CN107794843A - 一种桥梁减震限位器实施方法 - Google Patents
一种桥梁减震限位器实施方法 Download PDFInfo
- Publication number
- CN107794843A CN107794843A CN201711003178.1A CN201711003178A CN107794843A CN 107794843 A CN107794843 A CN 107794843A CN 201711003178 A CN201711003178 A CN 201711003178A CN 107794843 A CN107794843 A CN 107794843A
- Authority
- CN
- China
- Prior art keywords
- key
- abutment
- limiting plate
- beam body
- bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/06—Arrangement, construction or bridging of expansion joints
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明提供了一种桥梁减震限位器实施方法,包括以下步骤:A在梁体联两端、桥台上按设计位置预埋锚板;B限位板与锚板水平焊接;C梁体限位板上设置下减震键;D桥台限位板上设置上减震键和横向减震键,上、下减震键交错、分离、咬合。本发明的体系受力明确、结构安全可靠,整个过程操作简单,施工快速;能够有效限制地震作用下梁体移位,耗散地震能量,减小桥梁结构损伤。
Description
技术领域
本发明属于桥梁工程技术领域,具体来说,涉及一种桥梁减震限位器实施方法。
背景技术
连续梁桥一般设置有多道伸缩缝,地震作用下为主梁移位提供了空间,主梁易移位, 落梁风险大。在地震中,梁式桥的主梁、桥墩、支座、桥台、桥面连续、主梁横向连接 系、墩台挡块构成了一个完整的抗震系统,支座对主梁移位约束较弱,桥面铺装协调了 一联内主梁移位,起到了连梁装置的作用,桥台有效的约束了主梁的纵向移位,挡块有 效的约束了主梁的横向移位,这些都在很大程度上控制了主梁移位,防止了落梁。但应 看到,桥台的限位作用对于小桥是有效的,对于大、中桥梁,由于伸缩缝数量多,使得 桥台的纵向限位作用大打折扣,若桥台背墙破坏将使得桥台的约束作用大大减弱,从而 导致落梁,现有抗震技术和构造措施仍有较大改进余地。
发明内容
本发明所要解决的技术问题是解决连续梁桥在地震荷载作用下梁体移位较大、甚至 落梁的问题。
为了解决上述技术问题,本发明所采用的技术方案是提供了一种桥梁减震限位器实 施方法,包括以下步骤:
A、在混凝土连续梁桥桥台和梁体绑扎钢筋阶段,分别在两端桥台和梁体联结的两端 处预埋锚板,锚板纵向中心线重合;
B、限位板与桥台和梁体的预埋锚板焊接,限位板纵向中心线与预埋锚板对齐;
C、梁体限位板上设置双道下减震键;
D、桥台限位板上设置双道上减震键;
E、桥台限位板两侧分别设置一道横向减震键;
F、限位器焊接现场成型,连续梁安装就位后,减震键呈交错、分离或咬合状。
优选的,所述步骤B中,桥台限位板宽度大于梁体限位板,并保证限位板水平。
优选的,所述步骤C中,下减震键宽度与梁体限位板一致,高度小于梁体限位板与桥台限位板间净距。
优选的,所述步骤D中,上减震键宽度和高度与下减震键一致。
优选的,所述步骤E中,横向减震键高度小于上减震键,纵向长度大于两道上减震键间距离。
优选的,所述混凝土连续梁桥为现浇或装配式混凝土连续梁桥。
本发明的体系受力明确、结构安全可靠,整个过程操作简单,施工快速;能够有效限制地震作用下梁体纵、横向移位,防止落梁;释放主梁地震作用,耗散地震能量,有 效减小地震作用下桥台及梁体损伤。
附图说明
图1为桥梁减震限位器总体布置图。
图2为桥梁减震限位器构造示意图。
图3为桥梁减震限位器构造平面图。
图4为桥梁减震限位器构造正面图。
图5为地震作用下桥梁减震限位器工作总体示意图。
图6为桥梁减震限位器工作示意图。
图7为桥梁减震限位器工作平面图。
图8为桥梁减震限位器工作正面图。
图9为桥梁减震限位器横向工作示意图。
图10为桥梁减震限位器横向工作平面图。
具体实施方式
为使本领域的技术人员更好地理解本发明的技术方案,下面结合附图对本发明提供 的桥梁减震限位器实施方法进行详细描述。
如图1~图10所示,本发明提供一种桥梁减震限位器实施方法,包括以下步骤:
A在现浇或装配式混凝土连续梁桥桥台2、梁体1绑扎钢筋阶段,分别在两端桥台2、梁体1联的两端处按设计位置预埋锚板4,锚板4纵向中心线重合;
盖梁10与桥墩11刚性连接,在桥台2盖梁10上安装支座3,现浇连续梁桥直接在 支座3上立模、绑扎钢筋,预埋锚板4在桥台2、梁体1位置可直接确定;装配式混凝 土连续梁桥在预制场立模和绑扎钢筋,按照设计位置在桥台2、梁体1上预埋锚板4,预 制梁成型后最后安装至支座3上。
B限位板6、8与桥台2、梁体1的预埋锚板4焊接,限位板6、8纵向中心线与预 埋锚板4对齐,桥台限位板6宽度大于梁体限位板8,并保证限位板6、8水平,焊接牢 靠;
桥台限位板6与桥台2上的预埋锚板4焊接,梁体限位板8与梁体1上的预埋锚板 4焊接,为装配式混凝土连续梁桥施工方便,梁体限位板8在桥台限位板6之上。
C梁体限位板8上设置双道下减震键7,下减震键7宽度与梁体限位板8一致,高 度小于梁体限位板8与桥台限位板6间净距,双道下减震键7纵向距离符合计算要求;
D桥台限位板6上设置双道上减震键5,上减震键5宽度、高度与下减震键7一致, 双道上减震键5纵向距离符合计算要求;
E桥台限位板6两侧分别设置一道横向减震键9,横向减震键9高度小于上减震键5,纵向长度大于两道上减震键间5距离,正常使用情况下,横向减震键9与上5、下减震 键7不接触;
F现浇梁1桥限位器焊接现场成型,装配式连续梁1安装就位后,减震键5、7呈交错、分离、咬合状。
正常使用条件下,上减震键5、下减震键7交错、分离、咬合,横向减震键9与上5、 下减震键7不接触,保证梁体正常使用变形要求;地震条件下,通过两道上减震键5、 下减震键7相互错动、碰撞来释放主梁1地震作用,耗散地震能量,并限制梁体1纵向 移位过大及避免落梁,防止梁体1、桥台2结构损伤;梁体1横向移位时,下减震键7 横向受到横向减震键9约束,限制梁体1横向移位。桥台限位板6、梁体限位板8、上减 震键5、下减震键7、横向减震键9组成的减震限位器与主梁1、桥墩11、支座3、桥台 2等构成一个完整的抗震系统。
上述步骤完成后,进行桥面系后续施工。
可以理解的是,以上实施方式仅仅是为了说明本发明的原理而采用的示例性实施方 式,然而本发明并不局限于此。对于本领域内的普通技术人员而言,在不脱离本发明的精神和实质的情况下,可以做出各种变型和改进,这些变型和改进也视为本发明的保护 范围。
Claims (6)
1.一种桥梁减震限位器实施方法,其特征在于,包括以下步骤:
A、在混凝土连续梁桥桥台和梁体绑扎钢筋阶段,分别在两端桥台和梁体联结的两端处预埋锚板,锚板纵向中心线重合;
B、限位板与桥台和梁体的预埋锚板焊接,限位板纵向中心线与预埋锚板对齐;
C、梁体限位板上设置双道下减震键;
D、桥台限位板上设置双道上减震键;
E、桥台限位板两侧分别设置一道横向减震键;
F、限位器焊接现场成型,连续梁安装就位后,减震键呈交错、分离或咬合状。
2.根据权利要求1所述的桥梁减震限位器实施方法,其特征在于,所述步骤B中,桥台限位板宽度大于梁体限位板,并保证限位板水平。
3.根据权利要求2所述的桥梁减震限位器实施方法,其特征在于,所述步骤C中,下减震键宽度与梁体限位板一致,高度小于梁体限位板与桥台限位板间净距。
4.根据权利要求3所述的桥梁减震限位器实施方法,其特征在于,所述步骤D中,上减震键宽度和高度与下减震键一致。
5.根据权利要求4所述的桥梁减震限位器实施方法,其特征在于,所述步骤E中,横向减震键高度小于上减震键,纵向长度大于两道上减震键间距离。
6.根据权利要求1至5中任意一条所述的桥梁减震限位器实施方法,其特征在于,所述混凝土连续梁桥为现浇或装配式混凝土连续梁桥。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711003178.1A CN107794843B (zh) | 2017-10-24 | 2017-10-24 | 一种桥梁减震限位器实施方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711003178.1A CN107794843B (zh) | 2017-10-24 | 2017-10-24 | 一种桥梁减震限位器实施方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107794843A true CN107794843A (zh) | 2018-03-13 |
CN107794843B CN107794843B (zh) | 2019-08-06 |
Family
ID=61533529
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711003178.1A Active CN107794843B (zh) | 2017-10-24 | 2017-10-24 | 一种桥梁减震限位器实施方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107794843B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111794071A (zh) * | 2020-07-06 | 2020-10-20 | 上海崇明水利工程有限公司 | 一种水利桥梁结构 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU614156A1 (ru) * | 1976-12-30 | 1978-07-05 | Киевский Отдел Специального Конструкторского Бюро Главмостроя | Устройство дл надвижки пролетных строений мостов |
CN101476286A (zh) * | 2008-11-24 | 2009-07-08 | 中铁二局股份有限公司 | 铁路桥面预应力混凝土纵横梁格构式漂浮体系施工方法 |
CN102505637A (zh) * | 2011-10-31 | 2012-06-20 | 河南省新开元路桥工程咨询有限公司 | 连续箱梁桥的支座布置方法 |
CN105421218A (zh) * | 2015-11-26 | 2016-03-23 | 周汉林 | 桥梁上部结构和下部结构的连接部以及支座的施工方法 |
CN105908628A (zh) * | 2016-04-22 | 2016-08-31 | 上海市机械施工集团有限公司 | 钢桁架桥整体滚装上岸装置及其施工方法 |
-
2017
- 2017-10-24 CN CN201711003178.1A patent/CN107794843B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU614156A1 (ru) * | 1976-12-30 | 1978-07-05 | Киевский Отдел Специального Конструкторского Бюро Главмостроя | Устройство дл надвижки пролетных строений мостов |
CN101476286A (zh) * | 2008-11-24 | 2009-07-08 | 中铁二局股份有限公司 | 铁路桥面预应力混凝土纵横梁格构式漂浮体系施工方法 |
CN102505637A (zh) * | 2011-10-31 | 2012-06-20 | 河南省新开元路桥工程咨询有限公司 | 连续箱梁桥的支座布置方法 |
CN105421218A (zh) * | 2015-11-26 | 2016-03-23 | 周汉林 | 桥梁上部结构和下部结构的连接部以及支座的施工方法 |
CN105908628A (zh) * | 2016-04-22 | 2016-08-31 | 上海市机械施工集团有限公司 | 钢桁架桥整体滚装上岸装置及其施工方法 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111794071A (zh) * | 2020-07-06 | 2020-10-20 | 上海崇明水利工程有限公司 | 一种水利桥梁结构 |
Also Published As
Publication number | Publication date |
---|---|
CN107794843B (zh) | 2019-08-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101072259B1 (ko) | 피에스씨 거더와 교량 하부구조의 강결방법 | |
WO2019237678A1 (zh) | 桥台刚构桥的构造及其施工方法 | |
CN108374504B (zh) | 预制装配式钢筋混凝土剪力墙结构及其施工方法 | |
KR101653740B1 (ko) | 라멘교용 양 수직벽을 포함하는 거더, 이를 이용한 라멘교 및 그 시공방법 | |
CN107794843A (zh) | 一种桥梁减震限位器实施方法 | |
KR102369701B1 (ko) | 변형흡수 및 침하저감이 가능한 구조물 접속부 및 그 시공방법 | |
CN103469725A (zh) | 桥梁结构断缝错位伸缩缝构造 | |
CN209925003U (zh) | 一种盾构隧道内管道架空敷设抗震支墩 | |
CN208949745U (zh) | 一种满足新旧桥沉降差的桥梁拼宽构造 | |
JP5914624B1 (ja) | コンクリート構造物 | |
KR20210007420A (ko) | 완충부를 이용한 일체형 구조물 접속부 및 그 시공방법 | |
CN211171571U (zh) | 一种防治桥头跳车的引道与路面搭接结构 | |
CN112813852B (zh) | 一种在役桥梁桥面沉陷的修复加固方法 | |
CN212316578U (zh) | 一种快速装配的箱涵式路基结构 | |
JP7154715B2 (ja) | 軌道こう上工法 | |
CN207362678U (zh) | 一种连续梁桥纵向减震限系统 | |
CN212834958U (zh) | 一种墩梁缓冲构造及抗震桥梁 | |
CN113529516A (zh) | 一种下穿铁路桥公路的桩板路基结构及其施工方法 | |
KR101973657B1 (ko) | 교대 측방유동 방지용 역아치 구조 및 이를 이용한 개보수공법 | |
CN103437252B (zh) | 一种轨道路基结构及其施工方法 | |
JP6886811B2 (ja) | 基礎構造及び基礎構造の構築方法 | |
KR102105680B1 (ko) | 연속형 거더와 교각 일체화 접합구조 | |
KR102562385B1 (ko) | 교량상부구조 변형흡수가 가능한 돌출형 교량접속부 및 그 시공방법 | |
JP3806681B2 (ja) | 道路の構築方法及び構築材 | |
CN217678548U (zh) | 一种栈桥与坝体的过渡段结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |