CN107869156A CN201711264724.7A CN201711264724A CN107869156A CN 107869156 A CN107869156 A CN 107869156A CN 201711264724 A CN201711264724 A CN 201711264724A CN 107869156 A CN107869156 A CN 107869156A
Authority
CN
China
Prior art keywords
rig
pipe
foundation pile
pile
wave
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711264724.7A
Other languages
Chinese (zh)
Other versions
CN107869156B (en
Inventor
吴宝杰
杨桦
侯宏伟
黄林伟
徐芫蕾
臧端
唐绍明
顾晓卫
钱志华
金鑫
郑威
刘博�
饶秋琛
凌捷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Longzhou Construction Engineering Co., Ltd
Original Assignee
侯宏伟
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 侯宏伟 filed Critical 侯宏伟
Priority to CN201711264724.7A priority Critical patent/CN107869156B/en
Publication of CN107869156A publication Critical patent/CN107869156A/en
Application granted granted Critical
Publication of CN107869156B publication Critical patent/CN107869156B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Geophysics And Detection Of Objects (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Earth Drilling (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The detection means of foundation pile length is determined based on parallel seismic wave method, including rig and trigger under exciting hammer, main frame, rig, righting, trigger is placed on the cushion cap of the foundation pile, main frame is connected with data circuit group with trigger, it is characterized in that, the rig includes drill body, the bottom of the drill body is provided with drill bit, top is provided with motor, the screw rod of motor driven rotation is installed in the drill body, it is provided between the screw rod and drill bit and pulverizes pillar, beneficial effects of the present invention:The present invention is structure as a whole by the way that detection means is laid, and speed is fast when detection, and can detect at any time need not be pre-perforated, is reduced the engineering time, is adapted to promote the use of.

Description

Parallel seismic wave method determines the detection method of foundation pile length
Technical field
The present invention relates to one kind based on parallel seismic wave method detection foundation pile device for detecting length, belong to building detection technique neck Domain.
Background technology
With the fast development of economic construction, high buildings and large mansions are continued to bring out, and pile foundation engineering is developed on an unprecedented scale, pile foundation It is the base form being most widely used at present.Because pile foundation engineering construction has height disguised, it is found that quality problems are relative More difficult, industry is due to much caused by the quality problems of pile foundation engineering with the quality accident in civil buildings.
Test Technology of Pile Foundation has obtained significant progress in recent years, and coherent detection standard, specification are promulgated and implemented in succession, right Ensure that construction quality serves good effect.But conventional Test Technology of Pile Foundation at present, such as static load test, core drilling method, height Strain Method, low strain dynamic method and sound wave transmission method etc., be both needed to directly contact foundation pile stake top, thus its use occasion receive it is certain Limitation, before normally only not yet being constructed suitable for top-out structure.
Built however, being frequently encountered in engineering construction to existing(Structure)Build the foundation pile length under thing or integrality is suspected And contradiction and disputes are produced, and or because existing building is of the remote past, when lacking that stake is long to wait capsule information in subsequent adaptation engineering, with And need to build to existing because of situations such as causing pile foundation there occurs other reasonses such as surface subsidence, earthquakes later stage destruction Pile foundation under building is detected, but because now top-out structure has been present, and can not directly contact stake top, thus conventional Pile foundation inspection method is helpless.
Built because the country is existing at present(Structure)The system research for building Test Technology of Pile Foundation under thing still belongs to blank, therefore studies one Kind of strong adaptability, it is restricted few existing of condition and builds(Structure)The pile detection new technology under thing is built, to objectively and accurately evaluating work Cheng Zhiliang, solve the contradiction and disputes in engineering construction and improve existing build(Structure)Build amount of substance evaluation or dilapidated house secure authentication refers to Mark system etc., there is larger realistic meaning, will also promote the further development of architecture foundation pile detection technique.
As an Application No. CN101570974A discloses one kind side hole transmitted wave method detection existing building foundation pile matter The method of amount, it is that utilizing works seismic detector is along PVC by burying the pvc pipe parallel to foundation pile by existing building foundation pile Pipe depth direction is tested through foundation pile transmitted through the seismic wave come, the first arrival time and amplitude of seismic wave according to received by wave detector To judge the method for foundation pile length and integrality.The principle of the method for testing is:Seismic wave is much big in the spread speed of foundation pile In in soil around pile, and attenuation coefficient is less than soil around pile, and when wave detector is away from foundation pile bottom, the seismic wave received is in soil The distance increase of propagation, prolongs after necessarily increasing first arrival time and accelerates the decay of amplitude, similarly in the position of pile defect The unexpected increase of first arrival time and the unexpected decay of amplitude occurs, therefore can be by seismic wave wave train first arrival time and amplitude Comprehensive analysis, judge foundation pile length and integrality.
And for example an Application No. CN103255785A disclose it is a kind of using single tube normal beam technique carry out quality inspection of the piles and The technology of geology detecting, it is characterised in that the compressional wave for producing and being propagated downwards along pile body is tapped on foundation pile top surface, by sounding The reaching time-difference of compressional wave is detected in pipe, the longitudinal wave velocity of Accurate Determining foundation pile and stake are long, judge pile body concrete quality;In neighbour Compressional wave is surveyed in the pipeline or geotechnical boring of stake along the reaching time-difference for being tapped pile body downwards and being propagated from Pile side soil, determines base Pile length, pile quality and reaming degree;And the velocity of wave of geology soil layer can be measured, judge the situation of stake week geology soil layer, analyze Foundation pile enters rock situation.The present invention can outside match somebody with somebody on the basis of the detection devices such as existing low strain dynamic, ultrasonic wave or be embedded in signal transacting Device, realizes the technology of a kind of new pile quality Non-Destructive Testing and geology detecting, and economic, ready-made nondestructive quality detection of pile foundation is auxiliary Verification method is helped, the accuracy and service level of pile foundation quality judgement can be significantly improved.
The problem of above-mentioned two documents are the immediate prior arts of pre- the application, but it has is as follows:Preliminary examination Survey cumbersome, it is necessary to punch, note clear water, process is comparatively laborious.
The content of the invention
The problem of existing instant invention overcomes prior art, it is proposed that a kind of that foundation pile length is determined based on parallel seismic wave method Detection means and its detection method, the present invention are structure as a whole by the way that detection means is laid, and speed is fast when detection, can be with When detection need not be pre-perforated, reduce the engineering time.
The concrete technical scheme of the present invention is as follows:
Determine to be drilled with the detection means of foundation pile length, including exciting hammer, main frame, rig, righting based on parallel seismic wave method Standby and trigger, trigger are placed on the cushion cap of the foundation pile, and main frame is connected with data circuit group with trigger, and its feature exists In,
The rig includes drill body, and the bottom of the drill body is provided with drill bit, top is provided with motor, pacifies in the drill body Screw rod equipped with motor driven rotation, is provided between the screw rod and drill bit and pulverizes pillar, the top for pulverizing pillar End is provided with the upper planet wheel being meshed with the gear one of screw rod, and the bottom for pulverizing pillar is provided with the gear two-phase with drill bit Engage lower planetary gear;Protection pipe is provided with the drill body, wave detector is placed with the protection pipe, the wave detector connects with main frame It is connected to data circuit group two;For the exciting hammer by guiding conduit on horizontal cross bar, the cross bar fixed mount is located at base Stake top, described guide into be provided with tripping gear between conduit and cross bar, for adjust exciting hammer fall away from.
Preferably, the drill bit be routed over it is multiple lead native hole one and be passed through in drill body, the top for pulverizing pillar is also Filtering is installed and leads native dividing plate.
Preferably, the top of the drill body is also equipped with the unearthed pipe communicated with screw rod, the opening of the unearthed pipe to Under.
Preferably, rig includes car body under the righting, and one end of the car body is provided with mobile fixed cover, car body The other end is provided with rotary box, is provided with draw ring on mobile fixed cover, the rotary box end of the car body is provided with strander, described Steel wire rope is connected between draw ring and strander, the interlude of the steel wire rope is propped up by the support bar on car body.
Based on said apparatus, present invention also offers a kind of detection method that foundation pile length is determined based on parallel seismic wave method, It is characterised in that it includes following steps:
1)Test point is chosen, rig is placed under righting above rig, is fixed by mobile fixed cover and rotary box, Wherein:Mobile fixed cover fixes the top for entangling rig, and rotary box entangles the lower end of rig;
2)Drive steel wire rope pull-up rig is vertically attentioned by strander, unclamp mobile fixed cover, and start motor belt motor Set depth is bored under dynamic drill bit;Wherein:In going down process, soil is by leading native hole one into drill body and leading native dividing plate by filtering It is outer that the pipe that is unearthed is discharged in into screw rod;
3) trigger is placed on the cushion cap of foundation pile, and the data circuit group two of the data circuit group of trigger and wave detector is connected Main frame is connect, cross bar is set up above foundation pile, exciting hammer is arranged on below cross bar, Job readiness is completed before detection;
4) wave detector is first placed in the mouth of pipe or ttom of pipe of protection pipe when detecting, mechanical wave is generated on engineering pile by exciting mode While, vibration signal is detected in protection pipe, the quality of signal Analysis collection, the resampling if quality is bad, is otherwise protected Deposit the waveform of the measuring point, and decline the height of wave detector or lifting 0.5-1m in an exciting-after the detection cycle, continue to hammer into shape Hit sampling, until wave detector drop to ttom of pipe or on mention the mouth of pipe untill;
5) output image of main frame 400, by judging criterion to following:1st, when m- depth map in first arrival time slope change; 2nd, the significantly decay amplitude of energy;The comprehensive analysis of first arrival time and amplitude i.e. to the seismic wave wave train, judge pile body length and Integrality.
Beneficial effects of the present invention:The present invention is structure as a whole by the way that detection means is laid, and speed is fast when detection, Can detect at any time need not be pre-perforated, reduces the engineering time, is adapted to promote the use of.
Brief description of the drawings
Fig. 1 is the structural representation for the detection means that the present invention determines foundation pile length based on parallel seismic wave method;
Fig. 2 is the structural representation of rig;
Fig. 3 is the structural representation of rig under righting;
Structural representation when Fig. 4 is rig operation under righting.
Embodiment
Embodiment 1:
As illustrated, the detection means of foundation pile length is determined based on parallel seismic wave method, including exciting hammer 300, exciting hammer 300 are used for Mechanical wave is generated on engineering pile by exciting mode;The exciting hammer 300 is arranged on horizontal cross bar by guiding conduit 301 into On 302, the fixed mount of cross bar 302 is provided with unhook located at the top of foundation pile 100, described guide between conduit 301 and cross bar 302 Device 303, for ensureing that exciting hammer 300 falls away from every time identical.
Rig 600 and trigger 800, trigger 800 are placed on the base under main frame 400, rig 500, righting On the cushion cap of stake 100.
Main frame 400 is connected with data circuit group with trigger 800.Wherein, rig 500 is by rig under righting 600 Auxiliary accomplishes vertical lower brill.
Rig 500 includes drill body 501, and the bottom of the drill body 501 is provided with drill bit 1, top is provided with motor 12, The screw rod 5 that motor 12 drives rotation is installed in the drill body 501, is provided between the screw rod 5 and drill bit 1 and pulverizes post Son 7, the top for pulverizing pillar 7 is provided with the upper planet wheel 8 being meshed with the gear 1 of screw rod 5, described to pulverize pillar 7 Bottom be provided with the lower planetary gear that is meshed with the gear 2 502 of drill bit 1;The drill body 501 is provided with interior protection pipe, the protection Wave detector 4 is placed with pipe, the wave detector 4 is connected with data circuit group two with main frame 400.Motor 12 drives the spiral of rotation The rotation of bar 5 is rotated again to drive drill bit 1 to rotate by lower planetary gear so as to pulverize pillar 7 by the drive of upper planet wheel 8.
In addition, drill bit 1 be routed over it is multiple lead native hole 1 and be passed through in drill body 501, the top for pulverizing pillar 7 is also Filtering is installed and leads native dividing plate 9.The top of the drill body 501 is also equipped with the unearthed pipe 11 communicated with screw rod 5, described to be unearthed Open Side Down for pipe 11.In lower brill, the soil body enters spiral shell by leading native hole 1 into drill body 501 and leading native dividing plate 9 by filtering Be discharged in swing arm 5 outside unearthed pipe 11, such rig 500 can quickly under get into up to designated depth.
Rig 600 includes car body 25 under righting, and one end of the car body 25 is provided with mobile fixed cover 22, car body 25 The other end rotary box 28 is installed, draw ring 20, the end of rotary box 28 installation of the car body 25 are installed on mobile fixed cover 22 There is strander 16, steel wire rope 19 is connected between the draw ring 20 and strander 16, the interlude of the steel wire rope 19 passes through peace Support bar on car body 25 is propped up.
Based on said apparatus, present invention also offers a kind of detection method that foundation pile length is determined based on parallel seismic wave method, It is characterised in that it includes following steps:
1)Test point is chosen, rig 500 is placed under righting above rig 600, passes through mobile fixed cover 22 and rotation Case 28 is fixed, wherein:Mobile fixed cover 22 fixes the top for entangling rig 500, and rotary box 28 entangles rig 500 lower end;
2)Drive the pull-up of steel wire rope 19 rig 500 is vertically attentioned by strander 16, unclamp mobile fixed cover 22, and Start motor 12 and drive 1 time brill set depth of drill bit;Wherein:In going down process, soil enters drill body 501 by leading native hole 1 And led in the native entrance of dividing plate 9 screw rod 5 and be discharged to outside unearthed pipe 11 by filtering;
3) trigger 800 is placed on the cushion cap of foundation pile 100, and by the data circuit group of trigger 800 and the data of wave detector 4 Circuit group two connects main frame 400, and cross bar 302 is set up above foundation pile, exciting hammer 300 is arranged on below cross bar, work before detection Prepare completion;
4) wave detector is first placed in the mouth of pipe or ttom of pipe of protection pipe when detecting, machinery is generated on engineering pile by exciting hammer 300 While ripple, vibration signal is detected in protection pipe, the quality of signal Analysis collection, the resampling if quality is bad, otherwise Preserve the waveform of the measuring point, and decline the height of wave detector 4 or lifting 0.5-1m in an exciting-after the detection cycle, after Continuous hammering sampling, until wave detector drop to ttom of pipe or on mention the mouth of pipe untill;
5) output image of main frame 400, by judging criterion to following:1st, when m- depth map in first arrival time slope change; 2nd, the significantly decay amplitude of energy;The comprehensive analysis of first arrival time and amplitude i.e. to the seismic wave wave train, judge pile body length and Integrality.
Embodiment 2:
The present embodiment and the difference of embodiment 1 are that the wave detector 4 passes through wireless connection, the detection with main frame 400 Increase wireless transmitter module 41 on device 4, also increasing in the trigger 800 has wireless transmitter module two, pacifies inside main frame 400 Corresponding wireless receiving module is filled,
Based on said apparatus, present invention also offers a kind of detection method that foundation pile length is determined based on parallel seismic wave method, and it is special Sign is, comprises the following steps:
1)Test point is chosen, rig 500 is placed under righting above rig 600, passes through mobile fixed cover 22 and rotation Case 28 is fixed, wherein:Mobile fixed cover 22 fixes the top for entangling rig 500, and rotary box 28 entangles rig 500 lower end;
2)Drive the pull-up of steel wire rope 19 rig 500 is vertically attentioned by strander 16, unclamp mobile fixed cover 22, and Start motor 12 and drive 1 time brill set depth of drill bit;Wherein:In going down process, soil enters drill body 501 by leading native hole 1 And led in the native entrance of dividing plate 9 screw rod 5 and be discharged to outside unearthed pipe 11 by filtering;
3) trigger 800 is placed on the cushion cap of foundation pile 100, and by the data circuit group of trigger 800 and the data of wave detector 4 Circuit group two connects main frame 400, and cross bar is set up above foundation pile, and exciting hammer 300 is arranged on below cross bar, and work is accurate before detecting It is standby to complete;
4) wave detector is first placed in the mouth of pipe or ttom of pipe of protection pipe when detecting, machinery is generated on engineering pile by exciting hammer 300 While ripple, vibration signal is detected in protection pipe, the quality of signal Analysis collection, the resampling if quality is bad, otherwise Preserve the waveform of the measuring point, and decline the height of wave detector 4 or lifting 0.5-1m in an exciting-after the detection cycle, after Continuous hammering sampling, until wave detector drop to ttom of pipe or on mention the mouth of pipe untill;
5) output image of main frame 400, by judging criterion to following:1st, when m- depth map in first arrival time slope change; 2nd, the significantly decay amplitude of energy;The comprehensive analysis of first arrival time and amplitude i.e. to the seismic wave wave train, judge pile body length and Integrality.
Embodiment 3:
As illustrated, the detection means of foundation pile length is determined based on parallel seismic wave method, including exciting hammer 300, exciting hammer 300 are used for Mechanical wave is generated on engineering pile by exciting mode;The exciting hammer 300 is arranged on horizontal cross bar by guiding conduit 301 into On 302, the fixed mount of cross bar 302 is provided with unhook located at the top of foundation pile 100, described guide between conduit 301 and cross bar 302 Device 303, for ensureing that exciting hammer 300 falls away from every time identical.
Rig 600 and trigger 800, trigger 800 are placed on the base under main frame 400, rig 500, righting On the cushion cap of stake 100.
Main frame 400 is connected with data circuit group with trigger 800.Wherein, rig 500 is by rig under righting 600 Auxiliary accomplishes vertical lower brill.
Rig 500 includes drill body 501, and the bottom of the drill body 501 is provided with drill bit 1, top is provided with motor 12, The screw rod 5 that motor 12 drives rotation is installed in the drill body 501, is provided between the screw rod 5 and drill bit 1 and pulverizes post Son 7, the top for pulverizing pillar 7 is provided with the upper planet wheel 8 being meshed with the gear 1 of screw rod 5, described to pulverize pillar 7 Bottom be provided with the lower planetary gear that is meshed with the gear 2 502 of drill bit 1;Protection pipe, the protection are provided with the drill body 501 Wave detector 4 is placed with pipe, the wave detector 4 has data circuit group two to be wrapped on lifting device 401, data line group two Terminal and main frame 400.A control module is provided with the lifting device 401, the control module is connected by wireless device Main frame.Motor 12 drives the rotation of screw rod 5 of rotation to be rotated again and under so as to pulverize pillar 7 by the drive of upper planet wheel 8 Planetary gear drives drill bit 1 to rotate.
In addition, drill bit 1 be routed over it is multiple lead native hole 1 and be passed through in drill body 501, the top for pulverizing pillar 7 is also Filtering is installed and leads native dividing plate 9.The top of the drill body 501 is also equipped with the unearthed pipe 11 communicated with screw rod 5, described to be unearthed Open Side Down for pipe 11.In lower brill, the soil body enters spiral shell by leading native hole 1 into drill body 501 and leading native dividing plate 9 by filtering Be discharged in swing arm 5 outside unearthed pipe 11, such rig 500 can quickly under get into up to designated depth.
Rig 600 includes car body 25 under righting, and one end of the car body 25 is provided with mobile fixed cover 22, car body 25 The other end rotary box 28 is installed, draw ring 20, the end of rotary box 28 installation of the car body 25 are installed on mobile fixed cover 22 There is strander 16, steel wire rope 19 is connected between the draw ring 20 and strander 16, the interlude of the steel wire rope 19 passes through peace Support bar on car body 25 is propped up.
Based on said apparatus, present invention also offers a kind of detection method that foundation pile length is determined based on parallel seismic wave method, It is characterised in that it includes following steps:
1)Test point is chosen, rig 500 is placed under righting above rig 600, passes through mobile fixed cover 22 and rotation Case 28 is fixed, wherein:Mobile fixed cover 22 fixes the top for entangling rig 500, and rotary box 28 entangles rig 500 lower end;
2)Drive the pull-up of steel wire rope 19 rig 500 is vertically attentioned by strander 16, unclamp mobile fixed cover 22, and Start motor 12 and drive 1 time brill set depth of drill bit;Wherein:In going down process, soil enters drill body 501 by leading native hole 1 And led in the native entrance of dividing plate 9 screw rod 5 and be discharged to outside unearthed pipe 11 by filtering;
3) trigger 800 is placed on the cushion cap of foundation pile 100, and by the data circuit group of trigger 800 and the data of wave detector 4 Circuit group two connects main frame 400, and cross bar 302 is set up above foundation pile, exciting hammer 300 is arranged on below cross bar, work before detection Prepare completion;
4) wave detector is first placed in the mouth of pipe or ttom of pipe of protection pipe when detecting, machinery is generated on engineering pile by exciting hammer 300 While ripple, vibration signal is detected in protection pipe, the quality of signal Analysis collection, the resampling if quality is bad, otherwise Preserve the waveform of the measuring point, and in an exciting-after the detection cycle, control module receive information, control lifting device 401 opens The dynamic height by wave detector 4 declines or lifting 0.5-1m, continues hammering sampling, until wave detector drop to ttom of pipe or on mention pipe Untill mouthful;
5) output image of main frame 400, by judging criterion to following:1st, when m- depth map in first arrival time slope change; 2nd, the significantly decay amplitude of energy;The comprehensive analysis of first arrival time and amplitude i.e. to the seismic wave wave train, judge pile body length and Integrality.
In addition to the implementation, the present invention can also have other embodiment.It is all to use equivalent substitution or equivalent transformation shape Into technical scheme, all fall within the protection domains of application claims.

Claims (1)

1. parallel seismic wave method determines the detection method of foundation pile length, it is characterised in that comprises the following steps:
1)Test point is chosen, rig 500 is placed under righting above rig 600, passes through mobile fixed cover 22 and rotation Case 28 is fixed, wherein:Mobile fixed cover 22 fixes the top for entangling rig 500, and rotary box 28 entangles rig 500 lower end;
2)Drive the pull-up of steel wire rope 19 rig 500 is vertically attentioned by strander 16, unclamp mobile fixed cover 22, and Start motor 12 and drive 1 time brill set depth of drill bit;Wherein:In going down process, soil enters drill body 501 by leading native hole 1 And led in the native entrance of dividing plate 9 screw rod 5 and be discharged to outside unearthed pipe 11 by filtering;
3) trigger 800 is placed on the cushion cap of foundation pile 100, and by the data circuit group of trigger 800 and the data of wave detector 4 Circuit group two connects main frame 400, and cross bar 302 is set up above foundation pile, exciting hammer 300 is arranged on below cross bar, work before detection Prepare completion;
4) wave detector is first placed in the mouth of pipe or ttom of pipe of protection pipe when detecting, machinery is generated on engineering pile by exciting hammer 300 While ripple, vibration signal is detected in protection pipe, the quality of signal Analysis collection, the resampling if quality is bad, otherwise Preserve the waveform of the measuring point, and in an exciting-after the detection cycle, control module receive information, control lifting device 401 opens The dynamic height by wave detector 4 declines or lifting 0.5-1m, continues hammering sampling, until wave detector drop to ttom of pipe or on mention pipe Untill mouthful;
5) output image of main frame 400, by judging criterion to following:1st, when m- depth map in first arrival time slope change; 2nd, the significantly decay amplitude of energy;The comprehensive analysis of first arrival time and amplitude i.e. to the seismic wave wave train, judge pile body length and Integrality.
CN201711264724.7A 2016-08-09 2016-08-09 Parallel seismic wave method determines the detection method of foundation pile length Active CN107869156B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711264724.7A CN107869156B (en) 2016-08-09 2016-08-09 Parallel seismic wave method determines the detection method of foundation pile length

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610645232.1A CN106049567B (en) 2016-08-09 2016-08-09 Parallel seismic wave method determines the detection means and its detection method of foundation pile length
CN201711264724.7A CN107869156B (en) 2016-08-09 2016-08-09 Parallel seismic wave method determines the detection method of foundation pile length

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201610645232.1A Division CN106049567B (en) 2016-08-09 2016-08-09 Parallel seismic wave method determines the detection means and its detection method of foundation pile length

Publications (2)

Publication Number Publication Date
CN107869156A true CN107869156A (en) 2018-04-03
CN107869156B CN107869156B (en) 2019-11-15

Family

ID=57481827

Family Applications (4)

Application Number Title Priority Date Filing Date
CN201711264721.3A Expired - Fee Related CN107975076B (en) 2016-08-09 2016-08-09 Parallel seismic wave method determines the detection device and its detection method of foundation pile length
CN201610645232.1A Active CN106049567B (en) 2016-08-09 2016-08-09 Parallel seismic wave method determines the detection means and its detection method of foundation pile length
CN201711264553.8A Pending CN107869155A (en) 2016-08-09 2016-08-09 Parallel seismic wave method determines the detection means and its detection method of foundation pile length
CN201711264724.7A Active CN107869156B (en) 2016-08-09 2016-08-09 Parallel seismic wave method determines the detection method of foundation pile length

Family Applications Before (3)

Application Number Title Priority Date Filing Date
CN201711264721.3A Expired - Fee Related CN107975076B (en) 2016-08-09 2016-08-09 Parallel seismic wave method determines the detection device and its detection method of foundation pile length
CN201610645232.1A Active CN106049567B (en) 2016-08-09 2016-08-09 Parallel seismic wave method determines the detection means and its detection method of foundation pile length
CN201711264553.8A Pending CN107869155A (en) 2016-08-09 2016-08-09 Parallel seismic wave method determines the detection means and its detection method of foundation pile length

Country Status (1)

Country Link
CN (4) CN107975076B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110779475A (en) * 2019-10-16 2020-02-11 广西电网有限责任公司电力科学研究院 Method for measuring size of power transmission tower foundation

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110905012B (en) * 2018-05-12 2021-06-25 陕西秦军国防工业工程建设监理所 Building pile foundation detection method
CN108956766B (en) * 2018-06-09 2021-07-16 广东穗芳智慧建设科技有限公司 Pile foundation quality detection method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103255785A (en) * 2012-02-15 2013-08-21 陈彦平 Technology for performing foundation pile quality detection and geology survey by adopting single tube longitudinal wave method
CN102296645B (en) * 2011-06-02 2013-10-23 朱德兵 Pile foundation quality detection method and device
CN104264722A (en) * 2014-09-30 2015-01-07 云南航天工程物探检测股份有限公司 Finished bridge foundation pile nondestructive testing method
CN204662519U (en) * 2015-04-02 2015-09-23 福建省建筑工程质量检测中心有限公司 A kind of checkout gear of foundation pile integrity and weight thereof
CN105155504A (en) * 2015-10-09 2015-12-16 铁道第三勘察设计院集团有限公司 Side direction seismic wave transmission nondestructive testing system and method for railway subgrade

Family Cites Families (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5099696A (en) * 1988-12-29 1992-03-31 Takechi Engineering Co., Ltd. Methods of determining capability and quality of foundation piles and of designing foundation piles, apparatus for measuring ground characteristics, method of making hole for foundation pile such as cast-in-situ pile and apparatus therefor
JP3641771B2 (en) * 1997-05-12 2005-04-27 株式会社竹中工務店 Method for detecting damage of foundation pile from ground surface and apparatus used for the method
KR100655479B1 (en) * 2004-05-20 2006-12-14 미승씨엔에스검사주식회사 The non-destruction test method for the measure pipe length with underground and the existence or nonexistence of pipe, and the hammer impactor of the non-destruction tester
JP4667228B2 (en) * 2005-12-21 2011-04-06 株式会社竹中工務店 Pile inspection method and sensor crimping device
JP4954729B2 (en) * 2007-01-29 2012-06-20 株式会社竹中工務店 Concrete pile soundness evaluation support device, soundness evaluation support method, and soundness evaluation support program
CN101074872A (en) * 2007-06-13 2007-11-21 南昌大学 Method and apparatus for determining pile length by reflective wave method
CN101477084B (en) * 2008-12-22 2010-11-17 铁道第三勘察设计院集团有限公司 Method for detecting integrality of concrete pile body by elastic wave transmission mode
CN101570974A (en) * 2009-03-26 2009-11-04 浙江省建筑科学设计研究院有限公司 Method for detecting quality of existing building foundation piles with parallel seismic method
CN101775959B (en) * 2009-12-25 2013-01-23 王来朋 Drilling machine of coaxial double-drill large-caliber multifunctional foundation pile
CN202170756U (en) * 2011-07-18 2012-03-21 海城市石油机械制造有限公司 Lifting device of drilling machine headframe
CN202177602U (en) * 2011-07-27 2012-03-28 北京市康科瑞工程检测技术有限责任公司 Foundation pile integrity detection device utilizing acoustical wave transmission method
CN102535529A (en) * 2011-12-08 2012-07-04 中铁五局(集团)有限公司 Construction method of self-balancing method pile foundation bearing capacity test device
CN203551516U (en) * 2013-10-30 2014-04-16 天津市建联工程勘测有限公司 Device for detecting integrality of pile body by using low strain method
CN203846537U (en) * 2014-04-10 2014-09-24 中国葛洲坝集团三峡建设工程有限公司 Portable pile foundation hole inspection device
CN103953076B (en) * 2014-05-06 2016-01-13 上海交通大学 Based on depth determination method at the bottom of the existing engineering pile stake of other hole transmitted wave bathmometry
CN104594395B (en) * 2015-01-15 2016-06-29 中铁第四勘察设计院集团有限公司 A kind of method utilizing railway in operation roadbed side Bored Pile Foundation detection structure to carry out pile measurement
CN205875237U (en) * 2016-08-09 2017-01-11 浙江省建设工程质量检验站有限公司 Detection apparatus for foundation pile length is confirmed to parallel seismic wave method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102296645B (en) * 2011-06-02 2013-10-23 朱德兵 Pile foundation quality detection method and device
CN103255785A (en) * 2012-02-15 2013-08-21 陈彦平 Technology for performing foundation pile quality detection and geology survey by adopting single tube longitudinal wave method
CN104264722A (en) * 2014-09-30 2015-01-07 云南航天工程物探检测股份有限公司 Finished bridge foundation pile nondestructive testing method
CN204662519U (en) * 2015-04-02 2015-09-23 福建省建筑工程质量检测中心有限公司 A kind of checkout gear of foundation pile integrity and weight thereof
CN105155504A (en) * 2015-10-09 2015-12-16 铁道第三勘察设计院集团有限公司 Side direction seismic wave transmission nondestructive testing system and method for railway subgrade

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110779475A (en) * 2019-10-16 2020-02-11 广西电网有限责任公司电力科学研究院 Method for measuring size of power transmission tower foundation
CN110779475B (en) * 2019-10-16 2021-05-14 广西电网有限责任公司电力科学研究院 Method for measuring size of power transmission tower foundation

Also Published As

Publication number Publication date
CN107975076B (en) 2019-10-11
CN107869156B (en) 2019-11-15
CN107869155A (en) 2018-04-03
CN107975076A (en) 2018-05-01
CN106049567B (en) 2018-01-05
CN106049567A (en) 2016-10-26

Similar Documents

Publication Publication Date Title
CN101570974A (en) Method for detecting quality of existing building foundation piles with parallel seismic method
CN106088170B (en) The detection means and its detection method of foundation pile length are determined based on parallel seismic wave method
Rausche Non-destructive evaluation of deep foundations
CN103669428B (en) With the integrity detection system of cushion cap foundation pile
Davis Nondestructive evaluation of existing deep foundations
CN108318584A (en) Single-hole sound-wave combines the method for across hole CT detections pile quality and gradient
CN106049567B (en) Parallel seismic wave method determines the detection means and its detection method of foundation pile length
CN106770643B (en) Method for detecting pile bottom grouting effect of expanded-bottom cast-in-place pile based on sound wave propagation principle
CN108037184A (en) Tunnel inverted arch detection of construction quality method
CN104594395A (en) Operation railroad bed side drilling pile foundation detection structure and detection method
CN110512662B (en) Pile foundation quality detection method
CN101334368A (en) Steel tube centrifugal concrete pipe pile integrality endoscopic detection method
CN106049566B (en) Side hole transmitted wave method determines the detection means and its detection method of foundation pile length
CN205954717U (en) Detection device based on foundation pile length is confirmed to parallel seismic wave method
CN205875237U (en) Detection apparatus for foundation pile length is confirmed to parallel seismic wave method
CN110905012B (en) Building pile foundation detection method
Amir Single-tube ultrasonic testing of pile integrity
CN111158043B (en) System and method for detecting hidden danger at pile bottom of bored pile
CN113279435A (en) Foundation pile quality nondestructive testing method based on side-hole diffraction wave analysis
CN205875236U (en) Detection apparatus for foundation pile length is confirmed to other hole penetrated wave method
CN108427142A (en) A kind of prefabricated pile stake bottom CAVE DETECTION system and method
CN114323140A (en) System and method for detecting pile length and integrity of precast tubular pile
Chernauskas et al. Defect detection and examination of large drilled shafts using a new cross-hole sonic logging system
Lai et al. Integrity testing of model pile with embedded accelerometers
CN214749971U (en) Synchronous lifting device of sound wave test transducer and ultrasonic detection system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20191018

Address after: Room 1b, yuzhuge, building D, yujingtai garden, Dawang District, Zhaoqing City, Guangdong Province

Applicant after: Guangdong Longzhou Construction Engineering Co., Ltd

Address before: 310012 No. 28, Wen two road, Hangzhou, Zhejiang, China

Applicant before: Hou Hong Wei

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20180403

Assignee: Zhaoqing high tech Zone Henghui decoration design Engineering Co.,Ltd.

Assignor: Guangdong Longzhou Construction Engineering Co.,Ltd.

Contract record no.: X2021980016943

Denomination of invention: Detection method for determining the length of foundation pile by parallel seismic method

Granted publication date: 20191115

License type: Common License

Record date: 20211230

EE01 Entry into force of recordation of patent licensing contract