CN103469814A - Novel barricade supporting structure for road or river bank dam and construction method thereof - Google Patents

Novel barricade supporting structure for road or river bank dam and construction method thereof Download PDF

Info

Publication number
CN103469814A
CN103469814A CN201310435804XA CN201310435804A CN103469814A CN 103469814 A CN103469814 A CN 103469814A CN 201310435804X A CN201310435804X A CN 201310435804XA CN 201310435804 A CN201310435804 A CN 201310435804A CN 103469814 A CN103469814 A CN 103469814A
Authority
CN
China
Prior art keywords
anchor
wall
counterfort
prestressed anchor
bank protection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310435804XA
Other languages
Chinese (zh)
Inventor
朱彦鹏
吴意谦
周勇
叶帅华
任永忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lanzhou University of Technology
Original Assignee
Lanzhou University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lanzhou University of Technology filed Critical Lanzhou University of Technology
Priority to CN201310435804XA priority Critical patent/CN103469814A/en
Publication of CN103469814A publication Critical patent/CN103469814A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The invention relates to a novel barricade supporting structure for a road or river bank dam and a construction method thereof. A pre-stressed anchor (1) passes through a shingle (2) and a buttress (3) and is embedded in a reinforced soil mass (4); a cement mortar (6) is injected around an anchoring section (5) of the pre-stressed anchor (1); an end part of the pre-stressed anchor (1) is anchored on the shingle (2) by an anchor head (10); and expansion joints (11) and draining openings (12) are arranged in sections. The construction method comprises the following construction steps: constructing a base pile (13); pouring a wall base plate (14) and a reinforced concrete river bank dam (15); constructing the pre-stressed anchor (1); constructing the shingle (2) and the buttress (3) thereof; reserving the expansion joints (11) and draining openings (12) in sections; compacting wall-behind filling (16); applying a pre-stressing force by the pre-stressed anchor (1); fixedly locking the anchor head (10) fixedly connected with the pre-stressed anchor (1) by an anchoring tool (17); and constructing a next working surface according to the steps.

Description

Highway riverbank bank protection new type of retaining supporting and protection structure and job practices thereof
Technical field
The present invention relates to the support technology of side slope.
Background technology
The support technology of ,Dui highway riverbank bank protection adopted gravity (weight formula) barricade more in the past.The way of Gravity Retaining Wall can adopt free stone masonry, also can adopt plain concrete to build and form, and this kind of method mainly relies on the deadweight rigidity of barricade to carry out the lateral pressure of the soil body after resistance wall.
The shortcoming of this support technology is: (1) is from great; (2) rigidity is large, poor seismic behavior; (3) resistance to overturning is poor, the resistance to capsizing deficiency.Therefore, the situation of overturning of retaining wall and slippage often occurs, affect the safety of engineering services, at this moment should consider to improve supporting type selecting that supporting scheme, design make new advances to making such engineering safer, economical.
Summary of the invention
Highway riverbank bank protection new type of retaining supporting and protection structure and job practices thereof.
The present invention is highway riverbank bank protection new type of retaining supporting and protection structure and job practices thereof, highway riverbank bank protection new type of retaining supporting and protection structure, in structure, there is a cross section to be similar to leg-of-mutton counterfort wall 18, counterfort wall 18 is afterwards for being reinforced the soil body 4, prestressed anchor 1 pass through wall surface plate 2 and counterfort 3 build-ins are reinforced the inside of the soil body 4 after wall, circumfusion cement mortar 6 at the anchoring section 5 of prestressed anchor 1, be coated with one deck anti-corrosion material 8 on the free segment 7 of prestressed anchor 1, suit PVC plastic bushing 9 outside anti-corrosion material 8, wrap up cement mortar 6 around PVC plastic bushing 9, anchor head 10 fixes on the end anchor of prestressed anchor 1 on shingle nail 2, subsection setup shrinkage joint 11 and spilled water hole 12, counterfort wall 18 can reach suffered soil pressure the anchoring section 5 of prestressed anchor 1 by anchor head 10, and be anchored in good ground by anchoring section 5.
The job practices of highway riverbank bank protection new type of retaining supporting and protection structure, the steps include:
(1) apply foundation pile 13: put into reinforcing cage in the stake hole of excavation, cast foundation pile 13, stretch into wall base plate 14 by the top protruding bar of foundation pile 13;
(2) build and make wall base plate 14 and steel concrete riverbank bank protection 15: at design attitude place formwork, the reserved shrinkage joint 11 of segmentation and spilled water hole 12, cage of reinforcement the concreting of colligation wall base plate 14, steel concrete riverbank bank protection 15 in the groove formed at formwork;
(3) make and construction prestressed anchor 1: pore-forming 19 in soil layer at first, to be welded on reinforcing bar anchor tie 21 medium-height trestle 20, reinforcing bar anchor tie 21 is positioned in hole 19, at anchoring section 5 injected water cement mortars 6, smear anti-corrosion material 8 on the free segment 7 of reinforcing bar anchor tie 21, then put PVC plastic bushing 9 at free segment 7, wrap up cement mortar 6 around PVC plastic bushing 9;
(4) apply counterfort wall shingle nail 2 and counterfort 3 thereof: at design attitude place formwork, cage of reinforcement the concreting of colligation shingle nail 2, counterfort 3 in the groove formed at formwork, reach 85% when above until concrete strength, by counterfort wall 18 rolling earth behind retaining wall 16 compactings;
(5) prestressed anchor 1 applies prestressing force: the anchor head 10 that will be fastenedly connected with prestressed anchor 1 with ground tackle 17 is locked, then does the concrete spray coating 22 for the protection of anchor head 10 and ground tackle 17;
(6) according to this step construct prestressed anchor 1, wall base plate 14, riverbank bank protection 15 and the counterfort wall 18 thereof of next work plane.
The invention has the beneficial effects as follows: by the improvement to original unsettled Gravity Retaining Wall, the stress of change structure, passive stressed by original Gravity Retaining Wall, be transformed into a kind of active force structure, and the prestressing force applied has improved the stability of riverbank side slope; Novel counterfort wall+prestressed anchor supporting and protection structure can be controlled sidesway and the distortion of side slope better, and the existence of wall base plate can improve the bending resistance of supporting and protection structure; Overcome Gravity Retaining Wall remove to rebuild that cost is high, engineering quantity is large, safety is low, to shortcomings such as environmental disruption are large; The safety that perturbation to side slope in work progress is little, guaranteed work progress; Improve its antidetonation, overturning or slip resistance analysis performance simultaneously; Technology is simple, and good looking appearance is convenient to application, and can be effectively protected river levee.
The accompanying drawing explanation
Fig. 1 is the elevation of structure of the present invention, and Fig. 2 is the sectional side view in Fig. 1, and Fig. 3 is prestressed anchor detail of construction of the present invention, is also construction reference figure, the reinforcing bar anchor tie 21 in figure in construction and the name after applying prestressing force be called prestressed anchor 1.
The specific embodiment
The present invention is highway riverbank bank protection new type of retaining supporting and protection structure and job practices thereof, as Fig. 1, Fig. 2, shown in Fig. 3, in its structure, there is a cross section to be similar to leg-of-mutton counterfort wall 18, counterfort wall 18 is rear for being reinforced the soil body 4, prestressed anchor 1 pass through wall surface plate 2 is reinforced the soil body 4 inside with counterfort 3 build-ins after wall, anchoring section 5 circumfusion cement mortar 6 at prestressed anchor 1, be coated with one deck anti-corrosion material 8 on the free segment 7 of prestressed anchor 1, suit PVC plastic bushing 9 outside anti-corrosion material 8, wrap up cement mortar 6 around PVC plastic bushing 9, anchor head 10 fixes on the end anchor of prestressed anchor 1 on shingle nail 2, subsection setup shrinkage joint 11 and spilled water hole 12, the suffered soil pressure of counterfort wall 18 reaches the anchoring section 5 of prestressed anchor 1 by anchor head 10, and is anchored in good ground by anchoring section 5.
The anchor pole inclination angle that prestressed anchor 3 becomes with horizontal plane is 5 ° ~ 15 °.
When implementing, section construction, from bottom to top successively, section construction, the step of its job practices is:
(1) apply foundation pile 13: put into reinforcing cage in the stake hole of excavation, cast foundation pile 13, go deep into wall base plate 14 by the top protruding bar of foundation pile 13.
(2) build and make wall base plate 14 and steel concrete riverbank bank protection 15: at design attitude place formwork, the reserved shrinkage joint 11 of segmentation and spilled water hole 12, cage of reinforcement the concreting of colligation wall base plate 14, steel concrete riverbank bank protection 15 in the groove formed at formwork.
(3) make and construction prestressed anchor 1: pore-forming 19 in soil layer at first, to be welded on reinforcing bar anchor tie 21 medium-height trestle 20, reinforcing bar anchor tie 21 is positioned in hole 19, at anchoring section 5 injected water cement mortars 6, smear anti-corrosion material 8 on the free segment 7 of reinforcing bar anchor tie 21, then put PVC plastic bushing 9 at free segment 7, wrap up cement mortar 6 around PVC plastic bushing 9.
(4) apply counterfort wall shingle nail 2 and counterfort 3 thereof: at design attitude place formwork, cage of reinforcement the concreting of colligation shingle nail 2, counterfort 3 in the groove formed at formwork, reach 85% when above until concrete strength, by counterfort wall 18 rolling earth behind retaining wall 16 compactings.
(5) prestressed anchor 1 applies prestressing force: the anchor head 10 that will be fastenedly connected with prestressed anchor 1 with ground tackle 17 is locked, then does the concrete spray coating 22 for the protection of anchor head 10 and ground tackle 17.
(6) according to this step construct prestressed anchor 1, wall base plate 14, riverbank bank protection 15 and the counterfort wall 18 thereof of next work plane.

Claims (3)

1. highway riverbank bank protection new type of retaining supporting and protection structure, it is characterized in that in structure having a cross section to be similar to leg-of-mutton counterfort wall (18), counterfort wall (18) is afterwards for being reinforced the soil body (4), prestressed anchor (1) pass through wall surface plate (2) and counterfort (3) build-in are reinforced the inside of the soil body (4) after wall, circumfusion cement mortar (6) at the anchoring section (5) of prestressed anchor (1), be coated with one deck anti-corrosion material (8) on the free segment (7) of prestressed anchor (1), suit PVC plastic bushing (9) outside anti-corrosion material (8), wrap up cement mortar (6) around PVC plastic bushing (9), anchor head (10) fixes on the end anchor of prestressed anchor (1) on shingle nail (2), subsection setup shrinkage joint (11) and spilled water hole (12), counterfort wall (18) can reach suffered soil pressure the anchoring section (5) of prestressed anchor (1) by anchor head (10), and be anchored in good ground by anchoring section (5).
2. highway according to claim 1 riverbank bank protection new type of retaining supporting and protection structure, is characterized in that the anchor pole inclination angle that prestressed anchor (1) becomes with horizontal plane is 5 ° ~ 15 °.
3. the job practices of highway riverbank bank protection new type of retaining supporting and protection structure, the steps include:
(1) apply foundation pile (13): put into reinforcing cage in the stake hole of excavation, cast foundation pile (13), stretch into wall base plate (14) by the top protruding bar of foundation pile (13);
(2) build and make wall base plate (14) and steel concrete riverbank bank protection (15): at design attitude place formwork, shrinkage joint (11) and spilled water hole (12) are reserved in segmentation, cage of reinforcement the concreting of colligation wall base plate (14), steel concrete riverbank bank protection (15) in the groove formed at formwork;
(3) make and construction prestressed anchor (1): pore-forming (19) in soil layer at first, to be welded on reinforcing bar anchor tie (21) medium-height trestle (20), reinforcing bar anchor tie (21) is positioned in hole (19), at anchoring section (5) injected water cement mortar (6), smear anti-corrosion material (8) on the free segment (7) of reinforcing bar anchor tie (21), then put PVC plastic bushing (9) at free segment (7), at PVC plastic bushing (9), wrap up cement mortar (6) on every side;
(4) apply counterfort wall shingle nail (2) and counterfort (3) thereof: at design attitude place formwork, cage of reinforcement the concreting of colligation shingle nail (2), counterfort (3) in the groove formed at formwork, reach 85% when above until concrete strength, by counterfort wall (18) rolling earth behind retaining wall (16) compacting;
(5) prestressed anchor (1) applies prestressing force: the anchor head (10) that will be fastenedly connected with prestressed anchor (1) with ground tackle (17) is locked, then does the concrete spray coating (22) for the protection of anchor head (10) and ground tackle (17);
(6) according to this step construct prestressed anchor (1), wall base plate (14), riverbank bank protection (15) and the counterfort wall (18) thereof of next work plane.
CN201310435804XA 2013-09-24 2013-09-24 Novel barricade supporting structure for road or river bank dam and construction method thereof Pending CN103469814A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310435804XA CN103469814A (en) 2013-09-24 2013-09-24 Novel barricade supporting structure for road or river bank dam and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310435804XA CN103469814A (en) 2013-09-24 2013-09-24 Novel barricade supporting structure for road or river bank dam and construction method thereof

Publications (1)

Publication Number Publication Date
CN103469814A true CN103469814A (en) 2013-12-25

Family

ID=49794843

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310435804XA Pending CN103469814A (en) 2013-09-24 2013-09-24 Novel barricade supporting structure for road or river bank dam and construction method thereof

Country Status (1)

Country Link
CN (1) CN103469814A (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103866788A (en) * 2014-04-02 2014-06-18 李煜科 Retaining wall reformation method for column type bridge abutment foreslope
CN104863176A (en) * 2015-06-10 2015-08-26 上海煤气第二管线工程有限公司 Natural gas pipeline engineering retaining wall and construction method thereof
CN104894926A (en) * 2015-06-09 2015-09-09 中铁第一勘察设计院集团有限公司 Retaining structure on existing railway high embankment and construction method thereof
CN105507950A (en) * 2015-12-17 2016-04-20 大同煤矿集团有限责任公司 Waterproof airtight structure with arched cushion wall
CN106284341A (en) * 2016-08-21 2017-01-04 中国十九冶集团有限公司南京分公司 A kind of prestress anchorage cable hillside wall construction technology
CN106906842A (en) * 2017-04-20 2017-06-30 福建省建研工程顾问有限公司 One kind draws anchor formula L-type Reinforced Concrete Retaining Walls
CN107700527A (en) * 2017-11-07 2018-02-16 兰州理工大学 Add the cantilever retaining wall and construction method of pilaster and anchor pole
CN108277814A (en) * 2018-04-11 2018-07-13 王凯 Stake top counterfort wall supporting construction and construction method
CN108330910A (en) * 2018-01-10 2018-07-27 上海勘测设计研究院有限公司 Bank protection structure
CN108532594A (en) * 2018-06-22 2018-09-14 广西大学 Anchor pole and construction method suitable for the karst area with connected pore channel
CN108677980A (en) * 2018-07-12 2018-10-19 中国电建集团贵阳勘测设计研究院有限公司 A kind of upstream cofferdam that taking into account communication function increases method and structure
CN108677869A (en) * 2018-05-24 2018-10-19 上海勘测设计研究院有限公司 Bank protection structure suitable for flood passage, flood control and navigable river
CN109826211A (en) * 2019-02-18 2019-05-31 西安工程大学 A kind of sand slope protection construction method
CN109914448A (en) * 2019-04-16 2019-06-21 大连交通大学 A kind of composite supporting construction widened for rock matter embankment and construction method
CN110438991A (en) * 2019-07-17 2019-11-12 长安大学 A kind of freeze proof Ecological Slope barricade of the dark and damp Han Qu pin-connected panel of weather and assembly method
CN110700291A (en) * 2019-10-23 2020-01-17 山东建筑大学 Combined retaining structure and construction method thereof
CN110984218A (en) * 2019-12-30 2020-04-10 北京中景橙石科技股份有限公司 Construction process for one-time pouring of decorative concrete retaining wall in wading
CN115305950A (en) * 2022-07-26 2022-11-08 中国中材国际工程股份有限公司 Assembled cantilever retaining wall and mounting method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1219630A (en) * 1998-12-08 1999-06-16 李宪奎 Formation method for retaining wall
JP2010150821A (en) * 2008-12-25 2010-07-08 Jiban Risk Kenkyusho:Kk Method for reinforcing retaining wall
CN102251525A (en) * 2011-04-12 2011-11-23 兰州理工大学 Framework prestress anchor rod-reinforced supporting structure for gravity type retaining wall and construction method thereof
CN102330431A (en) * 2011-06-16 2012-01-25 兰州理工大学 Flexible support structure of pre-stress anchor rod for lattice type frame and construction method of flexible support structure
CN202830942U (en) * 2012-08-27 2013-03-27 中铁二院工程集团有限责任公司 Combined supporting structure with anchor cables and cast-in-situ bored piles

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1219630A (en) * 1998-12-08 1999-06-16 李宪奎 Formation method for retaining wall
JP2010150821A (en) * 2008-12-25 2010-07-08 Jiban Risk Kenkyusho:Kk Method for reinforcing retaining wall
CN102251525A (en) * 2011-04-12 2011-11-23 兰州理工大学 Framework prestress anchor rod-reinforced supporting structure for gravity type retaining wall and construction method thereof
CN102330431A (en) * 2011-06-16 2012-01-25 兰州理工大学 Flexible support structure of pre-stress anchor rod for lattice type frame and construction method of flexible support structure
CN202830942U (en) * 2012-08-27 2013-03-27 中铁二院工程集团有限责任公司 Combined supporting structure with anchor cables and cast-in-situ bored piles

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103866788B (en) * 2014-04-02 2016-01-20 李煜科 A kind of method of pillar abutment scarp slope barricadeization transformation
CN103866788A (en) * 2014-04-02 2014-06-18 李煜科 Retaining wall reformation method for column type bridge abutment foreslope
CN104894926A (en) * 2015-06-09 2015-09-09 中铁第一勘察设计院集团有限公司 Retaining structure on existing railway high embankment and construction method thereof
CN104863176A (en) * 2015-06-10 2015-08-26 上海煤气第二管线工程有限公司 Natural gas pipeline engineering retaining wall and construction method thereof
CN105507950B (en) * 2015-12-17 2018-02-23 大同煤矿集团有限责任公司 Arch cushion wall water-proof sealing structure
CN105507950A (en) * 2015-12-17 2016-04-20 大同煤矿集团有限责任公司 Waterproof airtight structure with arched cushion wall
CN106284341A (en) * 2016-08-21 2017-01-04 中国十九冶集团有限公司南京分公司 A kind of prestress anchorage cable hillside wall construction technology
CN106284341B (en) * 2016-08-21 2018-08-17 中国十九冶集团有限公司南京分公司 A kind of prestress anchorage cable hillside wall construction technology
CN106906842A (en) * 2017-04-20 2017-06-30 福建省建研工程顾问有限公司 One kind draws anchor formula L-type Reinforced Concrete Retaining Walls
CN107700527A (en) * 2017-11-07 2018-02-16 兰州理工大学 Add the cantilever retaining wall and construction method of pilaster and anchor pole
CN108330910A (en) * 2018-01-10 2018-07-27 上海勘测设计研究院有限公司 Bank protection structure
CN108277814A (en) * 2018-04-11 2018-07-13 王凯 Stake top counterfort wall supporting construction and construction method
CN108677869A (en) * 2018-05-24 2018-10-19 上海勘测设计研究院有限公司 Bank protection structure suitable for flood passage, flood control and navigable river
CN108532594A (en) * 2018-06-22 2018-09-14 广西大学 Anchor pole and construction method suitable for the karst area with connected pore channel
CN108677980A (en) * 2018-07-12 2018-10-19 中国电建集团贵阳勘测设计研究院有限公司 A kind of upstream cofferdam that taking into account communication function increases method and structure
CN108677980B (en) * 2018-07-12 2023-10-31 中国电建集团贵阳勘测设计研究院有限公司 Upstream cofferdam heightening method and structure taking traffic function into consideration
CN109826211A (en) * 2019-02-18 2019-05-31 西安工程大学 A kind of sand slope protection construction method
CN109826211B (en) * 2019-02-18 2021-01-29 西安工程大学 Sand slope protection construction method
CN109914448A (en) * 2019-04-16 2019-06-21 大连交通大学 A kind of composite supporting construction widened for rock matter embankment and construction method
CN110438991A (en) * 2019-07-17 2019-11-12 长安大学 A kind of freeze proof Ecological Slope barricade of the dark and damp Han Qu pin-connected panel of weather and assembly method
CN110438991B (en) * 2019-07-17 2024-02-23 长安大学 Assembled frost-resistant ecological side slope retaining wall for climate yin-dampness-cold region and assembly method
CN110700291A (en) * 2019-10-23 2020-01-17 山东建筑大学 Combined retaining structure and construction method thereof
CN110984218A (en) * 2019-12-30 2020-04-10 北京中景橙石科技股份有限公司 Construction process for one-time pouring of decorative concrete retaining wall in wading
CN115305950A (en) * 2022-07-26 2022-11-08 中国中材国际工程股份有限公司 Assembled cantilever retaining wall and mounting method thereof

Similar Documents

Publication Publication Date Title
CN103469814A (en) Novel barricade supporting structure for road or river bank dam and construction method thereof
CN203741868U (en) Reinforced concrete retaining wall structure with combined anchor wire
CN102330431A (en) Flexible support structure of pre-stress anchor rod for lattice type frame and construction method of flexible support structure
CN102251525A (en) Framework prestress anchor rod-reinforced supporting structure for gravity type retaining wall and construction method thereof
CN201722704U (en) Pre-stressed cantilever counter rib holding retaining wall
CN102330432A (en) Panel-type framework prestressed anchor rod flexible support structure and construction method thereof
CN101899839A (en) Counter-pulled type rib retaining wall of pre-stressing force cantilever
CN104532868A (en) Anchored high bearing platform grouped pile foundation building method for high-steep deformation slope area bridge
CN106284414A (en) Anti-grand supporting construction
CN107059882A (en) Arch anchor net and Anchor-Pile Retaining Structure structure
CN110258362A (en) A kind of city underground engineering passes through the deformation control method of existing bridge
CN204753604U (en) A excavation supporting system for expanding soil district
CN104863162A (en) Foundation pit support system applied to expansive soil regions and construction method thereof
CN108005094A (en) Pier and pier top beam section construction method in naked rock river bed water
CN103215889A (en) Arch bridge foundation used on bad geological conditions and construction method of arch bridge foundation
CN110629770B (en) Reservoir side slope hydro-fluctuation belt seepage-proofing slope protection structure and construction method thereof
CN108005097A (en) High gradient slope top of the slope construction/build thing anchor raft foundation construction and construction method
CN101368388B (en) Anchor pipe skeleton support method
CN110258600B (en) Vertical cofferdam construction method suitable for deepwater area
CN210369065U (en) Counter-force device for tensioning basement anti-floating prestress anti-pulling anchor rod
CN209873814U (en) A construction structures for handling foundation ditch inter-pile soil collapses
CN106917358A (en) A kind of cable-stayed bridge main-beam combination constructing method thereof and its counter weight construction system
CN106193120A (en) Basement is encorbelmented, and base plate is inverse makees structure and construction method
Wiggins et al. Rehabilitation of Brougham Castle Bridge, UK
JP5773755B2 (en) Pile foundation structure of exterior structure and construction method of pile foundation structure of exterior structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20131225

RJ01 Rejection of invention patent application after publication