CN108277982A - A kind of quick construction process for removing of scaffold for concrete floor - Google Patents

A kind of quick construction process for removing of scaffold for concrete floor Download PDF

Info

Publication number
CN108277982A
CN108277982A CN201810328510.XA CN201810328510A CN108277982A CN 108277982 A CN108277982 A CN 108277982A CN 201810328510 A CN201810328510 A CN 201810328510A CN 108277982 A CN108277982 A CN 108277982A
Authority
CN
China
Prior art keywords
scaffold
rib
concrete
layer board
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810328510.XA
Other languages
Chinese (zh)
Inventor
李英章
裴科
计永强
王殿聪
任杰
尚海
陈刚
马德利
曾现民
韩春涛
黄淑菊
周晓辉
李保彦
赵旺
刘鑫
宋宁宁
豆志周
王卫静
王华先
杨博宇
黄超轶
李佳怡
马玥莹
吴叔于
任珠珠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Aerospace Architectural Design And Research Institute Co Ltd
Safe Sincere Engineering Co Ltd Of Prestige In Beijing
China Aerospace Construction Group Co Ltd
Zhonghangtian Construction Engineering Co Ltd
Original Assignee
Aerospace Architectural Design And Research Institute Co Ltd
Safe Sincere Engineering Co Ltd Of Prestige In Beijing
Zhonghangtian Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Aerospace Architectural Design And Research Institute Co Ltd, Safe Sincere Engineering Co Ltd Of Prestige In Beijing, Zhonghangtian Construction Engineering Co Ltd filed Critical Aerospace Architectural Design And Research Institute Co Ltd
Priority to CN201810328510.XA priority Critical patent/CN108277982A/en
Publication of CN108277982A publication Critical patent/CN108277982A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G19/00Auxiliary treatment of forms, e.g. dismantling; Cleaning devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

A kind of quick construction process for removing of scaffold for concrete floor, by the way that temporary concrete plate support system is arranged in conventional scaffold support system, the span of concrete floor is less than to the span being divided into less than two meters, to realize premature removal routine scaffold support system, since temporary concrete plate support system and conventional scaffold support system are mutually independent support system, so that after conventional scaffold support system is removed, temporary concrete plate support system can be supported individually, and concrete floor is made to reach prescribed strength.The application of the technique realizes the quick turnover of conventional scaffold system, avoids the defect for largely causing construction cost high using conventional scaffold system, meanwhile, effectively accelerate construction speed.

Description

A kind of quick construction process for removing of scaffold for concrete floor
Technical field
The invention belongs to technical field of building construction more particularly to a kind of scaffolds for concrete floor quickly to remove Construction technology.
Background technology
In construction, shuttering supporting is essential process, in construction, needs a large amount of supporting rack and template Input, material volume of the circular flow is big.According to《Concrete structure engineering construction quality accident specification》, different components needs to be achieved The percentage for designing characteristic value of cubic concrete compressive strength is as follows:
1, plate:It is >=50% when span≤2 meter;Work as span>It is >=75% at 2 meters ,≤8 meters;Work as span>8 meters for >= 100%;
2, beam, arch, shell:It is >=75 when span≤8;Work as span>It is >=100% when 8;
3, cantilever member:No matter span is much, it must reach 100%.
According to the design of building and service life demand, the existing cast-in-place mode of building generally use pours flooring, and Generally above 2 meters of the flooring span of existing building, after this makes concrete floor pour, the scaffold under flooring usually requires It could remove within 14 days, with the construction speed of existing 3 to 5 days first floors of China's building, a large amount of scaffold tools be needed to be used to support Flooring, this brings more inconvenience for the management of site operation, while occupying a large amount of human and material resources and financial resources cost.
Invention content
In view of the deficiencies of the prior art, the present invention proposes a kind of quick Demolition Constructions of the scaffold for concrete floor Technique, the application of the technique efficiently solve existing cast-in-site concrete floor and occupy the big technological deficiency of scaffold amount, have foot Hand cradle turnaround speed is fast, occupies the low feature of production cost.
The quick construction process for removing of a kind of scaffold for concrete floor of the present invention is specific as follows:
Step 1:The scaffold support rod, main rib and secondary rib of concrete floor are built according to common process;
Step 2:It is laid with multi-layer board on secondary rib;
Step 3:Interim multi-layer board is set between multi-layer board and multi-layer board, temporary support time rib, institute are set under interim multi-layer board Temporary support time rib is stated to be placed on main rib and parallel with secondary rib;
Step 4:Temporary support rod piece is set under temporary support time rib;
Step 5:Concrete construction and maintenance are carried out to floor according to common process;
Step 6:When floorslab concrete intensity reaches 50%, scaffold support rod, main rib, secondary rib that common process is built are removed And multi-layer board;Retain the temporary supporting system of interim multi-layer board, temporary support time rib and temporary support bar composition simultaneously;
Step 7:When floorslab concrete intensity reaches construct and design desired strength, temporary supporting system is removed.
Further, multiple-plate size is 1800mm × 900mm.
Further, interim multiple-plate width and the secondary rib of temporary support is of same size.
Further, the interim multi-layer board is parallel with multiple-plate short side.
The advantageous effect of technical solution of the present invention is:It is interim mixed by being arranged in conventional scaffold support system The span of concrete floor is less than the span being divided into less than two meters, to realize that premature removal is normal by concrete board support system Scaffold support system is advised, since temporary concrete plate support system and conventional scaffold support system are mutually independent support System so that after conventional scaffold support system is removed, temporary concrete plate support system can be supported individually, make concrete floor Reach prescribed strength.The application of the technique realizes the quick turnover of conventional scaffold system, avoids largely using conventional foot hand The defect that frame system causes construction cost high.
Description of the drawings
Fig. 1 scaffolding structure schematic diagrames of the present invention for concrete floor.
Specific implementation mode
In order to make those skilled in the art more fully understand technical scheme of the present invention, with reference to specific embodiment to this Invention is described in further detail.
As shown in Figure 1, the quick construction process for removing of a kind of scaffold for concrete floor of the present invention be by Conventional scaffold system and temporary concrete plate support system two-part structure are combined the construction technology to be formed.
Conventional scaffold system and temporary concrete plate support system collectively form a kind of foot hand for concrete floor Frame quickly removes system, and the routine scaffold system and temporary concrete plate support system are mutual indepedent and mutually coordinated, Concrete structure is as follows:
The scaffold for concrete floor quickly the system of removing include multi-layer board 2, secondary rib 7, main rib 5, supporting bar 6, Interim multi-layer board 3, temporary support time rib 4, temporary support rod piece 8;
The multi-layer board 2, secondary rib 7, main rib 5, supporting bar 6 form conventional scaffold support system;
The interim multi-layer board 3 is layed between multi-layer board 2 and more side plates 2, and the interim multi-layer board 3 and 2 short side of multi-layer board It is mutually parallel;
The temporary support time rib 4 is located at immediately below interim multi-layer board 3 and the temporary support time rib 4 is parallel with time rib 7;It is described Temporary support time rib 4 is set on main rib 5;4 lower section of the temporary support time rib is supported by temporary support rod piece 8 to be fixed;
The multi-layer board 2 and interim multi-layer board 3 are in same plane, and casting concrete floor 1 is used for above plane.
Further, multiple-plate size is 1800mm × 900mm.
Further, interim multiple-plate width and the secondary rib of temporary support is of same size.
System is quickly removed based on a kind of above-mentioned scaffold for concrete floor, the present invention proposes one kind and is used for The quick construction process for removing of scaffold of concrete floor, Specific construction technique are as follows:
Step 1:The scaffold support rod, main rib and secondary rib of concrete floor are built according to common process;
Step 2:It is laid with multi-layer board on secondary rib;
Step 3:Interim multi-layer board is set between multi-layer board and multi-layer board, temporary support time rib, institute are set under interim multi-layer board Temporary support time rib is stated to be placed on main rib and parallel with secondary rib;
Step 4:Temporary support rod piece is set under temporary support time rib;
Step 5:Concrete construction and maintenance are carried out to floor according to common process;
Step 6:When floorslab concrete intensity reaches 50%, scaffold support rod, main rib, secondary rib that common process is built are removed And multi-layer board;Retain the temporary concrete plate supporter of interim multi-layer board, temporary support time rib and temporary support bar composition simultaneously System;
Step 7:When floorslab concrete intensity reaches construct and design desired strength, temporary concrete plate support system is removed.
The technical thought of construction technology of the present invention be by be arranged temporary concrete form bracing system by floor across Degree in a disguised form blocks to be less than or equal to 2 meters, thus when concrete building surface intensity reaches 50%, according to《Concrete structure engineering is constructed Inspection of quality specification》Conventional scaffold system is removed, the temporary concrete plate branch independently of conventional scaffold system is then utilized Support body system continues to support concrete floor, after concrete floor intensity reaches 75% or 100%, is removing temporary concrete plate branch Support body system.The turn around time of conventional scaffold system component was shortened to 5 days by 14 days, is arrived according to current 3 by the application of this method 5 days one layer of building construction speeds can be significantly reduced conventional scaffold system component and use, while be effectively reduced construction Cost and management cost;Secondly, after the conventional scaffold system in room is removed, subsequent construction personnel can be facilitated accordingly to be applied Work, and according to according to traditional construction technique, due to being covered with scaffold in room, subsequent construction can not be carried out, to influence to apply Work progress, the application of technical solution of the present invention so that conventional scaffold system can be into after floor concrete casting 5 days Row is removed, and the temporary concrete plate support system of simple structure ensures that the Strength Safety of concrete floor improves, on the other hand Open construction space is provided for subsequent construction, so can effectively accelerate the construction speed of building.
A kind of quick construction process for removing of scaffold for concrete floor provided by the present invention is carried out above It is discussed in detail, the principle and implementation of this application are described for embodiment used herein, and above example is said It is bright to be merely used to help understand the present processes and its core concept;Meanwhile for those of ordinary skill in the art, foundation The thought of the application, there will be changes in the specific implementation manner and application range, in conclusion the content of the present specification is not It is interpreted as the limitation to the application.

Claims (4)

1. a kind of quick construction process for removing of scaffold for concrete floor, it is characterised in that:
Step 1:The scaffold support rod, main rib and secondary rib of concrete floor are built according to common process;
Step 2:It is laid with multi-layer board on secondary rib;
Step 3:Interim multi-layer board is set between multi-layer board and multi-layer board, temporary support time rib, institute are set under interim multi-layer board Temporary support time rib is stated to be placed on main rib and parallel with secondary rib;
Step 4:Temporary support rod piece is set under temporary support time rib;
Step 5:Concrete construction and maintenance are carried out to floor according to common process;
Step 6:When floorslab concrete intensity reaches 50%, scaffold support rod, main rib, secondary rib that common process is built are removed And multi-layer board;Retain the temporary concrete plate supporter of interim multi-layer board, temporary support time rib and temporary support bar composition simultaneously System;
Step 7:When floorslab concrete intensity reaches construct and design desired strength, temporary concrete plate support system is removed.
2. a kind of quick construction process for removing of scaffold for concrete floor as described in claim 1, it is characterised in that: Multiple-plate size is 1800mm × 900mm.
3. a kind of quick construction process for removing of scaffold for concrete floor as described in claim 1, it is characterised in that: Interim multiple-plate width is of same size with temporary support time rib.
4. a kind of quick construction process for removing of scaffold for concrete floor as described in claim 1, it is characterised in that: The interim multi-layer board is parallel with multiple-plate short side.
CN201810328510.XA 2018-04-13 2018-04-13 A kind of quick construction process for removing of scaffold for concrete floor Pending CN108277982A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810328510.XA CN108277982A (en) 2018-04-13 2018-04-13 A kind of quick construction process for removing of scaffold for concrete floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810328510.XA CN108277982A (en) 2018-04-13 2018-04-13 A kind of quick construction process for removing of scaffold for concrete floor

Publications (1)

Publication Number Publication Date
CN108277982A true CN108277982A (en) 2018-07-13

Family

ID=62811407

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810328510.XA Pending CN108277982A (en) 2018-04-13 2018-04-13 A kind of quick construction process for removing of scaffold for concrete floor

Country Status (1)

Country Link
CN (1) CN108277982A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102121314A (en) * 2010-12-31 2011-07-13 李万山 Beam-slab framework early removal construction method
CN102720356A (en) * 2012-07-05 2012-10-10 中建一局集团建设发展有限公司 Steel beam grid floor formwork system
CN103572964A (en) * 2012-08-10 2014-02-12 中国水利水电第二工程局有限公司 Mounting method of precast air duct during construction stage of construction engineering structure
US20140263941A1 (en) * 2012-03-19 2014-09-18 Jianhua Zhang Early-removal formwork system for concreting of constructions comprising beams, plates and columns
CN205908017U (en) * 2016-06-17 2017-01-25 重庆瑞鑫科五金制品有限公司 Floor aluminum mould shores device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102121314A (en) * 2010-12-31 2011-07-13 李万山 Beam-slab framework early removal construction method
US20140263941A1 (en) * 2012-03-19 2014-09-18 Jianhua Zhang Early-removal formwork system for concreting of constructions comprising beams, plates and columns
CN102720356A (en) * 2012-07-05 2012-10-10 中建一局集团建设发展有限公司 Steel beam grid floor formwork system
CN103572964A (en) * 2012-08-10 2014-02-12 中国水利水电第二工程局有限公司 Mounting method of precast air duct during construction stage of construction engineering structure
CN205908017U (en) * 2016-06-17 2017-01-25 重庆瑞鑫科五金制品有限公司 Floor aluminum mould shores device

Similar Documents

Publication Publication Date Title
CN101603372B (en) Method for reinforcing integral replacement concrete for high-rise building steel bar concrete column
CN102814861B (en) Preparation method of reinforced concrete beam with demounting-free textile reinforced concrete (TRC) bottom mould
CN106193588B (en) A kind of method pouring building post-cast strip and pour mould
CN107288353A (en) Equipment hoisting transition support platform and its construction method on a kind of super-high buildings floor
CN102806592B (en) Manufacturing method for demolition-free textile fiber web reinforced concrete formwork
CN203403670U (en) Formwork system without support
CN106088493A (en) A kind of pin key connects mounting structure and the construction thereof of prefabricated bench
CN105201204B (en) A kind of method and structure of rotten when preventing pouring reinforcement concrete column suspension column
CN203961281U (en) Steel bar girder beam form frame and H section steel beam-cast-in-place concrete floor formwork system
CN114961263A (en) Large-area concrete skip construction method
CN104675112A (en) Steel stair formwork and constructing method for once pouring forming of building staircase
CN109457872A (en) A kind of prefabricated assembled constructing device of cast in place frame column steel reinforcement cage and construction method
CN104213728B (en) Oblique beam for grandstand of stadium and construction process for oblique beam
CN106049858B (en) A kind of production method of the material distributing machine support platform based on climb formwork platform
CN108277982A (en) A kind of quick construction process for removing of scaffold for concrete floor
CN103061518A (en) Method for constructing composite floor slabs of multi-storey residential building
CN107152112A (en) A kind of modularization Prefabricated stacking floor and its construction method for being used to drop plate region
CN105781159B (en) A kind of power plant main power house armored concrete coal hopper construction technology
CN105297957A (en) Prefabricated filled wallboard and mounting method thereof
CN205712151U (en) A kind of concrete foundation precoated plate
CN107012985A (en) A kind of prefabricated girder and the laminated floor slab construction technology containing the prefabricated girder
CN207314829U (en) A kind of wooden model early tears support device open
CN206034946U (en) Structure is handled to large -scale pressure vertical shaft concrete defect based on slipform technology
CN204626965U (en) For the steel stair template of poured up at a time between architectural stair
CN207934338U (en) A kind of cast-in-situ floor and thickness control of protection cover of rebar device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: No. A6, Courtyard 4, Kandan Road, Fengtai District, Beijing, 100101

Applicant after: China Aerospace Construction Engineering Group Co.,Ltd.

Applicant after: BEIJING TAIWEI XINCHENG ENGINEERING TECHNOLOGY CO.,LTD.

Applicant after: SPACEFLIGHT BUILDING DESIGN RESEARCH INSTITUTE Co.,Ltd.

Address before: No. A6, Courtyard 4, Kandan Road, Fengtai District, Beijing, 100101

Applicant before: ZHONG HANG TIAN CONSTRUCTION ENGINEERING Co.,Ltd.

Applicant before: BEIJING TAIWEI XINCHENG ENGINEERING TECHNOLOGY CO.,LTD.

Applicant before: SPACEFLIGHT BUILDING DESIGN RESEARCH INSTITUTE Co.,Ltd.