CN110029685A - An assembled structure of pile bearing anchor retaining wall - Google Patents

An assembled structure of pile bearing anchor retaining wall Download PDF

Info

Publication number
CN110029685A
CN110029685A CN201910302882.XA CN201910302882A CN110029685A CN 110029685 A CN110029685 A CN 110029685A CN 201910302882 A CN201910302882 A CN 201910302882A CN 110029685 A CN110029685 A CN 110029685A
Authority
CN
China
Prior art keywords
pile
barricade
anchor
draws
retaining wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910302882.XA
Other languages
Chinese (zh)
Inventor
翟玉新
芮瑞
崔梦麟
李世仲
王子照
陈静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Technology WUT
China Railway Construction Group Co Ltd
Original Assignee
Wuhan University of Technology WUT
China Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Technology WUT, China Railway Construction Group Co Ltd filed Critical Wuhan University of Technology WUT
Priority to CN201910302882.XA priority Critical patent/CN110029685A/en
Publication of CN110029685A publication Critical patent/CN110029685A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The invention discloses a kind of piles to draw anchor barricade fabricated construction, including the vertical bearing pile of multiple groups, pile cover is equipped at the top of the vertical bearing pile, coupling beam is equipped between the adjacent pile cover, it is respectively equipped with pile on pile cover described in every group of outside stake and draws anchor barricade, the pile draws anchor barricade side to be equipped with counterfort, and the pile draws the anchor barricade other side to be equipped with drag-line, and the drag-line is connected with the pile cover of inboard stake, coupling beam described in every group of outside stake is equipped with prefabricated barricade.It is prefabricated in factory normalization the invention has the advantages that: using, the period of construction is effectively shortened, shape is neat, succinct, and it is more beautiful, while achieving better supporting effect.

Description

一种桩承拉锚挡墙装配式结构An assembled structure of pile bearing anchor retaining wall

技术领域technical field

本发明涉及土木工程技术领域,具体来说,涉及一种桩承拉锚挡墙装配式结构。The invention relates to the technical field of civil engineering, in particular to an assembled structure of a pile-supported anchor-retaining wall.

背景技术Background technique

目前,各地城市化进程不断加快,扩容新建和旧路改造的城市建设力度不断提高,传统的路堤挡土墙多为工人在现场施工建设,机械化程度低,建设周期长,在经济飞速发展的今天,已然不适应经济的发展需求。At present, the process of urbanization is accelerating in various places, and the urban construction efforts for expansion of new construction and renovation of old roads are constantly increasing. Traditional embankment and retaining walls are mostly constructed by workers on site, with low degree of mechanization and long construction period. In today's rapid economic development , has not adapted to the needs of economic development.

针对相关技术中的问题,目前尚未提出有效的解决方案。For the problems in the related technologies, no effective solutions have been proposed so far.

发明内容SUMMARY OF THE INVENTION

针对相关技术中的上述技术问题,本发明提出一种桩承拉锚挡墙装配式结构,能够解决机械化程度低,建设周期长,建设成本高,建设效果差的问题。In view of the above-mentioned technical problems in the related art, the present invention proposes an assembled structure of a pile-supported anchor retaining wall, which can solve the problems of low degree of mechanization, long construction period, high construction cost and poor construction effect.

为实现上述技术目的,本发明的技术方案是这样实现的:For realizing the above-mentioned technical purpose, the technical scheme of the present invention is realized like this:

一种桩承拉锚挡墙装配式结构,包括多组竖向承载桩,所述竖向承载桩顶部设有桩帽,相邻所述桩帽之间设有连梁,外侧桩的每组所述桩帽上分别设有桩承拉锚挡墙,所述桩承拉锚挡墙一侧设有扶壁,所述桩承拉锚挡墙另一侧设有拉索,且所述拉索与里侧桩的所述桩帽相连接,外侧桩每组所述连梁上设有预制挡墙,且所述预制挡墙位于相邻所述桩承拉锚挡墙之间。An assembled structure of a pile bearing, tension anchor and retaining wall, comprising a plurality of groups of vertical bearing piles, the top of the vertical bearing piles is provided with a pile cap, and a connecting beam is arranged between the adjacent pile caps. The pile caps are respectively provided with a pile-supported anchor retaining wall, one side of the pile-supported anchor-anchor retaining wall is provided with a buttress, the other side of the pile-supported anchor-anchor retaining wall is provided with a cable, and the The cables are connected to the pile caps of the inner piles, and each group of the coupling beams of the outer piles is provided with a prefabricated retaining wall, and the prefabricated retaining wall is located between the adjacent pile anchor retaining walls.

进一步地,所述桩帽上设有预应力钢筋,所述桩承拉锚挡墙包括拉锚挡墙立板,所述拉锚挡墙立板上设有与所述预应力钢筋相对应的通孔,所述预应力钢筋与所述通孔相连接。Further, the pile caps are provided with prestressed steel bars, the pile-bearing tension anchor retaining wall includes a tension anchor retaining wall vertical plate, and the tension anchor retaining wall vertical plate is provided with a corresponding prestressed steel bar. A through hole, the prestressed steel bar is connected with the through hole.

进一步地,所述扶壁设置于所述挡墙拉锚挡墙立板的外侧,所述拉索设置于所述挡墙拉锚挡墙立板的里侧。Further, the buttress is arranged on the outer side of the retaining wall anchor and retaining wall vertical plate, and the stay cable is arranged on the inner side of the retaining wall tensile anchor retaining wall vertical plate.

进一步地,所述拉锚挡墙立板上设有与所述拉索相对应的锚固孔,所述锚固孔与所述拉索顶端相连接。Further, an anchoring hole corresponding to the cable is provided on the vertical plate of the anchor retaining wall, and the anchor hole is connected with the top end of the cable.

进一步地,所述拉锚挡墙立板左右两侧设有第一榫槽,所述预制挡墙左右两侧设有与所述第一榫槽相对应的第一凸榫,所述第一榫槽与所述第一凸榫相连接。Further, the left and right sides of the vertical plate of the anchor retaining wall are provided with first tenon grooves, and the left and right sides of the prefabricated retaining wall are provided with first tenons corresponding to the first tenon grooves. The tongue and groove are connected with the first tenon.

进一步地,所述连梁包括全断面连梁和半断面连梁,其中,纵向外侧相邻每组所述桩帽之间通过所述全断面连梁相连接,横向相邻每组所述桩帽之间通过所述半断面连梁相连接。Further, the coupling beams include full-section coupling beams and half-section coupling beams, wherein each group of adjacent pile caps on the longitudinal outer side are connected by the full-section coupling beams, and each group of adjacent piles in the lateral direction is connected. The caps are connected by the half-section connecting beams.

进一步地,所述全断面连梁上设有第二榫槽,所述预制挡墙底端设有与所述第二榫槽相对应的第二凸榫,所述第二榫槽与所述第二凸榫相连接。Further, the full-section connecting beam is provided with a second tenon groove, the bottom end of the prefabricated retaining wall is provided with a second tenon corresponding to the second tenon groove, and the second tenon groove and the The second tenon is connected.

进一步地,所述预制挡墙上设有若干排水孔。Further, a plurality of drainage holes are provided on the prefabricated retaining wall.

本发明的有益效果:采用在工厂标准化预制,有效的缩短了建设的周期,外形整齐、简洁,更加美观,同时取得了更好的支护效果。The beneficial effects of the present invention are as follows: the standardized prefabrication in the factory is adopted, which effectively shortens the construction period, the appearance is neat, concise, and more beautiful, and at the same time, a better supporting effect is achieved.

附图说明Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the accompanying drawings required in the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some of the present invention. In the embodiments, for those of ordinary skill in the art, other drawings can also be obtained according to these drawings without any creative effort.

图1是根据本发明实施例所述的桩承拉锚挡墙装配式结构的整体结构示意图;1 is a schematic diagram of the overall structure of the assembled structure of the pile-supported anchor retaining wall according to an embodiment of the present invention;

图2是根据本发明实施例所述的桩承拉锚挡墙的整体结构示意图;2 is a schematic diagram of the overall structure of the pile-supported anchor retaining wall according to an embodiment of the present invention;

图3是根据本发明实施例所述的桩承拉锚挡墙装配式结构的结构示意图;3 is a schematic structural diagram of the assembled structure of a pile-supported anchor retaining wall according to an embodiment of the present invention;

图4是根据本发明实施例所述的预制挡墙的结构示意图;4 is a schematic structural diagram of a prefabricated retaining wall according to an embodiment of the present invention;

图5是根据本发明实施例所述的桩帽预留钢筋的结构示意图;5 is a schematic structural diagram of a pile cap reserved steel bar according to an embodiment of the present invention;

图6是根据本发明实施例所述的拉索锚固的结构示意图;FIG. 6 is a schematic structural diagram of a stay cable anchoring according to an embodiment of the present invention;

图7是根据本发明实施例所述的第一骨架的结构示意图;7 is a schematic structural diagram of a first skeleton according to an embodiment of the present invention;

图8是根据本发明实施例所述的第二的结构示意图。FIG. 8 is a second structural schematic diagram according to an embodiment of the present invention.

图中:In the picture:

10、多组竖向承载桩;10. Multiple groups of vertical bearing piles;

20、桩帽; 21、预应力钢筋;20. Pile cap; 21. Prestressed steel bar;

30、全断面连梁; 31、第二榫槽;30. Full-section connecting beam; 31. Second tongue and groove;

40、半断面连梁;40. Half-section connecting beam;

50、桩承拉锚挡墙; 51、扶壁; 52、拉索; 53、通孔;54、第一榫槽; 55、锚固孔; 56、挡墙拉锚挡墙立板;57、第一骨架;50. Pile-supported anchor retaining wall; 51. Buttress; 52. Cable; 53. Through hole; 54. The first tenon and groove; 55. Anchoring hole; a skeleton;

60、预制挡墙; 61、第一凸榫; 62、第二凸榫; 63、排水孔;64、第二骨架;60, prefabricated retaining wall; 61, the first tenon; 62, the second tenon; 63, the drainage hole; 64, the second frame;

70、锚头; 71、钢垫片; 72、锚具。70. Anchor head; 71. Steel gasket; 72. Anchor.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by those of ordinary skill in the art fall within the protection scope of the present invention.

如图1-8所示,根据本发明实施例所述的一种桩承拉锚挡墙装配式结构,包括多组竖向承载桩10,所述竖向承载桩10顶部设有桩帽20,相邻所述桩帽20之间设有连梁,外侧桩的每组所述桩帽20上分别设有桩承拉锚挡墙50,桩承拉锚挡墙50为装配式桩承拉锚挡墙,所述桩承拉锚挡墙50一侧设有扶壁51,所述桩承拉锚挡墙50另一侧设有拉索52,且拉索52的一端和里侧桩的桩帽20进行连接,外侧桩每组所述连梁上设有预制挡墙60,且所述预制挡墙60位于相邻所述桩承拉锚挡墙50之间,预制挡墙60根据第二骨架64预制而成,预制挡墙60插入纵向相邻的桩帽20之间,第二骨架64也为钢筋骨架。As shown in Figures 1-8, an assembled structure of a pile bearing tension anchor retaining wall according to an embodiment of the present invention includes a plurality of sets of vertical bearing piles 10, and the top of the vertical bearing piles 10 is provided with a pile cap 20 , a connecting beam is provided between the adjacent pile caps 20, and each group of the pile caps 20 of the outer pile is respectively provided with a pile bearing anchor retaining wall 50, and the pile bearing anchor retaining wall 50 is an assembled pile bearing. Anchor retaining wall, a buttress 51 is provided on one side of the pile-supported anchor retaining wall 50, and a cable 52 is provided on the other side of the pile-supported anchor retaining wall 50, and one end of the cable 52 is connected to the inner side of the pile. The pile caps 20 are connected, and a prefabricated retaining wall 60 is arranged on each group of the coupling beams of the outer piles, and the prefabricated retaining wall 60 is located between the adjacent pile anchor retaining walls 50. The two frames 64 are prefabricated, the prefabricated retaining walls 60 are inserted between the longitudinally adjacent pile caps 20, and the second frame 64 is also a steel frame.

在本发明的一个具体实施例中,所述桩帽20上设有预应力钢筋21,即在纵向的外侧桩桩帽20上伸出竖向预留的预应力钢筋21,所述桩承拉锚挡墙50包括拉锚挡墙立板56,所述拉锚挡墙立板56上设有与所述预应力钢筋21相对应的通孔53,所述预应力钢筋21与所述通孔53相连接;通孔53为钢筋孔,使用时,将在工厂根据第一骨架57预制好的装配式桩承拉锚挡墙50上预留在拉锚挡墙立板56内的钢筋孔对准在纵向外侧桩桩帽20上预留的预应力钢筋21,第一骨架57为钢筋骨架。In a specific embodiment of the present invention, the pile cap 20 is provided with a prestressed steel bar 21, that is, a vertically reserved prestressed steel bar 21 extends from the longitudinal outer pile cap 20. The anchor retaining wall 50 includes a tension anchor retaining wall vertical plate 56, and the tension anchor retaining wall vertical plate 56 is provided with a through hole 53 corresponding to the prestressed steel bar 21, and the prestressed steel bar 21 is connected to the through hole. 53 are connected; the through hole 53 is a steel bar hole, when in use, the steel bar hole reserved in the tension anchor retaining wall vertical plate 56 on the prefabricated pile anchor retaining wall 50 prefabricated in the factory according to the first skeleton 57 will be paired. The prestressed steel bar 21 reserved on the longitudinal outer pile cap 20, the first frame 57 is a steel frame.

在本发明的一个具体实施例中,所述扶壁51设置于所述挡墙拉锚挡墙立板56的外侧,所述拉索52设置于所述挡墙拉锚挡墙立板56的里侧,即将设有扶壁51侧朝外侧,设有拉索52侧朝向里侧,把装配式桩承拉锚挡墙50安设在纵向外侧桩桩帽20上。In a specific embodiment of the present invention, the buttress 51 is disposed on the outer side of the retaining wall anchoring and retaining wall vertical plate 56 , and the stay cable 52 is disposed on the outer side of the retaining wall anchoring retaining wall vertical plate 56 . The inner side, that is, the side with the buttress 51 faces the outer side, and the side with the stay cable 52 faces the inner side.

在本发明的一个具体实施例中,所述拉锚挡墙立板56上设有与所述拉索52相对应的锚固孔55,所述锚固孔55与所述拉索52顶端相连接,即拉索52另一端穿过预留的锚固孔55,对拉索52进行预应力分级张拉,张拉结束后,经过一段时间进行补偿张拉,张拉预应力至可以抵抗路堤填土产生的土压力,并在外侧垫上钢垫片71,同时用锚具72施做在钢垫片71上锚固拉索52,并用混凝土浇筑保护由钢垫片71和锚具72组成的锚头70;对锚固孔55的孔洞进行灌浆处理,保护钢筋不受锈蚀。In a specific embodiment of the present invention, an anchor hole 55 corresponding to the cable 52 is provided on the vertical plate 56 of the anchor retaining wall, and the anchor hole 55 is connected with the top end of the cable 52 . That is, the other end of the cable 52 passes through the reserved anchoring hole 55, and the cable 52 is prestressed and tensioned by grades. At the same time, use the anchor 72 to anchor the cable 52 on the steel gasket 71, and pour concrete to protect the anchor head 70 composed of the steel gasket 71 and the anchor 72; The holes of the anchor holes 55 are grouted to protect the steel bars from corrosion.

在本发明的一个具体实施例中,所述拉锚挡墙立板56左右两侧设有第一榫槽54,所述预制挡墙60左右两侧设有与所述第一榫槽54相对应的第一凸榫61,所述第一榫槽54与所述第一凸榫61相连接,即将第一凸榫61对准第一榫槽54。In a specific embodiment of the present invention, the left and right sides of the anchor retaining wall vertical plate 56 are provided with first tongue grooves 54 , and the left and right sides of the prefabricated retaining wall 60 are provided with the first tongue grooves 54 . Corresponding to the first tenon 61 , the first tenon 54 is connected with the first tenon 61 , that is, the first tenon 61 is aligned with the first tenon 54 .

在本发明的一个具体实施例中,所述连梁包括全断面连梁30和半断面连梁40,其中,纵向外侧相邻每组所述桩帽20之间通过所述全断面连梁30相连接,横向相邻每组所述桩帽20之间通过所述半断面连梁40相连接。In a specific embodiment of the present invention, the coupling beams include full-section coupling beams 30 and half-section coupling beams 40 , wherein the full-section coupling beams 30 pass between each group of the pile caps 20 adjacent to the longitudinal outer side. The half-section connecting beams 40 are connected between each group of the pile caps 20 adjacent to each other in the lateral direction.

在本发明的一个具体实施例中,所述全断面连梁30上设有第二榫槽31,所述预制挡墙60底端设有与所述第二榫槽31相对应的第二凸榫62,所述第二榫槽31与所述第二凸榫62相连接,即第二凸榫62对准第二榫槽31,第二凸榫62安设在全断面连梁30上。In a specific embodiment of the present invention, the full-section connecting beam 30 is provided with a second tongue groove 31 , and the bottom end of the prefabricated retaining wall 60 is provided with a second protrusion corresponding to the second tongue groove 31 . Tenon 62, the second tenon 31 is connected with the second tenon 62, that is, the second tenon 62 is aligned with the second tenon 31, and the second tenon 62 is installed on the full-section connecting beam 30.

在本发明的一个具体实施例中,所述预制挡墙60上设有若干排水孔63。In a specific embodiment of the present invention, the prefabricated retaining wall 60 is provided with a plurality of drainage holes 63 .

为了方便理解本发明的上述技术方案,以下通过具体使用方式上对本发明的上述技术方案进行详细说明。In order to facilitate the understanding of the above-mentioned technical solutions of the present invention, the above-mentioned technical solutions of the present invention will be described in detail below through specific usage modes.

在具体使用时,根据本发明所述的桩承拉锚挡墙装配式结构,将竖向承载桩10、桩帽20和装配式桩承拉锚挡墙50连接形成整体,更好得约束路堤的横向变形,首先施做竖向承载桩10和桩帽20,桩帽20施做在竖向承载桩10中心位置上方,将纵向相邻的外侧桩桩帽20用全断面连梁30连接形成整体,横向相邻的桩帽20用半断面连梁40连接,加强桩承拉锚挡墙50和预制挡墙60的支护效果;将设有扶壁51侧朝外侧,设有拉索52侧朝向里侧,把装配式桩承拉锚挡墙50安设在纵向外侧桩桩帽20上。拉索52的一端和里侧桩的桩帽20进行连接,另一端拉索穿过预留的锚固孔55,对拉索进行预应力分级张拉,张拉结束后,经过一段时间进行补偿张拉,张拉预应力至可以抵抗路堤填土产生的土压力,并在外侧垫上钢垫片71,同时用锚具72施做在钢垫片71上锚固拉索,并用混凝土浇筑保护由钢垫片和锚具组成的锚头70。In specific use, according to the assembled structure of the pile-supported anchor retaining wall of the present invention, the vertical bearing pile 10, the pile cap 20 and the assembled pile-supported anchor retaining wall 50 are connected to form a whole, so as to better restrain the embankment First, the vertical bearing pile 10 and the pile cap 20 are applied, the pile cap 20 is applied above the center of the vertical bearing pile 10, and the longitudinally adjacent outer pile caps 20 are connected with the full-section connecting beams 30 to form As a whole, the horizontally adjacent pile caps 20 are connected by half-section connecting beams 40 to strengthen the support effect of the pile-supported anchor retaining wall 50 and the prefabricated retaining wall 60; With the side facing inward, the prefabricated pile anchor retaining wall 50 is installed on the longitudinal outer pile cap 20 . One end of the cable 52 is connected to the pile cap 20 of the inner pile, and the other end of the cable passes through the reserved anchoring hole 55, and the cable is prestressed and tensioned in stages. Pull and tension the prestressed force to resist the earth pressure generated by the embankment filling, and pad the steel gasket 71 on the outside, and at the same time use the anchor 72 to anchor the cable on the steel gasket 71, and pour concrete to protect the steel gasket. Anchor head 70 composed of sheet and anchor.

综上所述,借助于本发明的上述技术方案,采用在工厂标准化预制,有效的缩短了建设的周期,外形整齐、简洁,更加美观,同时取得了更好的支护效果,即采用工厂化标准预制和现场安装施工,缩短了建设工期,预制施工质量易于控制,且墙身轻小和占地较少,地基承载力要求较低,地基条件较差和石料缺乏地区均可采用,特别适用于大中型城市道路及桥梁引道工期要求紧张、周围有建筑物限制、交通压力大和地基承载力较差等路堤挡土墙施工。To sum up, with the help of the above technical solutions of the present invention, standardized prefabrication in the factory is adopted, which effectively shortens the construction period, the appearance is neat, concise, and more beautiful, and at the same time, a better supporting effect is achieved, that is, the factory-based method is adopted. Standard prefabrication and on-site installation and construction shorten the construction period, the quality of prefabrication construction is easy to control, and the wall is light and small and occupies less land. In large and medium-sized urban roads and bridge approaches, the construction period is tight, there are building restrictions around, the traffic pressure is high, and the foundation bearing capacity is poor.

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the scope of the present invention. within the scope of protection.

Claims (8)

1. a kind of pile draws anchor barricade fabricated construction, including the vertical bearing pile of multiple groups (10), vertical bearing pile (10) top Portion is equipped with pile cover (20), and coupling beam is equipped between the adjacent pile cover (20), which is characterized in that pile cover described in every group of outside stake (20) it is respectively equipped with pile on and draws anchor barricade (50), the pile draws anchor barricade (50) side to be equipped with counterfort (51), the pile Anchor barricade (50) other side is drawn to be equipped with drag-line (52), and the drag-line (52) is connected with the pile cover (20) of inboard stake, outside Coupling beam described in every group of side stake is equipped with prefabricated barricade (60).
2. pile according to claim 1 draws anchor barricade fabricated construction, which is characterized in that the pile cover (20) is equipped with Deformed bar (21), it includes drawing anchor barricade vertical plate (56) that the pile, which draws anchor barricade (50), the drawing anchor barricade vertical plate (56) It is equipped with through-hole (53) corresponding with the deformed bar (21), the deformed bar (21) and the through-hole (53) phase Connection.
3. pile according to claim 2 draws anchor barricade fabricated construction, which is characterized in that the counterfort (51) is set to The barricade draws the outside of anchor barricade vertical plate (56), and the drag-line (52) is set to the barricade and draws anchor barricade vertical plate (56) inner Side.
4. pile according to claim 2 draws anchor barricade fabricated construction, which is characterized in that the drawing anchor barricade vertical plate (56) anchor hole (55) corresponding with the drag-line (52), the anchor hole (55) and the drag-line (52) top phase are equipped with Connection.
5. pile according to claim 2 draws anchor barricade fabricated construction, which is characterized in that the drawing anchor barricade vertical plate (56) left and right sides is equipped with the first tongue-and-groove (54), is equipped with and the first tongue-and-groove (54) phase at left and right sides of the prefabricated barricade (60) Corresponding first tenon (61), first tongue-and-groove (54) are connected with first tenon (61).
6. pile according to claim 1 draws anchor barricade fabricated construction, which is characterized in that the coupling beam includes tunneling boring Coupling beam (30) and half section coupling beam (40), wherein pass through the tunneling boring between pile cover (20) described in longitudinally outboard is every group adjacent Coupling beam (30) is connected, and is connected between pile cover (20) described in laterally adjacent every group by the half section coupling beam (40).
7. pile according to claim 6 draws anchor barricade fabricated construction, which is characterized in that the tunneling boring coupling beam (30) It is equipped with the second tongue-and-groove (31), prefabricated barricade (60) bottom end is equipped with the second tenon corresponding with the second tongue-and-groove (31) (62), second tongue-and-groove (31) is connected with second tenon (62).
8. pile according to claim 1-7 draws anchor barricade fabricated construction, which is characterized in that the prefabricated gear Wall (60) is equipped with several drainage holes (63).
CN201910302882.XA 2019-04-16 2019-04-16 An assembled structure of pile bearing anchor retaining wall Pending CN110029685A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910302882.XA CN110029685A (en) 2019-04-16 2019-04-16 An assembled structure of pile bearing anchor retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910302882.XA CN110029685A (en) 2019-04-16 2019-04-16 An assembled structure of pile bearing anchor retaining wall

Publications (1)

Publication Number Publication Date
CN110029685A true CN110029685A (en) 2019-07-19

Family

ID=67238533

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910302882.XA Pending CN110029685A (en) 2019-04-16 2019-04-16 An assembled structure of pile bearing anchor retaining wall

Country Status (1)

Country Link
CN (1) CN110029685A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110344833A (en) * 2019-08-16 2019-10-18 招商局重庆交通科研设计院有限公司 Tunnel excavation support structure and method for tunnel construction
CN111794268A (en) * 2020-06-01 2020-10-20 中铁大桥科学研究院有限公司 A composite retaining wall and its construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205116217U (en) * 2015-10-30 2016-03-30 正平路桥建设股份有限公司 Height is filled and is prefabricated cast -in -place combination formula stake siding wall protective structure
CN106702840A (en) * 2017-02-10 2017-05-24 湖南大学 Embankment of Anchor-pull Pile Bearing Reinforced Soil Retaining Wall Treating Soft Soil Subgrade on the Bank
CN107130613A (en) * 2017-05-19 2017-09-05 重庆大学 Large span tunnel is just wearing the retaining structure and its construction method of existing barricade
CN108277814A (en) * 2018-04-11 2018-07-13 王凯 Stake top counterfort wall supporting construction and construction method
CN108560348A (en) * 2018-06-05 2018-09-21 武汉理工大学 Pile formula barricade embankment
CN210597363U (en) * 2019-04-16 2020-05-22 中铁建设集团有限公司 Pile bearing anchor retaining wall assembly type structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205116217U (en) * 2015-10-30 2016-03-30 正平路桥建设股份有限公司 Height is filled and is prefabricated cast -in -place combination formula stake siding wall protective structure
CN106702840A (en) * 2017-02-10 2017-05-24 湖南大学 Embankment of Anchor-pull Pile Bearing Reinforced Soil Retaining Wall Treating Soft Soil Subgrade on the Bank
CN107130613A (en) * 2017-05-19 2017-09-05 重庆大学 Large span tunnel is just wearing the retaining structure and its construction method of existing barricade
CN108277814A (en) * 2018-04-11 2018-07-13 王凯 Stake top counterfort wall supporting construction and construction method
CN108560348A (en) * 2018-06-05 2018-09-21 武汉理工大学 Pile formula barricade embankment
CN210597363U (en) * 2019-04-16 2020-05-22 中铁建设集团有限公司 Pile bearing anchor retaining wall assembly type structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110344833A (en) * 2019-08-16 2019-10-18 招商局重庆交通科研设计院有限公司 Tunnel excavation support structure and method for tunnel construction
CN111794268A (en) * 2020-06-01 2020-10-20 中铁大桥科学研究院有限公司 A composite retaining wall and its construction method

Similar Documents

Publication Publication Date Title
CN201121340Y (en) Prestressed prefabricated underground diaphragm wall and its prefabricated blocks
CN107905251A (en) A kind of module prestressing force Retaining Wall and its assembly method
CN213978405U (en) U-shaped groove structure of cast-in-situ bottom plate of underpass road
CN108396778A (en) A kind of construction method in precast assembly tunnel
CN113585293A (en) Ecological environmental protection pin-connected panel municipal administration side slope reinforced structure
KR100906161B1 (en) Corrugated Steel Sheet Structure Using Wire Rope
KR100758504B1 (en) Underground continuous wall construction method and serrated plywood underground continuous wall structure
CN114351757A (en) Assembled miniature pile foundation joist anchor cable retaining wall and construction method thereof
CN110029685A (en) An assembled structure of pile bearing anchor retaining wall
CN111622383B (en) A self-resetting concrete frame structure steel plate energy-consuming filling wall and its assembling method
CN211113674U (en) Double-row column supporting structure of foundation pit
KR100510092B1 (en) A one-piece type arch-shaped structure with the precast concrete pannel and the steel frame under the earth, and method for manufacturing it
CN211312485U (en) Profile steel connection type prefabricated underground continuous wall
CN210597363U (en) Pile bearing anchor retaining wall assembly type structure
CN108867664B (en) Road-to-bridge Duan Jikeng supporting structure based on reverse construction method and construction method thereof
CN116716787B (en) A prefabricated bridge spanning a deep, water-filled karst cave and its construction method
CN119373533A (en) A tunnel support system for tunnels with mined-out areas or covered minerals
CN112302033A (en) Pile anchor type cover plate foundation pit support structure and construction method thereof
CN118933166A (en) A frame type concrete module and a building containing the same and a construction method thereof
CN216766429U (en) Full precast concrete board beam node
CN217206469U (en) Large-section rectangular pipe jacking block pipe joint
CN216809984U (en) Assembled miniature pile foundation joist anchor cable retaining wall
CN205894061U (en) Underground structure interior lining wall and underground continuous wall coincide face structure
CN215562640U (en) Prefabricated assembled retaining wall structure in foundation ditch top
CN114369994B (en) Fully-prefabricated small box girder type invisible bent cap structure system and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190719