CN107605165A - A kind of prefabricated post construction method for hanging - Google Patents

A kind of prefabricated post construction method for hanging Download PDF

Info

Publication number
CN107605165A
CN107605165A CN201710711960.2A CN201710711960A CN107605165A CN 107605165 A CN107605165 A CN 107605165A CN 201710711960 A CN201710711960 A CN 201710711960A CN 107605165 A CN107605165 A CN 107605165A
Authority
CN
China
Prior art keywords
prefabricated post
diagonal brace
post
prefabricated
column cap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710711960.2A
Other languages
Chinese (zh)
Inventor
房岭锋
马骏
钱毅
袁清云
胡春华
徐笑非
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Shanghai Electric Power Co Ltd
Original Assignee
State Grid Shanghai Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Shanghai Electric Power Co Ltd filed Critical State Grid Shanghai Electric Power Co Ltd
Priority to CN201710711960.2A priority Critical patent/CN107605165A/en
Publication of CN107605165A publication Critical patent/CN107605165A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to a kind of prefabricated post construction method for hanging, comprise the following steps:Preparation before S1, lifting;S2, the correction of column cap reinforcing bar perpendicularity;S3, measurement prefabricated post elevation, are leveled up by bottom with steel disc, the locking of diagonal brace fixed seat;S4, the beam bit line for drawing prefabricated post column cap;S5, lifting and installation prefabricated post;S6, fixed diagonal brace simultaneously lock diagonal brace screw;S7, prefabricated post column cap crane hook pine hook, the perpendicularity of prefabricated post is adjusted, carry out the installation of next prefabricated post.Compared with prior art, the present invention adjusts the perpendicularity of prefabricated post by adjusting diagonal brace length-flexible, realizes the installation that is accurately positioned of prefabricated post, the support base of diagonal brace uses steel construction, reached support strength requirement.

Description

A kind of prefabricated post construction method for hanging
Technical field
The present invention relates to building technology field, more particularly, to a kind of prefabricated post construction method for hanging.
Background technology
In order to improve production efficiency, personnel labor intensity is reduced, and improves building element quality, at present in building industry Change field, the prefabricated of reinforced concrete building component generally is being studied, as reinforced concrete prefabricated column, armored concrete are prefabricated Beam, reinforced concrete prefabricated board.Development need design, production, the aspect of construction three of precasting process cooperate with, and what could be completed builds Build up product.Standardization and modularity are to need to pay attention at any time in prefabricated design, and the technique taken into account in production and construction is possible, to Composite and automation development reduce the dependence to labour to meet the diversified market demand.
The content of the invention
It is an object of the present invention to overcome the above-mentioned drawbacks of the prior art and provide a kind of lifting of prefabricated post is applied Work method.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of prefabricated post construction method for hanging, comprises the following steps:
Preparation before S1, lifting;
S2, the correction of column cap reinforcing bar perpendicularity;
S3, measurement prefabricated post elevation, are leveled up by bottom with steel disc, the locking of diagonal brace fixed seat;
S4, the beam bit line for drawing prefabricated post column cap;
S5, lifting and installation prefabricated post;
S6, fixed diagonal brace simultaneously lock diagonal brace screw;
S7, prefabricated post column cap crane hook pine hook, the perpendicularity of prefabricated post is adjusted, carry out the peace of next prefabricated post Dress.
The step S1 is specifically included:
S11, the position of review prefabricated post continued access lower floor reinforcing bar and elevation, lower concrete face is cleaned out;
S12, quality examination is carried out to prefabricated post;
S13, prepare required equipment and material;
S14, confirm that the column cap position of setting a roof beam in place of prefabricated post has been identified, and place first stirrup of column cap;
S15, confirm prefabricated post installation direction, component numbering, water power built-in pipe, suspension centre and construction weight.
Quality examination is carried out in the step S12 to prefabricated post to specifically include:Prefabricated post cage bar continued access sleeve quality is checked, The inside of prefabricated post is cleared up by pressure-air.
Equipment and material needed for the step step S13 specifically include:It is diagonal brace, diagonal brace fixing iron member, bolt, prefabricated Post is turned over bottom compliant pad, post bottom elevation adjustment iron plate, lifting tool, wind-proof miter square, ladder and oxygen-acetylene.
The angle of inclination of diagonal brace is 45~55 degree in the step S6, and the quantity of the diagonal brace is not less than 3 and located at pre- The not ipsilateral of post processed.
The perpendicularity of prefabricated post is realized by adjusting the length of its diagonal brace in the step S7.
Compared with prior art, the invention provides perfect prefabricated post construction method of installation, by adjusting diagonal brace length The perpendicularity of prefabricated post is adjusted flexibly, realizes the installation that is accurately positioned of prefabricated post, the support base of diagonal brace uses steel construction, reached Support strength requirement.
Brief description of the drawings
Fig. 1 is prefabricated post construction method for hanging flow chart of the present invention.
Embodiment
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.The present embodiment is with technical solution of the present invention Premised on implemented, give detailed embodiment and specific operating process, but protection scope of the present invention is not limited to Following embodiments.
As shown in figure 1, a kind of prefabricated post construction method for hanging, comprises the following steps:
Preparation before S1, lifting;
S2, the correction of column cap reinforcing bar perpendicularity;
S3, measurement prefabricated post elevation, are leveled up by bottom with steel disc, the locking of diagonal brace fixed seat;
S4, the beam bit line for drawing prefabricated post column cap;
S5, lifting and installation prefabricated post;
S6, fixed diagonal brace simultaneously lock diagonal brace screw;
S7, prefabricated post column cap crane hook pine hook, the perpendicularity of prefabricated post is adjusted, carry out the peace of next prefabricated post Dress.
Step S1 is specifically included:
S11, the position of review prefabricated post continued access lower floor reinforcing bar and elevation, lower concrete face is cleaned out;
S12, quality examination is carried out to prefabricated post;
S13, prepare required equipment and material;
S14, confirm that the column cap position of setting a roof beam in place of prefabricated post has been identified, and place first stirrup of column cap;
S15, confirm prefabricated post installation direction, component numbering, water power built-in pipe, suspension centre and construction weight.
Quality examination is carried out in step S12 to prefabricated post to specifically include:Prefabricated post cage bar continued access sleeve quality is checked, is passed through Pressure-air clears up the inside of prefabricated post, it is impossible to is cleared up with water.
Equipment and material needed for step step S13 specifically include:Diagonal brace, diagonal brace fixing iron member, bolt, prefabricated post are turned over Body bottom compliant pad, post bottom elevation adjustment iron plate, lifting tool, wind-proof miter square, ladder and oxygen-acetylene.
The error of the column cap elevation after grouting is required in step S3 between low 10mm~high 5mm, prefabricated post post muscle height It need to control between ± 10mm, pad is first positioned over the position that about 0.25 times of wide 4 points of post of center side is leaned in post position, treats that post perpendicularity adjusts Afterwards, pad is placed then at 4 corners.
Column cap beam bit line is drawn with model in step S4, drawn using unusual pen.
Bottom plate where the side of prefabricated post and prefabricated post is provided with the support base of steel construction, is provided between two support bases adjustable Save the diagonal brace of length.
The angle of inclination of diagonal brace is 45~55 degree in step S6, and the quantity of diagonal brace not less than 3 and is located at prefabricated post not Ipsilateral, pay attention to locking diagonal brace both ends during construction has at screw thread.
Suspension hook pine hook should should carry out work compound to ensure people to meet the execution of instrument of upper and lower equipment code in step S7 Member's safety, long column lifting should be reduced operating personnel and climb up the number lightened restrictions on using semi-automatic unhooked hanger as principle.Prefabricated post is hung down Straight degree is realized by adjusting the length of its diagonal brace.

Claims (6)

1. a kind of prefabricated post construction method for hanging, it is characterised in that comprise the following steps:
Preparation before S1, lifting;
S2, the correction of column cap reinforcing bar perpendicularity;
S3, measurement prefabricated post elevation, are leveled up by bottom with steel disc, the locking of diagonal brace fixed seat;
S4, the beam bit line for drawing prefabricated post column cap;
S5, lifting and installation prefabricated post;
S6, fixed diagonal brace simultaneously lock diagonal brace screw;
S7, prefabricated post column cap crane hook pine hook, the perpendicularity of prefabricated post is adjusted, carry out the installation of next prefabricated post.
2. a kind of prefabricated post construction method for hanging according to claim 1, it is characterised in that the step S1 is specifically wrapped Include:
S11, the position of review prefabricated post continued access lower floor reinforcing bar and elevation, lower concrete face is cleaned out;
S12, quality examination is carried out to prefabricated post;
S13, prepare required equipment and material;
S14, confirm that the column cap position of setting a roof beam in place of prefabricated post has been identified, and place first stirrup of column cap;
S15, confirm prefabricated post installation direction, component numbering, water power built-in pipe, suspension centre and construction weight.
3. a kind of prefabricated post construction method for hanging according to claim 2, it is characterised in that to pre- in the step S12 Post processed carries out quality examination and specifically included:Prefabricated post cage bar continued access sleeve quality is checked, prefabricated post is cleared up by pressure-air It is internal.
4. a kind of prefabricated post construction method for hanging according to claim 2, it is characterised in that in the step step S13 Required equipment and material specifically includes:Diagonal brace, diagonal brace fixing iron member, bolt, prefabricated post are turned over bottom compliant pad, post bottom Elevation adjustment iron plate, lifting tool, wind-proof miter square, ladder and oxygen-acetylene.
A kind of 5. prefabricated post construction method for hanging according to claim 1, it is characterised in that diagonal brace in the step S6 Angle of inclination is 45~55 degree, and the quantity of the diagonal brace is not less than 3 and located at the not ipsilateral of prefabricated post.
A kind of 6. prefabricated post construction method for hanging according to claim 1, it is characterised in that prefabricated post in the step S7 Perpendicularity realized by adjusting the length of its diagonal brace.
CN201710711960.2A 2017-08-18 2017-08-18 A kind of prefabricated post construction method for hanging Pending CN107605165A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710711960.2A CN107605165A (en) 2017-08-18 2017-08-18 A kind of prefabricated post construction method for hanging

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710711960.2A CN107605165A (en) 2017-08-18 2017-08-18 A kind of prefabricated post construction method for hanging

Publications (1)

Publication Number Publication Date
CN107605165A true CN107605165A (en) 2018-01-19

Family

ID=61065493

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710711960.2A Pending CN107605165A (en) 2017-08-18 2017-08-18 A kind of prefabricated post construction method for hanging

Country Status (1)

Country Link
CN (1) CN107605165A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108483215A (en) * 2018-04-27 2018-09-04 无锡市政设计研究院有限公司 A kind of hanging method of prefabricated post
CN112647590A (en) * 2020-12-01 2021-04-13 河北建工集团有限责任公司 Construction method for prefabricated assembled reinforced concrete beam column steel node prefabricated combination column
CN112695954A (en) * 2020-12-21 2021-04-23 成都城投远大建筑科技有限公司 Prefabricated column sectional prefabricating and mounting process

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
尹衍樑: "台湾地区润泰预制结构施工体系介绍", 《混凝土世界》 *
田黎: "预制装配式住宅现场施工技术与安全风险管理", 《住宅科技》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108483215A (en) * 2018-04-27 2018-09-04 无锡市政设计研究院有限公司 A kind of hanging method of prefabricated post
CN112647590A (en) * 2020-12-01 2021-04-13 河北建工集团有限责任公司 Construction method for prefabricated assembled reinforced concrete beam column steel node prefabricated combination column
CN112695954A (en) * 2020-12-21 2021-04-23 成都城投远大建筑科技有限公司 Prefabricated column sectional prefabricating and mounting process

Similar Documents

Publication Publication Date Title
CN102733545B (en) Section steel column for high-rise building section steel concrete combination structure, and construction method thereof
CN105839919B (en) Sectional hoisting construction method for large-span ultrahigh-section steel frame
CN104264920B (en) Construction method of ultrahigh large-curvature circular spiral as-cast-finish stair
CN107605165A (en) A kind of prefabricated post construction method for hanging
CN207294093U (en) A kind of large span steel truss integral lifting apparatus
CN205025086U (en) Strength nature skeleton concrete beam construction suspend template in midair
CN104631822A (en) Construction Method of High-rise Reinforced Concrete Elevator Shaft
CN106346596A (en) Precast stair template matching system
CN111395641A (en) Precast concrete external wallboard and construction method thereof
CN206352391U (en) Socket joint type key slot type Quick Release support system
CN106930531A (en) A kind of pull-up manomelia is encorbelmented the construction method of heavy frame
CN104674665A (en) Installation method for corridor bridge of large space steel structure
CN112211103A (en) Special safe construction process for assembling and installing coal conveying trestle steel truss
CN106437123A (en) Supporting leg automatic turnover type overall lifting elevator well operation platform
CN104775606A (en) Operation platform for prefabricated assembled residential building wall plate construction and construction method thereof
CN206917265U (en) A kind of adjustable small bore beam side reinforcement tools
CN206110635U (en) Automatic convertible integrally lift up elevator shaft operating platform of landing leg
CN109457872B (en) Cast-in-situ frame column reinforcement cage prefabricated construction device and construction method
CN106351245A (en) Tower crane foundation base and construction method thereof
CN106150105A (en) A kind of stiffened column installation method
CN107587770A (en) Disjunctor storehouse synchronization slding form operation method
CN102444275A (en) Silo flexible slip form torsion resistance construction device
CN208534069U (en) The assembled support device of steel bar truss floor support plate composite floor system
CN109025287B (en) Rear anchor construction method for large inclined cylindrical steel sleeve embedded part
CN103303789B (en) Adjustable buttress for supporting running rail of tunnel track laying gantry crane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180119

RJ01 Rejection of invention patent application after publication