CN108166514A - Greening Retaining Wall construction between stake - Google Patents

Greening Retaining Wall construction between stake Download PDF

Info

Publication number
CN108166514A
CN108166514A CN201810016403.3A CN201810016403A CN108166514A CN 108166514 A CN108166514 A CN 108166514A CN 201810016403 A CN201810016403 A CN 201810016403A CN 108166514 A CN108166514 A CN 108166514A
Authority
CN
China
Prior art keywords
retaining wall
stake
groove profile
side groove
profile web
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810016403.3A
Other languages
Chinese (zh)
Inventor
蒋楚生
李庆海
司文明
贺钢
许颖
邹川
黄献璋
杨飞翔
兰小平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201810016403.3A priority Critical patent/CN108166514A/en
Publication of CN108166514A publication Critical patent/CN108166514A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G25/00Watering gardens, fields, sports grounds or the like
    • A01G25/02Watering arrangements located above the soil which make use of perforated pipe-lines or pipe-lines with dispensing fittings, e.g. for drip irrigation
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G9/00Cultivation in receptacles, forcing-frames or greenhouses; Edging for beds, lawn or the like
    • A01G9/02Receptacles, e.g. flower-pots or boxes; Glasses for cultivating flowers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0266Retaining or protecting walls characterised by constructional features made up of preformed elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Water Supply & Treatment (AREA)
  • Cultivation Receptacles Or Flower-Pots, Or Pots For Seedlings (AREA)

Abstract

Greening Retaining Wall construction, integrates protection and greening between stake, has not only met the security and stability requirement of high gradient slope supporting and retaining system, but also realize greening function.Including the anchor pile set in a row along side slope lateral separation and the retaining wall being set between adjacent two anchor pile.The retaining wall is laterally in a row assembled, longitudinal assembled in column by prefabricated retaining wall module.The prefabricated retaining wall module forms the three-dimensional gridiron structure with plant growth space by plate from plant wastes, squab panel and left side groove profile web, right side groove profile web, and adjacent two arrange setting armored concrete rib column in the vertical cavity formed between the left side groove profile web of prefabricated retaining wall module, right side groove profile web.Vertically it is arranged at intervals anchor pole on the armored concrete rib column, the main body of each anchor pole extends into after retaining wall in Rock And Soil and anchor connection therewith, forepart exposure end are anchored on armored concrete rib column.

Description

Greening Retaining Wall construction between stake
Technical field
It is new more particularly to a kind of stake for having particular/special requirement to greening the present invention relates to Rail Highway high slope rockmass system Type support system.
Technical background
With flourishing for China railways and highway construction cause, occur in process of construction more and more high steep Side slope.Area particularly extremely complex in topography and geomorphology, that geological structure is extremely developed, high gradient slope increase construction and operation Difficulty, while the stability of side slope causes great test.In order to reduce slope height, enhance slope stability, " layering The reinforcing thinking of reinforcing, stable slope foot " is applied to more and more in high slope design work, the combination of wall between stake and stake The project slash of (such as inter-pile soil nail wall, pile plate wall) also comes into being, in order to prevent inter-pile soil body from being squeezed out between stake, Barricade is often built between adjacent studs, forms wall joint reinforcement measure between stake.
In terms of Afforestation Landscape, traditional retaining wall between piles have isolated greening system, and the stiff color of lines is gloomy, gives Thick and heavy, dull feeling;And cast-in-place construction is so that construction and maintenance work are more inconvenient;With the requirement to construction site compared with Harmful effect high, the duration is longer.
In fact, retaining wall between piles, other than it should have basic supporting role, it also belongs to one of landscape simultaneously Point.Many researchs have also been made in domestic and international project technical staff in terms of barricade greening.Trowel used for plastering is carried out for example, by using faced deorative engineering The beautification of work barricade, Fill Reinforced With Geogrids are combined with greening vegetation plants Climbing Plant greening instead of bricklaying barricade, setting planting groove Embedding hole of barricade, barricade etc., however the most artificial trace of these ways is dense, protective capacities reduces, effect is not satisfactory.
Invention content
The technical problems to be solved by the invention are to provide greening Retaining Wall construction between a kind of stake, collection protection with it is green Change the security and stability requirement in one, not only having met high gradient slope supporting and retaining system, but also realize greening function.
The technical solution adopted by the present invention to solve the technical problems is as follows:
Greening Retaining Wall construction between the stake of the present invention, including the anchor pile set in a row along side slope lateral separation, And the retaining wall between adjacent two anchor pile is set to, it is characterized in that:The retaining wall by prefabricated retaining wall module laterally into Row is assembled, longitudinal direction is assembled in column;The prefabricated retaining wall module is by plate from plant wastes, squab panel and left side groove profile web, right side Groove profile web forms the three-dimensional gridiron structure with plant growth space, the left side groove profile abdomen of the prefabricated retaining wall module of adjacent two row Setting armored concrete rib column in the vertical cavity formed between plate, right side groove profile web;It is erected on the armored concrete rib column To being arranged at intervals anchor pole, the main body of each anchor pole extends into after retaining wall in Rock And Soil and anchor connection therewith, forepart exposure end anchor Gu on armored concrete rib column.
The beneficial effects are mainly as follows following aspects:
1st, by carrying out Greening Design to traditional masonry structure, retaining wall between piles is made to form one of green ecological denfense, both The effect on its structure stress has been played, while has given full play to it and afforests aesthetic function, it is made to be organically combined with natural environment, it is real The aesthetic feeling of existing harmony between man and nature;
2nd, assembled barricade wall shortens completion time of project, dry wall using batch production standard is prefabricated, in-site installation construction Body construction quality is easily controllable;
3rd, between stake barricade often across by it is multiple it is small formed across greening assembled barricade, according to soil arching effect after wall, assembled gear The more general retaining wall between piles of wall stress greatly reduce, and further ensure the stability of barricade;
4th, greening assembled barricade utilizes rib intercolumniation anchor pole so that wall and soil body effective connection after wall and anchoring, so as to Wall assumes responsibility for part power, thus stress performance is more excellent, and the more general assembled greening soil blocking wall of structure is safer.
Description of the drawings
This specification includes following ten width attached drawing:
Fig. 1 is the elevation of greening Retaining Wall construction between stake of the present invention;
Fig. 2 is the cross-section diagram of greening Retaining Wall construction between stake of the present invention;
Fig. 3 is prefabricated retaining wall module laterally in a row assembled signal in greening Retaining Wall construction between stake of the present invention Figure;
Fig. 4 is that prefabricated retaining wall module is laterally in a row assembled, vertical in greening Retaining Wall construction between stake of the present invention Assembled stereoscopic schematic diagram in column;
Fig. 5 is the front view of prefabricated retaining wall module in greening Retaining Wall construction between stake of the present invention;
Fig. 6 is the left view of the front view of prefabricated retaining wall module in greening Retaining Wall construction between stake of the present invention;
Fig. 7 is the vertical view of the front view of prefabricated retaining wall module in greening Retaining Wall construction between stake of the present invention;
Fig. 8 is the stereogram of the front view of prefabricated retaining wall module in greening Retaining Wall construction between stake of the present invention;
Fig. 9 is drip irrigation system schematic diagram in greening Retaining Wall construction between stake of the present invention;
Figure 10 is drip irrigation system schematic diagram in greening Retaining Wall construction between stake of the present invention.
Component and corresponding label are shown in figure:Anchor pile 10, armored concrete rib column 11, anchor pole 20, prefabricated retaining wall Module 30, plate from plant wastes 31, squab panel 32, draining window 33, left side groove profile web 34, right side groove profile web 35, hole for hoist 36, dowel 37th, ribbed stiffener 38, pipe clamp 40, main-supply 41, trunk standpipe 42, drip irrigation pipe 43, shutoff valve 44, anchor pole space D 1.
Specific embodiment
The present invention is further described with reference to the accompanying drawings and examples.
Referring to Figures 1 and 2, Retaining Wall construction is afforested between stake of the invention, including in a row along side slope lateral separation The anchor pile 10 of setting and the retaining wall being set between adjacent two anchor pile 10.With reference to Fig. 3 and Fig. 4, the retaining wall by Prefabricated retaining wall module 30 is laterally in a row assembled, longitudinal assembled in column.The prefabricated retaining wall module 30 by plate from plant wastes 31, Squab panel 32 and left side groove profile web 34, right side groove profile web 35 form the three-dimensional gridiron structure with plant growth space.Ginseng According to Fig. 3, adjacent two arrange the vertical sky formed between the left side groove profile web 34 of prefabricated retaining wall module 30, right side groove profile web 35 Intracavitary setting armored concrete rib column 11.With reference to Fig. 2, anchor pole 20, the master of each anchor pole 20 are vertically arranged at intervals on the rib column 11 Body extends into after retaining wall in Rock And Soil and anchor connection therewith, forepart exposure end are anchored on rib column 11.
With reference to Fig. 2, it is a kind of improvement to traditional retaining wall between piles that Retaining Wall is afforested between stake of the present invention.Passing through will Retaining wall between piles and soil nail wall are changed to greening assembled barricade, so as to ensure high gradient slope safety and stability, while fill it again Afforestation Landscape effect is waved in distribution, realizes that retaining wall between piles develop, also, Retaining Wall from simple function to multifunctional direction Construction period, more traditional barricade was short, and quality is more conducive to control.Anchor pole 20 is set on reinforcing rib column 11, after anchor pole 20 is squeezed into wall In the natural soil body, improve stress performance using the effective connection between soil body three after anchor pole, barricade, wall, enhance structure Safety.
With reference to Fig. 5 to Fig. 8, joggle step is provided on the upper and lower end face of the prefabricated retaining wall module 30, makes vertically to spell The contiguous prefabricated retaining wall module 30 of dress will not misplace.The draining window towards side slope surface is opened up on the squab panel 32 33, plate from plant wastes 31 is formed slopely slope surface upwards from the inside to the outside, and planting soil is backfilled in the slope surface, plants green plants.The rear wall Plate 32, plate from plant wastes 31 are horizontally arranged at interval ribbed stiffener 38, and draining window 33 can be used as water body excretion and root system of plant and nature after wall The channel of soil body contact, is conducive to the growth of green plants.It sets and hangs on the left side groove profile web 34, right side groove profile web 35 Hole 36 is filled, and is embedded with dowel 37.
With reference to Fig. 9 and Figure 10, drip irrigation system is provided between adjacent two anchor pile 10, drip irrigation system includes and main-supply The 41 trunk standpipes 42 being connected, vertical interval connection drip irrigation pipe 43 on trunk standpipe 42, each drip irrigation pipe 43 it is logical live laterally in a row The top of the plate from plant wastes 31 of assembled each prefabricated retaining wall module 30, and be embedded in planting soil.When main-supply 41 and city supply When water system is connected, shutoff valve 44 is set between the trunk standpipe 42 and main-supply 41 on trunk standpipe 42.
Some principles of Retaining Wall construction are afforested between the stake of the present invention described above that only explains through diagrams, are not By the present invention be confined to shown in and the concrete structure and the scope of application in, it is therefore every it is possible that is be utilized corresponding repaiies Change and equivalent, belong to the apllied the scope of the claims of the present invention.

Claims (7)

1. Retaining Wall construction is afforested between, including the anchor pile (10) set in a row along side slope lateral separation, Yi Jishe The retaining wall being placed between adjacent two anchor pile (10), it is characterized in that:The retaining wall is lateral by prefabricated retaining wall module (30) It is in a row assembled, longitudinal assembled in column;The prefabricated retaining wall module (30) is by plate from plant wastes (31), squab panel (32) and left side Groove profile web (34), right side groove profile web (35) form the three-dimensional gridiron structure with plant growth space, and adjacent two row are prefabricated Setting reinforcing bar in the vertical cavity formed between the left side groove profile web (34) of retaining wall module (30), right side groove profile web (35) Concrete rib column (11);Anchor pole (20), the main body of each anchor pole (20) are vertically arranged at intervals on the armored concrete rib column (11) It extends into after retaining wall in Rock And Soil and anchor connection therewith, forepart exposure end is anchored on armored concrete rib column (11).
2. Retaining Wall construction is afforested between stake as described in claim 1, it is characterized in that:The prefabricated retaining wall module (30) joggle step is provided on upper and lower end face.
3. Retaining Wall construction is afforested between stake as claimed in claim 2, it is characterized in that:It is opened up on the squab panel (32) Towards the draining window (33) of side slope surface, plate from plant wastes (31) is formed slopely slope surface upwards from the inside to the outside.
4. Retaining Wall construction is afforested between stake as claimed in claim 3, it is characterized in that:The squab panel (32) plants life Plate (31) is horizontally arranged at interval ribbed stiffener (38).
5. Retaining Wall construction is afforested between stake as claimed in claim 3, it is characterized in that:The left side groove profile web (34), hole for hoist (36) on right side groove profile web (35) is set, and is embedded with dowel (37).
6. Retaining Wall construction is afforested between stake as described in claim 1, it is characterized in that:Adjacent two anchor pile (10) Between be provided with drip irrigation system, drip irrigation system includes the trunk standpipe (42) being connected with main-supply (41), trunk standpipe (42) vertically interval connects drip irrigation pipe (43), each prefabricated retaining wall module of the logical firmly lateral in a row assembly of each drip irrigation pipe (43) on (30) top of plate from plant wastes (31).
7. Retaining Wall construction is afforested between stake as described in claim 1, it is characterized in that:The trunk standpipe (42) and master Shutoff valve (44) is set between feed pipe (41) on trunk standpipe (42).
CN201810016403.3A 2018-01-08 2018-01-08 Greening Retaining Wall construction between stake Pending CN108166514A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810016403.3A CN108166514A (en) 2018-01-08 2018-01-08 Greening Retaining Wall construction between stake

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810016403.3A CN108166514A (en) 2018-01-08 2018-01-08 Greening Retaining Wall construction between stake

Publications (1)

Publication Number Publication Date
CN108166514A true CN108166514A (en) 2018-06-15

Family

ID=62517809

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810016403.3A Pending CN108166514A (en) 2018-01-08 2018-01-08 Greening Retaining Wall construction between stake

Country Status (1)

Country Link
CN (1) CN108166514A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867219A (en) * 2018-06-22 2018-11-23 中铁二院(成都)建设发展有限责任公司 A kind of construction method of green roadbed peg board wall construction
CN109356172A (en) * 2018-09-21 2019-02-19 浙江交工集团股份有限公司 Plate column type combined member and its construction method suitable for slope greening
CN109577348A (en) * 2018-11-09 2019-04-05 杭州江润科技有限公司 The construction method of slope retaining structure
CN109653214A (en) * 2019-02-28 2019-04-19 中铁五局集团建筑工程有限责任公司 A kind of construction method of prefabricated rib column and the vertical barricade slope retaining structure of trough plate type
CN110056012A (en) * 2019-04-25 2019-07-26 中铁二院工程集团有限责任公司 The guarded drainage system of prefabricated open caisson structure
CN111206615A (en) * 2020-02-24 2020-05-29 中铁第四勘察设计院集团有限公司 Ecological assembly retaining wall and construction method thereof
CN111656999A (en) * 2020-05-26 2020-09-15 重庆大学 Assembled ecological barricade with rainwater purifies and irrigation system
CN112873506A (en) * 2021-01-13 2021-06-01 中建一局集团第三建筑有限公司 Prefabricated assembly type ecological retaining wall side rib column and construction method thereof
CN115030198A (en) * 2022-07-25 2022-09-09 重庆路投科技有限公司 Assembly type ecological slope protection structure and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007154413A (en) * 2005-11-30 2007-06-21 Marui Kensetsu:Kk Soldier pile type earth retaining anchor type retaining wall and its construction method
CN102282315A (en) * 2009-01-16 2011-12-14 新日本制铁株式会社 Combined steel sheet pile, soil retaining wall formed by combined steel sheet pipe, and method for selecting combined steel sheet pile
CN103243665A (en) * 2013-05-27 2013-08-14 中铁工程设计咨询集团有限公司 Protection method and protection device for blocking deep cutting falling rocks
TWM477477U (en) * 2013-07-10 2014-05-01 qiu-cheng Liao Wall greening device of reinforced retaining wall
CN104404979A (en) * 2014-11-28 2015-03-11 中铁二十三局集团有限公司 H-shaped pile slab wall construction method
CN205116217U (en) * 2015-10-30 2016-03-30 正平路桥建设股份有限公司 Height is filled and is prefabricated cast -in -place combination formula stake siding wall protective structure
CN105625261A (en) * 2015-12-30 2016-06-01 四川宏洲新型材料股份有限公司 Precast concrete block, system and building method of fast-assembled green vegetation retaining wall
CN208219673U (en) * 2018-01-08 2018-12-11 中铁二院工程集团有限责任公司 Greening Retaining Wall construction between stake

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007154413A (en) * 2005-11-30 2007-06-21 Marui Kensetsu:Kk Soldier pile type earth retaining anchor type retaining wall and its construction method
CN102282315A (en) * 2009-01-16 2011-12-14 新日本制铁株式会社 Combined steel sheet pile, soil retaining wall formed by combined steel sheet pipe, and method for selecting combined steel sheet pile
CN103243665A (en) * 2013-05-27 2013-08-14 中铁工程设计咨询集团有限公司 Protection method and protection device for blocking deep cutting falling rocks
TWM477477U (en) * 2013-07-10 2014-05-01 qiu-cheng Liao Wall greening device of reinforced retaining wall
CN104404979A (en) * 2014-11-28 2015-03-11 中铁二十三局集团有限公司 H-shaped pile slab wall construction method
CN205116217U (en) * 2015-10-30 2016-03-30 正平路桥建设股份有限公司 Height is filled and is prefabricated cast -in -place combination formula stake siding wall protective structure
CN105625261A (en) * 2015-12-30 2016-06-01 四川宏洲新型材料股份有限公司 Precast concrete block, system and building method of fast-assembled green vegetation retaining wall
CN208219673U (en) * 2018-01-08 2018-12-11 中铁二院工程集团有限责任公司 Greening Retaining Wall construction between stake

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867219A (en) * 2018-06-22 2018-11-23 中铁二院(成都)建设发展有限责任公司 A kind of construction method of green roadbed peg board wall construction
CN109356172A (en) * 2018-09-21 2019-02-19 浙江交工集团股份有限公司 Plate column type combined member and its construction method suitable for slope greening
CN109577348A (en) * 2018-11-09 2019-04-05 杭州江润科技有限公司 The construction method of slope retaining structure
CN109653214A (en) * 2019-02-28 2019-04-19 中铁五局集团建筑工程有限责任公司 A kind of construction method of prefabricated rib column and the vertical barricade slope retaining structure of trough plate type
CN110056012A (en) * 2019-04-25 2019-07-26 中铁二院工程集团有限责任公司 The guarded drainage system of prefabricated open caisson structure
CN110056012B (en) * 2019-04-25 2024-03-22 中铁二院工程集团有限责任公司 Waterproof and drainage system of prefabricated open caisson structure
CN111206615A (en) * 2020-02-24 2020-05-29 中铁第四勘察设计院集团有限公司 Ecological assembly retaining wall and construction method thereof
CN111656999A (en) * 2020-05-26 2020-09-15 重庆大学 Assembled ecological barricade with rainwater purifies and irrigation system
CN112873506A (en) * 2021-01-13 2021-06-01 中建一局集团第三建筑有限公司 Prefabricated assembly type ecological retaining wall side rib column and construction method thereof
CN115030198A (en) * 2022-07-25 2022-09-09 重庆路投科技有限公司 Assembly type ecological slope protection structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN108166514A (en) Greening Retaining Wall construction between stake
CN103430731B (en) Method and architectural structure for virescence on rock mountain body
CN105756073B (en) A kind of ion type rareearth mine ecological slope protection building block and its ecological revetment system
CN110249813B (en) Method for greening high and steep rocky slope in mining pit
CN109594567A (en) A kind of shotcrete protection rock slope ecological safeguard structure arrangement and its method
CN110241849A (en) A kind of assembled concrete case retaining wall and its construction method
CN103437370A (en) Method and supporting structure for slip resisting and soil retaining of abrupt slope
CN109168385A (en) A kind of high precipitous rock slope Ecosystem restoration system and implementation method
CN109594568A (en) A kind of rock slope ecological safeguard structure and its method
CN206693140U (en) A kind of protection slope
CN208219673U (en) Greening Retaining Wall construction between stake
CN106120822B (en) A kind of method for protecting support and device that prevent mud stone from coming down
CN205369297U (en) Hollow building block formula barricade with prop up and keep off and afforest function
CN206607602U (en) A kind of new prefabricated section and new type of retaining system
CN109898552A (en) Composite ecotype retaining wall
CN206873395U (en) A kind of ecological revetment dike
CN210827555U (en) Ecological reinforced earth retaining wall slope protection that red mudstone packed
CN205776070U (en) Ecological revetment is combined retaining wall structure
CN210658432U (en) Assembled concrete box retaining wall
CN108867668B (en) Ecological retaining plate structure
CN216475115U (en) Recyclable slope lamination green protection grid
CN206143783U (en) Prevent supporting device on mud stone landslide
CN210621615U (en) Have drainage and afforestation function's ecological slope protection structure of frame lattice roof beam concurrently
CN213203979U (en) River course gravity type concrete flood control wall ecological reconstruction structure
CN110965577B (en) Construction method of chain lock type ecological block retaining wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180615

WD01 Invention patent application deemed withdrawn after publication