CN108222056B - 设备基础螺栓群安装方法 - Google Patents
设备基础螺栓群安装方法 Download PDFInfo
- Publication number
- CN108222056B CN108222056B CN201810182231.7A CN201810182231A CN108222056B CN 108222056 B CN108222056 B CN 108222056B CN 201810182231 A CN201810182231 A CN 201810182231A CN 108222056 B CN108222056 B CN 108222056B
- Authority
- CN
- China
- Prior art keywords
- foundation
- square frame
- adjusting
- bolt
- foundation bolts
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/44—Foundations for machines, engines or ordnance
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Foundations (AREA)
Abstract
本发明公开了一种设备基础螺栓群安装方法,采用夹具的内、外方形框架的各对应框边来夹装地脚螺栓,当夹具固定后,用水准仪进行地脚螺栓上口的标高复核,如有偏差则采用地脚螺栓丝扣上的调节螺母来微调标高,直至符合控制精度要求为止,地脚螺栓垂直度的调整是用钢丝线将地脚螺栓下部进行缠绕,在钢丝线缠绕过程中进行地脚螺栓垂直度的调整,标高和垂直度调节后通过各对应框边间设置的螺栓锁紧组件来锁紧地脚螺栓以防止其移动。本发明保证了地脚螺栓的安装精度,避免了地脚螺栓孔不吻合造成的扩孔,减少了工作量,提高了工作中的劳动效率。
Description
技术领域
本发明涉及设备基础施工方法,具体为一种设备基础螺栓群现场安装方法。
背景技术:
设备基础螺栓群现场安装一直是土建建筑业的一个难题,数量巨大的螺栓安装是施工过程中的关键点。
以往施工时遇到设备底板螺栓孔与地脚螺栓不吻合时,只能采用扩孔器对设备底板螺栓孔进行扩孔,不仅影响施工进度,而且过多的扩孔量也不符合设计规范要求。
螺栓现场安装质量是否到达设计及规范要求,安装进度是否达到工程工期要求,均是工程施工的关键点。
发明内容
针对现有技术的不足,本发明所要解决的技术问题是提出了一种设计及规范要求达标、安装进度符合要求的设备基础螺栓群现场安装方法。
能够解决上述技术问题的设备基础螺栓群现场安装方法,其实施方案的步骤为:
1、根据设备地基图制作螺栓群夹具,所述螺栓群夹具包括在同一平面内设置的内方形框架和外方形框架,内方形框架和外方形框架的各对应框边用来夹装地脚螺栓,夹装位置处于地脚螺栓的丝扣处,各地脚螺栓的丝扣上均旋合有调节螺母,内方形框架和外方形框架的各对应框边之间设有调节间距而夹紧地脚螺栓的螺栓锁紧组件。
2、根据设备地基图的设计要求,采用划线方式将各地脚螺栓的安装位置标识在内方形框架和外方形框架的框边上。
3、将内方形框架和外方形框架置于地基坑内设置的支撑架上,通过框架与支撑架之间的垫块调整框架的水平度并固定位置。
4、根据划线位置就位各地脚螺栓,初步调整使各地脚螺栓处于安装要求的同一高度上。
5、用水准仪进行地脚螺栓上口的标高复核,如有偏差则采用调节螺母来微调标高,直至符合控制精度要求为止。
6、标高调整完毕后进行各地脚螺栓垂直度的调整,用钢丝线在框架下方的各地脚螺栓间进行缠绕,在钢丝线缠绕过程中进行地脚螺栓垂直度的调整。
7、通过螺栓锁紧组件将全部地脚螺栓锁紧以防止其在内方形框架和外方形框架之间左、右移动,并于地脚螺栓的丝扣上包缠薄泡沫胶。
8、采用混凝土分层浇筑,泵送砼喂料时应避免冲击地脚螺栓而保证其位置正确,当混凝土干固到一定程度并确保地脚螺栓预埋稳固后拆除夹具。
内方形框架和外方形框架常规上采用等边角钢焊接制作。
优选的,所述等边角钢的规格为L50×5。
各地脚螺栓的安装精度应控制在2mm范围内。
本发明的有益效果:
1、本发明设备基础螺栓群现场安装方法基于使用灵活性、结构简易性及可操作性为原则,利用夹具调节装置来定位安装地脚螺栓,采用旋转地脚螺栓上口的调节螺母来微调标高,最后通过螺栓锁紧组件来夹紧地脚螺栓;该方法保证了地脚螺栓的安装精度,避免了地脚螺栓孔不吻合造成的扩孔,减少了工作量,提高了工作中的劳动效率。
2、本发明中采用的夹具调节装置,其制作材料使用量少、可拆卸、并可反复使用。
附图说明
图1为本发明一种实施方式的立体结构示意图。
图号标识:1、内方形框架;2、外方形框架;3、地脚螺栓;4、调节螺母;5、螺栓锁紧组件。
具体实施方式
下面结合附图所示实施方式对本发明的技术方案作进一步说明。
本发明设备基础螺栓群现场安装方法,其实施方案的步骤为:
第一步、根据设备地基图制作螺栓群夹具,所述螺栓群夹具(如图1所示)包括在同一平面内设置的内方形框架1和外方形框架2(采用规格为L50 ×5的等边角钢焊接制作),内方形框架1和外方形框架2的各对应框边保有相同的间隔,内方形框架1和外方形框架2的各对应框边之间设有调节间距的螺栓锁紧组件5,通过调节间距可将置于其内的地脚螺栓3以不同的夹紧力锁紧。
第二步、根据设备地基图的设计位置,采用划线方式将各地脚螺栓3的安装位置标识在内方形框架1和外方形框架2的框边上。
第三步、在基坑砼基础垫层浇筑时,于各地脚螺栓3预埋位置的两侧设置插装于砼垫层中且呈交错状的废短钢筋头,以此作为固定预埋地脚螺栓3 斜拉筋的支撑点。
第四步、将内方形框架1和外方形框架2置于地基坑内设置的支撑架上,通过框架与支撑架之间的垫块调整框架的水平度并固定位置。
第五步、根据划线位置就位各地脚螺栓3(如图1中,单边框边上纵向等距间隔布置七根地脚螺栓3、单边框边上横向布置两根地脚螺栓3),确保各地脚螺栓3的安装精度处在2mm范围内,调节螺栓锁紧组件5的松紧度使地脚螺栓3在垂直方向上通过调节工具可以上、下调节高度,地脚螺栓3的夹紧位置处于丝扣的下部,丝扣上旋合有调节螺母4(抵于内、外方形框架1、 2上),初步调整使各地脚螺栓3处于安装要求的同一高度上。
调整地脚螺栓3的次序为:先调整横向布置的四根地脚螺栓3的上口标高,然后调整纵向布置且中央相对的两根地脚螺栓3的上口标高,其余地脚螺栓3的上口标高则通过已调整到位的地脚螺栓3为基准,拉钢丝线作为地脚螺栓3上口标高的控制线来调整其余地脚螺栓3。
第六步、用水准仪进行地脚螺栓3上口(丝扣顶部)的标高复核,如有偏差则采用调节螺母4来微调标高,直至符合控制精度要求为止。
第七步、标高调整完毕后进行各地脚螺栓3垂直度的调整,用钢丝线在框架下方的各地脚螺栓3间进行缠绕,在钢丝线缠绕过程中进行地脚螺栓3 垂直度的调整(地脚螺栓3以夹紧点为摆动中心调节垂直度)。
第八步、进一步调节螺栓锁紧组件5将全部地脚螺栓3锁紧在内方形框架1和外方形框架2之间使其不能左、右移动,并于地脚螺栓3的丝扣上包缠薄泡沫胶。
第九步、采用混凝土分层浇筑,泵送砼喂料时应避免冲击地脚螺栓3而保证其位置不变,当混凝土干固到一定程度并确保地脚螺栓3预埋稳固后拆除内方形框架1和外方形框架2。
Claims (3)
1.设备基础螺栓群安装方法,其实施方案的步骤为:
①、根据设备地基图制作螺栓群夹具,所述螺栓群夹具包括在同一平面内设置的内方形框架(1)和外方形框架(2),内方形框架(1)、外方形框架(2)的各对应框边保有相同的间隔,内方形框架(1)、外方形框架(2)的各对应框边之间设有调节间距的螺栓锁紧组件(5),通过调节间距可将置于其内的地脚螺栓(3)以不同的夹紧力锁紧;
②、根据设备地基图的设计位置,采用划线方式将各地脚螺栓(3)的安装位置标识在内方形框架(1)、外方形框架(2)的框边上;
③、在基坑砼基础垫层浇筑时,于各地脚螺栓(3)预埋位置的两侧设置插装于砼垫层中且呈交错状的废短钢筋头,以此作为固定预埋地脚螺栓(3)斜拉筋的支撑点;
④、将内方形框架(1)、外方形框架(2)置于地基坑内设置的支撑架上,通过框架与支撑架之间的垫块调整框架的水平度并固定位置;
⑤、根据划线位置就位单边框边上纵向等距间隔布置的多根地脚螺栓(3)以及单边框边上横向布置的两根以上地脚螺栓(3),确保各地脚螺栓(3)的安装精度处在2mm范围内,调节螺栓锁紧组件(5)的松紧度使地脚螺栓(3)在垂直方向上通过调节工具可以上、下调节高度,地脚螺栓(3)的夹紧位置处于丝扣的下部,丝扣上旋合有抵于内方形框架(1)、外方形框架(2)上调节螺母(4),初步调整使各地脚螺栓(3)处于安装要求的同一高度上;
调整地脚螺栓(3)的次序为:先调整横向布置的四根以上地脚螺栓(3)的上口标高,然后调整纵向布置且中央相对的两根地脚螺栓(3)的上口标高,其余地脚螺栓(3)的上口标高则通过已调整到位的地脚螺栓(3)为基准,拉钢丝线作为地脚螺栓(3)上口标高的控制线来调整其余地脚螺栓(3);
⑥、用水准仪进行地脚螺栓(3)上口的标高复核,如有偏差则采用调节螺母(4)来微调标高,直至符合控制精度要求为止;
⑦、标高调整完毕后进行各地脚螺栓(3)垂直度的调整,用钢丝线在框架下方的各地脚螺栓(3)间进行缠绕,在钢丝线缠绕过程中进行地脚螺栓(3)垂直度的调整,地脚螺栓(3)以夹紧点为摆动中心调节垂直度;
⑧、进一步调节螺栓锁紧组件(5)将全部地脚螺栓(3)锁紧在内方形框架(1)、外方形框架(2)之间使其不能左、右移动,并于地脚螺栓(3)的丝扣上包缠薄泡沫胶;
⑨、采用混凝土分层浇筑,泵送砼喂料时应避免冲击地脚螺栓(3)而保证其位置不变,当混凝土干固到一定程度并确保地脚螺栓(3)预埋稳固后拆除内方形框架(1)、外方形框架(2)。
2.根据权利要求1所述的设备基础螺栓群安装方法,其特征在于:内方形框架(1)、外方形框架(2)采用等边角钢焊接制作。
3.根据权利要求2所述的设备基础螺栓群安装方法,其特征在于:所述等边角钢的规格为L50×5。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810182231.7A CN108222056B (zh) | 2018-03-06 | 2018-03-06 | 设备基础螺栓群安装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810182231.7A CN108222056B (zh) | 2018-03-06 | 2018-03-06 | 设备基础螺栓群安装方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108222056A CN108222056A (zh) | 2018-06-29 |
CN108222056B true CN108222056B (zh) | 2020-09-08 |
Family
ID=62666754
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810182231.7A Active CN108222056B (zh) | 2018-03-06 | 2018-03-06 | 设备基础螺栓群安装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108222056B (zh) |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110053707B (zh) * | 2019-04-29 | 2020-12-15 | 广船国际有限公司 | 一种船舶地脚螺栓安装划线方法 |
CN110080273B (zh) * | 2019-04-30 | 2021-01-26 | 中国化学工程第六建设有限公司 | 利用木方进行钢结构地脚螺栓安装的方法 |
CN110130391A (zh) * | 2019-05-31 | 2019-08-16 | 中国五冶集团有限公司 | 独立基础预埋螺栓安装结构和方法 |
CN110409854A (zh) * | 2019-08-30 | 2019-11-05 | 山西五建集团有限公司 | 一种地脚螺栓群集成组装安装模具及方法 |
CN110629782B (zh) * | 2019-09-02 | 2024-03-26 | 中冶天工集团有限公司 | 一种地脚螺栓离线组装装置的调整方法 |
CN111058644A (zh) * | 2019-12-03 | 2020-04-24 | 中启胶建集团有限公司 | 大面积冷库地面密集预埋件超高精度快速施工工艺 |
CN112878712A (zh) * | 2021-03-12 | 2021-06-01 | 安徽三建工程有限公司 | 一种压剪机地脚螺栓预埋安装装置及其施工方法 |
CN113502846A (zh) * | 2021-06-30 | 2021-10-15 | 上海宝冶集团有限公司 | 一种精密地脚螺栓的安装工具及其作业方法 |
CN113859473A (zh) * | 2021-10-27 | 2021-12-31 | 中船黄埔文冲船舶有限公司 | 一种船舶底座安装治具及船舶 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103590416A (zh) * | 2013-11-01 | 2014-02-19 | 浙江水利水电学院 | 高精度地脚螺栓预埋施工工法 |
CN105040717A (zh) * | 2015-07-24 | 2015-11-11 | 中国十九冶集团有限公司 | 地脚螺栓固定支架及安装方法 |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561712B (zh) * | 2012-01-11 | 2014-04-09 | 中国建筑第二工程局有限公司 | 大型钢柱、设备基础固定螺栓精确定位架及其施工方法 |
CN104895101B (zh) * | 2015-06-10 | 2016-08-24 | 杭州江润科技有限公司 | 筏板基础高精度整体预埋大直径螺栓群结构的施工方法 |
CN107178091B (zh) * | 2016-03-10 | 2019-04-23 | 五冶集团上海有限公司 | 罐式煅烧炉钢结构支柱地脚螺栓预埋精确定位的方法 |
CN205591245U (zh) * | 2016-04-08 | 2016-09-21 | 中国一冶集团有限公司 | 群桩高精度整体预埋螺栓定位装置 |
-
2018
- 2018-03-06 CN CN201810182231.7A patent/CN108222056B/zh active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103590416A (zh) * | 2013-11-01 | 2014-02-19 | 浙江水利水电学院 | 高精度地脚螺栓预埋施工工法 |
CN105040717A (zh) * | 2015-07-24 | 2015-11-11 | 中国十九冶集团有限公司 | 地脚螺栓固定支架及安装方法 |
Also Published As
Publication number | Publication date |
---|---|
CN108222056A (zh) | 2018-06-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108222056B (zh) | 设备基础螺栓群安装方法 | |
CN109914462B (zh) | 一种钢柱地脚螺栓预埋的定位支架以及施工方法 | |
CN206986916U (zh) | 一种地脚螺栓的预埋固定装置 | |
CN102619235B (zh) | 混凝土基础预埋螺栓支架及混凝土基础螺栓预埋方法 | |
EP2653630A1 (en) | Mounting base | |
CN203625921U (zh) | 地脚螺栓预埋安装精度控制装置 | |
CN111360978B (zh) | 一种能快速定位及拆除的预制箱梁端模 | |
CN109138457B (zh) | 用于安装装配式建筑的支撑系统及其施工方法 | |
CN116079890B (zh) | 竖向预制构件竖向钢筋定位装置及竖向预制构件加工方法 | |
CN212104166U (zh) | 一种核电站安注箱预埋螺栓精确定位装置 | |
CN113846607B (zh) | 装配式渠槽侧墙的现浇底板中预埋钢筋的精密定位固定装置及施工方法 | |
CN108661329B (zh) | 预制构件的安装支架、含该支架的预制墙体及其安装方法 | |
CN219509211U (zh) | 一种竖向预制构件竖向钢筋定位装置 | |
CN208363650U (zh) | 预制构件的安装支架、含该支架的预制墙体 | |
CN110629782A (zh) | 一种地脚螺栓离线组装装置及其调整方法 | |
CN111438800A (zh) | 一种高速道路上栅栏板的预制模板体系及其施工方法 | |
CN116254730A (zh) | 一种轨道地脚螺栓二次灌浆前的安装调整装置及施工方法 | |
CN217924959U (zh) | 框架结构厂房的钢梁连接预埋底板的准确定位装置 | |
CN110130391A (zh) | 独立基础预埋螺栓安装结构和方法 | |
CN212170795U (zh) | 一种能快速定位及拆除的预制箱梁端模 | |
CN114809672A (zh) | 框架结构厂房的钢梁连接预埋底板的准确定位方法 | |
CN211369584U (zh) | 一种地脚螺栓群集成组装安装模具 | |
CN211499849U (zh) | 预制板施工定位架 | |
CN215671150U (zh) | 一种混凝土一次性成形地面标高控制工具 | |
CA3159340A1 (en) | Anchoring device, anchorage comprising an anchoring device, and method for producing the anchorage |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |