CN103711078A - Temporary girder-type support for bridge construction and dismantling method thereof - Google Patents

Temporary girder-type support for bridge construction and dismantling method thereof Download PDF

Info

Publication number
CN103711078A
CN103711078A CN201310693007.1A CN201310693007A CN103711078A CN 103711078 A CN103711078 A CN 103711078A CN 201310693007 A CN201310693007 A CN 201310693007A CN 103711078 A CN103711078 A CN 103711078A
Authority
CN
China
Prior art keywords
steel pipe
ground
temporary
girder
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310693007.1A
Other languages
Chinese (zh)
Inventor
魏赞洋
张文学
黄荐
陈壮
刘海陆
李增银
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing University of Technology
Original Assignee
Beijing University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Technology filed Critical Beijing University of Technology
Priority to CN201310693007.1A priority Critical patent/CN103711078A/en
Publication of CN103711078A publication Critical patent/CN103711078A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种桥梁施工中临时梁式支架及拆除方法。首先,利用分配梁将临时梁组悬挂于已完成施工的桥梁主梁上。然后,断开分配梁与钢管的连接,在地面上从钢管根部割断钢管卸除临时梁式支架内的荷载,进而拆除钢管。最后,用起重设备将临时梁组整体下放到地面,在地面完成拆分。优点:避免了采用传统方法沙箱卸除荷载、自上而下拆除时高空作业多、结构复杂的缺点。工人基本上都在地面作业。因而提高了施工的效率和安全性,降低了施工成本。

Figure 201310693007

The invention relates to a temporary beam-type support in bridge construction and a removal method thereof. First, the temporary girder group is suspended on the main girder of the completed bridge by means of distribution beams. Then, disconnect the connection between the distribution beam and the steel pipe, cut the steel pipe from the root of the steel pipe on the ground to remove the load in the temporary beam support, and then remove the steel pipe. Finally, use lifting equipment to lower the temporary beam group to the ground as a whole, and complete the split on the ground. Advantages: It avoids the shortcomings of many high-altitude operations and complex structures when using the traditional method of sandbox unloading and top-down demolition. Workers basically work on the ground. Therefore, the efficiency and safety of the construction are improved, and the construction cost is reduced.

Figure 201310693007

Description

一种桥梁施工中临时梁式支架及其拆除方法Temporary beam support and its removal method in bridge construction

技术领域technical field

本发明涉及一种桥梁施工中临时梁式支架的拆除方法。适用于各种施工临时受力结构的拆除。能够大大减少拆除工作中工人的高空作业,提高施工效率和安全性。The invention relates to a method for removing temporary beam-type supports in bridge construction. It is suitable for the demolition of various construction temporary stress structures. It can greatly reduce the high-altitude work of workers in demolition work, and improve construction efficiency and safety.

技术背景technical background

临时梁式支架是一种施工临时结构,包括钢管、临时梁,以及分配梁,施工时在临时梁上搭建模板浇注主梁,临时梁(如贝雷梁、型钢、军用梁)负责水平传力,分配梁位于钢管和临时梁之间,用于分配各个临时梁的载荷,钢管完成竖向传力。Temporary beam support is a temporary structure for construction, including steel pipes, temporary beams, and distribution beams. During construction, formwork pouring main beams are built on temporary beams, and temporary beams (such as Bailey beams, shaped steel, and military beams) are responsible for horizontal force transmission. The distribution beam is located between the steel pipe and the temporary beam, and is used to distribute the load of each temporary beam, and the steel pipe completes the vertical force transmission.

相对于满堂支架梁式支架,临时梁式支架有跨度大对河道影响小的优点,被大量应用于采用整体现浇等方法施工的桥梁建设中。在桥梁建成后临时梁式支架就需要拆除。在传统的作法中,预先在钢管和临时梁之间设置沙箱。桥梁施工完成后放出沙箱内的沙子,卸除临时梁式支架内荷载。然后高空拆除临时梁,最后拆除钢管柱。这种拆除方法高空作业多效率低、结构复杂。Compared with the beam-type support of the full hall support, the temporary beam-type support has the advantage of large span and little impact on the river channel, and is widely used in the construction of bridges constructed by integral cast-in-place and other methods. The temporary beam supports will need to be removed after the bridge is built. In traditional practice, a sandbox is pre-set between steel pipes and temporary beams. After the bridge construction is completed, the sand in the sandbox is released, and the load in the temporary beam support is removed. Then the temporary beams are removed at high altitude, and finally the steel pipe columns are removed. This demolition method works at heights with low efficiency and complex structure.

发明内容Contents of the invention

本发明的目的是提供一种相对更安全高效的临时梁式支架拆除方法。利用本发明可以克服上述既有方法中的不足。The purpose of the present invention is to provide a relatively safer and more efficient temporary beam support removal method. Utilize the present invention can overcome the deficiency in above-mentioned existing method.

本发明的实施方案是:Embodiments of the present invention are:

一种桥梁施工中临时梁式支架,包括临时梁、分配梁、钢管,吊装钢丝,用于搭建模板浇注带有吊装孔的主梁的临时梁通过分配梁架于钢管上,钢管立于地面,所述的吊装孔位于分配梁正上方,穿过吊装孔和分配梁的吊装钢丝用于在主梁施工完成后吊起临时梁,所述的钢管在临时梁被吊起后直接被切割。A temporary beam support in bridge construction, including temporary beams, distribution beams, steel pipes, and hoisting steel wires. The temporary beams used to build formwork pouring main beams with hoisting holes are placed on steel pipes through distribution beams, and the steel pipes stand on the ground. The hoisting hole is located directly above the distribution beam, and the hoisting steel wire passing through the hoisting hole and the distribution beam is used to hoist the temporary beam after the construction of the main beam is completed, and the steel pipe is cut directly after the temporary beam is hoisted.

一种桥梁施工中临时梁式支架的拆除方法,包括以下步骤:主梁施工时,在主梁上预留吊装孔,吊装孔位于分配梁正上方,主梁施工完成后将钢丝绳穿过主梁上预留的吊装孔,并固定在分配梁上,将各个临时梁整体悬挂主梁上,做好安全防护后,接下来在地面直接切割钢管卸除临时梁式支架内的荷载,将钢管拆除,最后由主梁顶面上的起重设备将临时梁整体下放到地面,在地面完成拆除。A method for dismantling a temporary beam-type support in bridge construction, comprising the following steps: during the construction of the main beam, a hoisting hole is reserved on the main beam, the hoisting hole is located directly above the distribution beam, and the steel wire rope is passed through the main beam after the construction of the main beam is completed The hoisting holes reserved above are fixed on the distribution beam, and each temporary beam is hung on the main beam as a whole. After safety protection is done, the steel pipe is cut directly on the ground to remove the load in the temporary beam bracket, and the steel pipe is removed. , and finally the temporary beam is lowered to the ground as a whole by the lifting equipment on the top surface of the main beam, and the demolition is completed on the ground.

本发明的基本特征是:1.取消传统方法中预先在结构中设置的沙箱。通过在地面切割钢管直接卸除临时梁式支架内的荷载。2.切割钢管前将临时梁组悬挂于已经完成施工的主梁上,拆除钢管后用起重设备将临时梁整体下放到地面,在地面完成拆除。The basic features of the present invention are: 1. Cancel the sandbox that is pre-set in the structure in the traditional method. The load is relieved directly in the temporary beam support by cutting steel pipes at ground level. 2. Before cutting the steel pipe, hang the temporary beam group on the main beam that has been constructed. After removing the steel pipe, use the lifting equipment to lower the temporary beam to the ground as a whole, and complete the demolition on the ground.

有益效果Beneficial effect

主要的拆除工作都在地面完成,大大减少高空作业。提高拆除工作的效率和安全性。The main demolition work is done on the ground, greatly reducing work at heights. Improve the efficiency and safety of demolition work.

附图说明Description of drawings

图1一种桥梁施工中临时梁式支架施工示意图Figure 1 A schematic diagram of temporary beam support construction in bridge construction

图2切割钢管卸除支架内荷载示意图Figure 2 Schematic diagram of cutting the steel pipe to remove the internal load of the bracket

图3临时梁组整体下放到地面示意图Figure 3 Schematic diagram of the overall lowering of the temporary beam group to the ground

其中:in:

1-临时支架纵梁1-Temporary support stringer

2-分配梁2- distribution beam

3-钢管3-steel pipe

4-主梁4- main beam

5-起重设备5- Lifting equipment

6-吊装孔6-lifting hole

具体实施方式Detailed ways

以下结合实施例及附图作进一步详述。实例中采用贝雷梁作为临时梁、钢管作为竖向传力结构,仅为更详细说明本专利的具体实施方式,不做为对本专利的限定。Further details will be given below in conjunction with the embodiments and accompanying drawings. In the examples, Bailey beams are used as temporary beams, and steel pipes are used as vertical force transmission structures, which are only a more detailed description of the specific implementation of this patent, and are not intended to limit this patent.

采用本方案拆除临时梁式支架时第一步如图1所示。用钢丝绳穿过主梁上预留的吊装孔6,通过分配梁2将临时支架纵梁1整体悬挂在位于已完成施工主梁4顶面的起重设备5上。第二步如图2所示。做好安全防护后(本实例中采用履带吊吊挂钢管顶部防止钢管倒落),在地面直接切割钢管3卸除贝雷梁-钢管支架内的荷载,并将钢管3拆除。第三步如图3所示。由完成施工的主梁4上的起重设备5将临时支架梁1整体下放到地面,在地面完成拆除。The first step when removing the temporary beam support using this scheme is shown in Figure 1. Pass the hoisting hole 6 reserved on the main beam with a steel wire rope, and hang the temporary support longitudinal beam 1 integrally on the hoisting device 5 positioned at the top surface of the main beam 4 that has been constructed through the distribution beam 2 . The second step is shown in Figure 2. After the safety protection is done (in this example, the crawler crane is used to hang the top of the steel pipe to prevent the steel pipe from falling), the steel pipe 3 is directly cut on the ground to remove the load in the Bailey beam-steel pipe support, and the steel pipe 3 is removed. The third step is shown in Figure 3. The temporary support beam 1 is lowered to the ground as a whole by the hoisting device 5 on the main beam 4 after construction, and the demolition is completed on the ground.

本发明的基本特征是:Essential features of the present invention are:

1.取消传统方法中预先在结构中设置的沙箱。通过在地面切割钢管3直接卸除贝雷梁-钢管支架内的荷载。1. Cancel the sandbox pre-set in the structure in the traditional method. The load in the Bailey beam-steel tube bracket is directly unloaded by cutting the steel tube 3 on the ground.

2.主梁施工时预留吊装孔6,切割钢管前将临时支架纵梁1悬挂于已完成施工的主梁4上,拆除钢管3后用起重设备5将临时梁组1整体下放到地面,在地面完成拆除。2. Reserve the hoisting hole 6 during the construction of the main beam. Before cutting the steel pipe, hang the temporary support longitudinal beam 1 on the main beam 4 that has been constructed. After removing the steel pipe 3, use the lifting device 5 to lower the temporary beam group 1 to the ground as a whole , to complete the demolition on the ground.

以上所述,仅是本发明的较佳实施例而已,并非对本发明做任何形式上的限制,任何未脱离本发明技术方案内容,依据本发明的技术实质,在本发明的精神和原则之内所作的的任何修改、等同变化与修饰,都应视为本发明方案的技术范畴,均应包含在本发明的保护范围内。The above is only a preferred embodiment of the present invention, and is not intended to limit the present invention in any form. Any content that does not deviate from the technical solution of the present invention, according to the technical essence of the present invention, is within the spirit and principles of the present invention. Any modifications, equivalent changes and modifications made should be regarded as the technical scope of the solution of the present invention and should be included in the protection scope of the present invention.

Claims (2)

1. interim beam type support in a bridge construction, it is characterized in that comprising: interim beam, distribution beam, steel pipe, lifting steel wire, for build pouring template with the interim beam of the girder of hole for hoist by distributing roof beam structure in steel pipe, steel pipe stands on ground, described hole for hoist is positioned at directly over distribution beam, passes the lifting steel wire of hole for hoist and distribution beam for sling interim beam after main girder construction completes, and described steel pipe is directly cut after interim beam is lifted.
2. the method for dismounting of interim beam type support in a bridge construction, it is characterized in that comprising the following steps: during main girder construction, reserved hole for hoist on girder, hole for hoist is positioned at directly over distribution beam, after main girder construction completes by hole for hoist reserved on steel wire penetrating girder, and be fixed in distribution beam, by on each interim beam integral hanging girder, next the direct pipe cutting on ground, steel pipe is removed, finally by the crane gear on girder end face, interim beam integral body is transferred to ground, on ground, complete dismounting.
CN201310693007.1A 2013-12-17 2013-12-17 Temporary girder-type support for bridge construction and dismantling method thereof Pending CN103711078A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310693007.1A CN103711078A (en) 2013-12-17 2013-12-17 Temporary girder-type support for bridge construction and dismantling method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310693007.1A CN103711078A (en) 2013-12-17 2013-12-17 Temporary girder-type support for bridge construction and dismantling method thereof

Publications (1)

Publication Number Publication Date
CN103711078A true CN103711078A (en) 2014-04-09

Family

ID=50404398

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310693007.1A Pending CN103711078A (en) 2013-12-17 2013-12-17 Temporary girder-type support for bridge construction and dismantling method thereof

Country Status (1)

Country Link
CN (1) CN103711078A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638336A (en) * 2016-10-21 2017-05-10 中国水利水电第八工程局有限公司 Over-line continuous beam removing method and support for removing
CN107119921A (en) * 2017-06-19 2017-09-01 江苏省华建建设股份有限公司 A kind of skyscraper Bailey beam Demolition Construction method
CN108374351A (en) * 2018-05-17 2018-08-07 中交公局厦门工程有限公司 A kind of simple hoisting apparatus and method for removing box beam beret slice
CN109468937A (en) * 2018-12-28 2019-03-15 中铁十局集团第二工程有限公司 Bridge and its method for dismounting with falsework
CN110747761A (en) * 2019-10-21 2020-02-04 宁波市政工程建设集团股份有限公司 Dismantling construction method and tool for temporary supporting system of small box girder type hidden cover beam of road and bridge prefabricated
CN112663501A (en) * 2020-12-18 2021-04-16 湖北省路桥集团有限公司 Upper-span existing line steel box girder structure and construction method
CN113832868A (en) * 2021-11-04 2021-12-24 中铁三局集团有限公司 Dismantling device and construction method for railway temporary support
CN114734404A (en) * 2022-04-12 2022-07-12 交通运输部上海打捞局 Horizontal splitting method for end plate top beam and arc-shaped beam combination of integral salvage equipment of sunken ship
CN114776038A (en) * 2022-04-13 2022-07-22 北京首钢建设集团有限公司 Steel truss installation structure and step unloading method thereof
CN117888471A (en) * 2023-12-29 2024-04-16 湖北省路桥集团有限公司 Construction method of dismantling system of inclined-leg rigid-frame overpass in highway reconstruction and expansion

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1837485A (en) * 2006-04-19 2006-09-27 中国建筑第二工程局 Space-precasting translation-emplacing method for bridge construction
CN101736692A (en) * 2008-11-20 2010-06-16 中铁十六局集团有限公司 Construction technology for passenger railway line spanning existing railway cast-in-place box beam bracket
CN102031756A (en) * 2010-12-01 2011-04-27 中建五局土木工程有限公司 Support assembly and construction method of cast-in-place box girder
CN202688888U (en) * 2012-07-17 2013-01-23 中交第二公路工程局有限公司 Deck type reversely hung template hanging frame

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1837485A (en) * 2006-04-19 2006-09-27 中国建筑第二工程局 Space-precasting translation-emplacing method for bridge construction
CN101736692A (en) * 2008-11-20 2010-06-16 中铁十六局集团有限公司 Construction technology for passenger railway line spanning existing railway cast-in-place box beam bracket
CN102031756A (en) * 2010-12-01 2011-04-27 中建五局土木工程有限公司 Support assembly and construction method of cast-in-place box girder
CN202688888U (en) * 2012-07-17 2013-01-23 中交第二公路工程局有限公司 Deck type reversely hung template hanging frame

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
将军辉: ""和龙高架桥连续箱梁的施工"", 《公路》, no. 12, 30 December 2006 (2006-12-30), pages 23 - 25 *
王东刚: ""高架桥简支梁钢管贝雷支架的拆除方法"", 《交通世界》, no. 17, 30 September 2011 (2011-09-30), pages 184 - 185 *

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106638336A (en) * 2016-10-21 2017-05-10 中国水利水电第八工程局有限公司 Over-line continuous beam removing method and support for removing
CN106638336B (en) * 2016-10-21 2018-08-10 中国水利水电第八工程局有限公司 Cross-line continuous beam method for dismounting and dismounting holder
CN107119921A (en) * 2017-06-19 2017-09-01 江苏省华建建设股份有限公司 A kind of skyscraper Bailey beam Demolition Construction method
CN108374351A (en) * 2018-05-17 2018-08-07 中交公局厦门工程有限公司 A kind of simple hoisting apparatus and method for removing box beam beret slice
CN109468937A (en) * 2018-12-28 2019-03-15 中铁十局集团第二工程有限公司 Bridge and its method for dismounting with falsework
WO2021078310A1 (en) * 2019-10-21 2021-04-29 宁波市政工程建设集团股份有限公司 Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
CN110747761B (en) * 2019-10-21 2021-03-23 宁波市政工程建设集团股份有限公司 Dismantling construction method for temporary supporting system of small box girder type hidden cover beam prefabricated on road and bridge
CN110747761A (en) * 2019-10-21 2020-02-04 宁波市政工程建设集团股份有限公司 Dismantling construction method and tool for temporary supporting system of small box girder type hidden cover beam of road and bridge prefabricated
US11634877B2 (en) 2019-10-21 2023-04-25 Ningbo Municipal Engineering Construction Group Co., Ltd. Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
CN112663501A (en) * 2020-12-18 2021-04-16 湖北省路桥集团有限公司 Upper-span existing line steel box girder structure and construction method
CN113832868A (en) * 2021-11-04 2021-12-24 中铁三局集团有限公司 Dismantling device and construction method for railway temporary support
CN114734404A (en) * 2022-04-12 2022-07-12 交通运输部上海打捞局 Horizontal splitting method for end plate top beam and arc-shaped beam combination of integral salvage equipment of sunken ship
CN114734404B (en) * 2022-04-12 2023-06-30 交通运输部上海打捞局 Horizontal splitting method for end plate top beam and arc beam assembly of sunken ship integral salvaging equipment
CN114776038A (en) * 2022-04-13 2022-07-22 北京首钢建设集团有限公司 Steel truss installation structure and step unloading method thereof
CN114776038B (en) * 2022-04-13 2024-03-29 北京首钢建设集团有限公司 Steel truss installation structure and step unloading method thereof
CN117888471A (en) * 2023-12-29 2024-04-16 湖北省路桥集团有限公司 Construction method of dismantling system of inclined-leg rigid-frame overpass in highway reconstruction and expansion

Similar Documents

Publication Publication Date Title
CN103711078A (en) Temporary girder-type support for bridge construction and dismantling method thereof
CN104032678B (en) H type king-post internal force adjustable false stull structure and construction method thereof
CN103043526B (en) Integral hoisting device and method for super-long steel reinforcement cage of underground continuous wall
CN102900021B (en) Split mounting type bridge wet joint construction method
CN203794498U (en) Built-in self-elevating tower crane device
CN106012852B (en) Support integrally falls frame construction method
CN203173681U (en) Device for lifting whole ultra-long reinforcing cage of underground continuous wall
CN106368127A (en) Whole support landing device and method for box girder support
CN103669902A (en) Cast-in-place beam support truss integral dropping and dismounting tool and construction method thereof
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
CN103993745A (en) Integral transfer girder hoisting device and hoisting method thereof
CN104179121B (en) A kind of mobile mould frame support bracket four promotes from assembling method
CN103552911B (en) A kind of movable boom hoisting and the construction installation method of use thereof
CN204999517U (en) Coal transporting trestle steel truss hoist device in power plant's chimney
CN207484292U (en) Bent cap bed die removes device
CN204266133U (en) A kind of pier stud reinforcing cage whole lifting structure
CN205932979U (en) Auxiliary fixtures of stand hoist and mount
CN104746863B (en) A kind of concrete chimney Demolition Construction platform
CN208120600U (en) A kind of quick provision for disengagement of large size inside-climbing tower crane
CN204661146U (en) That lifts by crane for auxiliary large-scale component stands up bearing
CN210505201U (en) A kind of equipment for hoisting steel bars in batches
CN206408527U (en) A kind of box beam bracket integrally falls rack device
CN105696609A (en) Steel hanging box lowering system and installation method thereof
CN102733612B (en) Mounting method of electric hoist orbit
CN206554485U (en) Hoisting type operating platform in a kind of vertical shaft

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140409