CN108269013A - The foundation and coding method in hydroelectric project structure attribute inventory library - Google Patents
The foundation and coding method in hydroelectric project structure attribute inventory library Download PDFInfo
- Publication number
- CN108269013A CN108269013A CN201810041520.5A CN201810041520A CN108269013A CN 108269013 A CN108269013 A CN 108269013A CN 201810041520 A CN201810041520 A CN 201810041520A CN 108269013 A CN108269013 A CN 108269013A
- Authority
- CN
- China
- Prior art keywords
- attribute
- engineering
- project
- coding
- inventory
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 55
- 238000010276 construction Methods 0.000 claims abstract description 47
- 238000013461 design Methods 0.000 claims abstract description 12
- 238000012544 monitoring process Methods 0.000 claims description 26
- 238000004458 analytical method Methods 0.000 claims description 8
- 239000000203 mixture Substances 0.000 claims description 5
- 238000007689 inspection Methods 0.000 claims description 4
- 238000012360 testing method Methods 0.000 claims description 4
- 238000012550 audit Methods 0.000 claims description 3
- 238000010835 comparative analysis Methods 0.000 claims description 3
- 238000011156 evaluation Methods 0.000 claims description 3
- 238000002474 experimental method Methods 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 3
- 239000000463 material Substances 0.000 claims description 3
- 239000002184 metal Substances 0.000 claims description 3
- 239000011435 rock Substances 0.000 claims description 3
- 238000000354 decomposition reaction Methods 0.000 abstract description 9
- 238000007726 management method Methods 0.000 description 6
- 238000005516 engineering process Methods 0.000 description 4
- 238000009825 accumulation Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000007812 deficiency Effects 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 239000006185 dispersion Substances 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 239000003550 marker Substances 0.000 description 1
- 238000010327 methods by industry Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0639—Performance analysis of employees; Performance analysis of enterprise or organisation operations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Quality & Reliability (AREA)
- Development Economics (AREA)
- Operations Research (AREA)
- Educational Administration (AREA)
- Health & Medical Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Data Mining & Analysis (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention relates to a kind of foundation and coding method in hydroelectric project structure attribute inventory library, this method includes engineering attribute classification and includes primary attribute, environment attribute, procedure attribute and monitor four major class of attribute, and the primary attribute includes engineering characteristics, engineering design, geological information and detail design;Then pass through definition column dictionary encoding, accurate definition is carried out to construction unit type, partitioned project major class, subdivisional work, process, it realizes the standardization that engineering structure is decomposed, supports more decomposition levels, project progress, cost and the investment statistics being easy to implement based on budgetary estimate.The method of the present invention can realize all kinds of Attribute Associations using engineering structure site decomposition as core, establish hydroelectric project structure attribute inventory library, realize multi-disciplinary data sharing with cooperateing with.
Description
Technical field
The present invention relates to hydroelectric project textural classification, a kind of foundation in particular to hydroelectric project structure attribute inventory library and
Coding method.
Background technology
Due to hydroelectric project structure composition complexity, long construction period, construction and more, the traditional information management hand of technology specialty
Duan Caiyong points of professional vertical management modes, thus can not realize data sharing and multiplexing between different phase, different majors.
In addition, traditional hydroelectric project STRUCTURE DECOMPOSITION is using construction unit, partitioned project, subdivisional work, element project four
Grade coding, and not according to engineering construction it is special the characteristics of specification define its structure attribute and encode, all kinds of numbers of process of construction
According to dispersion, information describes disunity, can not carry out efficient association, identification and comparison, can not meet hydroelectric project and become more meticulous construction
The needs of management requirement and comprehensive performance analysis.Based on hydroelectric project BIM (DIM) technology, establish and built towards hydroelectric project
If the hydroelectric project STRUCTURE DECOMPOSITION and attribute coding's system of process are to realize that engineering design, progress, cost, quality, safety etc. are complete
Element information is collected, and establishes the basis of engineering big data, be realize hydroelectric project digitlization, intelligent management premise, meet
The comprehensive performance appraisal of engineering, the needs transferred to when Engineering Digitalization.
Invention content
Present invention aims to overcome that above-mentioned the deficiencies in the prior art and a kind of hydroelectric project structure attribute inventory library is provided
Method for building up, this method can realize all kinds of Attribute Associations using engineering structure site decomposition as core, establish hydroelectric project
Multi-disciplinary data sharing is realized with cooperateing in structure attribute inventory library, and by defining serial dictionary encoding, to construction unit
Type, partitioned project major class, subdivisional work, process carry out accurate definition, realize the standardization that engineering structure is decomposed, and support more
Decomposition level, project progress, cost and the investment statistics being easy to implement based on budgetary estimate.
Realize the object of the invention the technical solution adopted is that foundation and the coding in a kind of hydroelectric project structure attribute inventory library
Method, this method include:
First, hydroelectric project structure attribute inventory library is established, engineering attribute classification is specifically included and includes primary attribute, environment
Attribute, procedure attribute with monitoring four major class of attribute, the primary attribute include engineering characteristics, engineering design, geological information and
Detail design;The environment attribute includes the hydrometeorology of engineering entirety, the subenvironment data of part;The procedure attribute includes
Safety, quality, progress, cost, clearing, monitoring, experiment and the data of engineering;The monitoring attribute refers to the permanent secure of engineering
The monitoring temporarily of monitoring, construction time and special monitoring attribute:
Then, coding is followed the steps below:
S1, determine that three characters form unique engineering coding;
S2, foundation Budgetary Estimates and engineering works quantity and distribution characteristics, are decomposed to form construction unit inventory;
S3, for specific construction unit, to different construction unit types and structure composition, determine first order branch group
Into, and it is decomposed to form specific partitioned project inventory;
S4, type of being itemized according to the construction operation under specific branch, select corresponding subitem project and coding;
S5, the resolving cell engineering successively in order under subitem;
S6, to each element project, subitem, selects corresponding process inventory according to belonging to it;
S7, to each different structure rank and structure type, define corresponding engineering attribute inventory;
When S8, each profession are carried out the work, associated traffic data must be associated with corresponding engineering structure position, and according to association
Attribute is filled into corresponding public attribute inventory;
In S9, the special work progress of each construction, associated traffic data is associated with corresponding structure position, and will according to association
Attribute is filled into corresponding special attribute inventory;
S10, the various information based on structure connection form engineering big data, realize the comprehensive inquiry of project data, performance
Analysis and evaluation;
S11, based on same coding structure and system, carry out the comparative analysis of project data and Improvement;
Six grades of engineering, construction unit, partitioned project, subdivisional work, element project and process codings, per level encoder
It is divided into one or more snippets;Per level encoder include dictionary code and/or sequence code, the dictionary code refer to construction unit type,
Partitioned project major class, subdivisional work, process establishment dictionary code library.
In the above-mentioned technical solutions, the engineering is encoded to one section of 3 character, for the unique of one hydroelectric project of expression
Mark;The construction unit is encoded to five sections of 9 characters, wherein first four sections are dictionary code, latter section 2 are the suitable of unit engineering
Sequence code;1 character of first segment of the preceding four segment dictionaries code is works category, and 2 characters of second segment are unit engineering major class, the
Three sections of 2 characters are class in unit engineering, and the 4th section of 2 characters are unit engineering group;The partitioned project is encoded to two section 6
Position character, wherein 2 characters of the last period are the dictionary code of partitioned project major class, and latter section of 4 characters are the sequence of partitioned project
Code;The subdivisional work is two sections of 4 characters, wherein dictionary code of 2 characters of the last period for subdivisional work major class, latter section 2
Position character is the dictionary code of subdivisional work group;The element project is encoded to one section of 4 coding, is sequence code;The process
One section of 2 coding is encoded to, is dictionary code.
In the above-mentioned technical solutions, to the primary attribute, environment attribute, procedure attribute with monitoring in four major class of attribute
Specific object define basic coding, operation code rule and attribute project list respectively;The basic coding refers to post, work
Kind, device type, material type carry out basic coding and service basic coding, and every group of basic coding is by unduplicated digital number
And corresponding word description composition;Operation code rule is the coding create-rule defined in business object, specific for specification
Business, formed by combinations such as fixed character, one or more groups of basic codings, sequence code, data marks;The attribute project is clear
It is singly specific attribute inventory, it can be specified uniquely to encode each list item, title and data type.
In the above-mentioned technical solutions, the engineering attribute inventory includes public attribute and two class of special attribute, public attribute
Refer to the attribute that can be associated with concrete structure position that each profession is formed, including:Engineering characteristics, engineering design, geology letter
Breath, testing inspection, safety monitoring, target advance, visa clearing, engineering survey, engineering data, supervision audit, is built at safe mass
Build market;Special attribute refers to the special special attribute of each construction, specifically includes earth and rock works, concrete works, ground
It is made and installing engineering, mechanical and electric equipment installation engineering, safety monitoring project with foundation treatment engineering, metal structure.
The present invention has the following advantages:
1st, it by establishing engineering attribute classification, basic coding, operation code rule and the service attribute inventory of standard, supports
Cover engineering respectively management and technology specialty, each the accurate, timely, complete of subdivisional work basis, process, environment and monitoring data of constructing
Face is collected, and is established hydroelectric project big data warehouse, is realized all kinds of Attribute Associations using engineering structure site decomposition as core, is realized
Multi-disciplinary data sharing is the comprehensive analysis of the more elements of engineering, the accumulation of project data assets and the service analyzed with cooperateing with.
2nd, using hierarchical coding structure, each rank by way of dictionary code, sequence code or dictionary code+sequence code combination into
Row mixing fixed-length segmental coding.Hierarchical coding structure refers to that whole hierarchical structure is divided into Pyatyi, and every grade corresponds to different works respectively
Journey layer of structure;Dictionary code refers to construction unit type therein, partitioned project major class, subdivisional work, process establishment dictionary
Code library, can only select corresponding coding in actual coding, it is impossible to arbitrary to increase, delete or adjustment.Construction unit, partitioned project are adopted
Combinational code is formed with dictionary code+sequence code;Element project is encoded using digital code sequence, by actual quantity and sequentially successively
It is incremented by;Subdivisional work, process are pure dictionary code.
3rd, coding method of the present invention is by defining serial dictionary encoding, to construction unit type, partitioned project major class, subitem
Engineering, process carry out accurate definition, realize the standardization that engineering structure is decomposed, support it is more decompose levels, be easy to implement with
Project progress, cost and investment statistics based on budgetary estimate;It is easy to implement the working procedure flow control towards specific subdivisional work
System and process management;Accurately engineering real cost statistics is easy to implement to measure with construction norm;It is easy to implement different subitem works
Journey across position, across building, across the performance analyses such as the project progress, cost, quality of engineering with comparison.
Description of the drawings
Fig. 1 is the hydroelectric project structure attribute inventory library schematic diagram established using the method for the present invention.
Fig. 2 is the schematic diagram of one embodiment of the invention hydroelectric project STRUCTURE DECOMPOSITION coding.
Specific embodiment
The present invention is described in further detail in the following with reference to the drawings and specific embodiments.
The foundation and coding method in hydroelectric project structure attribute inventory library of the present invention initially set up hydroelectric project structure attribute
Inventory library, as shown in Figure 1, engineering structure attribute is divided into engineering by the method for building up in hydroelectric project structure attribute inventory library of the present invention
Attributive classification includes primary attribute, environment attribute, procedure attribute and monitoring four major class of attribute, the primary attribute and includes engineering
Feature, engineering design, geological information and detail design;It is the hydrometeorology of the environment attribute including engineering entirety, local small
Environmental data;The procedure attribute includes safety, quality, progress, cost, clearing, monitoring, experiment and the data of engineering;It is described
Monitoring attribute refers to the monitoring temporarily of the permanent safety monitoring of engineering, construction time and special monitoring attribute.
It is fixed respectively to above-mentioned primary attribute, environment attribute, procedure attribute and the specific object in monitoring four major class of attribute
Adopted basic coding, operation code rule and attribute project list;Basic coding refers to post, work post, device type, material type
Basic coding and service basic coding are carried out, every group of basic coding is by unduplicated digital number and corresponding word description group
Into;Operation code rule is the coding create-rule defined in business object, for the specific business of specification, by fixed character,
The combinations such as one or more groups of basic codings, sequence code, data mark are formed, such as:The coding rule of testing inspection sample marker code
It is then:" T "-detection project encodes -4 times -3 serial numbers of number;The attribute project list is specific attribute inventory,
It can be specified uniquely to encode each list item, title and data type.
In the present embodiment, engineering attribute inventory includes public attribute and two class of special attribute, and public attribute refers to each special
The attribute that can be associated with concrete structure position that industry is formed, including:Engineering characteristics, engineering design, geological information, safe matter
Amount, testing inspection, safety monitoring, target advance, visa clearing, engineering survey, supervision audit, engineering data, construction market;Specially
Refer to the special attribute of each construction profession with attribute, specifically include earth and rock works, concrete works, ground and based process
Engineering, metal structure make and installing engineering, mechanical and electric equipment installation engineering, safety monitoring project.
Hydroelectric project STRUCTURE DECOMPOSITION coding method of the present invention includes engineering, construction unit, partitioned project, subdivisional work, list
Six grades of codings of first engineering and process, are divided into one or more snippets per level encoder, can be separated by between every level-one with symbol "-";Often
Level encoder includes dictionary code and/or sequence code, wherein, dictionary code refers to construction unit type, partitioned project major class, subitem
Engineering, process establishment dictionary code library;Corresponding coding can only be wherein selected in actual coding, it is impossible to arbitrary to increase, delete or adjust
It is whole;Sequence code is to carry out sequential encoding to multiple entities under same type, can be increased newly according to actual demands of engineering sequence
Or adjustment.
As shown in Fig. 2, the present embodiment specifically encodes to illustrate the method for the present invention with one:
Engineering is encoded to one section of 3 character, for representing the unique mark of a hydroelectric project, such as:CTG represents three
Gorge.
Construction unit is encoded to five sections of 9 characters, wherein first four sections are dictionary code, latter section 2 are the suitable of unit engineering
Sequence code;1 character of first segment of the preceding four segment dictionaries code is works category, and 2 characters of second segment are unit engineering major class, the
Three sections of 2 characters are class in unit engineering, and the 4th section of 2 characters are unit engineering group, and the 5th section is 2 sequence codes, such as:
101010101 represent multi-purpose project-dam engineering-earth and rockfill dam-Shang Kuba.
Partitioned project is encoded to two sections of 6 characters, and wherein 2 characters of the last period are the dictionary code of partitioned project major class, after
One section of 4 character is the sequence code of partitioned project, such as:010005 represents 5# monoliths.
Subdivisional work is two sections of 4 characters, wherein dictionary code of 2 characters of the last period for subdivisional work major class, latter section 2
Position character is the dictionary code of subdivisional work group, such as:0201 represents the normal concrete in concrete works.
Element project is encoded to one section of 4 coding, is sequence code, such as:0005 represents Unit the 5th.
Coding is encoded for one section 2, for dictionary code, such as 01 expression model sheetinstallat.
Respectively according to method for building up of the invention described above to hydroelectric project structure attribute inventory library and coding method, this implementation
Example realizes that the process of a specific hydroelectric project structured coding is as follows:
S1, determine that three characters form unique engineering coding;
S2, foundation Budgetary Estimates and engineering works quantity and distribution characteristics, are decomposed to form construction unit inventory;
S3, for specific construction unit, to different construction unit types and structure composition, determine first order branch group
Into, and it is decomposed to form specific partitioned project inventory;
S4, type of being itemized according to the construction operation under specific branch, select corresponding subitem project and coding;
S5, the resolving cell engineering successively in order under subitem;
S6, to each different structure rank and structure type, define corresponding engineering attribute inventory;
When S7, each profession are carried out the work, associated traffic data must be associated with corresponding engineering structure position, and according to association
Attribute is filled into corresponding public attribute inventory;
In S8, the special work progress of each construction, associated traffic data is associated with corresponding structure position, and will according to association
Attribute is filled into corresponding special attribute inventory;
S9, the various information based on structure connection form engineering big data, realize the comprehensive inquiry of project data, performance
Analysis and evaluation;
S10, based on same coding structure and system, carry out the comparative analysis of project data and Improvement.
Engineering, construction unit, partitioned project, subdivisional work, element project and six grades of process in above-mentioned steps S1~S6
Coding is divided into one or more snippets per level encoder;Include dictionary code and/or sequence code per level encoder, the dictionary code refers to
To construction unit type, partitioned project major class, subdivisional work, process establishment dictionary code library.
The present invention realizes multi-disciplinary data sharing and association by the foundation in above-mentioned hydroelectric project structure attribute inventory library
Together, it is the comprehensive analysis of the more elements of engineering, the accumulation of project data assets and the service analyzed.It is compiled by defining serial dictionary
Code carries out accurate definition to construction unit type, partitioned project major class, subdivisional work, process, realizes the mark that engineering structure is decomposed
Standardization, support it is more decompose levels, be easy to implement different subdivisional works across position, across building, across engineering engineering into
The performance analyses such as degree, cost, quality and comparison.
Claims (4)
1. a kind of foundation and coding method in hydroelectric project structure attribute inventory library, it is characterised in that:
First, hydroelectric project structure attribute inventory library is established, engineering attribute classification is specifically included and includes primary attribute, environment category
Property, procedure attribute and monitoring four major class of attribute, the primary attribute include engineering characteristics, engineering design, geological information and apply
Work designs;The environment attribute includes the hydrometeorology of engineering entirety, the subenvironment data of part;The procedure attribute includes work
Safety, quality, progress, cost, clearing, monitoring, experiment and the data of journey;The monitoring attribute refers to the permanent secure prison of engineering
It surveys, the construction time monitors and special monitoring attribute temporarily:
Then, coding is followed the steps below:
S1, determine that three characters form unique engineering coding;
S2, foundation Budgetary Estimates and engineering works quantity and distribution characteristics, are decomposed to form construction unit inventory;
S3, for specific construction unit, to different construction unit types and structure composition, determine that first order branch forms,
And it is decomposed to form specific partitioned project inventory;
S4, type of being itemized according to the construction operation under specific branch, select corresponding subitem project and coding;
S5, the resolving cell engineering successively in order under subitem;
S6, to each element project, subitem, selects corresponding process inventory according to belonging to it;
S7, to each different structure rank and structure type, define corresponding engineering attribute inventory;
When S8, each profession are carried out the work, associated traffic data must be associated with corresponding engineering structure position, and will belong to according to association
Property is filled into corresponding public attribute inventory;
In S9, the special work progress of each construction, associated traffic data is associated with corresponding structure position, and according to association by attribute
It is filled into corresponding special attribute inventory;
S10, the various information based on structure connection form engineering big data, realize the comprehensive inquiry of project data, performance analysis
With evaluation;
S11, based on same coding structure and system, carry out the comparative analysis of project data and Improvement;
Six grades of engineering, construction unit, partitioned project, subdivisional work, element project and process codings, are divided into per level encoder
One or more snippets;Include dictionary code and/or sequence code per level encoder, the dictionary code refers to construction unit type, branch
Engineering major class, subdivisional work, process establishment dictionary code library.
2. the foundation and coding method in hydroelectric project structure attribute inventory library according to claim 1, it is characterised in that:It is described
Engineering is encoded to one section of 3 character, for representing the unique mark of a hydroelectric project;The construction unit is encoded to five section 9
Position character, wherein first four sections be dictionary code, latter section 2 be unit engineering sequence code;The first of the preceding four segment dictionaries code
1 character of section is works category, and 2 characters of second segment are unit engineering major class, and 2 characters of third section are class in unit engineering,
4th section of 2 characters are unit engineering group;The partitioned project is encoded to two sections of 6 characters, and wherein 2 characters of the last period are
The dictionary code of partitioned project major class, latter section of 4 characters are the sequence code of partitioned project;The subdivisional work is two sections of 4 words
Symbol, wherein 2 characters of the last period are the dictionary code of subdivisional work major class, and latter section of 2 characters are the dictionary of subdivisional work group
Code;The element project is encoded to one section of 4 coding, is sequence code;The coding is encoded for one section 2, is dictionary code.
3. the foundation and coding method in hydroelectric project structure attribute inventory library according to claim 2, it is characterised in that:To institute
It states primary attribute, environment attribute, procedure attribute and the specific object in monitoring four major class of attribute and defines basic coding, industry respectively
Business coding rule and attribute project list;The basic coding refers to that post, work post, device type, material type carry out basis
Coding and service basic coding, every group of basic coding are made of unduplicated digital number and corresponding word description;Business is compiled
Code rule is coding create-rule defined in business object, for the specific business of specification, by fixed character, one or more groups of
The combinations such as basic coding, sequence code, data mark are formed;The attribute project list is specific attribute inventory, to each clear
Individual event mesh can specify it uniquely to encode, title and data type.
4. the method for building up in hydroelectric project structure attribute inventory library according to claim 3, it is characterised in that:The engineering category
Property inventory include public attribute and two class of special attribute, public attribute refers to that each profession formed can be associated with concrete structure
The attribute at position, including:Engineering characteristics, engineering design, geological information, safe mass, testing inspection, safety monitoring, plan into
Degree, visa clearing, engineering survey, engineering data, supervision audit, construction market;Special attribute refers to the special of each construction special project
With attribute, earth and rock works, concrete works, ground and foundation treatment engineering are specifically included, metal structure makes and erector
Journey, mechanical and electric equipment installation engineering, safety monitoring project.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810041520.5A CN108269013A (en) | 2018-01-16 | 2018-01-16 | The foundation and coding method in hydroelectric project structure attribute inventory library |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810041520.5A CN108269013A (en) | 2018-01-16 | 2018-01-16 | The foundation and coding method in hydroelectric project structure attribute inventory library |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108269013A true CN108269013A (en) | 2018-07-10 |
Family
ID=62775696
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810041520.5A Pending CN108269013A (en) | 2018-01-16 | 2018-01-16 | The foundation and coding method in hydroelectric project structure attribute inventory library |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108269013A (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109145445A (en) * | 2018-08-22 | 2019-01-04 | 中国三峡建设管理有限公司 | A kind of hydroelectric project intelligent construction management system |
CN109784840A (en) * | 2018-12-28 | 2019-05-21 | 福建华闽通达信息技术有限公司 | A kind of construction survey automatic data collection processing method being associated with engineering structure task |
CN110956448A (en) * | 2019-11-28 | 2020-04-03 | 上海建工集团股份有限公司 | House construction project information coding method |
CN113065254A (en) * | 2021-04-02 | 2021-07-02 | 广东工业大学 | Carbon emission measuring and calculating method for process, working condition and project level highway construction activities |
CN113627128A (en) * | 2020-05-07 | 2021-11-09 | 上海同是科技股份有限公司 | Hidden danger troubleshooting check item coding method and system |
CN113762930A (en) * | 2021-09-10 | 2021-12-07 | 郑州市轨道交通设计研究院有限公司 | BIM-based digital asset transfer method, platform and system |
CN113850473A (en) * | 2021-08-25 | 2021-12-28 | 广州地铁集团有限公司 | Technical method for associating rail transit engineering construction cost with technical characteristics |
CN115186629A (en) * | 2022-06-30 | 2022-10-14 | 上海勘测设计研究院有限公司 | Coding method, system, terminal and medium for water conservancy and hydropower engineering management system |
CN116701661A (en) * | 2023-08-07 | 2023-09-05 | 中国建筑西南设计研究院有限公司 | Building engineering BIM design calculation method based on coding |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104881762A (en) * | 2015-06-25 | 2015-09-02 | 中铁四局集团有限公司 | Engineering quantity list decomposition method and system |
CN106095989A (en) * | 2016-06-21 | 2016-11-09 | 上海市建筑科学研究院(集团)有限公司 | A kind of architectural engineering information switching method based on BIM |
CN106934536A (en) * | 2017-03-01 | 2017-07-07 | 广东中建普联科技股份有限公司 | Construction industry quantities valuation listings data autocoding and recognition methods and system |
CN107220808A (en) * | 2017-05-26 | 2017-09-29 | 李扬球 | A kind of bill of quantities visualization method |
CN107358340A (en) * | 2017-06-23 | 2017-11-17 | 深圳云联万企科技有限公司 | A kind of project management system based on list of engineering |
-
2018
- 2018-01-16 CN CN201810041520.5A patent/CN108269013A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104881762A (en) * | 2015-06-25 | 2015-09-02 | 中铁四局集团有限公司 | Engineering quantity list decomposition method and system |
CN106095989A (en) * | 2016-06-21 | 2016-11-09 | 上海市建筑科学研究院(集团)有限公司 | A kind of architectural engineering information switching method based on BIM |
CN106934536A (en) * | 2017-03-01 | 2017-07-07 | 广东中建普联科技股份有限公司 | Construction industry quantities valuation listings data autocoding and recognition methods and system |
CN107220808A (en) * | 2017-05-26 | 2017-09-29 | 李扬球 | A kind of bill of quantities visualization method |
CN107358340A (en) * | 2017-06-23 | 2017-11-17 | 深圳云联万企科技有限公司 | A kind of project management system based on list of engineering |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109145445A (en) * | 2018-08-22 | 2019-01-04 | 中国三峡建设管理有限公司 | A kind of hydroelectric project intelligent construction management system |
CN109784840A (en) * | 2018-12-28 | 2019-05-21 | 福建华闽通达信息技术有限公司 | A kind of construction survey automatic data collection processing method being associated with engineering structure task |
CN110956448A (en) * | 2019-11-28 | 2020-04-03 | 上海建工集团股份有限公司 | House construction project information coding method |
CN113627128A (en) * | 2020-05-07 | 2021-11-09 | 上海同是科技股份有限公司 | Hidden danger troubleshooting check item coding method and system |
CN113065254A (en) * | 2021-04-02 | 2021-07-02 | 广东工业大学 | Carbon emission measuring and calculating method for process, working condition and project level highway construction activities |
CN113850473A (en) * | 2021-08-25 | 2021-12-28 | 广州地铁集团有限公司 | Technical method for associating rail transit engineering construction cost with technical characteristics |
CN113762930A (en) * | 2021-09-10 | 2021-12-07 | 郑州市轨道交通设计研究院有限公司 | BIM-based digital asset transfer method, platform and system |
CN115186629A (en) * | 2022-06-30 | 2022-10-14 | 上海勘测设计研究院有限公司 | Coding method, system, terminal and medium for water conservancy and hydropower engineering management system |
CN115186629B (en) * | 2022-06-30 | 2024-03-08 | 上海勘测设计研究院有限公司 | Coding method, coding system, coding terminal and coding medium of hydraulic and hydroelectric engineering management system |
CN116701661A (en) * | 2023-08-07 | 2023-09-05 | 中国建筑西南设计研究院有限公司 | Building engineering BIM design calculation method based on coding |
CN116701661B (en) * | 2023-08-07 | 2023-10-13 | 中国建筑西南设计研究院有限公司 | Building engineering BIM design calculation method based on coding |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108269013A (en) | The foundation and coding method in hydroelectric project structure attribute inventory library | |
CN112685804B (en) | Highway engineering design information-based WBS automatic construction method and system | |
CN104881762A (en) | Engineering quantity list decomposition method and system | |
Verburg et al. | Effects of selective logging on tree diversity, composition and plant functional type patterns in a Bornean rain forest | |
CN108710625A (en) | A kind of special topic knowledge automatic mining system and method | |
Carrera-Hernández et al. | The Basin of Mexico aquifer system: regional groundwater level dynamics and database development | |
CN112182234B (en) | Basin flood control planning data knowledge graph construction method | |
CN108959736A (en) | A kind of bridge technology status assessment method based on BIM | |
CN102750363A (en) | Construction method of urban geographic information data warehouse | |
CN108763752A (en) | The method that water channel determines construction boring parameter is worn under a kind of shield tunnel | |
KR100491407B1 (en) | generation and management system for flood hazard map using a GIS | |
Haselberger et al. | Quantification of biogeomorphic interactions between small‐scale sediment transport and primary vegetation succession on proglacial slopes of the Gepatschferner, Austria | |
CN106373032A (en) | Distribution network high-fault region identification method | |
CN109325665A (en) | A kind of project cost appraisal procedure and system | |
CN116167888A (en) | Construction method of sandstone-type uranium ore-forming geological background evolution framework | |
CN106382102A (en) | Overflow early warning method based on clustering algorithm | |
Chen | Hazards identification and characterisation of the tailings storage facility dam failure and engineering applications | |
CN108133049A (en) | The method for building up in hydroelectric project structure attribute inventory library | |
Chen et al. | Research on the impact of underground excavation metro on surface traffic safety and assessment method | |
CN112231301A (en) | Yellow river water sand change data warehouse | |
CN107194966A (en) | A kind of discrimination method of two-dimentional geological section geological boundary and its attribute information | |
CN113919533A (en) | Air quality tracing and forecasting method based on artificial intelligence | |
CN112802307A (en) | Geological monitoring and early warning method and system for geological exploration | |
Weil | Digital ground models in tunnelling–Status, chances and risks | |
Alberico et al. | GEOCITY: a drill-hole database as a tool to assess geological hazard in Napoli urban area |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20180710 |