CN108149922A - 一种适用于逆作法施工结构顶板的无排模板施工方法 - Google Patents
一种适用于逆作法施工结构顶板的无排模板施工方法 Download PDFInfo
- Publication number
- CN108149922A CN108149922A CN201711483378.1A CN201711483378A CN108149922A CN 108149922 A CN108149922 A CN 108149922A CN 201711483378 A CN201711483378 A CN 201711483378A CN 108149922 A CN108149922 A CN 108149922A
- Authority
- CN
- China
- Prior art keywords
- construction
- template
- row
- construction method
- structure roof
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/36—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
- E04G11/48—Supporting structures for shutterings or frames for floors or roofs
Abstract
本发明涉及一种适用于逆作法施工结构顶板的无排模板施工方法,包括如下步骤:S10:地基加固:对顶板底面以下4m深度范围内土体采用双轴水泥土搅拌桩进行加固;S20:土方开挖:将所述顶板分成多个施工段进行流水施工;S30:顶板跨中无排模板施工,从下至上依次包括整体浇筑的混凝土垫层、主龙骨、次龙骨以及面板,所述混凝土垫层浇筑于所述地基上,所述主龙骨在水平面上沿横向间隔铺设,所述次龙骨在水平面上沿纵向间隔铺设;S40:下返内衬墙模板施工;S50:下返柱帽模板施工;S60:下返结构剪力墙模板施工。本发明采用先地基加固后无排模板整体浇筑的施工方法,有效控制结构的不均匀沉降,同时满足大体积混凝土顶板的外观质量及强度要求。
Description
技术领域
本发明涉及建筑施工技术领域,特别涉及一种适用于逆作法施工结构顶板的无排模板施工方法。
背景技术
采用逆作法施工的地下室结构顶板,亦为上部结构的转换板,板厚较厚,属大体积混凝土结构,其受力要求和防水要求均较高,且所处土层多为回填土和砂质粉土,常规的高支模排架搭设属重大危险级工程,且不利于结构的差异沉降控制。
发明内容
本发明提供一种适用于逆作法施工结构顶板的无排模板施工方法,以解决上述技术问题。
为解决上述技术问题,本发明提供一种适用于逆作法施工结构顶板的无排模板施工方法,包括如下步骤:
S10:地基加固:对顶板底面以下4m深度范围内土体采用双轴水泥土搅拌桩进行加固,所述水泥土搅拌桩的格栅式加固体同其周边土体构成顶板下的复合地基;
S20:土方开挖:将所述顶板分成多个施工段进行流水施工;
S30:顶板跨中无排模板施工,从下至上依次包括整体浇筑的混凝土垫层、主龙骨、次龙骨以及面板,所述混凝土垫层浇筑于所述地基上,所述主龙骨在水平面上沿横向间隔铺设,所述次龙骨在水平面上沿纵向间隔铺设;
S40:下返内衬墙模板施工;
S50:下返柱帽模板施工;
S60:下返结构剪力墙模板施工。
较佳地,步骤S10中,所述双轴水泥土搅拌桩的规格为¢700@500,水泥掺量为13%。
较佳地,步骤S20中,将所述顶板分成五个施工段由基坑的北侧向南侧进行流水施工。
较佳地,步骤S20中,首皮土采用大开挖形式,开挖深度为2.318m。
较佳地,步骤S30中,所述混凝土垫层的厚度为150mm,强度为C20;所述主龙骨采用尺寸为50×200mm的木方,间距为600mm;所述次龙骨采用尺寸为50×100mm的木方,间距为200mm。
较佳地,步骤S30中,所述面板采用胶合板,所述胶合板为长1830mm×宽915mm,厚度为18mm。
较佳地,步骤S40中,内衬墙模板采用砖胎模,用砖砌120mm厚单砖墙作为下返内衬墙模板,表面用水泥砂浆粉刷涂脱模油;内衬墙水平施工缝底模采用胶合板;与地墙接合处将地墙凿毛处理;将下返内衬墙部位土体按1:1.5挖出,下返内衬墙500mm,在内衬墙水平施工缝处铺设模板。
较佳地,步骤S50中,柱帽模板采用定型钢模;柱帽底面水平施工缝采用胶合板,将下返的柱帽部位土体按1:1.5坡度挖出一盆状坑,柱帽底部铺设模板。
较佳地,步骤S50中,基坑内有160根钢管柱,用作逆作施工阶段承受上部荷载,待逆作结束后,有其中81根所述钢管柱需将地下三层至顶板段外包混凝土形成框架柱,作为正式使用阶段的受力构件。
较佳地,步骤S60中,结构剪力墙在逆作至底板后,由下向上顺柱完成;在浇筑B0板时所述结构剪力墙位置下返500mm;下返结构剪力墙的侧模采用砖胎模,底模采用木模板施工。
与现有技术相比,本发明提供的适用于逆作法施工结构顶板的无排模板施工方法,包括如下步骤:S10:地基加固:对顶板底面以下4m深度范围内土体采用双轴水泥土搅拌桩进行加固;S20:土方开挖:将所述顶板分成多个施工段进行流水施工;S30:顶板跨中无排模板施工,从下至上依次包括整体浇筑的混凝土垫层、主龙骨、次龙骨以及面板,所述混凝土垫层浇筑于所述地基上,所述主龙骨在水平面上沿横向间隔铺设,所述次龙骨在水平面上沿纵向间隔铺设;S40:下返内衬墙模板施工;S50:下返柱帽模板施工;S60:下返结构剪力墙模板施工。本发明采用先地基加固后无排模板整体浇筑的施工方法,有效控制结构的不均匀沉降,同时满足结构施工质量、安全的要求。
附图说明
图1为本发明一具体实施方式中适用于逆作法施工结构顶板的无排模板施工方法的流程示意图;
图2为本发明一具体实施方式中顶板跨中无排模板的结构示意图。
图中:10-混凝土垫层、20-主龙骨、30-次龙骨、40-面板。
具体实施方式
为使本发明的上述目的、特征和优点能够更加明显易懂,下面结合附图对本发明的具体实施方式做详细的说明。需说明的是,本发明附图均采用简化的形式且均使用非精准的比例,仅用以方便、明晰地辅助说明本发明实施例的目的。
本发明提供的适用于逆作法施工结构顶板的无排模板施工方法,如图1所示,包括如下步骤:
S10:地基加固:对顶板底面以下4m深度范围内土体采用双轴水泥土搅拌桩进行加固,具体地,所述双轴水泥土搅拌桩的规格为¢700@500,水泥掺量为13%,所述水泥土搅拌桩的格栅式加固体同其周边土体构成顶板下的复合地基;
S20:土方开挖:将所述顶板分成多个施工段进行流水施工,具体地,将所述顶板分成五个施工段由基坑的北侧向南侧进行流水施工,首皮土采用大开挖形式,开挖深度为2.318m;
S30:顶板跨中无排模板施工,从下至上依次包括整体浇筑的混凝土垫层10、主龙骨20、次龙骨30以及面板40,所述混凝土垫层10浇筑于所述地基上,所述主龙骨20在水平面上沿横向间隔铺设,所述次龙骨30在水平面上沿纵向间隔铺设;
S40:下返内衬墙模板施工;
S50:下返柱帽模板施工;
S60:下返结构剪力墙模板施工。
本发明采用先地基加固后无排模板整体浇筑的施工方法,有效控制结构的不均匀沉降,同时满足结构施工质量、安全的要求。
较佳地,请重点参考图2,步骤S30中,所述混凝土垫层10的厚度为150mm,强度为C20;所述主龙骨20采用尺寸为50×200mm的木方,间距为600mm;所述次龙骨30采用尺寸为50×100mm的木方,间距为200mm;所述面板40采用胶合板,所述胶合板为长1830mm×宽915mm,厚度为18mm。
较佳地,步骤S40中,内衬墙模板采用砖胎模,用砖砌120mm厚单砖墙作为下返内衬墙模板,表面用水泥砂浆粉刷涂脱模油;内衬墙水平施工缝底模采用胶合板;与地墙接合处将地墙凿毛处理;将下返内衬墙部位土体按1:1.5挖出,下返内衬墙500mm,在内衬墙水平施工缝处铺设模板。
较佳地,步骤S50中,柱帽模板采用定型钢模;柱帽底面水平施工缝采用胶合板,将下返的柱帽部位土体按1:1.5坡度挖出一盆状坑,柱帽底部铺设模板;基坑内有160根钢管柱,用作逆作施工阶段承受上部荷载,待逆作结束后,有其中81根所述钢管柱需将地下三层至顶板段外包混凝土形成框架柱,作为正式使用阶段的受力构件,本实施例结合逆作施工的特点及B0板支撑跨中模板形式,以确保结构的施工质量。
较佳地,步骤S60中,结构剪力墙在逆作至底板后,由下向上顺柱完成;在浇筑B0板时所述结构剪力墙位置下返500mm;下返结构剪力墙的侧模采用砖胎模,底模采用木模板施工。
综上所述,本发明提供的适用于逆作法施工结构顶板的无排模板施工方法,包括如下步骤:S10:地基加固:对顶板底面以下4m深度范围内土体采用双轴水泥土搅拌桩进行加固;S20:土方开挖:将所述顶板分成多个施工段进行流水施工;S30:顶板跨中无排模板施工,从下至上依次包括整体浇筑的混凝土垫层10、主龙骨20、次龙骨30以及面板40,所述混凝土垫层10浇筑于所述地基上,所述主龙骨20在水平面上沿横向间隔铺设,所述次龙骨30在水平面上沿纵向间隔铺设;S40:下返内衬墙模板施工;S50:下返柱帽模板施工;S60:下返结构剪力墙模板施工。本发明采用先地基加固后无排模板整体浇筑的施工方法,有效控制结构的不均匀沉降,同时满足结构施工质量、安全的要求。
显然,本领域的技术人员可以对发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包括这些改动和变型在内。
Claims (10)
1.一种适用于逆作法施工结构顶板的无排模板施工方法,其特征在于,包括如下步骤:
S10:地基加固:对顶板底面以下4m深度范围内土体采用双轴水泥土搅拌桩进行加固,所述水泥土搅拌桩的格栅式加固体同其周边土体构成顶板下的复合地基;
S20:土方开挖:将所述顶板分成多个施工段进行流水施工;
S30:顶板跨中无排模板施工:从下至上依次包括整体浇筑的混凝土垫层、主龙骨、次龙骨以及面板,所述混凝土垫层浇筑于所述地基上,所述主龙骨在水平面上沿横向间隔铺设,所述次龙骨在水平面上沿纵向间隔铺设;
S40:下返内衬墙模板施工;
S50:下返柱帽模板施工;
S60:下返结构剪力墙模板施工。
2.如权利要求1所述的适用于逆作法施工结构顶板的无排模板施工方法,其特征在于,步骤S10中,所述双轴水泥土搅拌桩的规格为¢700@500,水泥掺量为13%。
3.如权利要求1所述的适用于逆作法施工结构顶板的无排模板施工方法,其特征在于,步骤S20中,将所述顶板分成五个施工段由基坑的北侧向南侧进行流水施工。
4.如权利要求1所述的适用于逆作法施工结构顶板的无排模板施工方法,其特征在于,步骤S20中,首皮土采用大开挖形式,开挖深度为2.318m。
5.如权利要求1所述的适用于逆作法施工结构顶板的无排模板施工方法,其特征在于,步骤S30中,所述混凝土垫层的厚度为150mm,强度为C20;所述主龙骨采用尺寸为50×200mm的木方,间距为600mm;所述次龙骨采用尺寸为50×100mm的木方,间距为200mm。
6.如权利要求1所述的适用于逆作法施工结构顶板的无排模板施工方法,其特征在于,步骤S30中,所述面板采用胶合板,所述胶合板为长1830mm×宽915mm,厚度为18mm。
7.如权利要求1所述的适用于逆作法施工结构顶板的无排模板施工方法,其特征在于,步骤S40中,内衬墙模板采用砖胎模,用砖砌120mm厚单砖墙作为下返内衬墙模板,表面用水泥砂浆粉刷涂脱模油;内衬墙水平施工缝底模采用胶合板;与地墙接合处将地墙凿毛处理;将下返内衬墙部位土体按1:1.5挖出,下返内衬墙500mm,在内衬墙水平施工缝处铺设模板。
8.如权利要求1所述的适用于逆作法施工结构顶板的无排模板施工方法,其特征在于,步骤S50中,柱帽模板采用定型钢模;柱帽底面水平施工缝采用胶合板,将下返的柱帽部位土体按1:1.5坡度挖出一盆状坑,柱帽底部铺设模板。
9.如权利要求1所述的适用于逆作法施工结构顶板的无排模板施工方法,其特征在于,步骤S50中,基坑内有160根钢管柱,用作逆作施工阶段承受上部荷载,待逆作结束后,有其中81根所述钢管柱需将地下三层至顶板段外包混凝土形成框架柱,作为正式使用阶段的受力构件。
10.如权利要求1所述的适用于逆作法施工结构顶板的无排模板施工方法,其特征在于,步骤S60中,结构剪力墙在逆作至底板后,由下向上顺柱完成;在浇筑B0板时所述结构剪力墙位置下返500mm;下返结构剪力墙的侧模采用砖胎模,底模采用木模板施工。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711483378.1A CN108149922B (zh) | 2017-12-29 | 2017-12-29 | 一种适用于逆作法施工结构顶板的无排模板施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711483378.1A CN108149922B (zh) | 2017-12-29 | 2017-12-29 | 一种适用于逆作法施工结构顶板的无排模板施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108149922A true CN108149922A (zh) | 2018-06-12 |
CN108149922B CN108149922B (zh) | 2023-06-16 |
Family
ID=62460396
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711483378.1A Active CN108149922B (zh) | 2017-12-29 | 2017-12-29 | 一种适用于逆作法施工结构顶板的无排模板施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108149922B (zh) |
Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4605529A (en) * | 1985-08-05 | 1986-08-12 | Superior Walls Of America, Ltd. | Method of constructing a prefabricated concrete wall structure |
JPH07127081A (ja) * | 1993-11-05 | 1995-05-16 | Takenaka Komuten Co Ltd | 逆打ち工法における梁及び床の構築方法 |
JP2001003374A (ja) * | 1999-06-22 | 2001-01-09 | Sekisui House Ltd | 埋殺し型枠を用いた地下コンクリート壁の施工方法 |
CN2758328Y (zh) * | 2004-12-01 | 2006-02-15 | 上海市第二建筑有限公司 | 逆作法工程中的水平无排吊模结构 |
US20060179730A1 (en) * | 2005-02-01 | 2006-08-17 | Ben C. Gerwick, Inc. | Wall structural member and method for constructing a wall structure |
CN101353896A (zh) * | 2008-06-25 | 2009-01-28 | 江苏江都建设工程有限公司 | 超大直径、超埋深度调蓄池的半逆作施工方法 |
CN101736756A (zh) * | 2009-12-04 | 2010-06-16 | 上海市第二建筑有限公司 | 软土地基逆作隔层施工方法 |
CN102031785A (zh) * | 2009-09-24 | 2011-04-27 | 上海市第一建筑有限公司 | 永久结构板带代替临时围檩的基坑支护技术 |
CN102182325A (zh) * | 2011-03-28 | 2011-09-14 | 东南大学 | 一种框架结构独立基础既有建筑物地下室增层方法 |
CN102926403A (zh) * | 2012-11-15 | 2013-02-13 | 中国建筑第八工程局有限公司 | 盖挖法顶板施工方法 |
CN203160254U (zh) * | 2012-11-15 | 2013-08-28 | 上海市政工程设计研究总院(集团)有限公司 | 一种基坑围护结构 |
CN105735354A (zh) * | 2015-12-16 | 2016-07-06 | 贵州建工集团第建筑工程有限责任公司 | 一种城市地下工程盖挖全逆作施工方法 |
CN206110683U (zh) * | 2016-08-31 | 2017-04-19 | 陕西建工第六建设集团有限公司 | 一种用于仿古建筑斜坡形屋面板安装施工结构 |
-
2017
- 2017-12-29 CN CN201711483378.1A patent/CN108149922B/zh active Active
Patent Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4605529A (en) * | 1985-08-05 | 1986-08-12 | Superior Walls Of America, Ltd. | Method of constructing a prefabricated concrete wall structure |
JPH07127081A (ja) * | 1993-11-05 | 1995-05-16 | Takenaka Komuten Co Ltd | 逆打ち工法における梁及び床の構築方法 |
JP2001003374A (ja) * | 1999-06-22 | 2001-01-09 | Sekisui House Ltd | 埋殺し型枠を用いた地下コンクリート壁の施工方法 |
CN2758328Y (zh) * | 2004-12-01 | 2006-02-15 | 上海市第二建筑有限公司 | 逆作法工程中的水平无排吊模结构 |
US20060179730A1 (en) * | 2005-02-01 | 2006-08-17 | Ben C. Gerwick, Inc. | Wall structural member and method for constructing a wall structure |
CN101353896A (zh) * | 2008-06-25 | 2009-01-28 | 江苏江都建设工程有限公司 | 超大直径、超埋深度调蓄池的半逆作施工方法 |
CN102031785A (zh) * | 2009-09-24 | 2011-04-27 | 上海市第一建筑有限公司 | 永久结构板带代替临时围檩的基坑支护技术 |
CN101736756A (zh) * | 2009-12-04 | 2010-06-16 | 上海市第二建筑有限公司 | 软土地基逆作隔层施工方法 |
CN102182325A (zh) * | 2011-03-28 | 2011-09-14 | 东南大学 | 一种框架结构独立基础既有建筑物地下室增层方法 |
CN102926403A (zh) * | 2012-11-15 | 2013-02-13 | 中国建筑第八工程局有限公司 | 盖挖法顶板施工方法 |
CN203160254U (zh) * | 2012-11-15 | 2013-08-28 | 上海市政工程设计研究总院(集团)有限公司 | 一种基坑围护结构 |
CN105735354A (zh) * | 2015-12-16 | 2016-07-06 | 贵州建工集团第建筑工程有限责任公司 | 一种城市地下工程盖挖全逆作施工方法 |
CN206110683U (zh) * | 2016-08-31 | 2017-04-19 | 陕西建工第六建设集团有限公司 | 一种用于仿古建筑斜坡形屋面板安装施工结构 |
Non-Patent Citations (1)
Title |
---|
谢晨光;: "论桥涵构造物施工质量控制", 交通标准化 * |
Also Published As
Publication number | Publication date |
---|---|
CN108149922B (zh) | 2023-06-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102383443B (zh) | 基坑支护桩与地下室外墙之间的连接结构及施工方法 | |
CN102444142B (zh) | 一种群桩改柱扩建地下室及其施工工法 | |
CN101397852A (zh) | 一种对原建筑增建多层地下室的施工方法 | |
CN106088127A (zh) | 沉井施工方法 | |
CN108086343A (zh) | 悬挑式单侧墙体混合加固及置换结构及其施工方法 | |
CN103603359A (zh) | 一种深基坑斜撑支护结构拆除方法 | |
CN109706952A (zh) | 大型沉井施工方法 | |
CN112049011B (zh) | 一种大跨度预应力现浇桥梁逆作法施工方法 | |
CN202347534U (zh) | 基坑支护桩与地下室外墙之间的传力结构 | |
CN207934054U (zh) | 一种预制装配式筏板基础 | |
CN207846454U (zh) | 悬挑式单侧墙体混合加固及置换结构 | |
CN117127642A (zh) | 一种流态固化土承台结构及制作方法 | |
CN208121776U (zh) | 一种装配式可回收钢砼组合式基坑栈桥结构 | |
CN113585336B (zh) | 软弱地基环境中下沉式混凝土拌合站的快速施工方法 | |
CN108149922A (zh) | 一种适用于逆作法施工结构顶板的无排模板施工方法 | |
CN108222010A (zh) | 一种装配式可回收钢砼组合式基坑栈桥结构及施工方法 | |
CN110273435A (zh) | 一种城市明挖隧道的施工工法 | |
JP6522222B1 (ja) | 建物の基礎構造 | |
CN210122735U (zh) | 一种基于外凸式翼脚板的地下结构抗浮体系 | |
CN209260748U (zh) | 一种阶形塔吊基础 | |
RU2671019C1 (ru) | Способ возведения стенчатого фундамента с использованием ребристых плит перекрытий (покрытий) | |
CN207829013U (zh) | 一种中板浇筑土模 | |
CN218667613U (zh) | 一种适用于快速建造的模块化房屋的基础结构 | |
CN217581421U (zh) | 一种后浇带支撑系统 | |
GB2147635A (en) | Foundation for suspended floors |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |