CN107746012A - Building-brick type wall hanging method - Google Patents
Building-brick type wall hanging method Download PDFInfo
- Publication number
- CN107746012A CN107746012A CN201711223400.9A CN201711223400A CN107746012A CN 107746012 A CN107746012 A CN 107746012A CN 201711223400 A CN201711223400 A CN 201711223400A CN 107746012 A CN107746012 A CN 107746012A
- Authority
- CN
- China
- Prior art keywords
- wall
- hanging
- building
- suspension hook
- brick type
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/12—Slings comprising chains, wires, ropes, or bands; Nets
- B66C1/18—Band-type slings
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/18—Control systems or devices
- B66C13/40—Applications of devices for transmitting control pulses; Applications of remote control devices
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Automation & Control Theory (AREA)
- Load-Engaging Elements For Cranes (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention provides building-brick type wall hanging method, comprise the following steps:Using wall-building machine in ground Qi Chuyi faces wall;Hanging beam is placed on to the top of wall, the rectangular groove structure of hanging beam, the groove is interior to be provided with some hanging blocks;Hanging beam is together packed with wall using strap, the packing is to wind strap at a certain distance on the surface of wall;The main suspension hook being arranged on by slide rail on the suspension rod is connected with hanging device, the boom foot is provided with and is provided with component suspension hook with the equidistant chain sling of the hanging block, the chain sling bottom, the component suspension hook is hung in the hanging block of the hanging beam;Start hanging device, wall is then adjusted suspension rod slightly from the ground, balance the both ends of main suspension hook;Continue to operate hanging device, wall is lifted into fixed position.The present invention is easy to operate, safe and reliable, and improves the lifting efficiency of wall.
Description
Technical field
The present invention relates to the Hoisting Program of building-brick type wall in building, particularly building-brick type wall hanging method.
Background technology
With the development of science and technology the technology of building a wall will be from manually progressively to mechanization, large-scale development, and wall-building machine goes out
It is existing, this process is accelerated, wall-building machine is the high intelligence machine operation controlled by Digital Control panel, can be built with automatic transport
Block, brick, automatic plastering are taken automatically, after robotic arm has taken fragment of brick, a rotation wipes ash, and another rotation puzzles.Due to building
Wall telephone volume is larger, is not easy to directly construct in construction place, so needs will build a wall, device puzzles wall on ground, so
Wall is lifted into fixed position again afterwards.But because wall volume is larger, the problem of being not easy to lift be present.
The content of the invention
To solve the above problems, it is an object of the invention to provide a kind of building-brick type wall hanging method.
Building-brick type wall hanging method, comprises the following steps:
Step S1:Using wall-building machine in ground Qi Chuyi faces wall;
Step S2:Hanging beam is placed on to the top of wall, the rectangular groove structure of hanging beam, the groove is interior to be provided with some hang
Block;
Step S3:Hanging beam is together packed with wall using strap, the packing is twined at a certain distance on the surface of wall
Around strap;
Step S4:The main suspension hook being arranged on by slide rail on the suspension rod is connected with hanging device, the boom foot is provided with
With the equidistant chain sling of the hanging block, the chain sling bottom is provided with component suspension hook, and the component suspension hook is hung in into described hang
In the hanging block of beam;
Step S5:Start hanging device, wall is then adjusted suspension rod slightly from the ground, balance the both ends of main suspension hook;
Step S6:Continue to operate hanging device, wall is lifted into fixed position.
Further, the hanging beam is building-brick type wall entirety hanging beam, and its one end is provided with rectangular through-hole, and the other end is fixed with
Clamping apparatus, the through hole coordinate with clamping apparatus, so as to which two hanging beams be connected.
To ensure that packing is reliable, the strap is steel band.
For ease of adjusting suspension rod, the suspension rod is provided with the motor for controlling main suspension hook to slide, and the motor leads to
Cross remote control control.
To prevent suspension rod from being skidded off out of slide rail, the both ends of the suspension rod are respectively equipped with limited block.
The beneficial effect of building-brick type wall hanging method of the present invention is:The present invention is easy to operate, and staff is on ground
Operation achieves that the lifting of wall, reduces construction cost and insecurity, improves the lifting efficiency of wall.
Embodiment
The principle and feature of the present invention are described with reference to embodiments, illustrated embodiment is served only for explaining this hair
It is bright, it is not intended to limit the scope of the present invention.
Building-brick type wall hanging method, comprises the following steps:
Step S1:Using wall-building machine in ground Qi Chuyi faces wall;
Step S2:Hanging beam is placed on to the top of wall, the rectangular groove structure of hanging beam, the groove is interior to be provided with some hang
Block;
Step S3:Hanging beam is together packed with wall using strap, the packing is twined at a certain distance on the surface of wall
Around strap;
Step S4:The main suspension hook being arranged on by slide rail on the suspension rod is connected with hanging device, the boom foot is provided with
With the equidistant chain sling of the hanging block, the chain sling bottom is provided with component suspension hook, and the component suspension hook is hung in into described hang
In the hanging block of beam;
Step S5:Start hanging device, wall is then adjusted suspension rod slightly from the ground, balance the both ends of main suspension hook;
Step S6:Continue to operate hanging device, wall is lifted into fixed position.
Further, the hanging beam is building-brick type wall entirety hanging beam, and its one end is provided with rectangular through-hole, and the other end is fixed with
Clamping apparatus, the through hole coordinate with clamping apparatus, so as to which two hanging beams be connected.
To ensure that packing is reliable, the strap is steel band.
For ease of adjusting suspension rod, the suspension rod is provided with the motor for controlling main suspension hook to slide, and the motor leads to
Cross remote control control.
To prevent suspension rod from being skidded off out of slide rail, the both ends of the suspension rod are respectively equipped with limited block.
The present invention is achieved in the following ways:Using wall-building machine in ground Qi Chuyi faces wall, hanging beam is placed on
The top of wall, hanging beam is together packed with wall using steel band, the main suspension hook on the suspension rod is arranged on hanging device,
The component suspension hook is hung in the hanging block of the hanging beam;Start hanging device, make wall slightly from the ground, observation suspension rod is
No balance, if balance, continues to lift by crane, if uneven, using remote control control motor, so as to adjust suspension rod, make master
The both ends balance of suspension hook, continues to operate hanging device, wall is lifted into fixed position.
Protection scope of the present invention is not limited to the technical scheme disclosed in embodiment, every skill according to the present invention
Any modification, equivalent substitution and improvements that art is substantially made to above example etc., each fall within protection scope of the present invention.
Claims (5)
1. building-brick type wall hanging method, it is characterised in that:Comprise the following steps:
Step S1:Using wall-building machine in ground Qi Chuyi faces wall;
Step S2:Hanging beam is placed on to the top of wall, the rectangular groove structure of hanging beam, the groove is interior to be provided with some hang
Block;
Step S3:Hanging beam is together packed with wall using strap, the packing is twined at a certain distance on the surface of wall
Around strap;
Step S4:The main suspension hook being arranged on by slide rail on the suspension rod is connected with hanging device, the boom foot is provided with
With the equidistant chain sling of the hanging block, the chain sling bottom is provided with component suspension hook, and the component suspension hook is hung in into described hang
In the hanging block of beam;
Step S5:Start hanging device, wall is then adjusted suspension rod slightly from the ground, balance the both ends of main suspension hook;
Step S6:Continue to operate hanging device, wall is lifted into fixed position.
2. building-brick type wall hanging method as claimed in claim 1, it is characterised in that:The hanging beam is that building-brick type wall is overall
Hanging beam, its one end are provided with rectangular through-hole, and the other end is fixed with clamping apparatus, and the through hole coordinates with clamping apparatus, so as to by two
Root hanging beam connects.
3. building-brick type wall hanging method as claimed in claim 1, it is characterised in that:The strap is steel band.
4. building-brick type wall hanging method as claimed in claim 1, it is characterised in that:The suspension rod, which is provided with, controls main suspension hook
The motor of slip, the motor pass through remote control control.
5. the building-brick type wall hanging method as described in claim 1 or 4, it is characterised in that:The both ends of the suspension rod are set respectively
Limited location block.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711223400.9A CN107746012A (en) | 2017-11-29 | 2017-11-29 | Building-brick type wall hanging method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711223400.9A CN107746012A (en) | 2017-11-29 | 2017-11-29 | Building-brick type wall hanging method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107746012A true CN107746012A (en) | 2018-03-02 |
Family
ID=61249784
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711223400.9A Pending CN107746012A (en) | 2017-11-29 | 2017-11-29 | Building-brick type wall hanging method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107746012A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2475073A (en) * | 1944-09-08 | 1949-07-05 | Vacuum Concrete Inc | Handling apparatus |
CN201703968U (en) * | 2010-05-20 | 2011-01-12 | 中国核工业华兴建设有限公司 | Shoulder pole for hoisting steel mesh piece |
CN102491162A (en) * | 2011-11-24 | 2012-06-13 | 北京金风科创风电设备有限公司 | Hoisting equipment and hoisting method |
CN204958135U (en) * | 2015-08-14 | 2016-01-13 | 文登蓝岛建筑工程有限公司 | Hoist of handling modularization wall body |
CN206384709U (en) * | 2017-01-13 | 2017-08-08 | 贵州兴贵恒远新型建材有限公司 | A kind of suspension bracket for being used to sling wall |
-
2017
- 2017-11-29 CN CN201711223400.9A patent/CN107746012A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2475073A (en) * | 1944-09-08 | 1949-07-05 | Vacuum Concrete Inc | Handling apparatus |
CN201703968U (en) * | 2010-05-20 | 2011-01-12 | 中国核工业华兴建设有限公司 | Shoulder pole for hoisting steel mesh piece |
CN102491162A (en) * | 2011-11-24 | 2012-06-13 | 北京金风科创风电设备有限公司 | Hoisting equipment and hoisting method |
CN204958135U (en) * | 2015-08-14 | 2016-01-13 | 文登蓝岛建筑工程有限公司 | Hoist of handling modularization wall body |
CN206384709U (en) * | 2017-01-13 | 2017-08-08 | 贵州兴贵恒远新型建材有限公司 | A kind of suspension bracket for being used to sling wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103043526B (en) | Integral hoisting device and method for super-long steel reinforcement cage of underground continuous wall | |
CN103738834A (en) | Adjustable three-point lifting method | |
GB201209006D0 (en) | High rise building elevation concept | |
CN106006425B (en) | A kind of high-rise building ground machine room lower large scale equipment hoisting transportation method | |
CN103711078A (en) | Temporary girder-type support for bridge construction and dismantling method thereof | |
CN107502690A (en) | A kind of point of device and replacing options with integral replacing last furnace shell | |
CN203474231U (en) | Steel bar tower safety hoisting device | |
CN204057659U (en) | The prefabricated superimposed panel lifting appliance of super large | |
CN107746012A (en) | Building-brick type wall hanging method | |
CN102677907A (en) | Method for manually installing steel beam at top of silo | |
CN107675890A (en) | A kind of method at aerial regulation steel truss mast-up angle of inclination | |
CN204897283U (en) | Small -size crane is used to fitment | |
CN207243334U (en) | A kind of long and narrow working face large-sized transversal component high-altitude system in place | |
CN207030735U (en) | Prefabricated balcony lifts servicing unit | |
CN202988556U (en) | Special lifting appliance for angle-steel type frame body | |
CN205367457U (en) | Cast member installs special hoist | |
CN206051364U (en) | A kind of curtain wall profiles boom hoisting | |
CN207647196U (en) | It is a kind of to be used for the device that framework of steel reinforcement height is adjusted when anchor bolt construction | |
CN207330971U (en) | A kind of point of device with integral replacing last furnace shell | |
CN206538100U (en) | Steel rail hoisting tool | |
CN206395707U (en) | A kind of boom hoisting bolt type connector | |
CN205634695U (en) | Dolly is built by laying bricks or stones to blast furnace carbon brick | |
CN112125163A (en) | Supplementary device of building stones | |
CN204297905U (en) | A kind of lifting device of precast concrete | |
CN103601066B (en) | Lifting appliance for lifting equipment at hidden position and lifting method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180302 |