CN108277814A - Stake top counterfort wall supporting construction and construction method - Google Patents

Stake top counterfort wall supporting construction and construction method Download PDF

Info

Publication number
CN108277814A
CN108277814A CN201810322450.0A CN201810322450A CN108277814A CN 108277814 A CN108277814 A CN 108277814A CN 201810322450 A CN201810322450 A CN 201810322450A CN 108277814 A CN108277814 A CN 108277814A
Authority
CN
China
Prior art keywords
stake
wall
connection beam
chock
counterfort
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810322450.0A
Other languages
Chinese (zh)
Inventor
王凯
王森
邓丽华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING GAOXIN ENGINEERING SURVEY AND DESIGN INSTITUTE Co Ltd
Original Assignee
CHONGQING GAOXIN ENGINEERING SURVEY AND DESIGN INSTITUTE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING GAOXIN ENGINEERING SURVEY AND DESIGN INSTITUTE Co Ltd filed Critical CHONGQING GAOXIN ENGINEERING SURVEY AND DESIGN INSTITUTE Co Ltd
Priority to CN201810322450.0A priority Critical patent/CN108277814A/en
Publication of CN108277814A publication Critical patent/CN108277814A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Retaining Walls (AREA)

Abstract

The present invention discloses a kind of stake top counterfort wall supporting construction and construction method.Stake top counterfort wall supporting construction includes stake and counterfort wall, stake is embedded within the scope of the 2m of present situation slight slope face or less, and counterfort wall is formed in an over top by connection beam, wherein, the shingle nail of counterfort wall is stood on vertically above connection beam, and wall heel slab is laterally extended to backfill side.The supporting construction combination stake of the present invention and the advantage of counterfort wall, supporting construction itself stability against overturning when can enhance slope edges or weaker foundation soil body bearing capacity, the transverse pressure that side slope high fill generates supporting construction, resistance to deformation and sliding can be born again.

Description

Stake top counterfort wall supporting construction and construction method
One, technical field
The present invention relates to a kind of side slope embankment supporting construction and construction method, more particularly to a kind of stake top counterfort wall branch Protection structure and construction method.
Two, background technology
In Civil Engineering Construction, side slope embankment is common engineering usually to be needed to ensure the stability of engineering structure Will in side slope construction supporting structure, in the processing of side slope embankment through frequently with supporting construction mainly have Cantilever Retaining Structure and counterfort wall structure.
1, overhang mill pilework
In current slope retaining, overhang mill pilework is applied than wide.It is by artificial digging pile or drilling Bored concrete pile is arranged in a straight line, and is connected by connection beam, the common structure type for resisting soil lateral pressure or side slope thrust.Cantilevered branch The advantages of fender pile is, stake can bear larger vertical load, while also have the ability for undertaking stronger horizontal loading, structure by Force mode is clear, and structure Design and Calculation is simple.
It is more than that certain altitude and support pile fixed section Rock And Soil intensity are insufficient in side slope embankment, overhang mill Stake lateral force resisting is poor, and deformation is difficult to control, and safety is difficult to be guaranteed, to limit its use scope, even if It uses reluctantly, it is insufficient to will also result in material use, deficiency in economic performance.
2, counterfort wall structure
Counterfort wall is a kind of armored concrete thin wall-type retaining wall, is mainly characterized by simple structure, construction party Just, wall body section is smaller, and sole mass is light, can preferably play the strength character of material.On counterfort wall heel slab Soil body gravity can be reasonably resistant to topple and slide, and riser and counterfort bear the moment of flexure and shearing that soil pressure generates jointly, relatively Cantilever retaining wall stress is good.
Since the structural stability of counterfort wall is ensured by the gravity to banket above wall body and wall heel slab, And the setting main function of toe of wall plate is to enhance itself stability against overturning and substrate contact stress, therefore, to foundation soil Body self stability, bearing capacity and resistance to deformation are more demanding, when barricade ground is in slope edges, it is understood that there may be stability of slope Property, foundation soil body bearing capacity etc. cannot meet situation, safety it cannot be guaranteed that, then application is restricted.
Three, invention content
In order to overcome the advantage of the disadvantages mentioned above of the prior art, present invention combination stake and counterfort wall, one kind is provided Simply, practical, the superior new supporting structure of stress performance, i.e. stake top counterfort wall supporting construction, the supporting construction pass through Cantilever pile length is shortened, so that stake top is reduced to side slope top between the following ranges of original ground 2m, stake is in the side of the supporting and retaining system lower part soil body While to power (sliding force or soil pressure), also lateral resistance and vertical foundation bearing are provided to help arm-type barricade to slide Power, guarantee help arm-type barricade to stablize.Since pile length is reduced, the arm of force shortens, and torque reduces, and the moment of flexure of stake is also reduced by, to Achieve the purpose that the lateral resistance of enhancing.Stake top counterfort wall supporting construction and construction method provided by the invention, Ji Nengzeng Itself stability against overturning when strong slope edges or weaker foundation soil body bearing capacity, and side slope can be born and banketed to supporting construction The transverse pressure of generation, resistance to deformation and sliding.
The present invention is technical solution used by solving its technical problem:A kind of stake top counterfort wall supporting knot is provided Structure, including stake, connection beam, chock and counterfort wall, wherein the stake is embedded in present situation slight slope face hereinafter, the contact Beam is located at the stake top portion and connects adjacent studs, and the chock is located at the connection beam top edge and vertical with the connection beam Connection, the counterfort wall includes the toe of wall plate that bottom level is arranged at the top of the connection beam and rectangle wall heel slab, vertical In the shingle nail of bottom and the triangle floor of the connection shingle nail and the wall heel slab, the shingle nail is located at described Right at the top of binder, the wall heel slab and the floor extend to the backfill side of counterfort wall, the toe of wall plate with The chock horizontal connection.
Stake insertion protolith (soil) the body depth and stake top height determine that general stake top height exists according to stable calculation Present situation below ground 0.5m~2.0m;Counterfort wall height is determined according to specific geology and project situation, generally takes 4m~15m; Floor is triangular in shape, and thickness and height are calculated according to stress size and determined;Contact beam section size foundation helps arm-type barricade lotus It carries and determines;Chock plays the role of blocking and helps arm-type barricade horizontal sliding, and wall heel slab, shingle nail, toe of wall plate are respectively according to the soil body Horizontal and vertical load, which calculates, determines its thickness.
In the present invention, stake, connection beam, chock, counterfort wall use reinforced concrete structure, concrete grade to be not less than C30。
The construction method of the present invention:
According to engineering practice, operating condition and stress to stake and counterfort wall structure carry out Force Calculation, really Determine number of steel bars, structural form, concrete grade and the quantity of stake and buried depth of stake, chock, connection beam and counterfort wall. According to arrangement and method for construction, construction stake, connection beam, chock and counterfort wall backfill pressure after concrete strength reaches design strength The soil body after blank wall.
Compared with prior art, the present invention having the following advantages and beneficial effect:
(1) citation form of the present invention has the advantages that easy, safe efficient, anti-slipping property is good and bearing capacity is good.
(2) being directed to counterfort wall has wall body section smaller, and sole mass is light, gives full play to soil body Gravitative Loads, gear The strong feature of native ability, but when being used in that part of the foundation bearing capacity is poor or the place on soil-slope top, foundation capability is not It can meet or ground is unstable, influence its application, the present invention organically combines stake and counterfort wall, and it is excellent to give full play to the two Gesture can enhance vertical foundation bearing capacity using stake and enhance the self stability of slope foundation, be enhanced using counterfort wall The ability for resisting transversely acting of banketing, by stake and the common stress of barricade, to greatly improve the support capacity of retaining wall.
Four, it illustrates
Fig. 1 is the concrete structure schematic cross-sectional view of the construction embodiment of the present invention;
Fig. 2 is the concrete structure vertical view of the construction embodiment of the present invention.
In figure:1- 2- floor 3- chock 4- wall heel slab 5- shingle nails
6- toe of wall plate 7- connection beams
Specific implementation mode
Detailed description furtherly is made to the present invention in the following with reference to the drawings and specific embodiments, so as to people in the art Member understands.
The supporting construction of stake top counterfort wall shown in Fig. 1-2, the supporting construction include stake 1 and counterfort wall, stake 1 It is embedded in the soil body, the stake 1 is embedded in present situation slight slope face or less 0.5m~2.0m;Stake 1 passes through connection beam 7 along arranged in a straight line Connection, connection beam 7 are bound by reinforcing bar and are connect with 1 reserved steel bar of stake.The counterfort wall height is 4m~15m, including rib Plate 2, wall heel slab 4, shingle nail 5 and toe of wall plate 6, wherein shingle nail 5 and wall heel slab 4, toe of wall plate 6 are bound and are joined by reinforcing bar 7 reserved steel bar of binder is connected, and shingle nail 5 is vertical with connection beam 7, and wall heel slab 4 laterally prolongs to the backfill side of counterfort wall It stretches.Counterfort wall horizontal sliding in order to prevent, can also the top edge of connection beam 7 formed chock 3, chock 3 with contact Binding reinforcing bars are carried out between beam 7 and the toe of wall plate 6 of counterfort wall.The present invention, stake 1, connection beam 7, chock 3, buttress type gear Wall connection uses reinforced concrete structure, concrete grade to be not less than C30.
Construction method example:
A. according to engineering practice, to the working environment of the stake 1, connection beam 7, chock 3 and counterfort wall structure Calculated with stress condition, determine the number of steel bars of the stake 1, connection beam 7, chock 3 and counterfort wall, structural form, Concrete grade and the quantity and buried depth of the stake 1;
B. construction stake 1, connection beam 7 and chock 3:Use manually digging hole or machine drilling first, after manually digging hole pore-forming Fabrication and installation steel reinforcement cage in hole is then fixed the reinforcing bar cage hoisting made after machine drilling pore-forming, then carries out concrete and pours It builds and to form the stake 1 and reserved steel bar is connect with the connection beam 7;Conventional maintenance makes 1 concrete strength of the stake reach After 30%~70%, construct the connection beam 7 at the top of the stake 1;Excavation of foundation pit and foundation construction are carried out first, then It makes 7 reinforcing bar of connection beam and itself and 1 reserved steel bar of the stake is subjected to reinforcing bar binding, installation form carries out concreting shape At the connection beam 7, the top of the connection beam 7 be formed with reserved steel bar so as to the chock 3, wall heel slab 4, shingle nail 5, wall Toe board 6 connects;Conventional maintenance makes 7 concrete strength of the connection beam reach the 30%~70% of design strength, described Construction chock 3 in 7 top edge of binder makes 3 reinforcing bar of the chock and carries out reinforcing bar with 7 top reserved steel bar of the connection beam and ties up Prick, installation form, carry out concreting and form the chock 3, the chock 3 be formed with reserved steel bar so as to the toe of wall Plate 6 connects;
C. it constructs counterfort wall:Counterfort wall is formed in side slope leading edge, makes toe of wall plate 6, wall heel slab 4, wall first 6 reinforcing bar of toe of wall plate is then carried out reinforcing bar with the chock 3,7 reserved steel bar of connection beam and tied up by 2 reinforcing bar of panel 5 and floor It pricks, the wall heel slab 4, shingle nail 5 and 7 reserved steel bar of the connection beam carry out reinforcing bar binding, the floor 2 and wall heel slab 4, wall Panel 5 carries out reinforcing bar binding, then installation form, carries out concreting formation and helps arm-type barricade;
D. conventional maintenance make it is described help arm-type barricade concrete strength reach design strength 30%~70% after, backfill The soil body after compacting wall.
In the present invention, during paying attention to drilling construction, it is accurate, reasonable that stake position and barricade will be arranged, avoid wasting, protect simultaneously Card stake top is completely embedded with counterfort wall.
Although above-described embodiment is made that detailed description to the present invention, it is only a part of the embodiment of the present invention, Rather than whole embodiments, people can also obtain other embodiment according to the present embodiment under the premise of without creativeness, these Embodiment belongs to the scope of the present invention.

Claims (8)

1. a kind of stake top counterfort wall supporting construction, it is characterised in that:Including stake (1), connection beam (7), chock (3) and help Wall type barricade, wherein the stake (1) is embedded in present situation slight slope face hereinafter, the connection beam (7) is located at the top of the stake (1) simultaneously Adjacent studs (1) are connected, the chock (3) is located at the connection beam (7) top edge and is connect vertically with the connection beam (7), The counterfort wall include the toe of wall plate (6) that bottom level is arranged at the top of the connection beam (7) and rectangle wall heel slab (4), It is described perpendicular to the shingle nail (5) of bottom and the triangle floor (2) of the connection shingle nail (5) and the wall heel slab (4) Shingle nail (5) is located at the connection beam (7) top surface, the wall heel slab (4) and the floor (2) to counterfort wall Backfill side extend, the toe of wall plate (6) and the chock (3) horizontal connection.
2. stake top counterfort wall supporting construction as described in claim 1, it is characterised in that:The stake (1) is embedded in present situation 0.5m~2.0m below slight slope face.
3. stake top counterfort wall supporting construction as described in claim 1, it is characterised in that:The height of the counterfort wall For 4m~15m.
4. stake top counterfort wall supporting construction as described in claim 1, it is characterised in that:The stake (1), connection beam (7), Chock (3) and counterfort wall use reinforced concrete structure, concrete grade to be not less than C30.
5. a kind of construction method of stake top counterfort wall supporting construction as described in claim 1, which is characterized in that including with Lower step:
A. according to engineering practice, to the stake (1), connection beam (7), chock (3) and counterfort wall structure building ring Border and stress condition are calculated, determine the stake (1), connection beam (7), chock (3) and counterfort wall number of steel bars, structure The quantity and buried depth of appearance formula, concrete grade and the stake (1);
B. construction stake (1), connection beam (7) and chock (3):Manually digging hole or machine drilling are used first, after manually digging hole pore-forming The reinforcing bar cage hoisting made then is fixed after machine drilling pore-forming, then carries out concrete by the fabrication and installation steel reinforcement cage in hole It pours and to form the stake (1) and reserved steel bar is connect with the connection beam (7);Conventional maintenance makes the stake (1) strong concrete After degree reaches the 30%~70% of design strength, in the top of the stake (1) the construction connection beam (7);Foundation pit is carried out first Excavation and foundation construction then make connection beam (7) reinforcing bar and itself and the stake (1) reserved steel bar are carried out reinforcing bar binding, Installation form carries out concreting and forms the connection beam (7), the connection beam (7) be formed with reserved steel bar so as to institute State chock (3), wall heel slab (4), shingle nail (5), toe of wall plate (6) connection;Conventional maintenance makes the connection beam (7) strong concrete Degree reaches the 30%~70% of design strength, in the connection beam (7) top edge construction chock (3), makes the chock (3) Reinforcing bar simultaneously carries out reinforcing bar binding, installation form with reserved steel bar at the top of the connection beam (7), and progress concreting forms described Chock (3), the chock (3) are formed with reserved steel bar to be connect with the toe of wall plate (6);
C. it constructs counterfort wall:Counterfort wall is formed in side slope leading edge, makes toe of wall plate (6), wall heel slab (4), wall first Panel (5) and floor (2) reinforcing bar, then by toe of wall plate (6) reinforcing bar and the chock (3), connection beam (7) reserved steel bar Reinforcing bar binding is carried out, the wall heel slab (4), shingle nail (5) and the connection beam (7) reserved steel bar carry out reinforcing bar binding, described Floor (2) carries out reinforcing bar binding with wall heel slab (4), shingle nail (5), then installation form, carries out concreting formation and helps arm Formula barricade;
D. conventional maintenance make it is described help arm-type barricade concrete strength reach design strength 30%~70% after, be backfilling and compacted The soil body after wall.
6. the construction method of stake top counterfort wall supporting construction as claimed in claim 5, it is characterised in that:The stake (1) It is embedded in present situation slight slope face or less 0.5m~2.0m.
7. the construction method of stake top counterfort wall supporting construction as claimed in claim 5, it is characterised in that:The buttress type The height of barricade is 4m~15m.
8. the construction method of stake top counterfort wall supporting construction as claimed in claim 5, it is characterised in that:The stake (1), Connection beam (7), chock (3) and counterfort wall concrete grade are not less than C30.
CN201810322450.0A 2018-04-11 2018-04-11 Stake top counterfort wall supporting construction and construction method Pending CN108277814A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810322450.0A CN108277814A (en) 2018-04-11 2018-04-11 Stake top counterfort wall supporting construction and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810322450.0A CN108277814A (en) 2018-04-11 2018-04-11 Stake top counterfort wall supporting construction and construction method

Publications (1)

Publication Number Publication Date
CN108277814A true CN108277814A (en) 2018-07-13

Family

ID=62811714

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810322450.0A Pending CN108277814A (en) 2018-04-11 2018-04-11 Stake top counterfort wall supporting construction and construction method

Country Status (1)

Country Link
CN (1) CN108277814A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109881686A (en) * 2018-12-03 2019-06-14 中铁上海工程局集团有限公司 A kind of tall and big retaining structure of Unfavorable geology side slope
CN110029685A (en) * 2019-04-16 2019-07-19 中铁建设集团有限公司 A kind of pile drawing anchor barricade fabricated construction
CN110242306A (en) * 2019-06-28 2019-09-17 四川省交通勘察设计研究院有限公司 Open cut tunnel anti-side laminated structure and construction method
CN110578290A (en) * 2019-08-14 2019-12-17 山东高速工程检测有限公司 Abutment back backfilling structure of bridgehead and construction method thereof
CN111236258A (en) * 2020-03-12 2020-06-05 广西交通科学研究院有限公司 Prefabricated pile wall supporting structure with stiffening rib wall and unloading platform and construction method thereof
CN111236259A (en) * 2020-03-12 2020-06-05 广西交通科学研究院有限公司 Combined lattice-shaped prefabricated pile wall supporting structure and construction method thereof
CN111576454A (en) * 2020-06-17 2020-08-25 云南省建设投资控股集团有限公司 Combined protective structure for side slope retaining wall and steel pipe pile and construction method thereof
CN113047336A (en) * 2021-04-20 2021-06-29 湖南省交通规划勘察设计院有限公司 Pile bearing arm type retaining wall
CN113431083A (en) * 2021-06-10 2021-09-24 中南勘察设计院集团有限公司 Light supporting structure of pile foundation joist and construction method thereof
CN114108691A (en) * 2021-12-02 2022-03-01 国能朔黄铁路发展有限责任公司 Construction process of novel counterfort retaining wall
CN114233324A (en) * 2021-12-17 2022-03-25 中铁大桥勘测设计院集团有限公司 Tunnel structure suitable for bias working condition and construction method thereof
CN114790752A (en) * 2022-05-18 2022-07-26 中建八局第三建设有限公司 Recyclable temporary slope reinforcement device and construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090232608A1 (en) * 2008-03-14 2009-09-17 Chouery Farid A Retaining wall
CN103266622A (en) * 2013-06-09 2013-08-28 中铁第四勘察设计院集团有限公司 L-shaped retaining wall structure with cross-over type special-shaped counterfort
CN103469814A (en) * 2013-09-24 2013-12-25 兰州理工大学 Novel barricade supporting structure for road or river bank dam and construction method thereof
CN104894926A (en) * 2015-06-09 2015-09-09 中铁第一勘察设计院集团有限公司 Retaining structure on existing railway high embankment and construction method thereof
CN106284408A (en) * 2016-09-20 2017-01-04 广东舍卫工程技术咨询有限公司 Pile reinforced soil retaining wall
CN106930319A (en) * 2017-05-03 2017-07-07 中冶沈勘工程技术有限公司 A kind of high slope framed revetment and its construction method
CN107254880A (en) * 2017-07-19 2017-10-17 中铁上海设计院集团有限公司 A kind of curb is combined retaining structure
CN208088318U (en) * 2018-04-11 2018-11-13 王凯 Stake top counterfort wall supporting construction

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090232608A1 (en) * 2008-03-14 2009-09-17 Chouery Farid A Retaining wall
CN103266622A (en) * 2013-06-09 2013-08-28 中铁第四勘察设计院集团有限公司 L-shaped retaining wall structure with cross-over type special-shaped counterfort
CN103469814A (en) * 2013-09-24 2013-12-25 兰州理工大学 Novel barricade supporting structure for road or river bank dam and construction method thereof
CN104894926A (en) * 2015-06-09 2015-09-09 中铁第一勘察设计院集团有限公司 Retaining structure on existing railway high embankment and construction method thereof
CN106284408A (en) * 2016-09-20 2017-01-04 广东舍卫工程技术咨询有限公司 Pile reinforced soil retaining wall
CN106930319A (en) * 2017-05-03 2017-07-07 中冶沈勘工程技术有限公司 A kind of high slope framed revetment and its construction method
CN107254880A (en) * 2017-07-19 2017-10-17 中铁上海设计院集团有限公司 A kind of curb is combined retaining structure
CN208088318U (en) * 2018-04-11 2018-11-13 王凯 Stake top counterfort wall supporting construction

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
廖来兴;张可能;王在军;: "桩承扶壁式挡土墙在某住宅小区填方边坡的应用", 广东建材 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109881686A (en) * 2018-12-03 2019-06-14 中铁上海工程局集团有限公司 A kind of tall and big retaining structure of Unfavorable geology side slope
CN110029685A (en) * 2019-04-16 2019-07-19 中铁建设集团有限公司 A kind of pile drawing anchor barricade fabricated construction
CN110242306A (en) * 2019-06-28 2019-09-17 四川省交通勘察设计研究院有限公司 Open cut tunnel anti-side laminated structure and construction method
CN110578290B (en) * 2019-08-14 2024-04-05 山东高速工程检测有限公司 Bridge abutment back backfill structure and construction method thereof
CN110578290A (en) * 2019-08-14 2019-12-17 山东高速工程检测有限公司 Abutment back backfilling structure of bridgehead and construction method thereof
CN111236258A (en) * 2020-03-12 2020-06-05 广西交通科学研究院有限公司 Prefabricated pile wall supporting structure with stiffening rib wall and unloading platform and construction method thereof
CN111236259A (en) * 2020-03-12 2020-06-05 广西交通科学研究院有限公司 Combined lattice-shaped prefabricated pile wall supporting structure and construction method thereof
CN111576454A (en) * 2020-06-17 2020-08-25 云南省建设投资控股集团有限公司 Combined protective structure for side slope retaining wall and steel pipe pile and construction method thereof
CN113047336A (en) * 2021-04-20 2021-06-29 湖南省交通规划勘察设计院有限公司 Pile bearing arm type retaining wall
CN113431083A (en) * 2021-06-10 2021-09-24 中南勘察设计院集团有限公司 Light supporting structure of pile foundation joist and construction method thereof
CN114108691A (en) * 2021-12-02 2022-03-01 国能朔黄铁路发展有限责任公司 Construction process of novel counterfort retaining wall
CN114108691B (en) * 2021-12-02 2022-12-27 国能朔黄铁路发展有限责任公司 Construction process of novel counterfort retaining wall
CN114233324A (en) * 2021-12-17 2022-03-25 中铁大桥勘测设计院集团有限公司 Tunnel structure suitable for bias working condition and construction method thereof
CN114790752A (en) * 2022-05-18 2022-07-26 中建八局第三建设有限公司 Recyclable temporary slope reinforcement device and construction method

Similar Documents

Publication Publication Date Title
CN108277814A (en) Stake top counterfort wall supporting construction and construction method
CN103452147B (en) Self-balancing anchor counterweight broken pile forced-landing tilt correcting method
CN201125354Y (en) Steep hill road bed branch block reinforced structure
CN104790429B (en) A kind of construction method of monoblock type prestressing force reinforced soil retaining wall
CN105240018B (en) Construction of Silo device and method
CN207130754U (en) The large-span arch bridge combined type pile foundation construction of two-way cooperative bearing
CN107059882A (en) Arch anchor net and Anchor-Pile Retaining Structure structure
CN101793098B (en) Coordinated interactive combined rectification method
CN109183809A (en) A kind of construction method of Muddy Bottoms clay deep-foundation pit engineering composite support support replacement
CN103215889A (en) Arch bridge foundation used on bad geological conditions and construction method of arch bridge foundation
CN202865855U (en) Stabilizing plate type anchoring pile retaining structure
CN102839686A (en) Stabilizing plate type anchor pile retaining structure
CN106869138A (en) A kind of load retaining wall Retaining Structure with Double-row Piles and its foundation ditch excavation method
CN208088311U (en) Back-pressure de-bowed type pile slab supporting structure after stake
CN107100179A (en) Light-duty combination retaining structure and the method for administering a wide range of tall earth fill engineering
CN109944162A (en) A kind of Combined light anchorage and construction method for large-tonnage Hoisting with Cableway System
CN208088318U (en) Stake top counterfort wall supporting construction
CN106245673A (en) A kind of rib stake formula peg board retaining wall and construction method thereof
CN211285725U (en) Basin hills abrupt slope area high-rise building synthesizes earthquake-resistant structure
CN210151660U (en) Embedded concrete antiskid tenon grout stone retaining wall
CN209798847U (en) Structure for enhancing anti-floating capacity of underground construction/structure
CN111576479A (en) Retaining structure of filling slope and construction method
CN108360555A (en) A kind of the ground anchor structure formula cantilever barrier wall structure and its stability calculation method of railway sunk type station
CN108330986A (en) Back-pressure de-bowed type pile slab supporting structure and construction method after stake
CN205475266U (en) Side slope reinforcing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180713

RJ01 Rejection of invention patent application after publication