CN107988913A - A kind of bridge bilayer box beam upper former method for dismounting - Google Patents

A kind of bridge bilayer box beam upper former method for dismounting Download PDF

Info

Publication number
CN107988913A
CN107988913A CN201711320710.2A CN201711320710A CN107988913A CN 107988913 A CN107988913 A CN 107988913A CN 201711320710 A CN201711320710 A CN 201711320710A CN 107988913 A CN107988913 A CN 107988913A
Authority
CN
China
Prior art keywords
box beam
steel pipe
upper former
dismounting
former method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711320710.2A
Other languages
Chinese (zh)
Inventor
王东伟
黄永亮
周晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority to CN201711320710.2A priority Critical patent/CN107988913A/en
Publication of CN107988913A publication Critical patent/CN107988913A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete

Abstract

The present invention relates to a kind of bridge bilayer box beam upper former method for dismounting, include the following steps:Template suspension system is installed;Steel pipe post is removed;Upper former system is transferred;Support system is fixed and adjusted.Bridge bilayer box beam upper former method for dismounting provided by the invention, by optimizing construction procedure and execution conditions during firm structure box girder construction, so as to shorten the firm structure box girder construction cycle, construction cost is reduced, the probability for security incident occur is reduced, improves integral construction quality.

Description

A kind of bridge bilayer box beam upper former method for dismounting
Technical field
The present invention relates to technical field of bridge construction, more particularly to a kind of bridge bilayer box beam upper former method for dismounting.
Background technology
Box beam:Hollow or the beam in the day font section put upside down.More with the longspan structures such as viaduct, making material There are armored concrete (prestressing force), steel (plate) structure.Firm structure box beam has compared with armored concrete mechanism:It is fast (just from heavy and light, installation Structure box beam be mostly post stretching field fabrication), good rigidity the features such as be better than concrete box girder.
But box girder construction method of the prior art, long construction period is of high cost, it is higher the probability of security incident occur, Integral construction quality is low.
The content of the invention
The technical solution adopted by the present invention to solve the technical problems is:A kind of bridge bilayer box beam upper former dismounting side Method, it is characterised in that include the following steps:
Template suspension system is installed;
Steel pipe post is removed;
Upper former system is transferred;
Support system is fixed and adjusted.
Further it is improved to, the upper strata is directly removed and template system suspention decentralization, including:
Suspension system preformed hole is set in advance in the edge of a wing Board position during box girder construction of upper strata, treats that box beam reaches design strength Afterwards, suspension system is installed, fixed suspention spandrel girder template system supported above, removes steel pipe post upper segment, then utilize Suspension system transfers form bracing system to designed elevation, the support shuttering as lower floor's Cast-in-situ Beam.
Further it is improved to, the template suspension system installation, including:
Trestle pile top spandrel girder both ends set suspention preformed hole, corresponding with upper strata box beam top plate preformed hole, using finish rolling spiral shell Line steel locks strutting system.
Further it is improved to, the steel pipe post is removed, including:
After the suspention locking of upper former support system, upper strata steel pipe support column is removed using crawler crane or truck crane, is torn open The steel pipe post classification removed is stored by number, is gone to next hole box beam bracket week and is recycled.
Further it is improved to, the upper former system decentralization, including:
Hoist engine is installed on upper strata box beam top, utilizes the synchronous symmetrical decentralization of hoist engine to lower floor's box beam bracket designed elevation.
Further it is improved to, the support system is fixed and adjusted, including:
After template system decentralization in place, suspension system is removed, spandrel girder and steel pipe post reinforce again and welded, root Template system is readjusted according to lower floor's box-beam structure size and absolute altitude.
The beneficial effects of the invention are as follows:
Bridge double layer box beam construction method provided by the invention, by optimizing the construction procedure during firm structure box girder construction And execution conditions, so as to shorten the firm structure box girder construction cycle, construction cost is reduced, reduces the probability for security incident occur, Improve integral construction quality.
Brief description of the drawings
The present invention is further described with reference to the accompanying drawings and examples.
Fig. 1 is the bridge double layer box beam construction method flow diagram of the present invention;
Fig. 2 is the bridge bilayer box beam upper former method for dismounting flow diagram of the present invention.
Embodiment
In conjunction with the accompanying drawings, the present invention is further explained in detail.These attached drawings are simplified schematic diagram, only with Illustration illustrates the basic structure of the present invention, therefore it only shows composition related to the present invention.
In the description of invention, it is to be understood that term " " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", " thickness ", " on ", " under ", "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom " " interior ", " outer ", " up time The orientation or position relationship of the instruction such as pin ", " counterclockwise " are based on orientation shown in the drawings or position relationship, are for only for ease of Description is invented and simplified in description, rather than indicates or imply that the device of meaning or element must have specific orientation, with specific Azimuth configuration and operation, therefore it is not intended that limitation to invention.
In addition, term " first ", " second " are only used for description purpose, and it is not intended that instruction or hint relative importance Or the implicit quantity for indicating indicated technical characteristic.Thus, define " first ", the feature of " second " can be expressed or Implicitly include one or more this feature.In the description of invention, " multiple " are meant that two or more, remove It is non-separately to have clearly specific limit.
In invention, unless otherwise clearly defined and limited, the art such as term " installation ", " connected ", " connection ", " fixation " Language should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected, or be integrally connected;Can be machinery Connection or electrical connection;It can be directly connected, can also be indirectly connected by intermediary, can be two elements Internal connection.For the ordinary skill in the art, it can understand above-mentioned term in invention as the case may be Concrete meaning.
As described in Figure 1, the present invention provides a kind of bridge double layer box beam construction method, include the following steps:
S1, basement process;
S2, upper layer bracket and template system installation;
S3, upper strata is directly removed and template system suspention decentralization;
S4, cast-in-situ box girder pour.
Further it is improved to, the basement process, including:
First desurfacing unfavorable geology soil, foundation excavation to fresh scar simultaneously carry out leveling processing, then carry out ground and hold Power experiment is carried, after meeting requirement for bearing capacity, pours bar shaped Extended chemotherapy, basis uses C25 concrete, and top surface sets steel pipe post Built-in fitting.
Further it is improved to, the upper layer bracket and template system installation, including:
Steel pipe post is installed;
Spandrel girder is installed;
Bailey beam is installed;
Horizontal I-steel installation;
Adjust the installation of wrist buckle frame;
Template system is installed.
Further it is improved to, the upper layer bracket and template system installation, including:
Steel pipe support column uses Φ 800*8mm steel pipes, and steel pipe column vertically uses flanged joint, and merogenesis height is according to up and down Layer box girder construction headroom determines, is interconnected and fixed between column using lateral and bridging.Stake top spandrel girder using 3HN500 × 200 shaped steel, for stent longitudinally using Bailey beam as Anti-bending structure, Bailey beam top uses bowl buckle bracket support template system, and Box beam longitudinal slope and each position absolute altitude are effectively adjusted, box girder formwork uses bamboo slab rubber.
Further it is improved to, the cast-in-situ box girder pours, including:
Levels cast-in-situ box girder is single box double room prestressed concrete skew web plate continuous box girder, using placement layer by layer work twice Skill, pours to box girder web top surface first.
As shown in Fig. 2, being further improved to, the upper strata is directly removed and template system suspention decentralization, including:
S31, the installation of template suspension system;
S32, steel pipe post are removed;
S33, the decentralization of upper former system;
S34, support system are fixed and adjusted.
Further it is improved to, the upper strata is directly removed and template system suspention decentralization, including:
Suspension system preformed hole is set in advance in the edge of a wing Board position during box girder construction of upper strata, treats that box beam reaches design strength Afterwards, suspension system is installed, fixed suspention spandrel girder template system supported above, removes steel pipe post upper segment, then utilize Suspension system transfers form bracing system to designed elevation, the support shuttering as lower floor's Cast-in-situ Beam.
Further it is improved to, the template suspension system installation, including:
Trestle pile top spandrel girder both ends set suspention preformed hole, corresponding with upper strata box beam top plate preformed hole, using finish rolling spiral shell Line steel locks strutting system.
Further it is improved to, the steel pipe post is removed, including:
After the suspention locking of upper former support system, upper strata steel pipe support column is removed using crawler crane or truck crane, is torn open The steel pipe post classification removed is stored by number, is gone to next hole box beam bracket week and is recycled.
Further it is improved to, the upper former system decentralization, including:Hoist engine is installed on upper strata box beam top, utilizes volume The synchronous symmetrical decentralization of machine is raised to lower floor's box beam bracket designed elevation;
The support system is fixed and adjusted, including:After template system decentralization in place, suspension system is removed, to spandrel girder With steel pipe post reinforce again and weld, template system is readjusted according to lower floor's box-beam structure size and absolute altitude.
It is complete by above-mentioned description, relevant staff using the above-mentioned desirable embodiment according to the present invention as enlightenment Various changes and amendments can be carried out without departing from the scope of the technological thought of the present invention' entirely.The technology of this invention Property scope is not limited to the content on specification, it is necessary to determines its technical scope according to right.

Claims (6)

1. a kind of bridge bilayer box beam upper former method for dismounting, it is characterised in that include the following steps:
Template suspension system is installed;
Steel pipe post is removed;
Upper former system is transferred;
Support system is fixed and adjusted.
2. bridge bilayer box beam upper former method for dismounting according to claim 1, it is characterised in that the upper strata is direct Remove and template system suspention is transferred, including:
Suspension system preformed hole is set in advance in the edge of a wing Board position during box girder construction of upper strata, after box beam reaches design strength, peace Suspension system is filled, fixed suspention spandrel girder template system supported above, removes steel pipe post upper segment, then utilizes suspention system System decentralization form bracing system is to designed elevation, the support shuttering as lower floor's Cast-in-situ Beam.
3. bridge bilayer box beam upper former method for dismounting according to claim 1, it is characterised in that the template suspension System is installed, including:
Trestle pile top spandrel girder both ends set suspention preformed hole, corresponding with upper strata box beam top plate preformed hole, using fining twisted steel Lock strutting system.
4. bridge bilayer box beam upper former method for dismounting according to claim 1, it is characterised in that the steel pipe post Remove, including:
After the suspention locking of upper former support system, upper strata steel pipe support column is removed using crawler crane or truck crane, dismounting Steel pipe post classification is stored by number, is gone to next hole box beam bracket week and is recycled.
5. bridge bilayer box beam upper former method for dismounting according to claim 1, it is characterised in that the upper former System is transferred, including:
Hoist engine is installed on upper strata box beam top, utilizes the synchronous symmetrical decentralization of hoist engine to lower floor's box beam bracket designed elevation.
6. bridge bilayer box beam upper former method for dismounting according to claim 1, it is characterised in that the support system Fixed and adjustment, including:
After template system decentralization in place, suspension system is removed, spandrel girder and steel pipe post reinforce again and welded, under Layer box-beam structure size and absolute altitude readjust template system.
CN201711320710.2A 2017-12-12 2017-12-12 A kind of bridge bilayer box beam upper former method for dismounting Pending CN107988913A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711320710.2A CN107988913A (en) 2017-12-12 2017-12-12 A kind of bridge bilayer box beam upper former method for dismounting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711320710.2A CN107988913A (en) 2017-12-12 2017-12-12 A kind of bridge bilayer box beam upper former method for dismounting

Publications (1)

Publication Number Publication Date
CN107988913A true CN107988913A (en) 2018-05-04

Family

ID=62037373

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711320710.2A Pending CN107988913A (en) 2017-12-12 2017-12-12 A kind of bridge bilayer box beam upper former method for dismounting

Country Status (1)

Country Link
CN (1) CN107988913A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108611981A (en) * 2018-05-22 2018-10-02 江苏省交通工程集团有限公司 A kind of door opening holder and its method for dismounting simply removed
CN111364365A (en) * 2020-03-23 2020-07-03 中国十九冶集团有限公司 Method for dismantling combined support of spiral steel pipe pile
CN113585076A (en) * 2021-07-08 2021-11-02 中国建筑第六工程局有限公司 Construction method of overwater large-span double-layer cast-in-place beam

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003227108A (en) * 2002-02-04 2003-08-15 Teikoku Sekkei Jimusho:Kk Stain-proof structure of side of bridge by setting small projection
KR100933637B1 (en) * 2008-11-13 2009-12-23 덕주건설(주) Rain water double draining device for bridge
CN202017181U (en) * 2011-04-14 2011-10-26 中铁二十局集团第六工程有限公司 Falsework for constructing steel and concrete combined beam crossing over conventional route and arranged parallel to existing line
CN103255838A (en) * 2013-05-09 2013-08-21 北京安德固脚手架工程有限公司 Construction method with adoption of large-tonnage long-stroke oil cylinder jacking mold frame
CN103669832A (en) * 2013-12-13 2014-03-26 中建三局第一建设工程有限责任公司 Standard Bailey truss assembling type jacking formwork system
CN103979383A (en) * 2014-04-29 2014-08-13 山东腾飞建设机械工程有限公司 Multi-layer lifting platform for building construction
CN104695336A (en) * 2015-01-15 2015-06-10 中铁大桥局集团第五工程有限公司 Double-layer cast-in-situ beam support construction method adopting sequence from upper layer to lower layer

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003227108A (en) * 2002-02-04 2003-08-15 Teikoku Sekkei Jimusho:Kk Stain-proof structure of side of bridge by setting small projection
KR100933637B1 (en) * 2008-11-13 2009-12-23 덕주건설(주) Rain water double draining device for bridge
CN202017181U (en) * 2011-04-14 2011-10-26 中铁二十局集团第六工程有限公司 Falsework for constructing steel and concrete combined beam crossing over conventional route and arranged parallel to existing line
CN103255838A (en) * 2013-05-09 2013-08-21 北京安德固脚手架工程有限公司 Construction method with adoption of large-tonnage long-stroke oil cylinder jacking mold frame
CN103669832A (en) * 2013-12-13 2014-03-26 中建三局第一建设工程有限责任公司 Standard Bailey truss assembling type jacking formwork system
CN103979383A (en) * 2014-04-29 2014-08-13 山东腾飞建设机械工程有限公司 Multi-layer lifting platform for building construction
CN104695336A (en) * 2015-01-15 2015-06-10 中铁大桥局集团第五工程有限公司 Double-layer cast-in-situ beam support construction method adopting sequence from upper layer to lower layer

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
马建东: "黄冈长江大桥双层公铁两用混凝土连续梁逆向施工技术", 《卷宗》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108611981A (en) * 2018-05-22 2018-10-02 江苏省交通工程集团有限公司 A kind of door opening holder and its method for dismounting simply removed
CN111364365A (en) * 2020-03-23 2020-07-03 中国十九冶集团有限公司 Method for dismantling combined support of spiral steel pipe pile
CN113585076A (en) * 2021-07-08 2021-11-02 中国建筑第六工程局有限公司 Construction method of overwater large-span double-layer cast-in-place beam

Similar Documents

Publication Publication Date Title
CN108487252A (en) A kind of deep foundation pit open cutting is suitable to make construction method
CN206971268U (en) The working top plate mobile formwork body of underground pipe gallery
CN107988913A (en) A kind of bridge bilayer box beam upper former method for dismounting
CN205242436U (en) Supplementary soleplate traded interim bearing structure who props during system was gone along with sb. to guard him to underground complex
CN106087746A (en) A kind of cast-in-situ box girder falsework construction method and bridge
CN109322241A (en) Trestle work structure and construction method
CN105113539B (en) Combined multi-functional diaphram wall Core Walls Structure and its construction method in a kind of contrary sequence method
CN109403654A (en) A kind of underpinning method of existing building structure
CN112727075A (en) Integrated pouring structure of inclined roof and flat roof and construction method
CN209653108U (en) Prefabricated reinforced concrete column connection structure
CN108049314A (en) A kind of bridge double layer box beam construction method
CN107882234A (en) A kind of connecting node between the vertical member and floor of plate-column structure
CN109098207B (en) Template system of prefabricated gas cabin of underground comprehensive pipe rack and construction method
CN101215840B (en) Airplane-type foundation reinforcement given-force construction method
CN102767378B (en) Method for constructing distyle tunnel portal by framed bent
CN107859058A (en) A kind of cast-in-place concrete retaining wall anti-incline anti-floating large steel moulding plate device and installation method
CN209412681U (en) Trestle work structure
CN207277211U (en) Large steel pipe truss for bent cap cast-in-place construction
CN105625573A (en) Beam-bottom medium-strength prestressed steel bar and ordinary steel bar sleeve connecting beam-column joint
CN214833739U (en) Novel assembled shear force wall
CN210117724U (en) Garage foundation structure
CN206052565U (en) A kind of beam-column type bracket
CN209260748U (en) A kind of stepped tower crane
CN210194657U (en) Foundation of prefabricated substation distribution device building
CN208650067U (en) Underground increasing layer excavates new supporting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180504

RJ01 Rejection of invention patent application after publication