installation position of the insulation board 10, install the first fixing parts 12 at both ends of the bottom edge of the insulation board 10, and use each The horizontal direction of the bottom edge of the insulation board 10 is the reference line, ensure that the bottom surface of the first support base plate 13 is aligned with the reference line, then determine the position of the installation hole according to the position of the connection hole 15 on the fixed side plate 14, and then remove the first fixed Part 12 is drilled, and then the bottom surface of the first support base plate 13 coincides with the reference line, and then the first fixture 12 is fixedly connected to the wall surface by hook screws 16;
步骤4.1.2接着在保温板10的粘结界面层上均匀涂覆聚合物砂浆,同时预留出保温板10底边两端的位置,然后将保温板10粘贴到墙体表面,并且采用橡胶锤敲击保温板10的四周,调整保温板10的垂直度和水平度,同时确保保温板10的底部两端卡入到第一固定件12的第一卡槽17内,再对保温板10进行压平,保证其平整度及粘结牢固度;Step 4.1.2 Next, evenly coat the polymer mortar on the bonding interface layer of the insulation board 10, and reserve the positions at both ends of the bottom edge of the insulation board 10, and then paste the insulation board 10 on the wall surface, and use a rubber hammer Knock around the insulation board 10, adjust the verticality and levelness of the insulation board 10, and ensure that the two ends of the bottom of the insulation board 10 are snapped into the first slot 17 of the first fixture 12, and then the insulation board 10 is Flattening to ensure its flatness and bonding firmness;
步骤4.1.3再在保温板10的顶面两端安装第二固定件18,确保第二固定件18与第一固定件12对称设置,同时保温板10的顶端卡入到第二固定件18的第二卡槽19内,然后采用钩头螺钉16将第二支撑底板20与保温板10的顶面固定连接;Step 4.1.3 Install the second fixing piece 18 on both ends of the top surface of the insulation board 10 to ensure that the second fixing piece 18 and the first fixing piece 12 are arranged symmetrically, and at the same time the top of the insulation board 10 snaps into the second fixing piece 18 In the second draw-in slot 19 of the second support base plate 20 and the top surface of the insulation board 10 are then fixedly connected by hook screws 16;
步骤4.1.4第一块保温板10安装完成后,第二块保温板10在第一块保温板10的安装基础上,按照第一块保温板10的安装步骤进行安装,同时相邻两块保温板10之间紧密贴合,相邻保温板10之间的间隙小于2mm,直至完成整体墙体的铺设,当相邻两块保温板10之间的间隙大于2mm时,采用保温板10条将间隙塞满;Step 4.1.4 After the installation of the first insulation board 10 is completed, the second insulation board 10 is installed according to the installation steps of the first insulation board 10 on the basis of the installation of the first insulation board 10. At the same time, two adjacent insulation boards The insulation boards 10 are tightly fitted, and the gap between adjacent insulation boards 10 is less than 2mm until the laying of the whole wall is completed. When the gap between two adjacent insulation boards 10 is greater than 2mm, use 10 insulation boards fill up the gap;
步骤4.1.5在施工过程中,当放置框4前端的保温板10、隔音板11或装饰板使用完时,推料气缸8通过推料板9将放置框4内的保温板10、隔音板11或装饰板往放置框4前端推移,直至保温板10、隔音板11或装饰板移动到放置框4的前端部,从而便于施工人员的拿取;Step 4.1.5 During the construction process, when the insulation board 10, the sound insulation board 11 or the decorative board at the front end of the placement frame 4 are used up, the pusher cylinder 8 will push the insulation board 10 and the sound insulation board in the placement frame 4 through the pusher plate 9 11 or the decorative plate moves toward the front end of the placement frame 4 until the insulation board 10, the sound insulation board 11 or the decorative plate moves to the front end of the placement frame 4, thereby facilitating construction workers to take it;
步骤4.2隔音板11的安装:Step 4.2 Installation of the sound insulation board 11:
在保温板10层的外侧安装一层隔音板11,隔音板11覆盖在保温板10上,首先将隔音板11的顶边两端分别通过钩头螺钉16与第二固定件18上的第二卡板22固定连接,再将隔音板11的底边两端分别通过钩头螺钉16与第一固定件12上的第一卡板21固定连接;One layer of sound insulation board 11 is installed on the outer side of insulation board 10 layers, and sound insulation board 11 is covered on the insulation board 10, at first the two ends of the top edge of sound insulation board 11 pass hook head screw 16 and the second on the second fixing part 18 respectively. The clamping plate 22 is fixedly connected, and then the two ends of the bottom edge of the sound insulation board 11 are respectively fixedly connected to the first clamping plate 21 on the first fixing member 12 through the hook head screws 16;
步骤4.3网格布的安装:Step 4.3 Installation of grid cloth:
首先在隔音板11层的表面涂刷一层15mm~25mm厚的抗裂胶浆层,然后在抗裂胶浆层上铺设一层玻纤网格布,并且用膨胀锚栓将玻纤网格布与抗裂胶浆层固定连接,再在玻纤网格布的外表面涂刷一层10mm~12mm厚的抗裂胶浆层;First, paint a layer of 15mm-25mm thick anti-cracking glue layer on the surface of the 11th layer of the sound insulation board, and then lay a layer of glass fiber mesh cloth on the anti-cracking glue layer, and use expansion anchors to connect the glass fiber mesh The cloth is fixedly connected with the anti-cracking glue layer, and then a layer of 10mm-12mm thick anti-cracking glue layer is painted on the outer surface of the glass fiber mesh cloth;
步骤4.4装饰板的安装:Step 4.4 Installation of decorative panels:
网格布安装好后,在最外层的抗裂胶浆层的外表面粘贴装饰板,在装饰板的粘结界面层上均匀涂覆聚合物砂浆,然后将装饰板粘贴到抗裂胶浆层表面,并且压平压实,保温装饰板粘贴72h后,对其表面进行清理,保持相邻装饰板缝隙内的清洁,然后在缝隙中填入泡沫密封材料;After the grid cloth is installed, paste the decorative board on the outer surface of the outermost anti-cracking mortar layer, evenly coat the polymer mortar on the adhesive interface layer of the decorative board, and then paste the decorative board on the anti-cracking mortar After 72 hours of pasting the thermal insulation decorative board, clean the surface, keep the gap between adjacent decorative boards clean, and then fill the gap with foam sealing material;
步骤五、检测:Step five, detection:
完成整个保温墙的施工后,对施工墙体进行最终检测处理,采用随机抽样对整个保温墙体进行检测,每50m2抽查一点,并且做好记录,评定质量,对质量不符合要求的检测点周围进行进一步的检测,增加检测点个数,后续再对不符合要求的墙体进行维护巩固。After the construction of the entire insulation wall is completed, the final inspection process is carried out on the construction wall, and the entire insulation wall is inspected by random sampling, and a spot is checked every 50m2, and records are made to evaluate the quality. Carry out further testing, increase the number of testing points, and then maintain and consolidate the walls that do not meet the requirements.
本发明中通过板材放置台1的设计可以将施工中用到的各类板材进行归类划分,再将板材放置台1与施工平台固定连接,与施工平台一起吊装到高空,相对于现有技术中将板材直接堆放在施工平台上的设计,不仅可以便于施工人员的拿取,缩短施工周期,而且又可以提高施工安全性能,避免施工人员对板材进行抽取时板材从高空掉落,造成一定的安全隐患,同时板材放置台1上的放置框4又可以根据板材放置台1与施工平台之间的安装位置进行一定的位置调整,使得放置框4最大程度地靠近施工平台,从而便于板材的拿取,结构设计合理,使用方便,并且在后期施工过程中,当放置框4前端的板材使用完时,推料气缸8通过推料板9可以将放置框4后端的板材往前推进,使得后端的板材移动到放置框4前端,便于施工人员的拿取,整体设计更加的人性化,有效提高操作安全性能,设计更加的巧妙合理。In the present invention, through the design of the plate placement platform 1, various types of plates used in construction can be classified and divided, and then the plate placement platform 1 is fixedly connected to the construction platform, and hoisted to high altitude together with the construction platform. Compared with the prior art The design of stacking the boards directly on the construction platform can not only facilitate the construction personnel to take them, shorten the construction period, but also improve the construction safety performance, and avoid the boards falling from the height when the construction workers extract the boards, causing certain damage. safety hazard, and at the same time, the placement frame 4 on the plate placement platform 1 can be adjusted to a certain extent according to the installation position between the plate placement platform 1 and the construction platform, so that the placement frame 4 is closest to the construction platform to the greatest extent, thereby facilitating the taking of the plates The structure design is reasonable and easy to use, and in the post-construction process, when the plate at the front end of the placement frame 4 is used up, the pusher cylinder 8 can push the plate at the rear end of the placement frame 4 forward through the pusher plate 9, so that the rear end The plate at the end moves to the front end of the placement frame 4, which is convenient for construction personnel to take, the overall design is more humanized, the operation safety performance is effectively improved, and the design is more ingenious and reasonable.
本发明通过保温板10、隔音板11、网格布和装饰板的相互结合,实现了结构保温、隔音和装饰的一体化,使得建筑保温墙的功能更好,有效防止墙体出现翘曲空鼓现象,同时又能提高墙体的保温性能,并且第一固定件12的设计可以对保温板10起到支撑卡箍作用,通过聚合物砂浆和第一固定件12实现保温板10与墙体之间的连接固定,便于保温板10的安装定位,避免保温板10的错位移动,施工简单,结构安全可靠,并且将第一固定件12设置在保温板10的四周角上,可以有效避免保温板10的翘曲,再通过第二固定件18和第一固定件12的设计可以便于隔音板11与保温板10之间的定位安装,同时与聚合物砂浆相结合,有效确保保温板10与隔音板11之间的连接结构强度,整体结构设计合理,同时再通过网格布的铺设,有效防止墙体表面出现开裂现象,最后再通过装饰板增加墙体的美观性。The present invention realizes the integration of structural heat preservation, sound insulation and decoration through the mutual combination of heat preservation board 10, sound insulation board 11, grid cloth and decorative board, so that the function of the building heat preservation wall is better, and effectively prevents the wall from warping and voids. At the same time, the thermal insulation performance of the wall can be improved, and the design of the first fixing part 12 can play a role of supporting the insulation board 10, and the insulation board 10 and the wall can be realized through the polymer mortar and the first fixing part 12. The connection between them is fixed, which is convenient for the installation and positioning of the insulation board 10, and avoids the dislocation movement of the insulation board 10. The warping of the board 10, and the design of the second fixing part 18 and the first fixing part 12 can facilitate the positioning and installation between the sound insulation board 11 and the insulation board 10, and at the same time, it is combined with the polymer mortar to effectively ensure that the insulation board 10 and the The strength of the connection structure between the sound insulation boards 11 and the design of the overall structure are reasonable. At the same time, the laying of the grid cloth can effectively prevent cracking on the surface of the wall, and finally the aesthetics of the wall is increased by the decorative board.
本发明结构简单,施工周期短,施工简单,施工操作更安全,同时可以有效防止墙体出现空鼓翘曲现象,有效延长墙体的使用寿命,并且该墙体的隔音保温效果更好,有效增强了建筑保温墙的功能性特征。The invention has the advantages of simple structure, short construction period, simple construction and safer construction operation. At the same time, it can effectively prevent the phenomenon of hollowing and warping of the wall, effectively prolong the service life of the wall, and the sound insulation and heat preservation effect of the wall is better, effectively Enhances the functional characteristics of building insulation walls.
以上仅为本发明的具体实施例,但本发明的技术特征并不局限于此。任何以本发明为基础,为实现基本相同的技术效果,所作出地简单变化、等同替换或者修饰等,皆涵盖于本发明的保护范围之中。The above are only specific embodiments of the present invention, but the technical features of the present invention are not limited thereto. Any simple changes, equivalent replacements or modifications based on the present invention to achieve substantially the same technical effect are covered by the protection scope of the present invention.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810086547.6A CN108301529B (en) | 2018-01-30 | 2018-01-30 | A kind of construction method of building thermal insulation wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810086547.6A CN108301529B (en) | 2018-01-30 | 2018-01-30 | A kind of construction method of building thermal insulation wall |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN108301529A true CN108301529A (en) | 2018-07-20 |
| CN108301529B CN108301529B (en) | 2019-11-08 |
Family
ID=62866689
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810086547.6A Active CN108301529B (en) | 2018-01-30 | 2018-01-30 | A kind of construction method of building thermal insulation wall |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108301529B (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109487915A (en) * | 2018-12-07 | 2019-03-19 | 河南省第建设集团第七建筑工程有限公司 | A kind of outer wall heat insulation layer construction process |
| CN109989591A (en) * | 2019-04-25 | 2019-07-09 | 李秀娟 | A kind of prefabricated residential house construction wall assembling device |
| CN110924570A (en) * | 2019-12-13 | 2020-03-27 | 中铁二局集团有限公司 | Construction method of light foamed ceramic wall |
| CN111321903A (en) * | 2020-03-06 | 2020-06-23 | 郑州七彩装饰工程有限公司 | External wall heat insulation engineering equipment and method thereof |
| CN112392165A (en) * | 2020-11-11 | 2021-02-23 | 宁波市北仑大矸建筑工程有限公司 | Building heat-insulation outer wall structure and construction method thereof |
| CN115030460A (en) * | 2022-07-04 | 2022-09-09 | 中建八局第一建设有限公司 | Construction device and method for external wall heat-insulation and decoration integrated plate |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2888001Y (en) * | 2006-04-24 | 2007-04-11 | 张礼信 | Assembled heat preservation wallboard |
| CN1948654A (en) * | 2006-11-02 | 2007-04-18 | 邹家祥 | Manufacturing method of heat insulating wall board and construction method of its wall body |
| WO2008129174A1 (en) * | 2007-03-15 | 2008-10-30 | Arpegy | Panel for correcting acoustic properties and ceiling equipped with such a panel |
| CN203113679U (en) * | 2013-03-06 | 2013-08-07 | 刘兴兵 | Decoration heat insulation board system |
| CN107476471A (en) * | 2017-08-15 | 2017-12-15 | 浙江科达新型建材有限公司 | One kind assembling combined type external wall system and its construction method |
-
2018
- 2018-01-30 CN CN201810086547.6A patent/CN108301529B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2888001Y (en) * | 2006-04-24 | 2007-04-11 | 张礼信 | Assembled heat preservation wallboard |
| CN1948654A (en) * | 2006-11-02 | 2007-04-18 | 邹家祥 | Manufacturing method of heat insulating wall board and construction method of its wall body |
| WO2008129174A1 (en) * | 2007-03-15 | 2008-10-30 | Arpegy | Panel for correcting acoustic properties and ceiling equipped with such a panel |
| CN203113679U (en) * | 2013-03-06 | 2013-08-07 | 刘兴兵 | Decoration heat insulation board system |
| CN107476471A (en) * | 2017-08-15 | 2017-12-15 | 浙江科达新型建材有限公司 | One kind assembling combined type external wall system and its construction method |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109487915A (en) * | 2018-12-07 | 2019-03-19 | 河南省第建设集团第七建筑工程有限公司 | A kind of outer wall heat insulation layer construction process |
| CN109487915B (en) * | 2018-12-07 | 2020-08-11 | 河南省第一建设集团第七建筑工程有限公司 | Construction process of outer wall heat insulation layer |
| CN109989591A (en) * | 2019-04-25 | 2019-07-09 | 李秀娟 | A kind of prefabricated residential house construction wall assembling device |
| CN110924570A (en) * | 2019-12-13 | 2020-03-27 | 中铁二局集团有限公司 | Construction method of light foamed ceramic wall |
| CN111321903A (en) * | 2020-03-06 | 2020-06-23 | 郑州七彩装饰工程有限公司 | External wall heat insulation engineering equipment and method thereof |
| CN112392165A (en) * | 2020-11-11 | 2021-02-23 | 宁波市北仑大矸建筑工程有限公司 | Building heat-insulation outer wall structure and construction method thereof |
| CN115030460A (en) * | 2022-07-04 | 2022-09-09 | 中建八局第一建设有限公司 | Construction device and method for external wall heat-insulation and decoration integrated plate |
| CN115030460B (en) * | 2022-07-04 | 2023-06-16 | 中建八局第一建设有限公司 | Construction device and method for external wall heat-insulation and decoration integrated plate |
Also Published As
| Publication number | Publication date |
|---|---|
| CN108301529B (en) | 2019-11-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108301529A (en) | A kind of construction method of building heat preservation wall | |
| CN104790595B (en) | Pitched roof adjustable tile system construction method | |
| CN106499091A (en) | A kind of assembling type partition wall construction method based on ALC plates | |
| CN103046714A (en) | Construction method for double-sided inorganic composite phenolic aldehyde fire-proof heat-insulating decorating integration plates | |
| CN110258873A (en) | A kind of construction method of exterior wall dried hanging clay plate curtain wall | |
| CN104631232A (en) | Integrated pouring device for installation of rail column type inspection pit fastening system | |
| CN105298054A (en) | AEPS (class-A expandable polystyrene) zinc-magnesium steel plate fireproof insulation decorative integrated board and construction process thereof | |
| CN118187462A (en) | Curtain wall installation construction method | |
| CN109518865B (en) | Combined seamless building roof structure and installation method thereof | |
| CN201660981U (en) | An external thermal insulation wall with mechanically anchored metal mesh reinforced polystyrene board | |
| CN113073803A (en) | Assembled external wallboard waterproof system and construction method thereof | |
| CN117108032A (en) | A kind of construction method of thermal insulation decorative structure | |
| CN108277908B (en) | Energy-saving environment-friendly CL wall engineering construction method | |
| CN111287369A (en) | Rapid construction process of glass curtain wall | |
| CN111472524B (en) | Anti-hollowing floor construction method capable of achieving precise leveling | |
| CN112171853B (en) | Stone reverse-beating prefabricated outer wall and production method thereof | |
| CN217981197U (en) | Testing device for anti-sliding performance of ceramic tile adhesive | |
| CN111749441A (en) | A exterior wall ceramic brick laying device for individual layer building | |
| CN209163180U (en) | A kind of extensive high-altitude suspended-cable structure aluminum veneer moulding furred ceiling | |
| CN218493149U (en) | Mortar laying device for construction | |
| CN104018591B (en) | Mechanized construction method for wall thermal insulation | |
| CN104179265A (en) | Inorganic fireproof heat preservation structure and construction method thereof | |
| CN211007488U (en) | Indoor ground overhead structure | |
| CN116695963A (en) | A roof slope finding device and its construction method | |
| CN115749177A (en) | Internal and external corner construction structure and construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20180720 Assignee: Hangzhou Zuolian Advertising Co.,Ltd. Assignor: JIANG University OF TECHNOLOGY Contract record no.: X2022330000922 Denomination of invention: A construction method of building thermal insulation wall Granted publication date: 20191108 License type: Common License Record date: 20221229 |
|
| EE01 | Entry into force of recordation of patent licensing contract | ||
| EE01 | Entry into force of recordation of patent licensing contract | ||
| EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20180720 Assignee: Hangzhou Lianshi Decoration Engineering Co.,Ltd. Assignor: JIANG University OF TECHNOLOGY Contract record no.: X2023980033129 Denomination of invention: A Construction Method of Building Thermal Insulation Wall Granted publication date: 20191108 License type: Common License Record date: 20230306 |
|
| EE01 | Entry into force of recordation of patent licensing contract | ||
| EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20180720 Assignee: Deqing Yuanhao Building Materials Co.,Ltd. Assignor: JIANG University OF TECHNOLOGY Contract record no.: X2023980040860 Denomination of invention: A construction method for building insulation walls Granted publication date: 20191108 License type: Common License Record date: 20230831 |
|
| EE01 | Entry into force of recordation of patent licensing contract | ||
| EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20180720 Assignee: Zhejiang Tianzao Environmental Protection Technology Co.,Ltd. Assignor: JIANG University OF TECHNOLOGY Contract record no.: X2023980047334 Denomination of invention: A construction method for building insulation walls Granted publication date: 20191108 License type: Common License Record date: 20231116 Application publication date: 20180720 Assignee: Lishui Qianyuan Building Materials Technology Co.,Ltd. Assignor: JIANG University OF TECHNOLOGY Contract record no.: X2023980047331 Denomination of invention: A construction method for building insulation walls Granted publication date: 20191108 License type: Common License Record date: 20231116 Application publication date: 20180720 Assignee: Taizhou Nanyang building materials Co.,Ltd. Assignor: JIANG University OF TECHNOLOGY Contract record no.: X2023980047326 Denomination of invention: A construction method for building insulation walls Granted publication date: 20191108 License type: Common License Record date: 20231116 |