CN206971268U - The working top plate mobile formwork body of underground pipe gallery - Google Patents

The working top plate mobile formwork body of underground pipe gallery Download PDF

Info

Publication number
CN206971268U
CN206971268U CN201720734669.2U CN201720734669U CN206971268U CN 206971268 U CN206971268 U CN 206971268U CN 201720734669 U CN201720734669 U CN 201720734669U CN 206971268 U CN206971268 U CN 206971268U
Authority
CN
China
Prior art keywords
pipe gallery
underground pipe
top plate
bearing
mobile formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720734669.2U
Other languages
Chinese (zh)
Inventor
陈俊杰
卢国春
赵宗文
闫力
韩应祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201720734669.2U priority Critical patent/CN206971268U/en
Application granted granted Critical
Publication of CN206971268U publication Critical patent/CN206971268U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

A kind of working top plate mobile formwork body of underground pipe gallery is the utility model is related to, including:Supporting frame of the branch on underground pipe gallery bottom plate, the bottom of support frame as described above body is provided with shifting roller;Support frame as described above body bottom and the adjustable bearing of bearing height set close to the shifting roller are installed in, it is hanging with the shifting roller by adjusting the bearing height of the bearing;It is installed in support frame as described above body top and the adjustable branch membrane module of bearing height;And the top template on the branch membrane module is installed on, adjust bearing height by the branch membrane module is installed in place with the top template.Top template is arranged on moveable supporting frame so that during top plate pouring construction, without repeating formwork supporting plate and setting up scaffold, can be moved integrally by supporting frame to next construction section, save material and have bad luck expense.And material is once put into, repeatedly it is used in turn, spillage of material can be greatly reduced.

Description

The working top plate mobile formwork body of underground pipe gallery
Technical field
The construction field of underground pipe gallery is the utility model is related to, refers in particular to a kind of working top plate of underground pipe gallery Mobile formwork body.
Background technology
Underground pipe gallery, it is the facility for implementing unified planning, design, construction and maintenance, is built in Urban Underground and is used to apply If the public utility of municipal public use pipeline.General pipe gallery is located at along the supporting setting of basic road, i.e. pipe gallery The lower section of basic road is simultaneously parallel with basic road, and the pipe gallery is used to house underground utilities, solves the laying of underground utilities Problem.
Pipe gallery typically uses rectangular configuration, and its work progress is first excavates piping lane tunnel, then in piping lane tunnel Inside construct out Pipe rack, Pipe rack is concrete structure, existing Normal practice to be spliced using prefabricated components, or Person is that cast-in-place concrete forms, and operation, the construction such as splices again, it is necessary to lift and be transported to construction location when being constructed using prefabricated components It is cumbersome, using cast-in-place concrete construction, it is necessary to which formwork pours form removal again is transported to next construction area and carries out formwork again and pour Operation, the workload of construction is big, low construction efficiency.
Utility model content
A kind of the defects of the purpose of this utility model is to overcome prior art, there is provided working top of underground pipe gallery Plate mobile formwork body, solve existing cast-in-place piping lane and apply man-hour requirement formwork and pour form removal again to be transported to existing for next construction area Construction operation amount is big and the problem of low construction efficiency.
Realizing the technical scheme of above-mentioned purpose is:
The utility model provides a kind of working top plate mobile formwork body of underground pipe gallery, including:
Supporting frame of the branch on underground pipe gallery bottom plate, the bottom of support frame as described above body is provided with shifting roller;
Support frame as described above body bottom and the adjustable bearing of bearing height set close to the shifting roller are installed in, is passed through The bearing height of the bearing is adjusted to cause the shifting roller hanging;
It is installed in support frame as described above body top and the adjustable branch membrane module of bearing height;And
The top template being installed on the branch membrane module, bearing height is adjusted with described by the branch membrane module Top template installs in place.
By top template be arranged on moveable supporting frame on so that during top plate pouring construction, without repeat formwork supporting plate and Scaffold is set up, can be moved integrally by supporting frame to next construction section, material is saved and has bad luck expense.And material is once thrown Enter, be repeatedly used in turn, spillage of material can be greatly reduced.It is whole to save piping lane without assembly every time for top template and supporting frame The construction period of body, top plate mobile formwork body of the present utility model have the advantages of easy to operate, support system is safe and reliable.
The working top plate mobile formwork body of the utility model underground pipe gallery further improvement is that, the backform The bottom surface of plate is installed with main joist;
The branch membrane module includes support screw, the cradle being fixedly arranged on the support screw and located at the support The top bracing member of seat both sides;
The support screw is screwed together in the top of support frame as described above body, and the branch is screwed together in by adjusting the support screw Realize the bearing height regulation of the branch membrane module in position at the top of support body;
On the cradle corresponding tank is partially disposed in formed with the tank for housing the main joist, the main joist It is interior, and the part on the main joist in the tank is stayed on by the top bracing member, so as to which the main joist be consolidated Due in the cradle.
The working top plate mobile formwork body of the utility model underground pipe gallery further improvement is that, the support Seat includes bottom plate, the block that is erected on the side plate of the bottom plate both sides and is fixedly arranged in the middle part of the bottom plate, the block with it is right The tank is formed between the side plate answered, for the top bracing member to press closer bolt, the bolt that presses closer is screwed together in the side plate.
The working top plate mobile formwork body of the utility model underground pipe gallery further improvement is that, the support Support body includes adjustable for height vertical rod, supports the cross bar being connected between two adjacent vertical rods and skewed horizontal load to be connected to phase Brace between two adjacent vertical rods, the adjustable length of the brace.
The working top plate mobile formwork body of the utility model underground pipe gallery further improvement is that, the brace Including the sleeve pipe positioned at middle part, the right-hand thread screw mandrel and left-hand thread screw mandrel at described sleeve pipe both ends are screwed together in, is made by rotating described sleeve pipe The right-hand thread screw mandrel and left-hand thread screw mandrel for obtaining both ends are stretched into described sleeve pipe or overhang to described sleeve pipe simultaneously, it is achieved thereby that Adjust the length of the brace.
The working top plate mobile formwork body of the utility model underground pipe gallery further improvement is that, the vertical rod Including the first pole and the second pole being socketed up and down, fixing hole, second pole are offered at the top of first pole Upper be spaced apart is provided with connecting hole, adjusts the depth that second pole is inserted in first pole, and wear by connecting bolt If the fixing hole is fixedly connected with first pole and second pole with corresponding connecting hole, it is achieved thereby that described vertical The height regulation of bar.
The working top plate mobile formwork body of the utility model underground pipe gallery further improvement is that, the vertical rod Periphery be installed with connection otic placode.
The working top plate mobile formwork body of the utility model underground pipe gallery further improvement is that, the bearing Including base, it is erected on screw rod and the stiffener being fixedly arranged between the screw rod and the base on base, the screw rod spiral shell Together in the bottom of support frame as described above body, the branch is realized in the position that support frame as described above body bottom is screwed together in by adjusting the screw rod The regulation of the bearing height of seat.
The working top plate mobile formwork body of the utility model underground pipe gallery further improvement is that, it is in addition to vertical Supported rod erecting on the underground pipe gallery bottom plate and the morning at the top of the supported rod erecting tear structure, the support open Vertical rod is between two supporting frames, and the morning tears structure open and connect relatively with adjacent top template.
The working top plate mobile formwork body of the utility model underground pipe gallery further improvement is that, the backform Plate is connected with bracket close to the end of side wall, and the bottom of the bracket is connected with a side template, and the outside of the side wall corresponds to institute State to be sticked at side template and have Side Template, the either flush of the top of the Side Template and top plate to be poured, the Side Template and The side template is fastenedly connected on corresponding side wall by split bolt.
Brief description of the drawings
Fig. 1 is the structural representation of the first side of the working top plate mobile formwork body of the utility model underground pipe gallery Figure.
Fig. 2 is the structural representation of the second side of the working top plate mobile formwork body of the utility model underground pipe gallery Figure.
Fig. 3 is the brace in the supporting frame of the working top plate mobile formwork body of the utility model underground pipe gallery Structural representation.
Fig. 4 is the structural representation of branch membrane module in the working top plate mobile formwork body of the utility model underground pipe gallery Figure.
Fig. 5 is the structural representation of bearing in the working top plate mobile formwork body of the utility model underground pipe gallery.
Fig. 6 is the top view of bearing in the working top plate mobile formwork body of the utility model underground pipe gallery.
Fig. 7 is the working top plate mobile formwork body branch of the utility model underground pipe gallery in underground pipe gallery Structural representation.
Fig. 8 is that the working top plate mobile formwork body of the utility model underground pipe gallery moves along underground pipe gallery bottom plate Dynamic structural representation.
Embodiment
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
Refering to Fig. 1 and Fig. 2, the utility model provides the working top plate mobile formwork body of underground pipe gallery, is used for The construction of casting top slab in basement pipe gallery, the top plate mobile formwork body have assembling flexibly, tear down and reconstruct conveniently, process it is simple Advantage, and with may move, exempt to take the characteristics of exempting to tear open to tear open early.Top plate mobile formwork body provided by the utility model is applicable In various template, such as aluminum alloy mould plate, aluminium frame wooden model and steel framework wooden model etc..And top plate mobile formwork body of the present utility model can Coordinate and early tear structure and supported rod erecting open, realize and early tears function open, reach the 50% of design strength grade in the concrete roof poured When can be stripped and be moved to next section and constructed, and leave it is early tear structure open and continue to shore with supported rod erecting reached the last 50% The concrete roof of degree, the dismountable morning tears structure open when the concrete roof reaches the 75% of design strength grade and support is vertical Bar.The structure of the working top plate mobile formwork body of the utility model underground pipe gallery is illustrated below in conjunction with the accompanying drawings.
As depicted in figs. 1 and 2, the working top plate mobile formwork body 20 of underground pipe gallery provided by the utility model wraps Supporting frame 21, bearing 22, branch membrane module 23 and top template 24 are included, with reference to shown in Fig. 7, supporting frame 21 is comprehensive located at underground On the bottom plate 11 for closing piping lane 10, the bottom of the supporting frame 21 is provided with shifting roller 211, is made by the shifting roller 211 of setting Obtaining the supporting frame 21 has locomotive function.Bearing 22 is installed in the bottom of supporting frame 21 and set close to shifting roller 211, The bearing height of the bearing 22 is adjustable, and its bearing height refers to distance of the bottom of supporting frame 21 away from the upper surface of bottom plate 11, leads to The bearing height for overregulating bearing 22 make it that shifting roller 211 is hanging, so as to which supporting frame 21 is supported on into bottom by bearing 22 On plate 11, shifting roller 211 it is hanging, it can be ensured that the stability of strutting system of supporting frame 21.Branch membrane module 23 is installed in support The top of support body 21, and the bearing height of branch membrane module 23 is adjustable, the bearing height of branch membrane module 23 protrudes out branch for its own The length at the top of support body 21.Top template 24 is installed on branch membrane module 23, by branch membrane module 23 adjust bearing height so that Top template 24 installs in place, be used to pour the top plate 13 to form underground pipe gallery 10 on top template 24, by support frame After body 21 installs stabilization, pass through branch membrane module 23 and adjust installing highly for top template 24 so that the upper surface of the top template 24 is The bottom surface of the top plate 13 of design.
As a better embodiment of the present utility model, as shown in Figure 1, Figure 2 and Figure 4, consolidate in the bottom surface of top template 24 Provided with main joist 241, branch membrane module 23 includes support screw 231, cradle 232 and top bracing member 233, the spiral shell of support screw 231 Together in the top of supporting frame 21, formwork is realized in the position that the top of supporting frame 21 is screwed together in by adjusting the support screw 231 The bearing height regulation of component 23, when by inside precession of the support screw 231 to supporting frame 21 so that support screw 231 Partial Height more than the top of supporting frame 21 diminishes, and diminishes so as to adjust bearing height, now available for top template 24 The demoulding construction;When support screw 231 is screwed out to the outside of supporting frame 21 so that support screw 231 is located at support frame The Partial Height more than top of body 21 becomes big, becomes big so as to adjust bearing height, now the formwork construction available for top template 24. Cradle 232 is installed on support screw 231, and the cradle 232 is installed in the top of support screw 231, and top bracing member 233 is located at The both sides of cradle 232.Tank 2321 formed with accommodating main joist 241 on the cradle 232, main joist 241 are partially disposed in In corresponding tank 2321, and the part on main joist 241 in tank 2321 is stayed on by top bracing member 233, so that will Main joist 241 is fixed in cradle 232.Further, cradle 232 includes bottom plate 2322, is erected on the both sides of bottom plate 2322 Side plate 2323 and be fixedly arranged on the block 2324 at the middle part of bottom plate 2322, formed and held between block 2324 and corresponding side plate 2323 Groove 2321, top bracing member 233 press closer bolt and are screwed together in side plate 2323 to press closer bolt.Through hole is offered on side plate 2323 simultaneously In the fixed nut in outer surface of corresponding through hole, press closer that bolt is screwed together in the nut and tank 2321 is stretched into end from through hole It is interior.Bottom plate 2322 and side plate 2323 therein are stripe board, and block 2324 is square piece.
As another better embodiment of the present utility model, as depicted in figs. 1 and 2, supporting frame 21 includes height can The vertical rod 212 of tune, support are connected to cross bar 213 between two adjacent vertical rods 212 and skewed horizontal load be connected to it is adjacent Brace 214 between two vertical rods 212, the adjustable length of brace 214.Pass through the height adjustable supporting frame of vertical rod 212 The construction of the underground pipe gallery 10 of different height can be applied to.With reference to shown in Fig. 3, brace 214 includes the set positioned at middle part Pipe 2141, the right-hand thread screw mandrel 2142 and left-hand thread screw mandrel 2143 for being screwed together in the both ends of sleeve pipe 2141, pass through rotating casing 2,141 two The right-hand thread screw mandrel 2142 and left-hand thread screw mandrel 2143 at end are stretched into sleeve pipe 2141 or overhang to sleeve pipe 2141 simultaneously, so as to real The length of regulation brace 214 is showed.Gusset 2144 is connected with the outer end of right-hand thread screw mandrel 2142 and left-hand thread screw mandrel 2143, by this Brace 214 is connected in vertical rod 212 by gusset 2144.Further, vertical rod 212 includes the first pole and second being socketed up and down Pole, fixing hole is offered at the top of the first pole, is spaced apart on the second pole and is provided with connecting hole, the second pole of regulation inserts the Depth in one pole, and fixing hole is worn by connecting bolt and is fixedly connected with the first pole and second with corresponding connecting hole Bar, it is achieved thereby that the height regulation of vertical rod.Further, the periphery of vertical rod 212 is installed with connection otic placode 2121.The company of setting Ear connecting plate 2121 is used to connect cross bar 213 and brace 214.
As another better embodiment of the present utility model, as shown in Figure 2, Figure 5 and Figure 6, bearing 22 includes base 221st, screw rod 222 on base 221 and the stiffener 223 being fixedly arranged between screw rod 222 and base 221, the spiral shell of screw rod 222 are erected on Together in the bottom of supporting frame 21, the branch of bearing 22 is realized in the position that the bottom of supporting frame 21 is screwed together in by adjusting screw rod 222 Support the regulation of height.Base 221 is plate body structure.Inside precession of the screw rod 222 to supporting frame 21, regulation bearing height become It is small, and then shifting roller 211 is placed on bottom plate 11, realize the locomotive function of operation support body 21;Screw rod 222 is to supporting frame 21 outside back-out, regulation bearing height become big, and then make it that shifting roller 211 is hanging, improve the stability of operation support body 21.
As another better embodiment of the present utility model, as shown in fig. 7, top plate mould bases body 20 also includes being erected on ground Supported rod erecting 25 on the bottom plate 11 of lower pipe gallery 10 and the morning located at the top of supported rod erecting 25 tear structure 26, supported rod erecting 25 open Between two supporting frames 21, and early structure 26 of tearing open connects relatively with adjacent top template 24.Supported rod erecting 25 tears knot open with early The compartment of terrain of structure 26 is erected on bottom plate 11, the height adjustable of the supported rod erecting 25 so that and that early tears structure 26 open shores height adjustable, Early tear template of the structure 26 as top plate 13 open, directly connect with the concrete poured, after the demoulding of top template 24 is removed, by staying If supported rod erecting 25 and early tear structure 26 open and continue to shore the top plate 13 poured.Supported rod erecting 25 includes two to be mutually screwed together Individual loop bar, fixed position is screwed togather to realize that the height of supported rod erecting 25 is adjusted by adjusting loop bar.
As better embodiment another again of the present utility model, top template 24 is connected with bracket close to the end of side wall 12 27, the bottom of bracket 27 is connected with a side template 28, and the outside of side wall 12, which corresponds to be sticked at side template 28, Side Template 29, holds mould The either flush of the top of plate 29 and top plate 13 to be poured, Side Template 29 and side template 28 by split bolt be fastenedly connected in On corresponding side wall 12.The bottom of Side Template 29 is provided with support bracket 291, is erected Side Template 29 in side wall by support bracket 291 12 lateral surface, support bracket 291 are tripod and are installed in the lateral surface of side wall 12.For the middle part of pipe gallery 10 located underground Side wall 12 for, the end that top template 24 at the side wall 12 at middle part is located at this is connected with bracket 27, in the bottom of bracket 27 Fagging is installed with, the fagging of the both sides of side wall 12 is fastenedly connected by split bolt.
As shown in Figure 7 and Figure 8, the work progress of top plate mobile formwork body 20 of the present utility model is illustrated below.
The bottom plate 11 and side wall 12 of underground pipe gallery 10 have been constructed completion, cast-in-place construction need to be formed on side wall 12 Top plate 13, top plate mobile formwork body 20 of the present utility model are used for the formwork pouring construction of the top plate 13.First spelled on bottom plate 11 Assembled good supporting frame 21 is moved on bottom plate 11 by dress supporting frame 21, in the branch of formwork opening position regulation bearing 22 Height is supportted bearing 22 is supported on bottom plate 11 and makes the shifting roller 211 of the bottom of supporting frame 21 hanging, so that it is guaranteed that The structural stability of supporting frame 21.Backform component 23 then is installed at the top of supporting frame 21, by backform component 23 Support screw 231 is screwed on supporting frame 21, main joist 241 is then placed in the cradle 232 of backform component 23, then Assembled top template 24, top template 24 is fixed on main joist 241 on main joist 241, when splicing top template 24, is being set Positioning, which puts to stay to set, installs the early position for tearing structure 26 open.The bearing height of regulation backform component 23 causes top template 24 to install in place, By early tear open structure 26 by supported rod erecting 25 erect bottom plate 11 on, and adjust it is early tear structure 26 open install height, so as to early Tear the casting space that top plate 13 is formed on structure 26 and top template 24 open.Side template 28 and Side Template are installed on side wall 12 29, so as to pour pouring for top plate 13 with formation on structure 26 is early torn open in Side Template 29 and the inner side of side template 28 and top template 24 Space, into the casting space, casting concrete is so as to foring top plate 13.Treat that top plate 13 reaches the 50% of design strength grade When, top template 24 can be stripped, the bearing height of regulation branch membrane module 23 causes the absolute altitude of top template 24 to reduce, and adjusts bearing 22 Bearing height shifting roller 211 is placed on bottom plate 11, on bottom plate 11 set electrical hoist 31, by electrical hoist Rope connection supporting frame 21 on 31, next construction position is moved to by the traction of electrical hoist 31 by supporting frame 21 Put, then adjust bearing 22 again and be supported in bottom plate 11 to stablize movable support body 21, then adjust branch membrane module 23 by top template 24 Position is set to, another set early tears structure 26 and top template 24 open, installs side template 28 and Side Template 29, the top plate 13 of next section of progress Pouring construction.It is achieved thereby that mobile turnover construction.It can be incited somebody to action when the top plate 13 that the last period pours reaches the 75% of design strength Stay that the morning set tears structure 26 open and supported rod erecting 25 is removed to be used in turn.
Top plate mould bases body of the present utility model has the beneficial effect that:
Top plate mould bases body is integrally connected by screw bolts, convenient disassembly, and turnover utilization rate is high;It is not repeated in the cabin of piping lane Formwork supporting plate and scaffold is set up, can moved integrally to next section of construction area, saved material and have bad luck expense;Material is once put into, Repeatedly it is used in turn, spillage of material can be greatly reduced;Top template and supporting frame only need assembly first, are all spelled without every section Dress, saves the overall duration;Simple to operate, support safety is reliable;Top board construction is carried out according to aluminum alloy mould plate, quality is good.
The utility model is described in detail above in association with accompanying drawing embodiment, those skilled in the art can root Many variations example is made to the utility model according to described above.Thus, some details in embodiment should not be formed to this practicality New restriction, the utility model will be used as the scope of protection of the utility model using the scope that appended claims define.

Claims (10)

  1. A kind of 1. working top plate mobile formwork body of underground pipe gallery, it is characterised in that including:
    Supporting frame of the branch on underground pipe gallery bottom plate, the bottom of support frame as described above body is provided with shifting roller;
    Support frame as described above body bottom and the adjustable bearing of bearing height set close to the shifting roller are installed in, passes through regulation The bearing height of the bearing is hanging to cause the shifting roller;
    It is installed in support frame as described above body top and the adjustable branch membrane module of bearing height;And
    The top template being installed on the branch membrane module, bearing height is adjusted with the backform by the branch membrane module Plate installs in place.
  2. 2. the working top plate mobile formwork body of underground pipe gallery as claimed in claim 1, it is characterised in that the backform The bottom surface of plate is installed with main joist;
    The branch membrane module includes support screw, the cradle being fixedly arranged on the support screw and located at the cradle two The top bracing member of side;
    The support screw is screwed together in the top of support frame as described above body, and support frame as described above is screwed together in by adjusting the support screw Realize the bearing height regulation of the branch membrane module in position at the top of body;
    Formed with the tank for housing the main joist on the cradle, the main joist is partially disposed in corresponding tank, and Part on the main joist in the tank is stayed on by the top bracing member, so as to which the main joist is fixed on into institute State in cradle.
  3. 3. the working top plate mobile formwork body of underground pipe gallery as claimed in claim 2, it is characterised in that the support Seat includes bottom plate, the block that is erected on the side plate of the bottom plate both sides and is fixedly arranged in the middle part of the bottom plate, the block with it is right The tank is formed between the side plate answered, for the top bracing member to press closer bolt, the bolt that presses closer is screwed together in the side plate.
  4. 4. the working top plate mobile formwork body of underground pipe gallery as claimed in claim 1, it is characterised in that the support Support body includes adjustable for height vertical rod, supports the cross bar being connected between two adjacent vertical rods and skewed horizontal load to be connected to phase Brace between two adjacent vertical rods, the adjustable length of the brace.
  5. 5. the working top plate mobile formwork body of underground pipe gallery as claimed in claim 4, it is characterised in that the brace Including the sleeve pipe positioned at middle part, the right-hand thread screw mandrel and left-hand thread screw mandrel at described sleeve pipe both ends are screwed together in, is made by rotating described sleeve pipe The right-hand thread screw mandrel and left-hand thread screw mandrel for obtaining both ends are stretched into described sleeve pipe or overhang to described sleeve pipe simultaneously, it is achieved thereby that Adjust the length of the brace.
  6. 6. the working top plate mobile formwork body of underground pipe gallery as claimed in claim 4, it is characterised in that the vertical rod Including the first pole and the second pole being socketed up and down, fixing hole, second pole are offered at the top of first pole Upper be spaced apart is provided with connecting hole, adjusts the depth that second pole is inserted in first pole, and wear by connecting bolt If the fixing hole is fixedly connected with first pole and second pole with corresponding connecting hole, it is achieved thereby that described vertical The height regulation of bar.
  7. 7. the working top plate mobile formwork body of underground pipe gallery as claimed in claim 4, it is characterised in that the vertical rod Periphery be installed with connection otic placode.
  8. 8. the working top plate mobile formwork body of underground pipe gallery as claimed in claim 1, it is characterised in that the bearing Including base, the screw rod being erected on base and the stiffener being fixedly arranged between the screw rod and the base, the screw rod The bottom of support frame as described above body is screwed together in, is screwed together in by adjusting the screw rod described in the position realization of support frame as described above body bottom The regulation of the bearing height of bearing.
  9. 9. the working top plate mobile formwork body of underground pipe gallery as claimed in claim 1, it is characterised in that also include vertical Supported rod erecting on the underground pipe gallery bottom plate and the morning at the top of the supported rod erecting tear structure, the support open Vertical rod is between two supporting frames, and the morning tears structure open and connect relatively with adjacent top template.
  10. 10. the working top plate mobile formwork body of underground pipe gallery as claimed in claim 1, it is characterised in that the top Template is connected with bracket close to the end of side wall, and the bottom of the bracket is connected with a side template, and the outside of the side wall is corresponding Being sticked at the side template has Side Template, the top of the Side Template and the either flush of top plate to be poured, the Side Template It is fastenedly connected with the side template by split bolt on corresponding side wall.
CN201720734669.2U 2017-06-22 2017-06-22 The working top plate mobile formwork body of underground pipe gallery Expired - Fee Related CN206971268U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720734669.2U CN206971268U (en) 2017-06-22 2017-06-22 The working top plate mobile formwork body of underground pipe gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720734669.2U CN206971268U (en) 2017-06-22 2017-06-22 The working top plate mobile formwork body of underground pipe gallery

Publications (1)

Publication Number Publication Date
CN206971268U true CN206971268U (en) 2018-02-06

Family

ID=61409696

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720734669.2U Expired - Fee Related CN206971268U (en) 2017-06-22 2017-06-22 The working top plate mobile formwork body of underground pipe gallery

Country Status (1)

Country Link
CN (1) CN206971268U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589772A (en) * 2018-04-28 2018-09-28 中国建筑第八工程局有限公司 Method is torn open for the platform modular system of piping lane top plate and the morning of early stripping formwork system
CN109469098A (en) * 2018-11-14 2019-03-15 上海市基础工程集团有限公司 For concrete box cell structure inner template running gear
CN111364516A (en) * 2020-04-17 2020-07-03 中国建筑土木建设有限公司 Supporting and dismantling walking system for pipeline gallery wallboard running water construction and construction method thereof
CN111878098A (en) * 2020-07-31 2020-11-03 中交隧道工程局有限公司 Concrete pouring device and method for shield starting base
CN114412511A (en) * 2022-01-18 2022-04-29 无锡信泰模架科技有限公司 Movable modular construction structure capable of being partitioned
CN115075293A (en) * 2022-07-15 2022-09-20 中铁二十五局集团有限公司 Pipe gallery template mobile device

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589772A (en) * 2018-04-28 2018-09-28 中国建筑第八工程局有限公司 Method is torn open for the platform modular system of piping lane top plate and the morning of early stripping formwork system
CN108589772B (en) * 2018-04-28 2024-01-23 中国建筑第八工程局有限公司 Bench formwork system for pipe gallery top plate and early dismantling method of early dismantling formwork
CN109469098A (en) * 2018-11-14 2019-03-15 上海市基础工程集团有限公司 For concrete box cell structure inner template running gear
CN111364516A (en) * 2020-04-17 2020-07-03 中国建筑土木建设有限公司 Supporting and dismantling walking system for pipeline gallery wallboard running water construction and construction method thereof
CN111878098A (en) * 2020-07-31 2020-11-03 中交隧道工程局有限公司 Concrete pouring device and method for shield starting base
CN114412511A (en) * 2022-01-18 2022-04-29 无锡信泰模架科技有限公司 Movable modular construction structure capable of being partitioned
CN115075293A (en) * 2022-07-15 2022-09-20 中铁二十五局集团有限公司 Pipe gallery template mobile device

Similar Documents

Publication Publication Date Title
CN206971268U (en) The working top plate mobile formwork body of underground pipe gallery
CN107313589A (en) Outer wall of basement one side steel form support system and its construction method
CN107700533B (en) A kind of box quick assembly and disassembly mould piping lane construction technology
CN102758451B (en) Concrete cable channel construction process
CN109736353A (en) Construction method of composite single-side formwork deep foundation pit basement outer wall
CN206971270U (en) Exterior wall formwork system in underground pipe gallery cast-in-place construction
CN104631512A (en) Post-cast strip beam and slab construction method adopting formwork hanging method
CN103422667B (en) Double-plate prefabricated superposed wall supporting system
CN108360814A (en) The unilateral erecting device of adjustable steel tube and its installation method
CN107386327A (en) U-type groove side wall no pulling rod formwork integrated with barricade and the faced wall being made up of the template
CN109577166A (en) On across active service highway door opening bracket and construction method
CN207314852U (en) Outer wall of basement one side steel form support system
CN111622482A (en) Simple support frame for steel structure overhanging plate edge and mounting method thereof
CN207944339U (en) A kind of prefabricated superposed type anti-collision wall for urban viaduct
CN107988913A (en) A kind of bridge bilayer box beam upper former method for dismounting
CN205558264U (en) Space reentrant corner system of clear water inclined wall switching clear water swash plate
CN207143746U (en) Support beam template system under concrete support trestle plate
CN207376649U (en) U-type groove side wall no pulling rod formwork integrated with barricade and the faced wall being made of the template
CN206539012U (en) Large span form bracing system
CN212773372U (en) Simple support frame for steel structure overhanging plate edge
CN102418417B (en) Long-slab-span cast-in-situ beam ribbed floor early-dismantling template formwork system
CN111809792B (en) Assembled precast concrete wallboard
CN214245823U (en) Advance through structure of new and old structure girder on two sides of mid-partition wall
CN208168339U (en) The unilateral erecting device of adjustable steel tube
CN208981019U (en) Ladder type prefabricated plate with auxiliary block

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180206