CN104695336A - Double-layer cast-in-situ beam support construction method adopting sequence from upper layer to lower layer - Google Patents

Double-layer cast-in-situ beam support construction method adopting sequence from upper layer to lower layer Download PDF

Info

Publication number
CN104695336A
CN104695336A CN201510019803.6A CN201510019803A CN104695336A CN 104695336 A CN104695336 A CN 104695336A CN 201510019803 A CN201510019803 A CN 201510019803A CN 104695336 A CN104695336 A CN 104695336A
Authority
CN
China
Prior art keywords
cast
place beam
support
steel pipe
place
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510019803.6A
Other languages
Chinese (zh)
Other versions
CN104695336B (en
Inventor
尹振君
范万祥
付浩
严杰
张德致
彭颇
芦登科
陶志力
苏醒
胡腾飞
陈红
王俊华
陈文�
安东航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
5th Engineering Co Ltd of MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
5th Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC, 5th Engineering Co Ltd of MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN201510019803.6A priority Critical patent/CN104695336B/en
Publication of CN104695336A publication Critical patent/CN104695336A/en
Application granted granted Critical
Publication of CN104695336B publication Critical patent/CN104695336B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a double-layer cast-in-situ beam support construction method adopting the sequence from the upper layer to the lower layer. In combination of comprehensive consideration of construction of upper-layer cast-in-situ beams and lower-layer cast-in-situ beams, the method that construction of two layers of cast-in-situ beams is met through one support is designed, that is, the upper-layer cast-in-situ beams and the lower-layer cast-in-situ beams share one support. After construction of the upper-layer cast-in-situ beams is finished, upper-layer support steel tubes are dismounted, bailey beams are lowered integrally to a lower-layer cast-in-situ beam support, an upper-layer cast-in-situ beam support is converted into the lower-layer cast-in-situ beam support directly, the high-altitude construction difficulty of the support is reduced, meanwhile, the use time of large hoisting equipment is shortened, the construction process is accelerated, and damage of the lower-layer cast-in-situ beam body due to construction of the upper-layer cast-in-situ beams is avoided.

Description

双层现浇梁先上后下支架施工方法Construction method of double-layer cast-in-place beam first up and then down

技术领域 technical field

本发明涉及桥梁工程基础的施工方法,尤其是涉及一种根据上层现浇梁比下层现浇梁宽的结构形式,采用先施工上层现浇梁后施工下层的现浇梁支架施工方法。 The invention relates to a construction method of a bridge engineering foundation, in particular to a construction method for a cast-in-place beam support in which the upper-layer cast-in-place beam is constructed first and then the lower-layer cast-in-place beam is constructed according to the structural form that the upper layer is wider than the lower layer.

背景技术 Background technique

随着我国基础建设投入不断增大,桥梁建设迅速发展,为减少建设成本和建筑用地,国内很多跨江、跨河桥梁采用双层结构形式,且上层现浇梁比下层现浇梁宽的结构形式。 With the increasing investment in infrastructure construction in our country, bridge construction is developing rapidly. In order to reduce construction costs and construction land, many cross-river and river-crossing bridges in China adopt a double-layer structure, and the upper cast-in-place girder is wider than the lower cast-in-place girder. form.

传统的双层现浇梁支架施工方法一般采用先施工下层现浇梁,然后再按照上层现浇梁宽度搭设支架,本方法存在以下缺点:1、当上层现浇梁宽于下层现浇梁时,施工上层现浇梁的支架将受到已浇筑完成的下层现浇梁的影响,上层现浇梁现浇支架需一部分支撑在下层现浇梁顶面,另一部分需在下层现浇梁范围以外从地面搭设钢管支架,往往存在支撑于下层现浇梁上支架高度与支撑地面的支架高度长度相差较大(一般相差几十米),导致支架刚度不匹配问题、地基沉降和梁变形不一致问题。2、需单独增加布置部分上层现浇梁支架基础和支架,投入较大。3、支架的安装和拆除较烦琐,施工工期较长,整个支架施工成本较高。4、上层现浇梁施工容易造成对下层现浇梁的损伤。 The traditional double-layer cast-in-place beam support construction method generally adopts the construction of the lower floor cast-in-place beam first, and then erects the support according to the width of the upper floor cast-in-place beam. This method has the following disadvantages: 1. When the upper floor cast-in-place beam is wider than the lower floor cast-in-place beam The support of the cast-in-place beam on the upper floor will be affected by the cast-in-place beam on the lower floor. Part of the cast-in-place beam support on the upper floor needs to be supported on the top surface of the cast-in-place beam on the lower floor, and the other part needs to be supported outside the scope of the cast-in-place beam on the lower floor. When the steel pipe support is erected on the ground, there is often a large difference between the height of the support on the lower cast-in-place beam and the height and length of the support supporting the ground (generally, the difference is tens of meters), resulting in mismatching of support stiffness, foundation settlement and inconsistent beam deformation. 2. It is necessary to separately increase the layout of some upper cast-in-place beam support foundations and supports, and the investment is relatively large. 3. The installation and dismantling of the bracket is cumbersome, the construction period is long, and the construction cost of the whole bracket is relatively high. 4. The construction of the upper cast-in-place beams is easy to cause damage to the lower cast-in-place beams.

发明内容 Contents of the invention

本发明的目的在于提供一种上层现浇梁和下层现浇梁共用一套支架、减少支架高空施工难度、同时也减少大型起重设备的使用时间、加快施工进度、避免因上层现浇梁施工对下层现浇梁体的损坏双层现浇梁先上后下支架施工方法。 The purpose of the present invention is to provide a set of supports shared by the upper cast-in-place beam and the lower cast-in-place beam, which reduces the difficulty of high-altitude construction of the support, and at the same time reduces the use time of large lifting equipment, speeds up the construction progress, and avoids the construction of the upper cast-in-place beam. Damage to the cast-in-place beam body of the lower layer The construction method of the double-layer cast-in-place beam first up and then down.

本发明的目的是这样实现的: The purpose of the present invention is achieved like this:

一种双层现浇梁先上后下支架施工方法,特征是: A double-layer cast-in-place beam first up and then down support construction method, characterized by:

A、首先根据上层现浇梁和下层现浇梁的结构形式,合理设计上层现浇梁和下层现浇梁共用一套支架的设计图; A. Firstly, according to the structural form of the upper cast-in-place beam and the lower cast-in-place beam, rationally design the design drawing of the upper cast-in-place beam and the lower cast-in-place beam sharing a set of brackets;

B、按设计图纸在承台和跨中支架基础钻孔桩施工时预埋支架预埋件; B. According to the design drawings, pre-embed the embedded parts of the support during the construction of the bored pile of the cap platform and mid-span support foundation;

C、安装支架底节钢管,将支架底节钢管与支架预埋件焊接; C. Install the steel pipe at the bottom section of the bracket, and weld the steel pipe at the bottom section of the bracket with the embedded parts of the bracket;

D、支架底节钢管安装好后,在支架底节钢管上连接用来加长的下层现浇梁支架钢管标准节,下层现浇梁支架钢管标准节的节段与节段间通过法兰上螺栓连接; D. After the steel pipe of the bottom section of the bracket is installed, connect the standard steel pipe section of the lower cast-in-place beam support steel pipe for lengthening on the steel pipe of the bottom section of the support, and bolts on the flange are used between the sections and sections of the steel pipe standard section of the cast-in-place beam support of the lower floor connect;

E、下层现浇梁支架钢管标准节的节段安装完后,依次安装下层支架钢管横向连接系、纵向连接系; E. After the standard sections of the steel pipes of the cast-in-place beam support on the lower floor are installed, install the horizontal connection system and the longitudinal connection system of the steel pipes on the lower floor in sequence;

F、安装下层现浇梁支架柱顶节段钢管; F. Install the steel pipe at the top of the cast-in-place beam support column on the lower floor;

G、下层现浇梁支架安装完成后,在下层现浇梁支架柱顶节段钢管上连接用来加长的上层现浇梁支架钢管标准节,上层现浇梁支架钢管标准节的节段与节段间通过法兰上螺栓连接; G. After the installation of the lower cast-in-place beam support is completed, the upper cast-in-place beam support steel pipe standard section for lengthening is connected to the lower steel cast-in-place beam support column top section steel pipe, and the upper cast-in-place beam support steel pipe standard section and section The sections are connected by bolts on the flange;

H、上层现浇梁支架钢管标准节的节段安装完后,依次安装上层支架钢管横向连接系、纵向连接系; H. After the standard section of the steel pipe standard section of the upper cast-in-place beam support is installed, install the horizontal connection system and the longitudinal connection system of the steel pipe of the upper support in sequence;

I、安装上层现浇梁柱顶节段钢管; I. Install steel pipes at the top of cast-in-place beams and columns on the upper floor;

J、安装上层现浇梁支架砂筒; J. Install the upper cast-in-place beam support sand cylinder;

K、安装上层现浇梁支架柱顶分配梁; K. Install the distribution beam at the top of the cast-in-place beam support column;

L、根据吊机起吊能力在地面分组进行组拼上层现浇梁支架贝雷梁,然后利用吊机安装贝雷梁; L. According to the hoisting capacity of the crane, assemble the Bailey beam of the upper cast-in-place beam support in groups on the ground, and then use the crane to install the Bailey beam;

M、上层现浇梁支架堆载预压; M. Preloading of upper cast-in-place beam support;

N、上层现浇梁钢筋、模板、混凝土、预应力施工 N. Upper layer cast-in-place beam reinforcement, formwork, concrete, prestressed construction

O、安装贝雷梁的整体下放装置,拆除上层现浇梁支架钢管; O. Install the overall lowering device of the Bailey beam, and remove the upper cast-in-place beam support steel pipe;

P、安装下层现浇梁支架砂筒; P. Install the lower cast-in-place beam support sand cylinder;

Q、安装下层现浇梁支架柱顶分配梁; Q. Install the distribution beam at the top of the cast-in-place beam support column on the lower floor;

R、将上层现浇梁支架的贝雷梁整体下放至下层现浇梁支架上,并拆除多余的贝雷梁; R. Lower the Bailey beams of the cast-in-place beam support on the upper floor to the cast-in-place beam support of the lower floor as a whole, and remove the redundant Bailey beams;

S、下层现浇梁钢筋、模板、混凝土、预应力施工; S, cast-in-place beam reinforcement, formwork, concrete, and prestressed construction of the lower floor;

T、拆除下层现浇梁支架,完成上层现浇梁和下层现浇梁的施工。 T. Remove the lower cast-in-place beam support, and complete the construction of the upper cast-in-place beam and the lower cast-in-place beam.

本发明是结合上层现浇梁和下层现浇梁施工综合考虑,设计共用一套支架满足两层现浇梁施工(即上层现浇梁和下层现浇梁共用一套支架),上层现浇梁施工完后,通过拆除上层支架钢管和贝雷梁整体下放至下层现浇梁支架上,实现上层现浇梁支架直接转换成下层现浇梁支架,减少支架高空施工难度,同时也减少大型起重设备的使用时间,加快施工进度,避免了因上层现浇梁施工对下层现浇梁体的损坏。它具有如下优点: The present invention is based on the comprehensive consideration of the construction of the upper cast-in-place beam and the lower cast-in-place beam, and the design shares a set of supports to meet the construction of two layers of cast-in-place beams (that is, the upper cast-in-place beam and the lower cast-in-place beam share a set of supports), and the upper cast-in-place beam After the construction is completed, the steel pipes of the upper support and the Bailey beams are lowered to the lower cast-in-place beam support as a whole, so that the upper cast-in-place beam support can be directly converted into the lower cast-in-place beam support, reducing the difficulty of high-altitude construction of the support and reducing large-scale lifting The use time of the equipment is shortened, the construction progress is accelerated, and the damage to the lower cast-in-place beam body due to the construction of the upper cast-in-place beam is avoided. It has the following advantages:

1、支架布置结合上层现浇梁和下层现浇梁施工综合考虑,两层现浇梁施工共用一套支架,避免了支架刚度不匹配和基础变形不一致问题,有效地确保了现浇梁支架整体稳定性和结构安全; 1. The layout of the brackets is combined with the comprehensive consideration of the construction of the upper layer cast-in-place beams and the lower layer cast-in-place beams. The construction of the two layers of cast-in-place beams shares a set of brackets, which avoids the problems of mismatching bracket stiffness and inconsistent foundation deformation, and effectively ensures the integrity of the cast-in-place beam brackets. stability and structural safety;

2、上下两层现浇梁施工共用一套支架,能减少支架基础和支架投入。 2. The upper and lower floors of cast-in-place beams share a set of brackets, which can reduce the investment in bracket foundation and brackets.

3、施工完上层现浇梁后,可直接整体下放贝雷梁支架,用以施工下层现浇梁,减少支架安装和拆除施工难度, 缩短了关键工序转换时间。 3. After the construction of the upper cast-in-place beam, the Bailey beam support can be directly lowered as a whole to construct the lower cast-in-place beam, which reduces the difficulty of installing and dismantling the support, and shortens the conversion time of key processes.

4、避免了对下层现浇梁的损伤。 4. Avoiding damage to the lower cast-in-place beams.

附图说明 Description of drawings

图1 为本发明的上层现浇梁的支架结构示意图; Fig. 1 is the support structure schematic diagram of upper floor cast-in-place beam of the present invention;

图2 为图1中Ⅰ-Ⅰ向示意图; Figure 2 is a schematic diagram of the I-I direction in Figure 1;

图3 为图1中Ⅱ-Ⅱ向示意图; Figure 3 is a schematic diagram of II-II in Figure 1;

图4 为本发明的下层现浇梁的支架结构示意图; Fig. 4 is the support structure schematic diagram of lower floor cast-in-place beam of the present invention;

图5 为图2中Ⅲ-Ⅲ向示意图; Fig. 5 is a schematic diagram of direction III-III in Fig. 2;

图6 为图2中Ⅳ-Ⅳ向示意图; Fig. 6 is a schematic diagram in the direction of IV-IV in Fig. 2;

图7为贝雷梁整体下放装置的示意图; Fig. 7 is the schematic diagram of Bailey beam overall lowering device;

图8-图26 依次为本发明的施工步骤B-T示意图。 Fig. 8-Fig. 26 is the schematic diagram of construction step B-T of the present invention successively.

具体实施方式 Detailed ways

下面结合实施例并对照附图对本发明作进一步详细说明。 The present invention will be described in further detail below in conjunction with the embodiments and with reference to the accompanying drawings.

本发明的施工设备由支架基础钻孔桩1、支架钢管预埋件2、支架钢管300、连接系400、砂筒5、柱顶分配梁6、贝雷梁7、下放装置800、吊机9组成。 The construction equipment of the present invention consists of a support foundation bored pile 1, a support steel pipe embedded part 2, a support steel pipe 300, a connecting system 400, a sand cylinder 5, a column top distribution beam 6, a Bailey beam 7, a lowering device 800, and a crane 9 composition.

支架基础钻孔桩1:跨中支架基础处理采用比钢管直径大20cm钻孔桩。 Bored piles for support foundation 1: Bored piles 20cm larger in diameter than steel pipes are used for mid-span support foundation treatment.

支架钢管预埋件2:墩旁承台和支架基础钻孔桩混凝土施工时,在其顶面埋设支架钢管预埋件。 Support steel pipe embedded parts 2: During the concrete construction of the pier side cap and support foundation bored pile concrete, the support steel pipe embedded parts are buried on the top surface.

支架钢管300:根据设计图支架钢管总长度,合理对支架钢管进行分节,底节钢管301长度根据预埋件顶标高而确定,顶口带法兰,标准节段302长度为8m,顶底口带法兰,柱顶节段303长度为1m,顶底口带法兰,均由专业钢结构生产。底节钢管301与预埋件2焊接,底节钢管301、标准节段302、柱顶节段303之间采用法兰上螺栓连接。 Support steel pipe 300: According to the total length of the support steel pipe in the design drawing, reasonably divide the support steel pipe into sections. The length of the bottom section steel pipe 301 is determined according to the top elevation of the embedded part. The mouth has a flange, the column top section 303 has a length of 1m, and the top and bottom mouths have flanges, all of which are produced by professional steel structures. The bottom section steel pipe 301 is welded to the embedded part 2, and the bottom section steel pipe 301, the standard section 302, and the column top section 303 are connected by flange bolts.

连接系400:支架钢管安装到连接系400的位置时,及时将钢管通过连接系400进行连接。 Connection system 400 : when the support steel pipe is installed at the position of the connection system 400 , connect the steel pipe through the connection system 400 in time.

砂筒5:根据设计荷载,由专业钢结构厂家生产,砂筒5主要用来拆除底模,砂筒布置在钢管柱顶节段303上。 Sand cylinder 5: According to the design load, it is produced by a professional steel structure manufacturer. The sand cylinder 5 is mainly used to remove the bottom mold, and the sand cylinder is arranged on the top segment 303 of the steel pipe column.

柱顶分配梁6:根据计算,采用型钢组合加工而成,柱顶分配梁6摆放在砂筒5上。 Column top distribution beam 6: According to the calculation, it is processed by combination of section steel, and the column top distribution beam 6 is placed on the sand cylinder 5.

贝雷梁7:租赁市场上标准贝雷梁7,根据设计计算,合理布置贝雷梁7,同时综合考虑上层和下层贝雷梁7分组的通用性,这样上层贝雷梁7可以直接转换成下层贝雷梁7使用。 Bailey beam 7: The standard Bailey beam 7 in the rental market, according to the design calculation, the Bailey beam 7 is reasonably arranged, and at the same time, the versatility of the grouping of the upper and lower Bailey beams is considered, so that the upper Bailey beam 7 can be directly converted into Lower Bailey Beam 7 used.

下放装置800:每套下放装置由2根精轧螺纹钢筋801、6个螺母802、2个垫板803、4个活动垫板804、1根下锚梁806、1根垫梁807、1套千斤顶设备805,1根上锚梁A808、1根上锚梁B809组成。精轧螺纹钢筋801、螺母802、垫板803、活动垫板804、千斤顶设备805为定型产品,下锚梁806、垫梁807、上锚梁A808、上锚梁B809为由型钢组合加工而成。 Lowering device 800: each set of lowering device consists of 2 fine-rolled threaded steel bars 801, 6 nuts 802, 2 backing plates 803, 4 movable backing plates 804, 1 lower anchor beam 806, 1 backing beam 807, 1 set Jack equipment 805 consists of one upper anchor beam A808 and one upper anchor beam B809. Finished threaded steel bar 801, nut 802, backing plate 803, movable backing plate 804, and jack equipment 805 are stereotyped products, and the lower anchor beam 806, backing beam 807, upper anchor beam A808, and upper anchor beam B809 are combined and processed by section steel .

吊机9:根据现场工况,选择机械性能满足吊距吊重的要求吊机9。 Crane 9: According to the on-site working conditions, select the crane 9 whose mechanical properties meet the requirements of the lifting distance.

一种双层现浇梁先上后下支架施工方法,具体步骤如下: A construction method for double-layer cast-in-place beams first up and then down, the specific steps are as follows:

A、首先根据上层现浇梁和下层现浇梁的结构形式,合理设计上层现浇梁和下层现浇梁共用一套支架的设计图; A. Firstly, according to the structural form of the upper cast-in-place beam and the lower cast-in-place beam, rationally design the design drawing of the upper cast-in-place beam and the lower cast-in-place beam sharing a set of brackets;

B、按设计图纸在承台和跨中支架基础钻孔桩施工时预埋支架预埋件; B. According to the design drawings, pre-embed the embedded parts of the support during the construction of the bored pile of the cap platform and mid-span support foundation;

C、安装支架底节钢管,将支架底节钢管与支架预埋件焊接; C. Install the steel pipe at the bottom section of the bracket, and weld the steel pipe at the bottom section of the bracket with the embedded parts of the bracket;

D、支架底节钢管安装好后,在支架底节钢管上连接用来加长的下层现浇梁支架钢管标准节,下层现浇梁支架钢管标准节的节段与节段间通过法兰上螺栓连接; D. After the steel pipe of the bottom section of the bracket is installed, connect the standard steel pipe section of the lower cast-in-place beam support steel pipe for lengthening on the steel pipe of the bottom section of the support, and bolts on the flange are used between the sections and sections of the steel pipe standard section of the cast-in-place beam support of the lower floor connect;

E、下层现浇梁支架钢管标准节的节段安装完后,依次安装下层支架钢管横向连接系、纵向连接系; E. After the standard sections of the steel pipes of the cast-in-place beam support on the lower floor are installed, install the horizontal connection system and the longitudinal connection system of the steel pipes on the lower floor in sequence;

F、安装下层现浇梁支架柱顶节段钢管; F. Install the steel pipe at the top of the cast-in-place beam support column on the lower floor;

G、下层现浇梁支架安装完成后,在下层现浇梁支架柱顶节段钢管上连接用来加长的上层现浇梁支架钢管标准节,上层现浇梁支架钢管标准节的节段与节段间通过法兰上螺栓连接; G. After the installation of the lower cast-in-place beam support is completed, the upper cast-in-place beam support steel pipe standard section for lengthening is connected to the lower steel cast-in-place beam support column top section steel pipe, and the upper cast-in-place beam support steel pipe standard section and section The sections are connected by bolts on the flange;

H、上层现浇梁支架钢管标准节的节段安装完后,依次安装上层支架钢管横向连接系、纵向连接系; H. After the standard section of the steel pipe standard section of the upper cast-in-place beam support is installed, install the horizontal connection system and the longitudinal connection system of the steel pipe of the upper support in sequence;

I、安装上层现浇梁柱顶节段钢管; I. Install steel pipes at the top of cast-in-place beams and columns on the upper floor;

J、安装上层现浇梁支架砂筒; J. Install the upper cast-in-place beam support sand cylinder;

K、安装上层现浇梁支架柱顶分配梁; K. Install the distribution beam at the top of the cast-in-place beam support column;

L、根据吊机起吊能力在地面分组进行组拼上层现浇梁支架贝雷梁,然后利用吊机安装贝雷梁; L. According to the hoisting capacity of the crane, assemble the Bailey beam of the upper cast-in-place beam support in groups on the ground, and then use the crane to install the Bailey beam;

M、上层现浇梁支架堆载预压; M. Preloading of upper cast-in-place beam support;

N、上层现浇梁钢筋、模板、混凝土、预应力施工 N. Upper layer cast-in-place beam reinforcement, formwork, concrete, prestressed construction

O、安装贝雷梁的整体下放装置,拆除上层现浇梁支架钢管; O. Install the overall lowering device of the Bailey beam, and remove the upper cast-in-place beam support steel pipe;

P、安装下层现浇梁支架砂筒; P. Install the lower cast-in-place beam support sand cylinder;

Q、安装下层现浇梁支架柱顶分配梁; Q. Install the distribution beam at the top of the cast-in-place beam support column on the lower floor;

R、将上层现浇梁支架的贝雷梁整体下放至下层现浇梁支架上,并拆除多余的贝雷梁; R. Lower the Bailey beams of the cast-in-place beam support on the upper floor to the cast-in-place beam support of the lower floor as a whole, and remove the redundant Bailey beams;

S、下层现浇梁钢筋、模板、混凝土、预应力施工; S, cast-in-place beam reinforcement, formwork, concrete, and prestressed construction of the lower floor;

T、拆除下层现浇梁支架,完成上层现浇梁和下层现浇梁的施工。 T. Remove the lower cast-in-place beam support, and complete the construction of the upper cast-in-place beam and the lower cast-in-place beam.

Claims (1)

1.一种双层现浇梁先上后下支架施工方法,其特征在于: 1. A double-layer cast-in-place beam first up and down support construction method, characterized in that: A、首先根据上层现浇梁和下层现浇梁的结构形式,合理设计上层现浇梁和下层现浇梁共用一套支架的设计图; A. Firstly, according to the structural form of the upper cast-in-place beam and the lower cast-in-place beam, rationally design the design drawing of the upper cast-in-place beam and the lower cast-in-place beam sharing a set of brackets; B、按设计图纸在承台和跨中支架基础钻孔桩施工时预埋支架预埋件; B. According to the design drawings, pre-embed the embedded parts of the support during the construction of the bored pile of the cap platform and mid-span support foundation; C、安装支架底节钢管,将支架底节钢管与支架预埋件焊接; C. Install the steel pipe at the bottom section of the bracket, and weld the steel pipe at the bottom section of the bracket with the embedded parts of the bracket; D、支架底节钢管安装好后,在支架底节钢管上连接用来加长的下层现浇梁支架钢管标准节,下层现浇梁支架钢管标准节的节段与节段间通过法兰上螺栓连接; D. After the steel pipe of the bottom section of the bracket is installed, connect the standard steel pipe section of the lower cast-in-place beam support steel pipe for lengthening on the steel pipe of the bottom section of the support, and bolts on the flange are used between the sections and sections of the steel pipe standard section of the cast-in-place beam support of the lower floor connect; E、下层现浇梁支架钢管标准节的节段安装完后,依次安装下层支架钢管横向连接系、纵向连接系; E. After the standard sections of the steel pipes of the cast-in-place beam support on the lower floor are installed, install the horizontal connection system and the longitudinal connection system of the steel pipes on the lower floor in sequence; F、安装下层现浇梁支架柱顶节段钢管; F. Install the steel pipe at the top of the cast-in-place beam support column on the lower floor; G、下层现浇梁支架安装完成后,在下层现浇梁支架柱顶节段钢管上连接用来加长的上层现浇梁支架钢管标准节,上层现浇梁支架钢管标准节的节段与节段间通过法兰上螺栓连接; G. After the installation of the lower cast-in-place beam support is completed, the upper cast-in-place beam support steel pipe standard section for lengthening is connected to the lower steel cast-in-place beam support column top section steel pipe, and the upper cast-in-place beam support steel pipe standard section and section The sections are connected by bolts on the flange; H、上层现浇梁支架钢管标准节的节段安装完后,依次安装上层支架钢管横向连接系、纵向连接系; H. After the standard section of the steel pipe standard section of the upper cast-in-place beam support is installed, install the horizontal connection system and the longitudinal connection system of the steel pipe of the upper support in sequence; I、安装上层现浇梁柱顶节段钢管; I. Install steel pipes at the top of cast-in-place beams and columns on the upper floor; J、安装上层现浇梁支架砂筒; J. Install the upper cast-in-place beam support sand cylinder; K、安装上层现浇梁支架柱顶分配梁; K. Install the distribution beam at the top of the cast-in-place beam support column; L、根据吊机起吊能力在地面分组进行组拼上层现浇梁支架贝雷梁,然后利用吊机安装贝雷梁; L. According to the hoisting capacity of the crane, assemble the Bailey beam of the upper cast-in-place beam support in groups on the ground, and then use the crane to install the Bailey beam; M、上层现浇梁支架堆载预压; M. Preloading of upper cast-in-place beam support; N、上层现浇梁钢筋、模板、混凝土、预应力施工 N. Upper layer cast-in-place beam reinforcement, formwork, concrete, prestressed construction O、安装贝雷梁的整体下放装置,拆除上层现浇梁支架钢管; O. Install the overall lowering device of the Bailey beam, and remove the upper cast-in-place beam support steel pipe; P、安装下层现浇梁支架砂筒; P. Install the lower cast-in-place beam support sand cylinder; Q、安装下层现浇梁支架柱顶分配梁; Q. Install the distribution beam at the top of the cast-in-place beam support column on the lower floor; R、将上层现浇梁支架的贝雷梁整体下放至下层现浇梁支架上,并拆除多余的贝雷梁; R. Lower the Bailey beams of the cast-in-place beam support on the upper floor to the cast-in-place beam support of the lower floor as a whole, and remove the redundant Bailey beams; S、下层现浇梁钢筋、模板、混凝土、预应力施工; S, cast-in-place beam reinforcement, formwork, concrete, and prestressed construction of the lower floor; T、拆除下层现浇梁支架,完成上层现浇梁和下层现浇梁的施工。 T. Remove the lower cast-in-place beam support, and complete the construction of the upper cast-in-place beam and the lower cast-in-place beam.
CN201510019803.6A 2015-01-15 2015-01-15 The double-deck first up and then down stand construction method of Cast-in-situ Beam Active CN104695336B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510019803.6A CN104695336B (en) 2015-01-15 2015-01-15 The double-deck first up and then down stand construction method of Cast-in-situ Beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510019803.6A CN104695336B (en) 2015-01-15 2015-01-15 The double-deck first up and then down stand construction method of Cast-in-situ Beam

Publications (2)

Publication Number Publication Date
CN104695336A true CN104695336A (en) 2015-06-10
CN104695336B CN104695336B (en) 2016-09-28

Family

ID=53342852

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510019803.6A Active CN104695336B (en) 2015-01-15 2015-01-15 The double-deck first up and then down stand construction method of Cast-in-situ Beam

Country Status (1)

Country Link
CN (1) CN104695336B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107044090A (en) * 2017-05-09 2017-08-15 中铁大桥局集团有限公司 A kind of construction method of dual deck bridge
CN107268682A (en) * 2017-07-04 2017-10-20 中铁十二局集团有限公司 The inverted construction method of railway station building half
CN107988913A (en) * 2017-12-12 2018-05-04 中交公局第二工程有限公司 A kind of bridge bilayer box beam upper former method for dismounting
CN108049314A (en) * 2017-12-12 2018-05-18 中交公局第二工程有限公司 A kind of bridge double layer box beam construction method
CN110878525A (en) * 2019-11-06 2020-03-13 武船重型工程股份有限公司 Double-layer steel box girder bridge installation method and combined support for installation
CN112160254A (en) * 2020-11-02 2021-01-01 中建八局第二建设有限公司 Construction method of high-simply-supported cast-in-place beam assembly type steel pipe-Bailey beam support
CN112832136A (en) * 2021-01-06 2021-05-25 中铁大桥局集团第四工程有限公司 A cast-in-place bracket on a beam and its graded local preloading method
CN112921813A (en) * 2021-01-25 2021-06-08 中建科工集团有限公司 Double-layer multi-span bridge construction method
CN113481853A (en) * 2021-07-02 2021-10-08 中交武汉港湾工程设计研究院有限公司 Mobile factory for concrete cast-in-place of door type double-layer highway-railway dual-purpose bridge
CN113585076A (en) * 2021-07-08 2021-11-02 中国建筑第六工程局有限公司 Construction method of overwater large-span double-layer cast-in-place beam

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101457515A (en) * 2008-12-26 2009-06-17 中铁大桥局集团第二工程有限公司 In situ cast-in-situ steel girder railway bridge deck pre-stress concrete channel beam construction method
CN101793006A (en) * 2009-12-23 2010-08-04 中铁大桥局集团第一工程有限公司 Construction method for rapid construction of support cast-in-situ continuous beam
CN102383374A (en) * 2011-11-28 2012-03-21 湖南大学 Prefabricated Fiber Concrete Composite Bridge Deck Structure and Its Construction Method
JP2012229071A (en) * 2011-04-25 2012-11-22 Ihi Infrastructure Systems Co Ltd Operational construction method by means of goliath crane
KR20120132084A (en) * 2011-05-27 2012-12-05 삼표건설 주식회사 Composite bridge and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101457515A (en) * 2008-12-26 2009-06-17 中铁大桥局集团第二工程有限公司 In situ cast-in-situ steel girder railway bridge deck pre-stress concrete channel beam construction method
CN101793006A (en) * 2009-12-23 2010-08-04 中铁大桥局集团第一工程有限公司 Construction method for rapid construction of support cast-in-situ continuous beam
JP2012229071A (en) * 2011-04-25 2012-11-22 Ihi Infrastructure Systems Co Ltd Operational construction method by means of goliath crane
KR20120132084A (en) * 2011-05-27 2012-12-05 삼표건설 주식회사 Composite bridge and construction method thereof
CN102383374A (en) * 2011-11-28 2012-03-21 湖南大学 Prefabricated Fiber Concrete Composite Bridge Deck Structure and Its Construction Method

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107044090A (en) * 2017-05-09 2017-08-15 中铁大桥局集团有限公司 A kind of construction method of dual deck bridge
CN107044090B (en) * 2017-05-09 2019-02-15 中铁大桥局集团有限公司 A method of constructing a double-deck bridge
CN107268682A (en) * 2017-07-04 2017-10-20 中铁十二局集团有限公司 The inverted construction method of railway station building half
CN107268682B (en) * 2017-07-04 2019-12-27 中铁十二局集团有限公司 Semi-reverse-sequence construction method for railway station house
CN107988913A (en) * 2017-12-12 2018-05-04 中交公局第二工程有限公司 A kind of bridge bilayer box beam upper former method for dismounting
CN108049314A (en) * 2017-12-12 2018-05-18 中交公局第二工程有限公司 A kind of bridge double layer box beam construction method
CN110878525A (en) * 2019-11-06 2020-03-13 武船重型工程股份有限公司 Double-layer steel box girder bridge installation method and combined support for installation
CN110878525B (en) * 2019-11-06 2022-04-05 武船重型工程股份有限公司 Double-layer steel box girder bridge installation method and combined support for installation
CN112160254A (en) * 2020-11-02 2021-01-01 中建八局第二建设有限公司 Construction method of high-simply-supported cast-in-place beam assembly type steel pipe-Bailey beam support
CN112160254B (en) * 2020-11-02 2024-09-06 中建八局第二建设有限公司 Construction method of high-simple-support cast-in-situ beam assembled steel pipe-bailey beam bracket
CN112832136A (en) * 2021-01-06 2021-05-25 中铁大桥局集团第四工程有限公司 A cast-in-place bracket on a beam and its graded local preloading method
CN112921813A (en) * 2021-01-25 2021-06-08 中建科工集团有限公司 Double-layer multi-span bridge construction method
CN113481853A (en) * 2021-07-02 2021-10-08 中交武汉港湾工程设计研究院有限公司 Mobile factory for concrete cast-in-place of door type double-layer highway-railway dual-purpose bridge
CN113585076A (en) * 2021-07-08 2021-11-02 中国建筑第六工程局有限公司 Construction method of overwater large-span double-layer cast-in-place beam

Also Published As

Publication number Publication date
CN104695336B (en) 2016-09-28

Similar Documents

Publication Publication Date Title
CN104695336B (en) The double-deck first up and then down stand construction method of Cast-in-situ Beam
CN208072213U (en) A kind of steel box-girder installation temporary support
CN102808383B (en) Curved bridge counter-slope jacking construction process
CN203229874U (en) Repeatedly used cast-in-place support system for simply-supported beam
CN105735139B (en) Supporting system for construction of cast-in-situ box beam in overpass and construction method of box beam
CN211947993U (en) Support for large-span cast-in-situ bridge construction
CN102691266B (en) Construction Method of Superelevation Composite Support in Cast-in-place Section of Side Span of Bridge
CN105507168A (en) Multi-span box girder integral ultrahigh alternate jacking construction system and method
CN115369749A (en) Pier column-beam-bent cap beam integrated public rail double-layer viaduct and construction method
CN110409319A (en) A kind of cast-in-place floorings bracket of large span steel reinforced concrete combination beam and construction method
CN101691813B (en) Device and method for elevation synchronous compensation for super-high structure construction
CN103233426A (en) Bailey beam support free of buttress in soft foundation and supporting method thereof
CN111622091B (en) Stress test method for prefabricated bridge pier
CN111851252A (en) A steel-concrete composite arch bridge spanning a karst cave in a tunnel and its construction method
CN114086473B (en) High pier cast-in-situ beam bracket and construction method thereof
CN116084293A (en) Cast-in-place concrete main arch ring three-angle steel arch frame formwork system and construction method
CN116254783A (en) A high-level falling beam construction method suitable for the erection of prefabricated box girders on high-speed railways
CN110184915A (en) The cast-in-place king-post of cable-stayed bridge and its construction method
CN116145556A (en) Construction method for ectopic assembly and translational positioning of high-large steel truss girder adjacent to high-speed railway line
WO2025152576A1 (en) Segmented jacking device with alternately stressed steel slideways and column cores and construction method therefor
CN116516983B (en) Tide-affected steel-concrete combined inner support for deep foundation pit in river and construction method
CN112160247A (en) An asynchronous hydraulic climbing formwork construction method for hollow high piers in a limited space bridge pier group
CN218813204U (en) Few-bracket self-bearing system for corrugated steel web
CN205501840U (en) A braced system for construction of overpass cast -in -situ box girder
CN116837739A (en) Bailey beam disc buckling frame mixing method suitable for middle-small cast-in-situ box beam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant