CN205875237U - Detection apparatus for foundation pile length is confirmed to parallel seismic wave method - Google Patents

Detection apparatus for foundation pile length is confirmed to parallel seismic wave method Download PDF

Info

Publication number
CN205875237U
CN205875237U CN201620853224.1U CN201620853224U CN205875237U CN 205875237 U CN205875237 U CN 205875237U CN 201620853224 U CN201620853224 U CN 201620853224U CN 205875237 U CN205875237 U CN 205875237U
Authority
CN
China
Prior art keywords
foundation pile
trigger
rig
drill bit
seismic wave
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620853224.1U
Other languages
Chinese (zh)
Inventor
吴宝杰
杨桦
侯宏伟
黄林伟
徐芫蕾
臧端
唐绍明
顾晓卫
钱志华
金鑫
郑威
刘博�
饶秋琛
凌捷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG PROVINCIAL CONSTRUCTION ENGINEERING QUALITY INSPECTION STATION Co Ltd
Original Assignee
ZHEJIANG PROVINCIAL CONSTRUCTION ENGINEERING QUALITY INSPECTION STATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG PROVINCIAL CONSTRUCTION ENGINEERING QUALITY INSPECTION STATION Co Ltd filed Critical ZHEJIANG PROVINCIAL CONSTRUCTION ENGINEERING QUALITY INSPECTION STATION Co Ltd
Priority to CN201620853224.1U priority Critical patent/CN205875237U/en
Application granted granted Critical
Publication of CN205875237U publication Critical patent/CN205875237U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Detection apparatus for foundation pile length is confirmed to parallel seismic wave method includes excitation hammer, host computer, drilling equipment, rights the equipment of running the drilling tool into the well and trigger, and the trigger is placed on the cushion cap of foundation pile, the host computer is connected with data circuit group with the trigger, its characterized in that, drilling equipment is including boring the body, brill bottom physically is provided with the drill bit, the motor is installed on the top, it drives rotatory hob to bore the internal motor of installing, install between hob and the drill bit and pulverize the post, the beneficial effect of the utility model: the utility model discloses a lay structure as an organic whole with detection device, fast in the time of the detection, can detect does not at any time need to punch in advance, reduces the engineering time, is fit for using widely.

Description

Parallel seismic wave method determines the detection device of foundation pile length
Technical field
This utility model relates to a kind of based on parallel seismic wave method detection foundation pile device for detecting length, belongs to building detection technique Field.
Background technology
Along with the fast development of economic construction, high buildings and large mansions continue to bring out, and pile foundation engineering obtains and develops on an unprecedented scale, pile foundation It it is the base form being most widely used at present.Owing to pile foundation engineering construction has highly disguised, find that quality problems are relative More difficult, industry is much owing to the quality problems of pile foundation engineering cause with the quality accident in civil buildings.
Test Technology of Pile Foundation has obtained significant progress in recent years, and coherent detection standard, specification are in succession promulgated and implement, right Ensure that construction quality serves good effect.But the most conventional Test Technology of Pile Foundation, such as static load test, core drilling method, height Strain Method, low strain dynamic method and sound wave transmission method etc., be both needed to directly contact Under Pile top, thus its use occasion receive certain Limit, be normally only applicable to before top-out structure not yet constructs.
But, engineering construction is frequently encountered the foundation pile length under existing buildings or structures or integrity are suspected And produce contradiction and disputes, or owing to existing building is of the remote past, when subsequent adaptation engineering lacks stake capsule information such as long grade, with And owing to there occurs that the other reasons such as surface subsidence, earthquake causes the situations such as later stage destruction to pile foundation and needs to build existing Pile foundation under building detects, but owing to now top-out structure has existed, it is impossible to directly contact stake top, thus routine Pile foundation inspection method is helpless.
Owing under current domestic existing buildings or structures, the systematic study of Test Technology of Pile Foundation still belongs to blank, therefore research one Pile detection new technique under the existing buildings or structures that kind strong adaptability, restricted condition are few, to objectively and accurately evaluating work Cheng Zhiliang, the contradiction and disputes solved in engineering construction and improve existing buildings or structures performance rating or dilapidated house secure authentication refers to Mark systems etc., have bigger realistic meaning, also will promote the further development of architecture foundation pile detection technique.
As Application No. CN101570974A discloses one side hole transmitted wave method detection existing building foundation pile matter The method of amount, it is by burying the pvc pipe being parallel to foundation pile by existing building foundation pile underground, and utilizing works seismic detector is along PVC Pipe depth direction tests the seismic wave come through foundation pile transmission, according to first arrival time and the amplitude of seismic wave received by cymoscope The method judging foundation pile length and integrity.The principle of this method of testing is: seismic wave is the biggest in the spread speed of foundation pile In at soil around pile, and attenuation quotient is less than soil around pile, and when cymoscope is away from foundation pile bottom, the seismic wave received is in soil The distance propagated increases, and prolongs and accelerate the decay of amplitude, in like manner in the position of pile defect also after necessarily strengthening first arrival time There will be increasing suddenly and the unexpected decay of amplitude of first arrival time, therefore can be by seismic wave wave train first arrival time and amplitude Comprehensive analysis, judges foundation pile length and integrity.
And for example Application No. CN103255785A disclose a kind of use single tube normal beam technique carry out quality inspection of the piles and The technology of geology detecting, it is characterised in that tap on foundation pile end face and produce the compressional wave along pile body travel downward, by sounding The time of advent detecting compressional wave in pipe is poor, and longitudinal wave velocity and the stake of Accurate Determining foundation pile are long, it is determined that pile body concrete quality;Neighbour The pipeline of stake or geotechnical boring are surveyed compressional wave downward and poor from the time of advent that Pile side soil is propagated along being tapped pile body, measure base Pile length, pile quality and reaming degree;And the velocity of wave of geology soil layer can be measured, judge the situation of stake week geology soil layer, analyze Foundation pile enters rock situation.This utility model can be joined outward or embed signal in the detection equipment Foundations such as existing low strain dynamic, ultrasound wave Processor, it is achieved the lossless inspection of pile foundation that a kind of new pile quality Non-Destructive Testing and the technology of geology detecting are also economic, ready-made Survey auxiliary verification method, accuracy and service level that pile foundation quality judges can be significantly improved.
Above-mentioned two documents is the immediate prior art of pre-the application, but its problem having is as follows: preliminary examination Surveying cumbersome, need punching, note clear water, operation is comparatively laborious.
Summary of the invention
This utility model overcomes the problem that prior art exists, it is proposed that based on parallel seismic wave method, one determines that foundation pile is long The detection device of degree and detection method thereof, this utility model is structure as a whole by being laid by detection device, the speed when of detection Degree is fast, can detect at any time and need not pre-punching, reduces the engineering time.
Concrete technical scheme of the present utility model is as follows:
The detection device of foundation pile length is determined, including under exciting hammer, main frame, rig, righting based on parallel seismic wave method Rig and trigger, trigger is placed on the cushion cap of described foundation pile, and main frame is connected with trigger data circuit group, and it is special Levy and be,
Described rig includes drill body, and the bottom of described drill body is provided with drill bit, top is provided with motor, described drill body Inside be provided with driven by motor rotate screw rod, be provided with between described screw rod and drill bit and pulverize pillar, described in pulverize pillar Top be provided with the upper planet wheel that the gear one with screw rod is meshed, the bottom of described broken pillar is provided with the gear two with drill bit Be meshed lower planetary gear;It is provided with protection pipe in described drill body, in described protection pipe, is placed with cymoscope, described cymoscope and main frame Connect and have data circuit group two;Described exciting hammer is arranged on horizontal cross bar by guiding conduit into, described cross bar is fixing set up with Above foundation pile, described in guide into tripping gear be installed between conduit and cross bar, for adjust exciting hammer fall away from.
Preferably, described drill bit be routed over multiple lead soil hole one be passed through in drill body, described in pulverize the top of pillar also Filtration is installed and leads soil dividing plate.
Preferably, the top of described drill bit is also equipped with the unearthed pipe communicated with screw rod, the opening of described unearthed pipe to Under.
Preferably, under described righting, rig includes that car body, the two ends of described car body are provided with mobile fixed cover and rotation Case, mobile fixed cover is provided with draw ring, and the rotary box end of described car body is provided with strander, between described draw ring and strander Connecting has steel wire rope, the interlude of described steel wire rope to be propped up by the support bar being arranged on car body.
Based on said apparatus, this utility model additionally provides the detection side determining foundation pile length in based on parallel seismic wave method Method, it is characterised in that comprise the steps:
1) test point is chosen, by being placed under righting above rig by rig, by mobile fixed cover and rotation Case is fixed, wherein: mobile fixed cover fixes the top entangling rig, and rotary box entangles the lower end of rig;
2) drive steel wire rope pull-up to make rig vertically attention by strander, unclamp mobile fixed cover, and start electricity Machine drives and bores set depth under drill bit;Wherein: in going down process, soil enters drill body by leading soil hole one and leads soil by filtration Dividing plate is discharged in entering screw rod be unearthed outside pipe;
3) on the cushion cap of foundation pile, trigger is placed, and by the data circuit group of trigger and the data circuit group of cymoscope Two connect main frame, set up cross bar above foundation pile, are arranged on below cross bar by exciting hammer, and before detection, Job readiness completes;
4) first cymoscope is placed in during detection at the bottom of the mouth of pipe or the pipe of protection pipe, on engineering pile, generates machine by exciting mode While tool ripple, in test tube, detect vibration signal, analyze the quality of signals collecting, if quality is the best, resampling, otherwise Preserve the waveform of this measuring point, and one exciting detection week after date the height of cymoscope declined or promotes 0.5-1m, continue Hammering is sampled, till mentioning on cymoscope at the bottom of the mouth of pipe or pipe;
5) main frame 400 exports image, by passing judgment on criterion as follows: 1, time m-depth map in first arrival time slope Change;2, the significantly decay amplitude of energy;I.e. first arrival time and the comprehensive analysis of amplitude to the seismic wave wave train, it is judged that pile body is long Degree and integrity.
The beneficial effects of the utility model: this utility model by by detection device laying be structure as a whole, detection time Time speed is fast, can detect at any time and need not pre-punching, reduces the engineering time, is suitable for promoting the use of.
Accompanying drawing explanation
Fig. 1 is the structural representation that this utility model determines the detection device of foundation pile length based on parallel seismic wave method;
Fig. 2 is the structural representation of rig;
Fig. 3 is the structural representation of rig under righting;
Structural representation time Fig. 4 is rig operation under righting.
Detailed description of the invention
Embodiment 1:
As it can be seen, determine the detection device of foundation pile length based on parallel seismic wave method, hammer 300 into shape including exciting, exciting hammer 300 It is used on engineering pile, generating mechanical wave by exciting mode;Described exciting hammer 300 is arranged on level by guiding conduit 301 into On cross bar 302, described cross bar 302 is fixing set up with foundation pile 100 above, described in guide into and be provided with between conduit 301 and cross bar 302 Tripping gear 303, for ensureing exciting hammer 300 fall away from the most identical.
Rig 600 and trigger 800 under main frame 400, rig 500, righting, trigger 800 is placed on described base On the cushion cap of stake 100.
Main frame 400 is connected with trigger 800 data circuit group.Wherein, rig 500 is by rig 600 under righting Auxiliary accomplishes vertical lower brill.
Rig 500 includes drill body 501, and the bottom of described drill body 501 is provided with drill bit 1, top is provided with motor 12, The screw rod 5 that motor 12 is rotated is installed in described drill body 501, is provided with between described screw rod 5 and drill bit 1 and pulverizes post Son 7, described in pulverize the top of pillar 7 and be provided with the upper planet wheel 8 that the gear 1 with screw rod 5 is meshed, described broken pillar 7 Bottom is provided with the gear 2 502 with drill bit 1 and is meshed lower planetary gear;Protection pipe it is provided with, in described protection pipe in described drill body 501 Being placed with cymoscope 4, described cymoscope 4 is connected with main frame 400 data circuit group two.The screw rod 5 that motor 12 is rotated Rotate thus by upper planet wheel 8 drive pulverize pillar 7 rotate again and by lower planetary gear drive drill bit 1 rotate.
Additionally, drill bit 1 be routed over multiple lead soil hole 1 be passed through in drill body 501, described in pulverize the top of pillar 7 also Filtration is installed and leads soil dividing plate 9.The top of described drill bit 1 is also equipped with the unearthed pipe 11 communicated with screw rod 5, described unearthed pipe 11 Open Side Down.When lower boring, the soil body enters drill body 501 by leading soil hole 1 and leads native dividing plate 9 by filtration and enter spiral Be discharged in bar 5 be unearthed outside pipe 11, such rig 500 can quickly under get into and reach designated depth.
Under righting, rig 600 includes that car body 25, the two ends of described car body 25 are provided with mobile fixed cover 22 and rotary box 28, mobile fixed cover 22 is provided with draw ring 20, rotary box 28 end of described car body 25 is provided with strander 16, described draw ring Being connected between 20 with strander 16 and have steel wire rope 19, the interlude of described steel wire rope 19 is by being arranged on the support bar on car body 25 Prop up.
Based on said apparatus, this utility model additionally provides the detection side determining foundation pile length in based on parallel seismic wave method Method, it is characterised in that comprise the steps:
1) test point is chosen, by being placed under righting above rig 600 by rig 500, by mobile fixed cover 22 and rotary box 28 fix, wherein: the mobile fixing top entangling rig 500 of fixed cover 22, rotary box 28 entangles brill The lower end of hole equipment 500;
2) drive steel wire rope 19 pull-up to make rig 500 vertically attention by strander 16, unclamp mobile fixed cover 22, and start motor 12 and drive drill bit 1 time to bore set depth;Wherein: in going down process, soil enters brill by leading soil hole 1 Body 501 is also led in soil dividing plate 9 enters screw rod 5 by filtration and is discharged to be unearthed outside pipe 11;
3) on the cushion cap of foundation pile 100, trigger 800 is placed, and by the data circuit group of trigger 800 and cymoscope 4 Data circuit group two connects main frame 400, sets up cross bar 302 above foundation pile, is arranged on below cross bar by exciting hammer 300, detection Front Job readiness completes;
4) first cymoscope is placed in during detection at the bottom of the mouth of pipe or the pipe of protection pipe, is generated on engineering pile by exciting hammer 300 While mechanical wave, in test tube, detect vibration signal, analyze the quality of signals collecting, if quality is the best, resampling, no Then preserve the waveform of this measuring point, and one exciting detection week after date the height of cymoscope 4 declined or promotes 0.5-1m, Continue hammering sampling, till mentioning on cymoscope at the bottom of the mouth of pipe or pipe;
5) main frame 400 exports image, by passing judgment on criterion as follows: 1, time m-depth map in first arrival time slope Change;2, the significantly decay amplitude of energy;I.e. first arrival time and the comprehensive analysis of amplitude to the seismic wave wave train, it is judged that pile body is long Degree and integrity.
Embodiment 2:
The present embodiment is with the difference of embodiment 1, and described cymoscope 4 and main frame 400 are by wireless connections, described Increasing wireless transmitter module 41 on cymoscope 4, also increasing in described trigger 800 has wireless transmitter module two, in main frame 400 Corresponding wireless receiving module is installed in portion,
Based on said apparatus, this utility model additionally provides the detection side determining foundation pile length in based on parallel seismic wave method Method, it is characterised in that comprise the steps:
1) test point is chosen, by being placed under righting above rig 600 by rig 500, by mobile fixed cover 22 and rotary box 28 fix, wherein: the mobile fixing top entangling rig 500 of fixed cover 22, rotary box 28 entangles brill The lower end of hole equipment 500;
2) drive steel wire rope 19 pull-up to make rig 500 vertically attention by strander 16, unclamp mobile fixed cover 22, and start motor 12 and drive drill bit 1 time to bore set depth;Wherein: in going down process, soil enters brill by leading soil hole 1 Body 501 is also led in soil dividing plate 9 enters screw rod 5 by filtration and is discharged to be unearthed outside pipe 11;
3) on the cushion cap of foundation pile 100, trigger 800 is placed, and by the data circuit group of trigger 800 and cymoscope 4 Data circuit group two connects main frame 400, sets up cross bar above foundation pile, is arranged on below cross bar by exciting hammer 300, work before detection Prepare;
4) first cymoscope is placed at the bottom of inspecting hole test tube mouth or pipe during detection, on engineering pile, generates machine by exciting hammer 300 While tool ripple, in test tube, detect vibration signal, analyze the quality of signals collecting, if quality is the best, resampling, otherwise Preserve the waveform of this measuring point, and one exciting detection week after date the height of cymoscope 4 declined or promotes 0.5-1m, continue Continuous hammering sampling, till mentioning at the bottom of the mouth of pipe or pipe on cymoscope;
5) main frame 400 exports image, by passing judgment on criterion as follows: 1, time m-depth map in first arrival time slope Change;2, the significantly decay amplitude of energy;I.e. first arrival time and the comprehensive analysis of amplitude to the seismic wave wave train, it is judged that pile body is long Degree and integrity.
Embodiment 3:
As it can be seen, determine the detection device of foundation pile length based on parallel seismic wave method, hammer 300 into shape including exciting, exciting hammer 300 It is used on engineering pile, generating mechanical wave by exciting mode;Described exciting hammer 300 is arranged on level by guiding conduit 301 into On cross bar 302, described cross bar 302 is fixing set up with foundation pile 100 above, described in guide into and be provided with between conduit 301 and cross bar 302 Tripping gear 303, for ensureing exciting hammer 300 fall away from the most identical.
Rig 600 and trigger 800 under main frame 400, rig 500, righting, trigger 800 is placed on described base On the cushion cap of stake 100.
Main frame 400 is connected with trigger 800 data circuit group.Wherein, rig 500 is by rig 600 under righting Auxiliary accomplishes vertical lower brill.
Rig 500 includes drill body 501, and the bottom of described drill body 501 is provided with drill bit 1, top is provided with motor 12, The screw rod 5 that motor 12 is rotated is installed in described drill body 501, is provided with between described screw rod 5 and drill bit 1 and pulverizes post Son 7, described in pulverize the top of pillar 7 and be provided with the upper planet wheel 8 that the gear 1 with screw rod 5 is meshed, described broken pillar 7 Bottom is provided with the gear 2 502 with drill bit 1 and is meshed lower planetary gear;Protection pipe in described drill body 501, places in described protection pipe Having cymoscope 4, the data circuit group two that has of described cymoscope 4 is wrapped on lifting device 401, the terminal of data line group two and master Machine 400.Being provided with a control module in described lifting device 401, described control module connects main frame by wireless device.Motor The screw rod 5 that 12 are rotated is rotated thus is driven by upper planet wheel 8 and pulverizes pillar 7 and rotate and driven by lower planetary gear Drill bit 1 rotates.
Additionally, drill bit 1 be routed over multiple lead soil hole 1 be passed through in drill body 501, described in pulverize the top of pillar 7 also Filtration is installed and leads soil dividing plate 9.The top of described drill bit 1 is also equipped with the unearthed pipe 11 communicated with screw rod 5, described unearthed pipe 11 Open Side Down.When lower boring, the soil body enters drill body 501 by leading soil hole 1 and leads native dividing plate 9 by filtration and enter spiral Be discharged in bar 5 be unearthed outside pipe 11, such rig 500 can quickly under get into and reach designated depth.
Under righting, rig 600 includes that car body 25, the two ends of described car body 25 are provided with mobile fixed cover 22 and rotary box 28, mobile fixed cover 22 is provided with draw ring 20, rotary box 28 end of described car body 25 is provided with strander 16, described draw ring Being connected between 20 with strander 16 and have steel wire rope 19, the interlude of described steel wire rope 19 is by being arranged on the support bar on car body 25 Prop up.
Based on said apparatus, this utility model additionally provides the detection side determining foundation pile length in based on parallel seismic wave method Method, it is characterised in that comprise the steps:
1) test point is chosen, by being placed under righting above rig 600 by rig 500, by mobile fixed cover 22 and rotary box 28 fix, wherein: the mobile fixing top entangling rig 500 of fixed cover 22, rotary box 28 entangles brill The lower end of hole equipment 500;
2) drive steel wire rope 19 pull-up to make rig 500 vertically attention by strander 16, unclamp mobile fixed cover 22, and start motor 12 and drive drill bit 1 time to bore set depth;Wherein: in going down process, soil enters brill by leading soil hole 1 Body 501 is also led in soil dividing plate 9 enters screw rod 5 by filtration and is discharged to be unearthed outside pipe 11;
3) on the cushion cap of foundation pile 100, trigger 800 is placed, and by the data circuit group of trigger 800 and cymoscope 4 Data circuit group two connects main frame 400, sets up cross bar 302 above foundation pile, is arranged on below cross bar by exciting hammer 300, detection Front Job readiness completes;
4) first cymoscope is placed at the bottom of inspecting hole test tube mouth or pipe during detection, on engineering pile, generates machine by exciting hammer 300 While tool ripple, in test tube, detect vibration signal, analyze the quality of signals collecting, if quality is the best, resampling, otherwise Preserve the waveform of this measuring point, and one exciting detection week after date, control module receives information, controls lifting device 401 and opens The dynamic height decline by cymoscope 4 or lifting 0.5-1m, continuing hammering sampling, until mentioning on cymoscope at the bottom of the mouth of pipe or pipe being Only;
5) main frame 400 exports image, by passing judgment on criterion as follows: 1, time m-depth map in first arrival time slope Change;2, the significantly decay amplitude of energy;I.e. first arrival time and the comprehensive analysis of amplitude to the seismic wave wave train, it is judged that pile body is long Degree and integrity.
In addition to the implementation, this utility model can also have other embodiments.All employing equivalents or equivalence become Change the technical scheme of formation, all fall within the protection domain of this utility model requirement.

Claims (3)

1. determine the detection device of foundation pile length based on parallel seismic wave method, hammer (300), main frame (400), rig into shape including exciting (500), rig (600) and trigger (800) under righting, trigger (800) is placed on the cushion cap of described foundation pile (100), Main frame (400) is connected with trigger (800) data circuit group, it is characterised in that
Described rig (500) includes that drill body (501), the bottom of described drill body (501) are provided with drill bit (1), top is installed There is motor (12), the screw rod (5) that motor (12) is rotated, described screw rod (5) and brill are installed in described drill body (501) Be provided with and pulverize pillar (7) between head (1), described in pulverize the top of pillar (7) and be provided with gear one (6) phase with screw rod (5) The upper planet wheel (8) of engagement, the bottom of described broken pillar (7) is provided with the gear two (502) with drill bit (1) and is meshed lower planet Wheel;It is provided with protection pipe in described drill body (501), in described protection pipe, is placed with cymoscope (4), described cymoscope (4) and main frame (400) connection has data circuit group two;
Described exciting hammer (300) is arranged on horizontal cross bar (302) by guiding conduit (301) into, described cross bar (302) fixed mount If with foundation pile (100) top, described in guide into tripping gear (303) be installed between conduit (301) and cross bar (302), be used for adjusting Whole exciting hammer (300) fall away from.
2. determine the detection device of foundation pile length as claimed in claim 1 based on parallel seismic wave method, it is characterised in that described drill bit (1) be routed over and multiple led in soil hole one (2) is passed through drill body (501), described in pulverize the top of pillar (7) and be also equipped with filtering Lead soil dividing plate (9).
3. determine the detection device of foundation pile length as claimed in claim 1 based on parallel seismic wave method, it is characterised in that described drill bit (1) top is also equipped with the unearthed pipe (11) communicated with screw rod (5), and Open Side Down for described unearthed pipe (11).
CN201620853224.1U 2016-08-09 2016-08-09 Detection apparatus for foundation pile length is confirmed to parallel seismic wave method Active CN205875237U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620853224.1U CN205875237U (en) 2016-08-09 2016-08-09 Detection apparatus for foundation pile length is confirmed to parallel seismic wave method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620853224.1U CN205875237U (en) 2016-08-09 2016-08-09 Detection apparatus for foundation pile length is confirmed to parallel seismic wave method

Publications (1)

Publication Number Publication Date
CN205875237U true CN205875237U (en) 2017-01-11

Family

ID=57701571

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620853224.1U Active CN205875237U (en) 2016-08-09 2016-08-09 Detection apparatus for foundation pile length is confirmed to parallel seismic wave method

Country Status (1)

Country Link
CN (1) CN205875237U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049567A (en) * 2016-08-09 2016-10-26 浙江省建设工程质量检验站有限公司 Detecting device for determining length of foundation pile by parallel earthquake method and detecting method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049567A (en) * 2016-08-09 2016-10-26 浙江省建设工程质量检验站有限公司 Detecting device for determining length of foundation pile by parallel earthquake method and detecting method thereof
CN106049567B (en) * 2016-08-09 2018-01-05 浙江省建设工程质量检验站有限公司 Parallel seismic wave method determines the detection means and its detection method of foundation pile length

Similar Documents

Publication Publication Date Title
CN106088170B (en) The detection means and its detection method of foundation pile length are determined based on parallel seismic wave method
CN104181581B (en) Earthquake wave underground construction space observation system and method based on random arrangement
CN101570974A (en) Method for detecting quality of existing building foundation piles with parallel seismic method
CN103255785A (en) Technology for performing foundation pile quality detection and geology survey by adopting single tube longitudinal wave method
CN102736124A (en) Tunnel excavation surrounding rock dynamic refined classification method based on integrated parameters
CN108318584A (en) Single-hole sound-wave combines the method for across hole CT detections pile quality and gradient
CN105318824B (en) A kind of method that wall rock loosening ring is measured based on distributed resistance foil gauge
Rausche Non-destructive evaluation of deep foundations
CN103669428B (en) With the integrity detection system of cushion cap foundation pile
CN103953076A (en) Existing engineering pile bottom depth determination method based on parallel seismic inflexion-point method
CN102819046B (en) Two D type coil nuclear magnetic resonance analyser is with roadway front gushing water detection method
CN106049567B (en) Parallel seismic wave method determines the detection means and its detection method of foundation pile length
CN106597528A (en) Tunnel geology three-dimensional seismic reflection and seismo-electric integrated advanced exploration device and method
CN108037184A (en) Tunnel inverted arch detection of construction quality method
CN104594395A (en) Operation railroad bed side drilling pile foundation detection structure and detection method
CN108343432A (en) A kind of drilling pouring pile hole quality detection device and its detection method
CN205875237U (en) Detection apparatus for foundation pile length is confirmed to parallel seismic wave method
CN205954717U (en) Detection device based on foundation pile length is confirmed to parallel seismic wave method
CN106049566B (en) Side hole transmitted wave method determines the detection means and its detection method of foundation pile length
CN210395465U (en) Side surface excitation structure for detecting integrity of foundation pile by double-speed method and detection device
CN109469119B (en) Test method of offshore wind power socketed steel pipe pile
CN205875236U (en) Detection apparatus for foundation pile length is confirmed to other hole penetrated wave method
CN111158043B (en) System and method for detecting hidden danger at pile bottom of bored pile
CN104729915A (en) Device and method for searching looseness and emptiness of urban subway interval road in detail
CN108825136B (en) Building pile foundation detection device

Legal Events

Date Code Title Description
GR01 Patent grant