CN110344833A - Tunnel excavation support structure and method for tunnel construction - Google Patents

Tunnel excavation support structure and method for tunnel construction Download PDF

Info

Publication number
CN110344833A
CN110344833A CN201910759371.0A CN201910759371A CN110344833A CN 110344833 A CN110344833 A CN 110344833A CN 201910759371 A CN201910759371 A CN 201910759371A CN 110344833 A CN110344833 A CN 110344833A
Authority
CN
China
Prior art keywords
tunnel
friction pile
stake
support
support stake
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910759371.0A
Other languages
Chinese (zh)
Inventor
吴胜忠
李科
肖博
皮小强
方林
丁浩
胡学兵
廖峻
王建华
江星宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Merchants Chongqing Communications Research and Design Institute Co Ltd
Original Assignee
China Merchants Chongqing Communications Research and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Merchants Chongqing Communications Research and Design Institute Co Ltd filed Critical China Merchants Chongqing Communications Research and Design Institute Co Ltd
Priority to CN201910759371.0A priority Critical patent/CN110344833A/en
Publication of CN110344833A publication Critical patent/CN110344833A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The invention discloses a kind of tunnel excavation support structure and method for tunnel construction, which arranges row's friction pile the following steps are included: being close to existing barricade at tunnel, and is respectively arranged wall and tunnel two sides in tunnel;Stake is being supported away from arrangement at friction pile pre-determined distance, and is making to support stake top lower than road surface elevation, support stake is correspondingly arranged with friction pile;Arrange ground beam, in length and breadth at road surface elevation to connect two neighboring friction pile and adjacent friction pile and support stake;Diagonal brace is applied between support stake and friction pile, friction pile and support stake is made to bear soil pressure jointly;Tunnel middle drift excavation is carried out from inside to outside and applies middle wall;Ecto-entad, left and right hole successively carry out main hole tunnel excavation.Above-mentioned tunnel excavation support structure and method for tunnel construction, excavate and do not destroy existing barricade, uninterrupted traffic into hole, it can be ensured that construction safety and later period operation security, from inside to outside, main hole ecto-entad excavates middle drift, can reduce friction pile soil pressure.

Description

Tunnel excavation support structure and method for tunnel construction
Technical field
The present invention relates to technical field of tunnel construction, and in particular to a kind of tunnel excavation support structure and constructing tunnel side Method.
Background technique
With a large amount of constructions of highway and railway tunnel, tunnel is all over the place, no longer only passes through the mountain ridge in waste Yezhong, Also occurs a large amount of Tunnel Engineering in urban construction.These Tunnel Engineering near hole inevitably with city road Road, barricade, building etc. are existing to have buildings or structures mutually to influence.
By the environmental influence of the special sensitivity in city, Tunnel Engineering takes slope into the side in hole near inlet and outlet cave Formula, effect on environment is serious, destroys existing ecology, destroys original geology and geomorphology and Rock And Soil stress balance, influences traffic above-ground, Destroy existing buildings or structures.Tunnel Engineering in urban construction is even more unavoidable when excavating into hole to remove existing set It applies or Existing reinforced concrete bridge, existing historic reservation, existing road or bridge foundation etc..
Summary of the invention
Based on this, it is necessary to for the problem that traditional method for tunnel construction influences traffic above-ground, existing building is destroyed, A kind of tunnel excavation support structure and method for tunnel construction are provided.
A kind of tunnel excavation support structure, comprising:
Friction pile is close to existing barricade and arranges a row, and wall and tunnel two sides are correspondingly provided with the friction pile in tunnel;
Stake is supported, with the friction pile arranged for interval, the support stake is correspondingly arranged with the friction pile, and the support The top of stake is lower than road surface elevation;
Ground beam is arranged in length and breadth at road surface elevation, to connect the two neighboring friction pile and the adjacent friction pile With the support stake;And
Diagonal brace is connected between the friction pile and the corresponding support stake.
It in one of the embodiments, further include crown beam, the crown beam is set to the top of friction pile described in a row.
It in one of the embodiments, further include crossbeam, the crossbeam is set to the top of tunnel excavation contour line, described Crossbeam is connected with the friction pile.
Rib column is equipped between the crown beam and the crossbeam in one of the embodiments,.
It in one of the embodiments, further include anchor pole, the anchor pole is set to the top of the friction pile and anchors into In the soil body, and the friction pile of tunnel two sides is equipped at intervals with multiple anchor poles.
A kind of method for tunnel construction utilizes tunnel excavation support structure described in above-mentioned any one, which is characterized in that packet Include following steps:
It is close to existing barricade at tunnel and arranges row's friction pile, and is respectively arranged wall and tunnel two in tunnel Side;
Stake is being supported away from arrangement at the friction pile pre-determined distance, and is making to support stake top lower than road surface elevation, the support Stake is correspondingly arranged with the friction pile;
Arrange ground beam in length and breadth at road surface elevation, with connect the two neighboring friction pile and the adjacent friction pile and The support stake;
Diagonal brace is applied between the support stake and the friction pile, the friction pile and the support stake is made to bear soil jointly Pressure;
Tunnel middle drift excavation is carried out from inside to outside and applies middle wall;
Ecto-entad, left and right hole successively carry out main hole tunnel excavation.
It is close to existing barricade at tunnel in one of the embodiments, and arranges row's friction pile, and is respectively arranged In tunnel wall and the step of tunnel two sides after further include:
Apply anchor pole in the antiskid stake top of middle wall, mid-board is anchored into, in close proximity to the friction pile edge of tunnel two sides Stake top is spaced downwards the multiple anchor poles of setting, anchors into the soil body respectively.
Stake is being supported away from arrangement at the friction pile pre-determined distance in one of the embodiments, and is making to support stake top low In road surface elevation, after the step of each friction pile is correspondingly provided with the support stake further include:
Crown beam is arranged between the friction pile, the crossbeam between cloth friction pile at the top of tunnel excavation contour line, in the hat Rib column is arranged between beam and the crossbeam.
Above-mentioned tunnel excavation support structure and method for tunnel construction, by the way that the double support pattern of diagonal brace, structural body is arranged Rationally, load assignment is clear, and Path of Force Transfer is clear for system, securely and reliably, excavates and does not destroy existing barricade into hole, uninterrupted traffic, It can ensure construction safety and later period operation security.Tunnel excavation is carried out after first supporting, from inside to outside, main hole is by extroversion for middle drift It inside successively advances wide open digging, friction pile soil pressure when abolishing existing barricade in tunnel contour can be reduced.
Detailed description of the invention
Fig. 1 is the front view of tunnel excavation support structure in an embodiment;
Fig. 2 is the longitudinal section view of tunnel excavation support structure shown in Fig. 1;
Fig. 3 is the flow chart of method for tunnel construction in an embodiment.
Specific embodiment
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing to the present invention Specific embodiment be described in detail.Many details are explained in the following description in order to fully understand this hair It is bright.But the invention can be embodied in many other ways as described herein, those skilled in the art can be not Similar improvement is done in the case where violating intension of the present invention, because the invention is not limited by following public specific implementation.
It should be noted that it can directly on the other element when element is referred to as " being fixed on " another element Or there may also be elements placed in the middle.When an element is considered as " connection " another element, it, which can be, is directly connected to To another element or it may be simultaneously present centering elements.Term as used herein " vertical ", " horizontal ", " left side ", " right side " and similar statement for illustrative purposes only, are not meant to be the only embodiment.
Unless otherwise defined, all technical and scientific terms used herein and belong to technical field of the invention The normally understood meaning of technical staff is identical.Term as used herein in the specification of the present invention is intended merely to description tool The purpose of the embodiment of body, it is not intended that in the limitation present invention.
Fig. 1 and Fig. 2 is please referred to, the tunnel excavation support structure in an embodiment is used for the existing barricade of supporting, avoids tunnel Road destroys existing building when excavating.Specifically, which includes friction pile 100, support stake 200, ground beam 300 and diagonal brace 400.
Friction pile 100 is close to existing barricade and arranges a row, and wall and tunnel two sides are correspondingly provided with friction pile in tunnel 100.Specifically, it is arranged one in tunnel at wall and is used as stress king pile, the two sides in tunnel is respectively arranged a friction pile 100, should The wall 13m in tunnel of friction pile 100.Further, each at the 100 outside 5m of friction pile of two sides in the same plane to arrange one Outside soil pressure is kept out in root friction pile 100, assistance.In present embodiment, the sectional dimension of friction pile 100 is 2m × 3m, is resisted Sliding pile 100 is 38m long, wherein aerial part 19m, under ground portion 19m.
Stake 200 and 100 arranged for interval of friction pile are supported, support stake 200 is correspondingly arranged with friction pile 100, and supports stake 200 Top be lower than road surface elevation.Specifically, the spacing of support stake 200 and friction pile 100 is 13.1m.Support stake 200 quantity be 3, in the corresponding arrangement one of the same axis of friction pile 100 of Zhong Qiangchu, the corresponding same axis of the friction pile 100 of hole two sides is each Arrangement one.The sectional dimension for supporting stake 200 is 2m × 3m, and supporting the length of the under ground portion of stake 200 is 15m.
Ground beam 300 is arranged in length and breadth at road surface elevation, and ground beam 300 connects two neighboring friction pile 100, connects adjacent Friction pile 100 and support stake 200, make whole stress.It is that it is anti-that lateral ground beam 300 connects adjacent two Sliding pile 100, longitudinal ground beam 300 connect friction pile 100 and support column.Specifically, the sectional dimension of ground beam 300 be 3m × 1.5m。
Diagonal brace 400 is connected between friction pile 100 and corresponding support stake 200, makes to support stake 200 and friction pile 100 total With receiving soil pressure.Specifically, the angle of diagonal brace 400 and horizontal plane is 45 °, and the sectional dimension of diagonal brace 400 is 2m × 2m.
In order to improve the bearing capacity of friction pile 100, tunnel excavation support structure further includes anchor pole 500, and anchor pole 500 is arranged In friction pile 100 top and anchor into the soil body, the friction pile 100 of tunnel two sides is equipped at intervals with multiple anchor poles 500.Specifically Ground applies anchor pole 500 being located at the top of the friction pile 100 that middle wall goes out, anchors into mid-board 9m.In close proximity to portal two sides friction pile 100 tops apply anchor pole 500, to guarantee that diagonal brace 400 applies space, apply second row anchor at the downward 9m of roll bolt 500 Bar 500 anchors into middle weathered rock formation 9m respectively.At the top of outermost friction pile 100 apply anchor pole 500, apart from roll bolt 500 to Apply totally 3 row's anchor pole 500 at lower 4m, 9m, 13m, anchors into middle weathered rock formation 9m respectively.
In present embodiment, tunnel excavation support structure further includes crown beam 600, and crown beam 600 is set to row's friction pile 100 Top.Specifically, the sectional dimension of crown beam 600 is 3m × 1.5m, and crown beam 600 is sequentially connected five friction piles 100.In close proximity to Tunnel excavation contour line top position is equipped with crossbeam 700, and crossbeam 700 is located at the lower section of crown beam 600, crossbeam 700 and friction pile 100 It is connected.Specifically, sectional dimension 3m × 1.5m of crossbeam 700.Rib column 800, rib column are equipped between crown beam 600 and crossbeam 700 800 sectional dimension is 1m × 0.6m, and the spacing between two neighboring rib column 800 is 2.2m.
Referring to Fig. 3, the present invention also provides a kind of method for tunnel construction.To realize the method for tunnel construction, use State tunnel excavation support structure.The method for tunnel construction specifically comprises the following steps:
Step S110: it is close to existing barricade at tunnel and arranges row's friction pile 100, and be respectively arranged in tunnel Wall and tunnel two sides.
Specifically, row's friction pile 100 is arranged against barricade in tunnel position, a stress is set at wall in tunnel King pile, sectional dimension 2m × 3m, king pile are total to long 38m, aerial part 19m, under ground portion 19m.Each arrangement 1 of tunnel two sides difference Friction pile 100, wall king pile 13m, sectional dimension 2m × 3m, stake long 33m, aerial part 19m, under ground portion 14m in.Into one Step ground, outside soil body pressure is kept out in a piece friction pile 100 of each arrangement at 100 outside 5m of two sides friction pile, assistance in the same plane Power, sectional dimension 2m × 3m, stake long 33m, aerial part 19m, under ground portion 14m.It, can be anti-when pouring friction pile 100 Casting concrete between sliding pile 100 and barricade, concrete can pour simultaneously with friction pile 100.
In present embodiment, after tunnel goes out and arranges friction pile 100, pushed up being located at the friction pile 100 that middle wall goes out Portion applies anchor pole 500, anchors into mid-board 9m.Apply anchor pole 500, at the top of portal two sides friction pile 100 to guarantee diagonal brace 400 perform space, apply second row anchor pole 500 at the downward 9m of roll bolt 500, anchor into middle weathered rock formation 9m respectively.? Apply anchor pole 500 at the top of outermost friction pile 100, applies totally 3 row's anchor pole at roll bolt 500 downward 4m, 9m, 13m 500, middle weathered rock formation 9m is anchored into respectively.
Step S120: stake 200 is being supported away from arrangement at 100 pre-determined distance of friction pile, and is making to support the top of stake 200 lower than road surface Elevation, support stake 200 are correspondingly arranged with friction pile 100.
Specifically, support stake 200 is 13.1m at a distance from friction pile 100, and the top of support stake 200 is below road surface elevation. Supporting the part stake of the insertion of stake 200 underground long is 15m.The quantity for supporting stake 200 is three, the corresponding friction pile 100 of middle wall A support stake 200 is arranged at same axis, respectively arranges one at the corresponding same axis of friction pile 100 of hole two sides. Certainly, the spacing between stake 200 and friction pile 100 is supported, can specifically be adjusted according to tunnel spacing and span.
Top layout crown beam 600 in present embodiment, after arrangement supports stake 200, on antiskid top.Specifically, it is preced with The sectional dimension of beam 600 is 3m × 1.5m, and crown beam 600 is sequentially connected five friction piles 100.In close proximity to tunnel excavation contour line top Position has installed crossbeam 700, and crossbeam 700 is connected with friction pile 100, and crossbeam 700 is located at the lower section of crown beam 600, crossbeam 700 with Crown beam 600 is parallel.Further, rib column 800 is equipped between crown beam 600 and crossbeam 700, the sectional dimension of rib column 800 is 1m × 0.6m, the spacing between two neighboring rib column 800 are 2.2m.
Step S130: arranging ground beam 300 in length and breadth at road surface elevation, to connect two neighboring friction pile 100 and adjacent Friction pile 100 and support stake 200.
Specifically, ground beam 300 is arranged in length and breadth at design road surface elevation, connect lateral ground beam 300 two neighboring anti- Sliding pile 100, longitudinal ground beam 300 connect friction pile 100 and support stake 200.
Step S140: diagonal brace 400 is applied between the support stake 200 and the friction pile 100, makes the friction pile 100 Soil pressure is born jointly with the support stake 200.
Specifically, apply 3 diagonal braces 400, the section of diagonal brace 400 between 3 supports stake 200 and corresponding friction piles 100 Having a size of 2m × 2m, the angle of diagonal brace 400 and horizontal plane is 45 °.
Step S150: tunnel middle drift excavation is carried out from inside to outside and applies middle wall.
Step S160: ecto-entad, left and right hole successively carry out main hole tunnel excavation.
Above-mentioned tunnel excavation support structure and method for tunnel construction, by the way that the double support pattern of diagonal brace 400, structure is arranged System is reasonable, and load assignment is clear, and Path of Force Transfer is clear, securely and reliably, excavates and does not destroy existing barricade into hole, not in break off a friendship It is logical, it can be ensured that construction safety and later period operation security.Carry out tunnel excavation after first supporting, middle drift from inside to outside, main hole by It successively advances outside to inside wide open digging, 100 soil pressure of friction pile when abolishing existing barricade in tunnel contour can be reduced.
Each technical characteristic of embodiment described above can be combined arbitrarily, for simplicity of description, not to above-mentioned reality It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, all should be considered as described in this specification.
The embodiments described above only express several embodiments of the present invention, and the description thereof is more specific and detailed, but simultaneously It cannot therefore be construed as limiting the scope of the patent.It should be pointed out that coming for those of ordinary skill in the art It says, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to protection of the invention Range.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.

Claims (8)

1. a kind of tunnel excavation support structure characterized by comprising
Friction pile is close to existing barricade and arranges a row, and wall and tunnel two sides are correspondingly provided with the friction pile in tunnel;
Stake is supported, with the friction pile arranged for interval, the support stake is correspondingly arranged with the friction pile, and the support stake Top is lower than road surface elevation;
Ground beam is arranged in length and breadth at road surface elevation, to connect the two neighboring friction pile and the adjacent friction pile and institute State support stake;And
Diagonal brace is connected between the friction pile and the corresponding support stake.
2. tunnel excavation support structure according to claim 1, which is characterized in that it further include crown beam, the crown beam setting The top of the friction pile described in a row.
3. tunnel excavation support structure according to claim 2, which is characterized in that it further include crossbeam, the crossbeam setting In the top of tunnel excavation contour line, the crossbeam is connected with the friction pile.
4. tunnel excavation support structure according to claim 3, which is characterized in that set between the crown beam and the crossbeam There is rib column.
5. tunnel excavation support structure according to claim 1, which is characterized in that it further include anchor pole, the anchor pole setting In the friction pile top and anchor into the soil body, and the friction pile of tunnel two sides is equipped at intervals with multiple anchor poles.
6. a kind of method for tunnel construction utilizes the tunnel excavation support structure as described in claim 1-5 any one, feature It is, comprising the following steps:
It is close to existing barricade at tunnel and arranges row's friction pile, and is respectively arranged wall and tunnel two sides in tunnel;
Away from arrangement support stake at the friction pile pre-determined distance, and make to support stake top lower than road surface elevation, the support stake and The friction pile is correspondingly arranged;
Arrange ground beam, in length and breadth at road surface elevation to connect the two neighboring friction pile and the adjacent friction pile and described Support stake;
Diagonal brace is applied between the support stake and the friction pile, the friction pile and the support stake is made to bear soil pressure jointly Power;
Tunnel middle drift excavation is carried out from inside to outside and applies middle wall;
Ecto-entad, left and right hole successively carry out main hole tunnel excavation.
7. method for tunnel construction according to claim 6, which is characterized in that be close to existing barricade arrangement at tunnel One row's friction pile, and after the step of being respectively arranged wall and tunnel two sides in tunnel further include:
Apply anchor pole in the antiskid stake top of middle wall, anchors into mid-board, the friction pile in close proximity to tunnel two sides is along stake top Multiple anchor poles are arranged in interval downwards, anchor into the soil body respectively.
8. method for tunnel construction according to claim 6, which is characterized in that away from arrangement at the friction pile pre-determined distance Stake is supported, and makes to support stake top lower than road surface elevation, is gone back after the step of each friction pile is correspondingly provided with the support stake Include:
Arrange crown beam between the friction pile, the crossbeam between cloth friction pile at the top of tunnel excavation contour line, in the crown beam and Rib column is arranged between the crossbeam.
CN201910759371.0A 2019-08-16 2019-08-16 Tunnel excavation support structure and method for tunnel construction Pending CN110344833A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910759371.0A CN110344833A (en) 2019-08-16 2019-08-16 Tunnel excavation support structure and method for tunnel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910759371.0A CN110344833A (en) 2019-08-16 2019-08-16 Tunnel excavation support structure and method for tunnel construction

Publications (1)

Publication Number Publication Date
CN110344833A true CN110344833A (en) 2019-10-18

Family

ID=68185314

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910759371.0A Pending CN110344833A (en) 2019-08-16 2019-08-16 Tunnel excavation support structure and method for tunnel construction

Country Status (1)

Country Link
CN (1) CN110344833A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11350896A (en) * 1998-06-10 1999-12-21 Kajima Corp Construction method for underground structure
CN202416333U (en) * 2012-02-03 2012-09-05 招商局重庆交通科研设计院有限公司 Anti-sliding support device for h-shaped piling wall combination
CN107130613A (en) * 2017-05-19 2017-09-05 重庆大学 Large span tunnel is just wearing the retaining structure and its construction method of existing barricade
CN107419731A (en) * 2017-08-04 2017-12-01 广州市市政工程设计研究总院 A kind of board-like double-row pile foundation pit support structure of counterfort and its construction method
CN108119149A (en) * 2018-01-02 2018-06-05 兰州理工大学 The tunnel support structure and construction method of existing building are worn under a kind of
CN109989767A (en) * 2019-01-17 2019-07-09 中铁二院贵阳勘察设计研究院有限责任公司 The ruggedized construction and construction method of existing railway are worn under Large span tunnel
CN110029685A (en) * 2019-04-16 2019-07-19 中铁建设集团有限公司 A kind of pile drawing anchor barricade fabricated construction
CN210264696U (en) * 2019-08-16 2020-04-07 招商局重庆交通科研设计院有限公司 Tunnel excavation supporting construction

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11350896A (en) * 1998-06-10 1999-12-21 Kajima Corp Construction method for underground structure
CN202416333U (en) * 2012-02-03 2012-09-05 招商局重庆交通科研设计院有限公司 Anti-sliding support device for h-shaped piling wall combination
CN107130613A (en) * 2017-05-19 2017-09-05 重庆大学 Large span tunnel is just wearing the retaining structure and its construction method of existing barricade
CN107419731A (en) * 2017-08-04 2017-12-01 广州市市政工程设计研究总院 A kind of board-like double-row pile foundation pit support structure of counterfort and its construction method
CN108119149A (en) * 2018-01-02 2018-06-05 兰州理工大学 The tunnel support structure and construction method of existing building are worn under a kind of
CN109989767A (en) * 2019-01-17 2019-07-09 中铁二院贵阳勘察设计研究院有限责任公司 The ruggedized construction and construction method of existing railway are worn under Large span tunnel
CN110029685A (en) * 2019-04-16 2019-07-19 中铁建设集团有限公司 A kind of pile drawing anchor barricade fabricated construction
CN210264696U (en) * 2019-08-16 2020-04-07 招商局重庆交通科研设计院有限公司 Tunnel excavation supporting construction

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
吴梦军;肖博;吴胜忠;: "敏感复杂区域城市隧道进洞技术研究", 公路交通技术, no. 06, pages 97 - 103 *
肖博;吴胜忠;廖峻;: "隧道穿越既有支挡结构设计方案优化研究", 地下空间与工程学报, no. 1, pages 197 - 203 *
谭江南: "重庆市曾家岩嘉陵江大桥隧道工程南侧主线出口钻孔桩工程施工质量控制要点", 四川水泥, no. 4, 15 April 2018 (2018-04-15), pages 263 *
黄伦海;肖博;吴梦军;: "主城区复杂环境道路隧道重难点建造解决方案", 公路交通技术, no. 1, 30 September 2018 (2018-09-30), pages 89 - 101 *
黄伦海;肖博;吴梦军;: "主城区复杂环境道路隧道重难点建造解决方案", 公路交通技术, no. 1, pages 93 - 101 *

Similar Documents

Publication Publication Date Title
KR101834847B1 (en) Echo-environmental construction method of tunnel portal area using mini pipe-roof
CN102748040B (en) Main structure for metro long-span station and pillar arching construction method thereof
CN202707075U (en) Long-span subway station main structure constructed based on column and arch method
CN105041349A (en) Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel
CN108425678B (en) Construction method of large-section subway crossover tunnel
CN105370289B (en) A kind of existing pipeline overlength Dryopteris sublaetaChing et Hsu method of complex environment
CN107130613A (en) Large span tunnel is just wearing the retaining structure and its construction method of existing barricade
CN104453948B (en) A kind of construction technology of big cross section bored tunnel vertical prestressing steel pipe support
CN109057817A (en) Suitable for folding the c-type service channel structure and construction method that fall Subway Tunnel up and down
CN101838957B (en) Integral type T-shaped outer cantilever roads and construction method thereof
CN112878193A (en) Suspension bridge channel type anchorage foundation and construction method
CN105431593A (en) Strut connection structure for constructing temporary earth retaining structure
CN109610481A (en) A kind of supporting improvement construction method for tunnel portal concordant strong-weathered rock matter high gradient slope
CN206888990U (en) A kind of Shallow Covered Metro Station separates open type structure
KR20120037212A (en) Excavation tunnel constructing method using vertical side wall and arch celling, and excavation tunnel using vertical side wall and arch celling constructed by this
CN204780938U (en) Novel recoverable anchor formula double row pile supporting construction that draws
CN211200459U (en) Piping lane normal position protection architecture
CN209780907U (en) Opening section structure of bias-pressure terrain combined tunnel
CN107190630A (en) Road changes the new cap excavation method of stealthy bridge type
CN111608196A (en) Tunnel type pile foundation bearing platform combined anchorage structure and installation method thereof
CN110344833A (en) Tunnel excavation support structure and method for tunnel construction
CN210264696U (en) Tunnel excavation supporting construction
CN113931169B (en) Bias multi-arch tunnel portal soft foundation zone combined structure and construction method
CN213775385U (en) Isolation and reinforcement structure for water-rich sand layer shield tunnel to pass through viaduct
CN104746530A (en) Novel construction method for closing traffic in short time

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination