CN205776070U - Ecological revetment is combined retaining wall structure - Google Patents

Ecological revetment is combined retaining wall structure Download PDF

Info

Publication number
CN205776070U
CN205776070U CN201620542839.2U CN201620542839U CN205776070U CN 205776070 U CN205776070 U CN 205776070U CN 201620542839 U CN201620542839 U CN 201620542839U CN 205776070 U CN205776070 U CN 205776070U
Authority
CN
China
Prior art keywords
retaining wall
foundation
ecological
stepped
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620542839.2U
Other languages
Chinese (zh)
Inventor
闫慧玉
黄道宏
汪斌
廖律宾
杨荣华
马雅文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changjiang Institute of Survey Planning Design and Research Co Ltd
Original Assignee
Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changjiang Institute of Survey Planning Design and Research Co Ltd filed Critical Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority to CN201620542839.2U priority Critical patent/CN205776070U/en
Application granted granted Critical
Publication of CN205776070U publication Critical patent/CN205776070U/en
Anticipated expiration legal-status Critical
Active legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Revetment (AREA)

Abstract

本实用新型公开了一种生态护坡复合挡土墙结构,包括沿库岸边坡修建的生态陡坡和基础挡土墙,所述生态陡坡位于正常蓄水位以上,所述基础挡土墙位于正常蓄水位以下;所述基础挡土墙包括挡土墙台阶式基础和挡土墙墙身,所述挡土墙墙身位于挡土墙台阶式基础之上,所述挡土墙台阶式基础置于基槽开挖线下的中风化基岩上。本实用新型能够适用于水位变幅较大、边坡较陡的地质条件;其不但占用水库防洪库容较小,而且还可以长期浸泡在水中。

The utility model discloses an ecological slope protection compound retaining wall structure, which comprises an ecological steep slope and a foundation retaining wall built along the reservoir bank slope, the ecological steep slope is located above the normal water storage level, and the foundation retaining wall is located at the normal Below the water storage level; the foundation retaining wall includes a stepped foundation of the retaining wall and a wall body of the retaining wall, the body of the retaining wall is located on the stepped foundation of the retaining wall, and the stepped foundation of the retaining wall Placed on moderately weathered bedrock below the trench excavation line. The utility model can be applied to geological conditions with large water level fluctuations and steep slopes; it not only occupies a small flood control storage capacity of the reservoir, but also can be soaked in water for a long time.

Description

生态护坡复合挡土墙结构Composite retaining wall structure for ecological slope protection

技术领域technical field

本实用新型涉及边坡支挡结构,具体的指一种生态护坡复合挡土墙结构。The utility model relates to a side slope retaining structure, in particular to an ecological slope protection compound retaining wall structure.

背景技术Background technique

在水利水电工程中,为满足防洪和发电需要,一般水库的水位变幅较大,并且水库的防洪库容不能侵占较多;对于山区型库区,库岸边坡较陡。因此,在库区的城集镇沿江修建道路,会受到水库水位变幅大、库岸地质条件较差和水库防洪库容限制等多种因素的影响。所以在库区临江区域选择合适的道路路基支挡措施显得十分重要。In water conservancy and hydropower projects, in order to meet the needs of flood control and power generation, the water level of the general reservoir varies greatly, and the flood control storage capacity of the reservoir cannot be encroached on much; for mountainous reservoir areas, the slope of the reservoir bank is steep. Therefore, the construction of roads along the river in Chengji towns in the reservoir area will be affected by various factors such as large fluctuations in the water level of the reservoir, poor geological conditions on the banks of the reservoir, and limited flood control capacity of the reservoir. Therefore, it is very important to choose appropriate road subgrade support measures in the riverside area of the reservoir area.

在传统的支挡结构中,非加强筋回填放坡支护需要的土石方回填量较大,工程占地较多,因此会占用水库防洪库容较大,对行洪影响较大;加强筋回填放坡虽然可以运用在较陡的坡岸上,占用水库防洪库容较小,但是由于长期浸泡其耐水性较差,因此对于水库临江区域适用性较差;传统的植物护面抗冲刷能力较差,并且不宜应用于较陡和长期浸水的边坡;传统挡土墙支护墙体结构尺寸较大、并且造价高,虽然稳固,但是城市景观效果较差,对于水库临江区域适用性也较差。In the traditional retaining structure, backfilling with non-reinforcing ribs requires a large amount of earth and stone backfilling, and the project occupies a large area, so it will occupy a large flood control storage capacity of the reservoir and have a great impact on flood discharge; Although slopes can be used on steep slope banks and occupy a small reservoir capacity for flood control, they have poor water resistance due to long-term immersion, so they are not suitable for the riverside area of the reservoir; traditional plant protection has poor erosion resistance. And it is not suitable for steep and long-term flooded slopes; the traditional retaining wall support wall structure is large in size and high in cost. Although it is stable, the urban landscape effect is poor, and the applicability to the riverside area of the reservoir is also poor. .

综上所述,在水库临江区域需要建设一种边坡支挡结构,其不但可以适用于较陡的边坡,并且占用水库防洪库容较小,还能够长期浸泡在水中。另外对于上述边坡支挡结构,其耐冲刷能力和抗雨水能力要好,最好还可以提高城市景观效果。To sum up, it is necessary to build a slope retaining structure in the riverside area of the reservoir, which can not only be applied to steeper slopes, but also occupy a small flood control storage capacity of the reservoir, and can also be immersed in water for a long time. In addition, for the above-mentioned slope retaining structure, its erosion resistance and rain resistance are better, and it is better to improve the urban landscape effect.

发明内容Contents of the invention

本实用新型的目的就是要提供一种生态护坡复合挡土墙结构,能够适用于水位变幅较大、边坡较陡的地质条件;其不但占用水库防洪库容较小,而且还可以长期浸泡在水中。The purpose of this utility model is to provide an ecological slope protection composite retaining wall structure, which can be applied to geological conditions with large water level fluctuations and steep slopes; it not only occupies a small flood control storage capacity of the reservoir, but also can be soaked in in the water.

为实现上述目的,本实用新型设计的生态护坡复合挡土墙结构,包括沿库岸边坡修建的生态陡坡和基础挡土墙,其特殊之处在于:所述生态陡坡位于正常蓄水位以上,所述基础挡土墙位于正常蓄水位以下;所述基础挡土墙包括挡土墙台阶式基础和挡土墙墙身,所述挡土墙墙身位于挡土墙台阶式基础之上,所述挡土墙台阶式基础置于基槽开挖线下的中风化基岩上。In order to achieve the above purpose, the ecological slope protection composite retaining wall structure designed by the utility model includes an ecological steep slope and a foundation retaining wall built along the reservoir bank slope, and its special feature is that the ecological steep slope is located above the normal water storage level , the foundation retaining wall is located below the normal water storage level; the foundation retaining wall includes a stepped foundation of the retaining wall and a wall body of the retaining wall, and the body of the retaining wall is located on the stepped foundation of the retaining wall , the stepped foundation of the retaining wall is placed on the moderately weathered bedrock below the excavation line of the foundation trench.

进一步地,所述生态陡坡由多层填料分层回填碾压而成,所述相邻的两层填料之间铺设有土工格栅。Further, the ecological steep slope is formed by layered backfilling and rolling of multiple layers of fillers, and a geogrid is laid between the two adjacent layers of fillers.

更进一步地,所述多层填料的临水侧回填形成阶梯式坡面,所述每层填料的临水侧都并排设置有多个L型面板;所述每个L型面板的长边都插入对应的相邻两层填料之间,所述每个L型面板的短边朝上;所述每个L型面板的短边与对应一层填料的临水侧之间填充有耕植土,所述每层耕植土内种有植物,所述每层植物组成植生护面。Furthermore, the backfilling of the water-facing side of the multi-layer packing forms a stepped slope, and multiple L-shaped panels are arranged side by side on the water-facing side of each layer of packing; the long sides of each L-shaped panel are Insert between corresponding adjacent two layers of fillers, the short side of each L-shaped panel faces upwards; the short side of each L-shaped panel and the water side of the corresponding layer of fillers are filled with cultivated soil , plants are planted in each layer of cultivated soil, and each layer of plants forms a vegetation protection surface.

再进一步地,所述每层耕植土上面都铺设有碎石。Still further, crushed stones are laid on each layer of cultivated soil.

在上述技术方案中,所述基础挡土墙还包括石渣填料,所述石渣填料位于生态陡坡的下方,设置在挡土墙墙身与基槽开挖线之间。In the above technical solution, the foundation retaining wall further includes gravel filler, and the gravel filler is located below the ecological steep slope and arranged between the body of the retaining wall and the excavation line of the foundation trench.

进一步地,所述挡土墙墙身内设置有多个排水孔,所述每个排水孔都连通挡土墙墙身靠近水域的外侧和靠近基槽开挖线的内侧。Further, the retaining wall body is provided with a plurality of drain holes, and each drain hole connects the outer side of the retaining wall body close to the water area and the inner side close to the excavation line of the foundation trench.

更进一步地,所述石渣填料与挡土墙台阶式基础之间填充有粘土,所述粘土位于挡土墙墙身与基槽开挖线之间;所述石渣填料与生态陡坡之间设置有粘土隔水层。Furthermore, clay is filled between the gravel filler and the stepped foundation of the retaining wall, and the clay is located between the wall body of the retaining wall and the excavation line of the foundation trench; between the gravel filler and the ecological steep slope Set with clay water barrier.

再进一步地,所述挡土墙墙身与石渣填料之间设置有反滤层。Still further, a reverse filter layer is arranged between the retaining wall body and the gravel filler.

还进一步地,所述挡土墙台阶式基础通过锚杆沿基槽开挖线分级锚固。Still further, the stepped foundation of the retaining wall is anchored in stages along the excavation line of the foundation groove through anchor rods.

又进一步地,所述挡土墙台阶式基础靠近水域的外侧回填有原土。Still further, the outer side of the stepped foundation of the retaining wall near the water area is backfilled with original soil.

在本实用新型所设计的生态护坡复合挡土墙结构中,分为生态陡坡和基础挡土墙,由于生态陡坡不宜长时间浸泡在水中,所以将其设置在正常蓄水位以上,而将基础挡土墙设置在正常蓄水位以下,可以长期浸泡在水中。传统的放坡结构都需要回填至与岸坡表面相交处,对于较陡的岸坡,放坡坡脚较远,这样的结构则会占用防洪库容较大。所以在本实用新型中,将基础挡土墙设置在岸坡上,其中挡土墙台阶式基础建设在中风化基岩之上,这样的结构不但占用防洪库容较小,还能够减小水库蓄水对工程施工的影响。基础挡土墙包括挡土墙台阶式基础和挡土墙墙身,挡土墙墙身设置在挡土墙台阶式基础之上。在挡土墙墙身下设置挡土墙台阶式基础不但可以使整个挡土墙结构稳固,而且在边坡较陡的地质条件下,挡土墙台阶式基础能够更好地与地形相适应,减小挡土墙的结构尺寸。生态陡坡与基础挡土墙的结合,使整个支挡结构占用防洪库容较小,效益较好。In the ecological slope protection composite retaining wall structure designed by the utility model, it is divided into an ecological steep slope and a foundation retaining wall. Since the ecological steep slope should not be soaked in water for a long time, it is set above the normal water storage level, and the foundation The retaining wall is set below the normal water storage level and can be soaked in water for a long time. Traditional grading structures need to be backfilled to the intersection with the bank slope surface. For steeper bank slopes, the toe of the grading is far away, and such a structure will occupy a large flood control storage capacity. Therefore, in the utility model, the foundation retaining wall is arranged on the bank slope, wherein the stepped foundation of the retaining wall is built on the moderately weathered bedrock. The impact of water on engineering construction. The basic retaining wall includes a stepped foundation of the retaining wall and a body of the retaining wall, and the body of the retaining wall is arranged on the stepped foundation of the retaining wall. Setting the stepped foundation of the retaining wall under the retaining wall can not only make the whole structure of the retaining wall stable, but also under the geological conditions of steep slope, the stepped foundation of the retaining wall can better adapt to the terrain. Reduce the structural size of the retaining wall. The combination of the ecological steep slope and the foundation retaining wall makes the entire retaining structure occupy less flood control storage capacity and have better benefits.

在本实用新型中,生态陡坡由多层填料分层回填碾压而成,相邻的两层填料之间铺设有土工格栅。土工格栅能与填料之间能产生较好的摩擦和咬合作用,从而为填料提供横向拉力。当填料发生形变时,土工格栅将产生横向拉力,阻止填料进一步形变发展,从而可以提高生态陡坡自身的稳定性,并减少生态陡坡下方基础挡土墙所受的土压力,最终提高生态护坡复合挡土墙结构的稳定性。In the utility model, the ecological steep slope is formed by layered backfilling and rolling of multiple layers of fillers, and geogrids are laid between adjacent two layers of fillers. The geogrid can produce better friction and bite action between the filler and the filler, thus providing lateral tension for the filler. When the filler deforms, the geogrid will generate lateral tension to prevent further deformation and development of the filler, thereby improving the stability of the ecological steep slope itself, reducing the earth pressure on the foundation retaining wall under the ecological steep slope, and ultimately improving the ecological slope protection. Stability of retaining wall structures.

L型面板不但使生态陡坡的坡面稳固,而且还为铺设植生护面提供了基础。用传统方法铺设植物护面时,一般是将草皮、灌木等植物直接种植在坡面上。受雨水或洪水冲刷时,沿坡面种植的植物容易被水流冲刷带走,抗冲刷能力较差。然而在本实用新型中,生态陡坡的坡面为阶梯式坡面,在每层L型面板临水侧的填料上种植植物,形成植生护面。L型面板的长边插入两层填料之间,短边朝上,所以每层耕植土都是水平方向设置的,由此每层耕植土内的植物都是水平方向种植。上述结构形成植生护面是沿阶梯状的平面种植,所以抗冲刷能力较好。每层耕植土上面铺设的碎石是为了更好防止耕植土流失,进一步提高植生护面的抗冲刷能力。The L-shaped panel not only stabilizes the slope of the ecological steep slope, but also provides a foundation for laying the vegetation protection surface. When using traditional methods to lay plant protection, plants such as turf and shrubs are usually planted directly on the slope. When washed by rain or flood, the plants planted along the slope are easy to be washed away by the water flow, and the anti-scouring ability is poor. However, in the present utility model, the slope of the ecological steep slope is a stepped slope, and plants are planted on the filler on the water side of each layer of L-shaped panels to form a vegetation protection surface. The long side of the L-shaped panel is inserted between the two layers of fillers, and the short side faces upwards, so each layer of cultivated soil is arranged horizontally, so that the plants in each layer of cultivated soil are planted horizontally. The vegetation protective surface formed by the above structure is planted along the stepped plane, so the anti-scouring ability is better. The gravel laid on each layer of cultivated soil is to better prevent the loss of cultivated soil and further improve the anti-scouring ability of the vegetation protection surface.

在挡土墙墙身后采用石渣填料回填,提高了填料的强度,从而减小了基础挡土墙的所受的土压力,有利于减小挡土墙墙身的结构尺寸。在挡土墙墙身内设置排水孔和墙后设置反滤层,可以有效排出墙后地下水,减小地下水对挡土墙墙身稳定性的影响。石渣填料与挡土墙台阶式基础之间填充有粘土,防止石渣填料内的地下水向下渗入挡土墙台阶式基础内影响挡土墙台阶式基础的稳定性。石渣填料与生态陡坡之间设置的粘土隔水层是为了将生态陡坡内的地下水直接排入外侧水域,防止地下水向下流入石渣填料内而影响挡土墙墙身的稳定性。Backfilling with gravel filler behind the retaining wall increases the strength of the filler, thereby reducing the earth pressure on the foundation retaining wall, which is beneficial to reducing the structural size of the retaining wall. Setting drainage holes in the wall body of the retaining wall and setting a reverse filter layer behind the wall can effectively drain the groundwater behind the wall and reduce the influence of groundwater on the stability of the wall body of the retaining wall. Clay is filled between the gravel filler and the stepped foundation of the retaining wall to prevent groundwater in the gravel filler from penetrating downward into the stepped foundation of the retaining wall and affecting the stability of the stepped foundation of the retaining wall. The clay water-resisting layer set between the gravel fill and the ecological steep slope is to discharge the groundwater in the ecological steep slope directly into the outer waters, preventing groundwater from flowing downward into the gravel fill and affecting the stability of the retaining wall.

挡土墙台阶式基础内的锚杆使挡土墙台阶式基础更稳定地与岸坡岩层结合。在挡土墙台阶式基础的临水侧回填有原土。当水库水位下降时,基础挡土墙部分会露出,将原土回填至挡墙台阶式接触的外侧,不仅使挡土墙结构美观,而且还提供了一个亲水平台。在本实用新型所述的挡土墙结构施工完成后,不仅可以在基础挡土墙墙顶马道上形成人行道路,还可以在回填的原土上形成人行道路。这样在水位较低时,人们也可以在靠近水域的区域活动。The anchor rods in the stepped foundation of the retaining wall make the stepped foundation of the retaining wall more stably combined with the bank slope rock formation. The water side of the stepped foundation of the retaining wall is backfilled with original soil. When the water level of the reservoir drops, part of the foundation retaining wall will be exposed, and the original soil will be backfilled to the outside of the stepped contact of the retaining wall, which not only makes the structure of the retaining wall beautiful, but also provides a hydrophilic platform. After the construction of the retaining wall structure described in the utility model is completed, not only a sidewalk can be formed on the horseway on the top of the foundation retaining wall, but also a sidewalk can be formed on the backfilled original soil. In this way, when the water level is low, people can also move around the area close to the water.

综上所述,本实用新型所设计的生态护坡复合挡土墙结构具有以下优点:In summary, the ecological slope protection composite retaining wall structure designed by the utility model has the following advantages:

1、能够适用于水位变幅较大、边坡较陡的地质条件;1. It can be applied to geological conditions with large water level fluctuations and steep slopes;

2、占用水库防洪库容较小;2. The flood control storage capacity of the reservoir is small;

3、可以长期浸泡在水中;3. Can be soaked in water for a long time;

4、形成的植生护面外形美观、抗冲刷能力好;4. The formed vegetation protection surface has beautiful appearance and good erosion resistance;

5、结构稳固,造价低,实用性强。5. The structure is stable, the cost is low, and the practicability is strong.

附图说明Description of drawings

图1为本实用新型的剖视结构示意图。Fig. 1 is a schematic cross-sectional structure diagram of the utility model.

图2为本实用新型中生态陡坡临水侧的剖视放大结构示意图。Fig. 2 is a cross-sectional enlarged structural schematic diagram of the water side of the ecological steep slope in the utility model.

图中:挡土墙台阶式基础1、锚杆2、挡土墙墙身3、粘土4、排水孔5、反滤层6、石渣填料7、粘土隔水层8、土工格栅9、填料10、L型面板11、原地面线12、原土13、基槽开挖线14、耕植土15。In the figure: stepped foundation of retaining wall 1, anchor rod 2, wall body of retaining wall 3, clay 4, drainage hole 5, reverse filter layer 6, gravel filling 7, clay water-resistant layer 8, geogrid 9, Filler 10, L-shaped panel 11, original ground line 12, original soil 13, foundation trench excavation line 14, cultivated soil 15.

具体实施方式detailed description

下面结合附图详细说明本实用新型的实施情况,但它并不构成对本实用新型的限定,仅做举例而已。同时通过说明,本实用新型的优点将变得更加清楚和容易理解。The implementation of the utility model will be described in detail below in conjunction with the accompanying drawings, but it does not constitute a limitation of the utility model, and it is only used as an example. At the same time, through explanation, the advantages of the utility model will become clearer and easier to understand.

如图1所示,本实用新型所述的生态护坡复合挡土墙结构沿水库库岸边坡修建,包括生态陡坡和建造在生态陡坡之下的基础挡土墙。生态陡坡在正常蓄水位以上,基础挡土墙在正常蓄水位以下。基础挡土墙包括挡土墙台阶式基础1、挡土墙墙身3和石渣填料7。挡土墙台阶式基础1设置在整个挡土墙结构的最下部,位于挡土墙墙身3之下、中风化基岩之上,通过锚杆2沿基槽开挖线14锚固。在挡土墙台阶式基础1的临水侧回填有原土13。设置在挡土墙台阶式基础1之上的挡土墙墙身3为衡重式挡土墙墙身(也可为扶臂式挡土墙墙身、悬臂式挡土墙墙身等),在挡土墙墙身3后面采用石渣填料7回填,使石渣填料7填满于挡土墙墙身3与基槽开挖线14之间。在石渣填料7与挡土墙台阶式基础1之间利用粘土4进行封堵,防止石渣填料7内的地下水下渗至挡土墙台阶式基础1。挡土墙墙身3内设置有多个排水孔5,每个排水孔5都将挡土墙墙身3靠近石渣填料7的内侧与靠近水域的外侧连通,使石渣填料7内的地下水流出。在挡土墙墙身3与石渣填料7之间设置有防止石渣进入排水孔5的反滤层6。在石渣填料7和生态陡坡之间铺设有粘土隔水层8,使生态陡坡与基础挡土墙隔开,防止生态陡坡内的地下水下渗入基础挡土墙内。As shown in Figure 1, the ecological slope protection composite retaining wall structure described in the utility model is built along the bank slope of the reservoir, including the ecological steep slope and the foundation retaining wall built under the ecological steep slope. The ecological steep slope is above the normal water storage level, and the foundation retaining wall is below the normal water storage level. The foundation retaining wall includes a stepped foundation 1 of the retaining wall, a body of the retaining wall 3 and a gravel filler 7 . The stepped foundation 1 of the retaining wall is set at the bottom of the entire retaining wall structure, under the retaining wall body 3 and above the weathered bedrock, and is anchored along the excavation line 14 of the foundation groove by the anchor rod 2 . Original soil 13 is backfilled on the water-facing side of the stepped foundation 1 of the retaining wall. The retaining wall body 3 arranged on the stepped foundation 1 of the retaining wall is a counterweight type retaining wall body (also can be a buttress type retaining wall body, a cantilever type retaining wall body, etc.), The backfill of the retaining wall body 3 is backfilled with gravel filler 7 so that the gravel filler 7 is filled between the retaining wall body 3 and the excavation line 14 of the foundation trench. Clay 4 is used to seal between the gravel filler 7 and the stepped foundation 1 of the retaining wall, so as to prevent groundwater in the gravel filler 7 from infiltrating into the stepped foundation 1 of the retaining wall. The retaining wall body 3 is provided with a plurality of drain holes 5, and each drain hole 5 connects the inner side of the retaining wall body 3 near the gravel filler 7 with the outer side near the water area, so that the groundwater in the gravel filler 7 flow out. Between the wall body 3 of the retaining wall and the gravel filler 7, an anti-filter layer 6 for preventing the gravel from entering the drainage hole 5 is arranged. A clay water-resisting layer 8 is laid between the gravel filling 7 and the ecological steep slope to separate the ecological steep slope from the foundation retaining wall and prevent underground water in the ecological steep slope from infiltrating into the foundation retaining wall.

如图2所示,生态陡坡由多层填料10分层回填碾压而成,填料10靠近水面的一侧堆叠形成阶梯式坡面,坡比为1:0.5-1:1。填料10为碎石,在相邻两层填料10之间铺设有一层土工格栅9。土工格栅9由坡面的一侧延伸至靠近基槽开挖线14的一侧。相邻两侧土工格栅9之间的层间距为0.3-0.6m。每层填料10的临水侧都并排设置有多个L型面板11。L型面板采用钢筋砼结构,长度取30~50cm,厚度8~12cm,高度和宽度可根据边坡坡度进行调整,侧边设置凹凸状卡槽。在同一层内的相邻两个L型面板11之间通过设置在L型面板11两侧的凹凸状卡槽配合连接,增加了L型面板11整体的紧固性。每个L型面板11的长边都插入对应的相邻两层填料10之间,其短边都朝上。每个L型面板11的短边与对应一层填料10的临水侧之间填充有耕植土15。每层耕植土15内种有植物,每层植物组成植生护面16。在每层耕植土15上都铺设有碎石。As shown in Figure 2, the ecological steep slope is formed by layered backfilling and rolling of multiple layers of filler 10. The side of the filler 10 close to the water surface is stacked to form a stepped slope with a slope ratio of 1:0.5-1:1. The filler 10 is gravel, and a layer of geogrid 9 is laid between two adjacent layers of filler 10 . The geogrid 9 extends from one side of the slope to the side close to the excavation line 14 of the foundation trench. The layer spacing between the geogrids 9 on adjacent sides is 0.3-0.6m. A plurality of L-shaped panels 11 are arranged side by side on the water side of each layer of packing 10 . The L-shaped panel adopts reinforced concrete structure, the length is 30-50cm, the thickness is 8-12cm, the height and width can be adjusted according to the slope, and the side is provided with concave-convex grooves. Two adjacent L-shaped panels 11 in the same layer are fitted and connected through concave-convex grooves provided on both sides of the L-shaped panels 11 , which increases the overall fastness of the L-shaped panels 11 . The long sides of each L-shaped panel 11 are inserted between corresponding two adjacent layers of fillers 10, and the short sides thereof all face upward. Cultivation soil 15 is filled between the short side of each L-shaped panel 11 and the water-facing side of a corresponding layer of filler 10 . Plants are planted in each layer of cultivated soil 15, and each layer of plants forms a vegetation protection surface 16. On every layer of cultivated soil 15, gravel is all paved.

生态护坡复合挡土墙结构在工程施工过程中,分为基础挡土墙工程和生态陡坡工程两个部分,具体施工步骤如下:During the construction process of the ecological slope protection composite retaining wall structure, it is divided into two parts: the basic retaining wall project and the ecological steep slope project. The specific construction steps are as follows:

步骤一、将原地面线12开挖形成基槽开挖线14,基槽开挖线14靠近岩土分界线,同时实施锚杆2;完成后,浇筑挡土墙台阶式基础1,锚杆2采用全长粘结型水泥砂浆锚杆,钻孔孔向水平下倾15°,锚孔直径75mm;Step 1. Excavate the original ground line 12 to form the excavation line 14 of the foundation trench. The excavation line 14 of the foundation trench is close to the rock-soil boundary line, and implement the anchor bolt 2 at the same time; after completion, pour the stepped foundation 1 of the retaining wall, and the anchor bolt 2 Use full-length bonded cement mortar anchor rod, the drilled hole is inclined 15° to the horizontal, and the diameter of the anchor hole is 75mm;

步骤二、浇筑挡土墙台阶式基础1完成后,实施浇筑挡土墙墙身3并埋设排水孔5,排水孔5采用φ100PVC管,间距2×2m,上下交错设置;Step 2. After pouring the stepped foundation 1 of the retaining wall, pour the retaining wall body 3 and bury the drain hole 5. The drain hole 5 uses a φ100 PVC pipe with a spacing of 2×2m and is arranged staggered up and down;

步骤三、浇筑挡土墙墙身3达到一定的高度,可实施粘土4回填,同时可进行原土13回填;Step 3: pouring the wall body 3 of the retaining wall to a certain height, the clay 4 can be backfilled, and the original soil 13 can be backfilled at the same time;

步骤四、完成挡土墙墙身3浇筑后,实施反滤层6和石渣填料7的回填,排水反滤层6采用厚度为50cm、外包土工布的碎石组成;Step 4: After the retaining wall body 3 is poured, backfill the anti-filter layer 6 and the gravel filler 7, and the drainage anti-filter layer 6 is composed of crushed stones with a thickness of 50 cm and an outsourcing geotextile;

步骤五、在石渣填料7的上部铺设粘土隔水层8,至此第一部分的基础挡土墙工程完成;Step 5, lay clay water-resisting layer 8 on the top of gravel filling 7, so far the foundation retaining wall project of the first part is completed;

步骤六、基础挡土墙工程完成后,开始生态陡坡工程;同步进行土工格栅9地铺设、填料10地回填和L型面板11地安设,然后在L型面板11上植草或种植低矮灌木,从而形成植生护面16。Step 6. After the basic retaining wall project is completed, start the ecological steep slope project; simultaneously carry out the laying of geogrid 9, the backfill of filler 10 and the installation of L-shaped panel 11, and then plant grass or plant low-rise on the L-shaped panel 11 Shrubs, thereby forming the vegetation cover 16.

其余未详述部分为现有技术。Other unspecified parts are prior art.

Claims (10)

1.一种生态护坡复合挡土墙结构,包括沿库岸边坡修建的生态陡坡和基础挡土墙,其特征在于:所述生态陡坡位于正常蓄水位以上,所述基础挡土墙位于正常蓄水位以下;所述基础挡土墙包括挡土墙台阶式基础(1)和挡土墙墙身(3),所述挡土墙墙身(3)位于挡土墙台阶式基础(1)之上,所述挡土墙台阶式基础(1)置于基槽开挖线(14)下的中风化基岩上。1. A composite retaining wall structure for ecological slope protection, comprising an ecological steep slope and a foundation retaining wall built along the bank slope of the reservoir, characterized in that: the ecological steep slope is located above the normal water storage level, and the foundation retaining wall is located at Below the normal water storage level; the foundation retaining wall includes a stepped foundation (1) and a retaining wall body (3), and the retaining wall body (3) is located at the stepped foundation of the retaining wall ( 1), the stepped foundation (1) of the retaining wall is placed on the moderately weathered bedrock under the excavation line (14) of the foundation trench. 2.根据权利要求1所述的生态护坡复合挡土墙结构,其特征在于:所述生态陡坡由多层填料(10)分层回填碾压而成,所述相邻的两层填料(10)之间铺设有土工格栅(9)。2. The ecological slope protection composite retaining wall structure according to claim 1, characterized in that: the ecological steep slope is formed by layered backfilling and rolling of multiple layers of fillers (10), and the adjacent two layers of fillers (10) ) is laid with a geogrid (9). 3.根据权利要求2所述的生态护坡复合挡土墙结构,其特征在于:所述多层填料(10)的临水侧回填形成阶梯式坡面,所述每层填料(10)的临水侧都并排设置有多个L型面板(11);3. The ecological slope protection composite retaining wall structure according to claim 2, characterized in that: the backfilling of the water-facing side of the multi-layer filler (10) forms a stepped slope, and the adjacent surface of each layer of filler (10) Multiple L-shaped panels (11) are arranged side by side on the water side; 所述每个L型面板(11)的长边都插入对应的相邻两层填料(10)之间,所述每个L型面板(11)的短边朝上;The long sides of each of the L-shaped panels (11) are inserted between corresponding adjacent two layers of fillers (10), and the short sides of each of the L-shaped panels (11) face upward; 所述每个L型面板(11)的短边与对应一层填料(10)的临水侧之间填充有耕植土(15),所述每层耕植土(15)内种有植物,所述每层植物组成植生护面(16)。Cultivation soil (15) is filled between the short side of each L-shaped panel (11) and the water-facing side of the corresponding layer of filler (10), and plants are planted in each layer of cultivation soil (15) , the plants of each layer form the vegetation protection (16). 4.根据权利要求3所述的生态护坡复合挡土墙结构,其特征在于:所述每层耕植土(15)上面都铺设有碎石。4. The ecological slope protection composite retaining wall structure according to claim 3, characterized in that: gravel is laid on each layer of cultivated soil (15). 5.根据权利要求1至4中任一项所述的生态护坡复合挡土墙结构,其特征在于:所述基础挡土墙还包括石渣填料(7),所述石渣填料(7)位于生态陡坡的下方,设置在挡土墙墙身(3)与基槽开挖线(14)之间。5. The ecological slope protection composite retaining wall structure according to any one of claims 1 to 4, characterized in that: the foundation retaining wall also includes gravel filler (7), and the gravel filler (7) It is located below the steep ecological slope and is arranged between the retaining wall body (3) and the excavation line (14) of the foundation trench. 6.根据权利要求5所述的生态护坡复合挡土墙结构,其特征在于:所述挡土墙墙身(3)内设置有多个排水孔(5),所述每个排水孔(5)都连通挡土墙墙身(3)靠近水域的外侧和靠近基槽开挖线(14)的内侧。6. The ecological slope protection composite retaining wall structure according to claim 5, characterized in that: a plurality of drainage holes (5) are arranged in the body of the retaining wall (3), and each drainage hole (5) ) are all connected to the outer side of the retaining wall body (3) near the water area and the inner side near the foundation trench excavation line (14). 7.根据权利要求6所述的生态护坡复合挡土墙结构,其特征在于:所述石渣填料(7)与挡土墙台阶式基础(1)之间填充有粘土(4),所述粘土(4)位于挡土墙墙身(3)与基槽开挖线(14)之间;所述石渣填料(7)与生态陡坡之间设置有粘土隔水层(8)。7. The ecological slope protection composite retaining wall structure according to claim 6, characterized in that: clay (4) is filled between the gravel filler (7) and the stepped foundation (1) of the retaining wall, and the The clay (4) is located between the retaining wall body (3) and the foundation trench excavation line (14); and a clay water-resisting layer (8) is arranged between the gravel filling (7) and the ecological steep slope. 8.根据权利要求7所述的生态护坡复合挡土墙结构,其特征在于:所述挡土墙墙身(3)与石渣填料(7)之间设置有反滤层(6)。8. The composite retaining wall structure for ecological slope protection according to claim 7, characterized in that: a reverse filter layer (6) is arranged between the retaining wall body (3) and the gravel filling (7). 9.根据权利要求8所述的生态护坡复合挡土墙结构,其特征在于:所述挡土墙台阶式基础(1)通过锚杆(2)沿基槽开挖线(14)分级锚固。9 . The ecological slope protection composite retaining wall structure according to claim 8 , characterized in that: the stepped foundation ( 1 ) of the retaining wall is anchored in stages along the excavation line ( 14 ) of the foundation trench through anchor rods ( 2 ). 10.根据权利要求9所述的生态护坡复合挡土墙结构,其特征在于:所述挡土墙台阶式基础(1)靠近水域的外侧回填有原土(13)。10. The composite retaining wall structure for ecological slope protection according to claim 9, characterized in that: the outer side of the stepped foundation (1) of the retaining wall near the water area is backfilled with original soil (13).
CN201620542839.2U 2016-06-06 2016-06-06 Ecological revetment is combined retaining wall structure Active CN205776070U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620542839.2U CN205776070U (en) 2016-06-06 2016-06-06 Ecological revetment is combined retaining wall structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620542839.2U CN205776070U (en) 2016-06-06 2016-06-06 Ecological revetment is combined retaining wall structure

Publications (1)

Publication Number Publication Date
CN205776070U true CN205776070U (en) 2016-12-07

Family

ID=58134980

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620542839.2U Active CN205776070U (en) 2016-06-06 2016-06-06 Ecological revetment is combined retaining wall structure

Country Status (1)

Country Link
CN (1) CN205776070U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105887757A (en) * 2016-06-06 2016-08-24 长江勘测规划设计研究有限责任公司 Ecological slope protection composite retaining wall structure and construction method
CN109235486A (en) * 2018-09-18 2019-01-18 中铁二院工程集团有限责任公司 The multistage assembled cantilevered reinforced earth bulkhead of green
CN110258449A (en) * 2019-06-25 2019-09-20 中国电建集团成都勘测设计研究院有限公司 Urban Water Environment landscape gentle slope water-retaining structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105887757A (en) * 2016-06-06 2016-08-24 长江勘测规划设计研究有限责任公司 Ecological slope protection composite retaining wall structure and construction method
CN109235486A (en) * 2018-09-18 2019-01-18 中铁二院工程集团有限责任公司 The multistage assembled cantilevered reinforced earth bulkhead of green
CN110258449A (en) * 2019-06-25 2019-09-20 中国电建集团成都勘测设计研究院有限公司 Urban Water Environment landscape gentle slope water-retaining structure
CN110258449B (en) * 2019-06-25 2024-05-24 中国电建集团成都勘测设计研究院有限公司 Gentle slope water retaining structure for urban water environment landscape

Similar Documents

Publication Publication Date Title
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN104131575B (en) A kind of karst height grows the leak stopping water discharge method of the stratum dam foundation
CN105887757A (en) Ecological slope protection composite retaining wall structure and construction method
CN102966072B (en) Construction method for treating widened and heightened engineering joint surfaces of dikes on soft clay foundation
CN110306491A (en) A kind of river channel ecology bank protection construction technique
CN102383413A (en) Method for constructing strengthened saturated-flow plastic silt soft soil foundation
CN113818300B (en) Sponge city ecological roadbed structure based on original road and construction method thereof
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN106149625A (en) A kind of ecological self-purification type landscape revetment reconstruction structure and construction method thereof
CN205502034U (en) Slope protective structure of step gobi desert cobble plants in arch skeleton
CN104074166A (en) Method for recovering dried-up river
CN107288120A (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN113818402A (en) Reinforcement and reinforcement structure of clay core rockfill dam and its construction method
CN112195965A (en) Expansive soil cutting retaining wall
CN205776070U (en) Ecological revetment is combined retaining wall structure
CN106761914B (en) A kind of routed water water damage prevention and controls of shallow buried coal seam mine raceway groove flood
CN207032212U (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN107761668A (en) A kind of strand Bin Ku makes ground type bank protection structure and its construction process
CN205875176U (en) Ventilation embankment step grouts slabstone and completely spreads slope protection structure
CN210507006U (en) A high-strength steel wire mesh reinforced material filling structure for road embankment
CN108914959B (en) Foundation structure suitable for mountain house building and construction method thereof
CN107130644A (en) Coffering composite geo-membrane and gravelly clay combination against seepage construction method
CN102425179A (en) Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile
CN219386351U (en) High-filling reinforced slope internal drainage structure
CN205062744U (en) Half gravity type two -stage view anti -flood wall on half cantilever

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant